Effective with the December 2018 Letting 381 2019 Standard Spec ifications Section 628 Erosion Control
628.1Description
and other erosion control devices.
628.2Materials
628.2.1 General 628.2.1.1 Acronyms
ECRM Class I, II, and IIIA erosion co ntrol revegetative mats. TRM Class III B, C, and D turf reinforcement mats. 628.2.1.2 Product Acceptability
specifies, furnish pr oducts of the class, type, and subject to the seasonal limitati ons the department's PAL designates. Before installing a product from the department's PAL , submit to the engineer a written copy of the manufacturer' s specifications for installin g that product on slopes, channels, shorelines, high wind locations , and next to live traffic lanes as applicable to the contract installation. Install products from the department's PAL conforming to those manufacturer's specifications. The department may specify modificati ons to the manufacturer's proc edures for individual materials here within 628.
department's PAL prequalification requirements . Provide samples as the engineer directs. 628.2.2 Erosion Mat
from the department's PAL.
class and type of erosion mat t he plans show or the engineer sp ecifies. The contractor may furnish any prequalified erosion mat p roduct of the class and type the plans show or that the engineer specifies.
single jute yarn. Use a jute ya rn of loosely twisted constructi on with an average twist of not less than 1 1/2 turns per one inch. Ensure the average size of the warp and weft yarns are a pproximately the same. Furnish the woven fabric i n rolled strips. Submit a certi ficate of compliance certifying that the jute fabric erosion mat conforms to the following: - Is a minimum 48 inches wide with a tolerance of minus one inch. - Has 78 warp ends, +/- one for each 48 inches of width. Has 45 weft yarns, +/- 2, per linear yard of length. - Weighs 92 pounds per 100 square yards +/ - 10 percent, measure d under average atmospheric conditions. - Is non-toxic to vegetation. 628.2.3 Staples
material, are one to 2 inches wide, and not less than 6 inches long for firm soils and not less than 12 inches for loose soils. The contractor may use anchors the staple gun manufacturer recommends, either lighter gage staples or equivalent, for engineer-approve d staple gun systems. 628.2.4 Bales
the plans show. 628.2.5 Stakes
628.2.6 Silt Fence 628.2.6.1 Geotextile
nylon, polyethylene, or polyvinylidene chloride. For non-woven fabric the contractor may use needle punched, heat bonded, resin bonded, or combinations of all 3. S ubmit a certificate of compliance certifying that the geotextile conforms to the following:
Effective with the December 2018 Letting 382 2019 Standard Spec ifications TEST REQUIREMENT METHOD VALUE[1] Minimum grab tensile strength ASTM D4632 120 lb (machine direction) Minimum grab tensile strength ASTM D4632 100 lb (cross machine direction) Maximum apparent opening size ASTM D4751 No. 30 (equivalent standard sieve) Minimum Permittivity ASTM D4491 0.05 s-1 Minimum ultraviolet stability ASTM D4355 70% (strength retained at 500 hrs of exposure) [1] All numerical values represent m inimum or maximum average roll values. Average test results from all rolls in a lot must conform the tabulated values. 628.2.6.2 Fence Support System
628.2.7 Silt Screen
Thickness ..................................................... ............................................................... ............................. 15 mils Minimum grab tens ile strength ................................. ............................................................... .................... 120 lb Minimum equiva lent opening .................................... ............................................................... ........ No.170 sieve
a buoyancy of approxim ately 20 pounds per foot. Do not use poly styrene beads or chips.
628.2.8 Sand Bags
sand or other engineer-approved granular material. 628.2.9 Polyethylene Sheeting
628.2.10 Turbidity Barriers
placed. It shall have a cable, with a 5/16 inch or larger diame ter, capable of supporting the barrier at the required height above the water. It shall have a self-conta ined ballast that weighs at least 0.7 pound per foot. The ballast may be either chain or flexible cable. Barrier ends shall have grommets to lace together adjoining sections. For anchor posts use one of t he following: steel fence posts, steel pipes, or steel channels.
TEST REQUIREMENT METHOD VALUE[1] Minimum grab tensile strength ASTM D4632 200 lb Minimum puncture strength ASTM D4833 90 lb Maximum permeability ASTM D4491 1x10-7 cm/s Minimum ultraviolet stability ASTM D4355 70% (strength retained at 500 hrs of exposure) [1] All numerical values represent m inimum or maximum average roll values. Average test results from all rolls in a lot must conform the tabulated values. 628.2.11 Soil Stabilizer
mulch, or a bonded fiber matrix . Soil stabilizer type B is a po lyacrylimide.
628.2.12 Inlet Protection
type FF geotextiles, or bags man ufactured from type FF geotexti les, from the department's PAL .
Effective with the December 2018 Letting 383 2019 Standard Spec ifications 628.2.13 Rock Bags
will retain 70 percent of its original strength after 500 hours of exposure according to ASTM D4355 and a minimum in-place filled size of 18 inches long by 12 inches wide by 6 inches high. Ensure that the fabric conforms to the following: TEST REQUIREMENT METHOD VALUE Minimum Tensile ASTM D4632 Machine direction 70 lb minimum Cross direction 40 lb minimum Elongation ASTM D4632 Machine direction 20% minimum Cross direction 10% min Puncture ASTM D4833 65 lbs minimum Minimum Apparent Opening 0.0234 inches (No. 30 sieve) Maximum Apparent Opening 0.0787 inches (No. 10 sieve)
visual inspection to the gradation specified for No. 2 coarse a ggregate for concrete in 501.2.5.4.5 . 628.2.14 Tracking Pads
shall be substantially free of particles passing the No. 10 sie ve. Furnish type R geotextile conforming to 645.2.2.6 .
628.3Construction
628.3.1 General
to protect the project site from erosion at all times during construction. Includeer osion mat, erosion bales, silt fence, manufactured alternative materials for temporary ditch checks, and other temporary erosion control materials the contract requires.
maintained to remain in place and functioning as the contracts pecifies. 628.3.2 Erosion Mat
of slopes, ditches, channels, or shorelines, at locations the p lans show or the engineer directs. Conform to the seasonal limitations designated in the departmen t's PAL for photodegradable products.
active traffic lanes.
for all mats the department's PAL designates as urban.
manufacturer’s recommended rate unless the contract or engineer specifies otherwise.
completely on the surfac e before placing the mat.
the original seeding.
in preparing for placing the mat.
depth of 2 inches and in a way that precludes washing or erosio n.
Effective with the December 2018 Letting 384 2019 Standard Spec ifications 628.3.3 Erosion Bales
than ditch checks. Install at loc ations the plans show or as th e engineer directs.
erosion bales after slopes and di tches are stable and turf develops enough to make future erosion unlikely. The engineer will determine when the contractor meets these criteria satisfactorily. The contractor may use bales as mulch. Dispose of bales not used as mulch in a manner acceptable to the engineer. Reshape ditches; fill sumps and trenches; dispose of excess eroded material; and topsoil, fertilize, and seed the affected area. 628.3.4 Silt Fence 628.3.4.1 Installation and Removal
at the site of the proposed silt fence.
Construct the silt fenc e to the dimensions , and according to th e details the plans show. Remove silt fences, as the engineer determines, after stabilizing the slopes and ditches and developing the turf to the extent that future erosion i s unlikely. Clean up and restor e the surface after removal. The contractor owns all materials re maining after removal and is re sponsible for their disposal off the right- of-way. 628.3.4.2 Inspection and Maintenance
Correct any deficiencies immediately. Additionally, review the locations for silt fences and filter barriers in areas that construction activity changed the earth contour a nd drainage runoff on a daily basis to ensure that the silt fences are p roperly and effectively locate d. If deficiencies exis t, install additional silt fences as the engineer directs or approves.
silt fence. The engineer may order the contractor to remove dep osits if the engineer determines deposits exceed 1/2 the volume c apacity of the silt fence. The contractor shall dress, to the existing grade, sediment deposits remaini ng in place after the silt fenc e is no longer requi red, this includes topsoiling, fertilizing, and seeding the affected area. 628.3.5 Silt Screen
fabric in both the horizontal and vertical direction.
of silt screen. Seal a 1/4-inch chain in the lower hem for ballast.
for its entire height with grommets and lacing rope.
deadman or engineer-approved equal fo r shore anchors. Ensure st ream anchors are of sufficient size, type, and strength to stabilize the barrier bey ond the construction area.
and heavy kedge type or mushroo m anchors on mud bottoms.
628.3.6 Cleaning Sediment Basins
impairs the effectiveness of the sediment basin.
628.3.7 Mobilizations for Erosion Control
the stages the contract indic ates or the engineer directs.
control work. Stage the ECIP erosion control wor k to conform to the number of Mobilizations Erosion Control bid items the contract plans show. The department will not allow any deviation from approved
Effective with the December 2018 Letting 385 2019 Standard Spec ifications staging without the engineer’s w ritten approval. The engineer w ill direct each of the mobilizations. Mobilize with sufficient personnel, equipment, supplies, and incidentals, within 72 hours of the engineer’s written order. 628.3.8 Mobilizations Emergency Erosion Control
on an emergency basis as the engineer directs.
the engineer’s written order to install temporary erosion contr ol items on an emergency basis.
erosion control items and mobiliz ations the ECIP includes. Unde r this definition, an emergency mobilization requires immediate action to move necessary person nel, equipment, and materials to the emergency site followed by immediate installation of temporary erosion control measures.
quantities in 628.3.1 and subsequently used for emergen cy erosion control to the pre -emergency totals of these stockpiles. 628.3.9 Polyethylene Sheeting
other materials that interfere w ith the sheeting bearing completely on the soil. Overlap adjacent sheets a minimum of 3 feet in the di rection of flow; and seal the edges with waterproof tape or other engineer- approved method. Patch damaged ar eas with sheeting overlapped a minimum of 3 feet and seal the joints with waterproof tape or other engineer-approved method. Maintain the sheeting and make satisfactory repairs of damaged areas.
of all removed material. 628.3.10 Turbidity Barriers
of the streambed and banks. Extend the barrier into the stream banks far enough to preclude washing out or erosion around the ends. D rive posts securely into the s treambed at 10 foot intervals along the line of the barrier installation. Fasten the barrier to the pos ts and securely anchor the barrier load lines at the barrier ends and at 10 foo t intervals between the barrie r ends, unless the engineer directs otherwise. Provide additional anc horing if necessary to maintai n the barrier location during construction operations. Install sand bags as the plans show to anchor the barrier to the streambed. The engineer may require additional sand bags to ensure adequat e performance. The contractor, as required by permit under 107.19 , shall provide and anchor both danger buoys and navigational markers.
operations. Promptly correct all deficiencies. Barrier maintena nce includes removing and disposing of accumulations of soil and ot her detrimental material.
accumulated soils and other susp ended materials, and all suspen ded materials settle. Minimize disturbing the streambed and banks during removal operations.
construction operation for all or part of the turbidity barrier the plans show. 628.3.11 (Vacant) 628.3.12 Soil Stabilizer 628.3.12.1 General
surfaces of temporary or permanen t slopes as the plans show or as the engineer directs. 628.3.12.2 Soil Stabilizer Type A
structures, signs, trees, and shr ubs are not over-sprayed. The engineer will not accept the work until the contractor cleans over-spr ayed surfaces. Provide a finished application 3/16 to 1/4 inches thick.
Effective with the December 2018 Letting 386 2019 Standard Spec ifications (2) For permanent slope applicatio ns, sow seed separately, before applying the soil stabilizer, to ensure that the seed has direct contact with the soil. 628.3.12.3 Soil Stabilizer Type B
material at the manufacturer's recommended rate unless the engi neer directs otherwise.
stabilizer or after applying it to protect the seed. 628.3.13 Inlet Protection
for inlet protection where the plans show or the engineer direc ts. The contractor may provide manufactured alternatives selected from the department's PAL.
around pavement inlets before pla cing curb, gutter, or curb & g utter.
surrounding pavement surfaces.
front of the curb head as the plans show. The wood shall not bl ock the entire opening of the curb box.
manufactured type FF bag from the department's PAL. Ensure that the device is designed to fit the size and shape of the inlet. At a m inimum, inspect and maintain after every precipitation event. 628.3.14 Temporary Ditch Checks
engineer directs.
from the department's PAL. Place temporary ditch checks ac ross ditches at locations the plans show or as the engineer directs immediat ely after shaping the ditches or slopes. Excavate upstream sumps as the engineer directs.
volume capacity. The engineer may order the contractor to remov e deposits if the engi neer determines that sediment deposits exceed 1/2 the erosion bale structures v olume capacity. Dispose of excess sediment as the engineer directs.
future erosion unlikely. The engineer will determine when the c ontractor meets these criteria. The contractor may use bales as mulch. Dispose of bales not used as mulch in a manner acceptable to the engineer. Reshape the ditch; fill sumps and trenches; dispose of excess eroded material; and topsoil, fertilize, and seed the affected area. 628.3.15 Culvert Pipe Checks
immediately after installing new culverts and before beginning earth disturbing activities in areas drained by existing culverts. P lace rock bags on the inlet end of the culvert only. Leave rock bags in place until slopes and ditches are stable and turf develops eno ugh to make future erosion unlikely. Periodically remove sediment to m aintain effective function. Re move and dispose o f the bags and rock filler when they are no longer n eeded to control erosion. Dispose of accumulated sediment and restore the site. The contractor may spread accumulated sediment to for m a surface suitable for seeding. 628.3.16 Tracking Pads
ECIP, or where the engineer direc ts before allowing constructio n traffic to leave the site. Ensure that the pad is wide enough to cover t he full width of the egress po int. Design the inst allation to divert surface water flow away from the pad and, if field conditions d ictate, provide a culvert to channel flow under the pad.
Maintain the driving surface in a clean and safe operating cond ition. Remove the pad and restore the site upon completion of contract work.
Effective with the December 2018 Letting 387 2019 Standard Spec ifications 628.3.17 Rock Bags
other contract bid items or as s tand-alone erosion control devi ces. Periodically remove sediment to maintain effective function. Rem ove and dispose of the bags and rock filler when they are no longer needed to control erosion. Dispose of accumulated sediment and restore the site. The contractor may spread accumulated sediment to fo rm a surface suitable for seeding.
628.4Measurement
628.4.1 General 628.4.1.1 Borrow Sites and Material Disposal Sites
sites and material disposal sites if that work is consistent wi th an engineer-approved ECIP. The department will measure only the following bid items using the methods described in their respective measurement subsections: Erosion Mat (type) Soil Stabilizer (type) Mulching Erosion Bales Culvert Pipe Checks Seeding Temporary Ditch Checks Polyethylene Sheeting Seeding Temporary Silt Fence Tracking Pads Fertilizer Type (type) Silt Fence Maintenance Rock Bags Inlet Protection (type) Mobilizations Emergency Erosion Control 628.4.1.2 Sand Bags
bags. 628.4.2 Erosion Mat
department will not make allowanc e for portions of the mat that must be entrenched in the soil for any end or junction slot, or for required overlaps. 628.4.3 (Vacant) 628.4.4 Erosion Bales
628.4.5 (Vacant) 628.4.6 Silt Fence
measure along the base of the f ence, center-to-center of end po st, for each section of fence. 628.4.7 (Vacant) 628.4.8 Silt Fence Maintenance
department will measure along the base of the fence, end-to-end of the section maintained, for each time a section of fence is cleaned and repaired. 628.4.9 Silt Screen
628.4.10 Cleaning Sediment Basins
measured in the vehicle. 628.4.11 Mobilizations Erosion Control
completed. The department will not include the following:
necessary for normal contractor maintenance of erosion control items.
erosion control items the engineer deems necessary to control e rosion between the stages contained in the department-approved plan of operations, unless the engineer directs otherwise in writing.
Effective with the December 2018 Letting 388 2019 Standard Spec ifications 628.4.12 Mobilizations Emergency Erosion Control
acceptably completed. The department will not include deliverin g and installing te mporary erosion control materials provided for in specific contract bid items. 628.4.13 Polyethylene Sheeting
628.4.14 Turbidity Barriers
department will make no allowance for portions of the turbidity barrier considered as part of the anchorages, required overlaps, or having a bottom flap greater than 48 inches.
measure that turbidity barrier a s the plan quantity in square y ards of material replaced. 628.4.15 Soil Stabilizer
limits the contract designates or as the engineer directs. 628.4.16 Inlet Protection
acceptably completed. 628.4.17 Temporary Ditch Checks
using erosion bales, the departm ent will only measure the length across the ditch, not the length of each row of bales. The departm ent will not measure ditch checks constructed with a single row of bales. 628.4.18 (Vacant) 628.4.19 Culvert Pipe Checks
628.4.20 Tracking Pads
measured only at the locations the plans show, consistent with an engineer-approved ECIP, and where the engineer directs. 628.4.21 Rock Bags
628.5Payment
628.5.1 General
items: ITEM NUMBER DESCRIPTION UNIT
628.1104 Erosion Bales EACH
628.1504 Silt Fence LF
20 Silt Fence Maintenance LF
50 Silt Screen LF
628.1905 Mobilizations Erosion Control EACH
10 Mobilizations Emergency Erosion Control EACH
20 Cleaning Sediment Basins CY
628.2000 - 2099 Erosion Mat (class) (type) SY
628.5505 Polyethylene Sheeting SY
628.6005 Turbidity Barriers SY
628.6500 - 6599 Soil Stabilizer (type) ACRE
628.7000 - 7099 Inlet Protection (type) EACH
628.7504 Temporary Ditch Checks LF
55 Culvert Pipe Checks EACH
60 Tracking Pads EACH
Effective with the December 2018 Letting 389 2019 Standard Spec ifications 628.7570 Rock Bags EACH
placed on borrow sites and mater ial disposal sites if that work is consistent with an engineer-approved ECIP. The department will pay for only the following bid items using the methods described in their respective payment subsections: Erosion Mat (type) Soil Stabilizer (type) Mulching Erosion Bales Culvert Pipe Checks Seeding Temporary Ditch Checks Polyethylene Sheeting Seeding Temporary Silt Fence Tracking Pads Fertilizer Type (type) Silt Fence Maintenance Rock Bags Inlet Protection (type) Mobilizations Emergency Erosion Control 628.5.2 Erosion Mat
erosion mat materials on the project; for placing and anchoring the mat, including staples; for preparing the seeded areas; for installing end and junction slots; for repairing an d reseeding damaged areas; for providing and applying water; and for disposing of a ll surplus and waste materials.
the applicable Erosion Mat bid i tem, or with type A soil stabilizer under the Soil Stabilizer Type A bid item. 628.5.3 (Vacant) 628.5.4 Erosion Bales
the project; for placing materials, including stakes; for ancho ring the bales; for all excavating, including trenches and sumps; for removing excess sedim ent during constru ction; for removing and disposing of the bales and all waste or surpl us materials, including eroded materials; and for shaping and restoring ditches.
applicable bid item. 628.5.5 (Vacant) 628.5.6 Silt Fence
project; for erecting fence, including all excavating, placing posts, backfilling, and attaching geotextile; and for removing the fence at project completion. 628.5.7 (Vacant) 628.5.8 Silt Fence Maintenance
removing or spreading the accumu lated sediment to form a surfac e suitable for seeding; and for replacing silt fence and all damages caused by overloading sediment material or ponding water adjacent to the silt fence. 628.5.9 Silt Screen
removing the silt screen barrier. 628.5.10 Cleaning Sediment Basins
surplus material. 628.5.11 Mobilizations Erosion Control
moving equipment, and moving mate rials. The department will pay separately for delivery and installation of erosion control devices under the other bid ite ms in this section.
deduction from money due under the contract, for ea ch calendar day of delay. The engineer may extend the 72-hour period for del ays not the contractor's fault .
Effective with the December 2018 Letting 390 2019 Standard Spec ifications 628.5.12 Mobilizations Emergency Erosion Control
personnel, moving equipment, and mo ving materials. The departme nt will pay separately for delivery and installation of temporaryer osion control devices under the other bid items in this section.
under the contract, for each cal endar day of del ay. The enginee r may extend the 8-hour period for delays not the contractor's fault. 628.5.13 Polyethylene Sheeting
sheeting to the project site; fo r storing on the project; for i nstalling the sheeting; for all excavating and backfilling; for securing the shee ting and seali ng the edges of the sheeting; and for removing and disposing of the sheeting and surplus materials. 628.5.14 Turbidity Barriers
and removing the turbidity barrier; and for sandbags, buoys, na vigational markers, anchors, and anchor ropes.
pay for the plan quantity of tu rbidity barrier replaced. 628.5.15 Soil Stabilizer
stabilizer. 628.5.16 Inlet Protection
installing materials; and for maintaining and removing the inle t protection devices. 628.5.17 Temporary Ditch Checks
check materials on the projec t; for installing and removing dit ch checks at project completion or as the engineer directs; for repairing and reseeding damaged areas; an d for disposing of all surplus and waste material.
628.5.18 (Vacant) 628.5.19 Culvert Pipe Checks
removal; for removing and disposing of rock bags and rock fille r; for disposing of surplus eroded materials; and for restoring the site. 628.5.20 Tracking Pads
geotextile; for replacing or rewor king material as required to maintain performance; and for removing the pad and restoring the site. 628.5.21 Rock Bags
removing and disposing of rock bags and rock f iller; for disposing of surplus eroded materials; and for restoring the site.
Effective with the December 2018 Letting 391 2019 Standard Spec ifications Section 629 Fertilizer and Agricultural Limestone
629.1Description
seeding or proposed sodding.
629.2Materials
629.2.1 Fertilizers 629.2.1.1 General
products in granular or liquid fo rm conforming to Wisconsin sta tutes and the Wisconsin administrative code chapter ATCP 40. Ensure that each container of packaged fe rtilizer is plainly marked with the analysis of the contents showing m inimum percentages of total n itrogen, available phosphoric acid, and soluble potash. If furnishing the fertilizer in bulk, include an invoice in each shipment indicating the minimum percentages of total nitrogen, available phosphoric aci d, and soluble potash in the contents. http://docs.legis.wi.gov /statutes/statutes/ http://docs.legis.wi.gov/code/ admin_code/atcp/020/40.pdf
or 50 percent for type B, apply t hem at a rate that provides eq ual nitrogen, phosphoric acid, and potash. 629.2.1.2 Type A
Nitrogen, not l ess than ....................................... ............................................................... ............................. 16% Phosphoric Acid, not less than ................................ ............................................................... ......................... 6% Potash, not l ess than ......................................... ............................................................... ............................... 6%
629.2.1.3 Type B
Nitrogen, not l ess than ....................................... ............................................................... ............................. 16% Phosphoric Acid, not less than ................................ ............................................................... ......................... 6% Potash, not l ess than ......................................... ............................................................... ............................. 24%
629.2.2 Agricultural Limestone
ATCP 41. Furnish limestone with a neutralizing index of not less than 40 or more than 109. http://docs.legis.wi.gov /statutes/statutes/94 http://docs.legis.wi.gov/code/ admin_code/atcp/020/41.pdf
for each deposit.
629.3Construction
629.3.1 Fertilizer 629.3.1.1 General
discing or harrowing. If applying granular fertilizer, ensure i t is well pulverized and free from lumps.
with, final discing or harrowing, o r if hand manipulating the t opsoil, apply it just before final raking and leveling.
inches deep and then incorporate the fertilizer as specified ab ove.
in the tank, mixing with the water and the seed, agitating constantly, and apply during the seeding operation. If applying fertilizer th is way then the department will not require discing and harrowing after placement.