628Erosion Control

WI · 2019 Standard SpecificationsBook pages 390399View official source ↗

Effective with the December 2018 Letting 381 2019 Standard Spec ifications Section 628 Erosion Control

628.1Description

(1)This section describes providi ng erosion control mats, bale ch ecks or dikes, fences, screens, blankets,

and other erosion control devices.

(2)This section also describes cleaning sediment basins and mobil izations for erosion control.

628.2Materials

628.2.1 General 628.2.1.1 Acronyms

(1)Interpret acronyms used thr oughout this section as follows:

ECRM Class I, II, and IIIA erosion co ntrol revegetative mats. TRM Class III B, C, and D turf reinforcement mats. 628.2.1.2 Product Acceptability

(1)The department prequalifies sele cted erosion control products in the department's PAL. If the contract

specifies, furnish pr oducts of the class, type, and subject to the seasonal limitati ons the department's PAL designates. Before installing a product from the department's PAL , submit to the engineer a written copy of the manufacturer' s specifications for installin g that product on slopes, channels, shorelines, high wind locations , and next to live traffic lanes as applicable to the contract installation. Install products from the department's PAL conforming to those manufacturer's specifications. The department may specify modificati ons to the manufacturer's proc edures for individual materials here within 628.

(2)The department may sample and test products supplied in the fi eld to verify that they conform to the

department's PAL prequalification requirements . Provide samples as the engineer directs. 628.2.2 Erosion Mat

(1)The department must prequalify all erosion mat products before use. Furnish erosion mat products

from the department's PAL.

(2)The department's PAL identifies prequalified erosi on mat products by class and type . Use the required

class and type of erosion mat t he plans show or the engineer sp ecifies. The contractor may furnish any prequalified erosion mat p roduct of the class and type the plans show or that the engineer specifies.

(3)If using jute fabric for a Class II Type A erosion mat, use a woven fabric of a uni form open weave of

single jute yarn. Use a jute ya rn of loosely twisted constructi on with an average twist of not less than 1 1/2 turns per one inch. Ensure the average size of the warp and weft yarns are a pproximately the same. Furnish the woven fabric i n rolled strips. Submit a certi ficate of compliance certifying that the jute fabric erosion mat conforms to the following: - Is a minimum 48 inches wide with a tolerance of minus one inch. - Has 78 warp ends, +/- one for each 48 inches of width. Has 45 weft yarns, +/- 2, per linear yard of length. - Weighs 92 pounds per 100 square yards +/ - 10 percent, measure d under average atmospheric conditions. - Is non-toxic to vegetation. 628.2.3 Staples

(1)Furnish U-shaped staples, made of No. 11 or larger diameter steel wire, or other engineer-approved

material, are one to 2 inches wide, and not less than 6 inches long for firm soils and not less than 12 inches for loose soils. The contractor may use anchors the staple gun manufacturer recommends, either lighter gage staples or equivalent, for engineer-approve d staple gun systems. 628.2.4 Bales

(1)For bales, use straw, hay, or other engineer-approved material , in good condition, of the dimensions

the plans show. 628.2.5 Stakes

(1)Furnish wood or metal stakes of the dimensions the plans show.

628.2.6 Silt Fence 628.2.6.1 Geotextile

(1)Furnish one of the following geot extiles: woven or non-woven polyester, polypropylene, stabilized

nylon, polyethylene, or polyvinylidene chloride. For non-woven fabric the contractor may use needle punched, heat bonded, resin bonded, or combinations of all 3. S ubmit a certificate of compliance certifying that the geotextile conforms to the following:

Effective with the December 2018 Letting 382 2019 Standard Spec ifications TEST REQUIREMENT METHOD VALUE[1] Minimum grab tensile strength ASTM D4632 120 lb (machine direction) Minimum grab tensile strength ASTM D4632 100 lb (cross machine direction) Maximum apparent opening size ASTM D4751 No. 30 (equivalent standard sieve) Minimum Permittivity ASTM D4491 0.05 s-1 Minimum ultraviolet stability ASTM D4355 70% (strength retained at 500 hrs of exposure) [1] All numerical values represent m inimum or maximum average roll values. Average test results from all rolls in a lot must conform the tabulated values. 628.2.6.2 Fence Support System

(1)Conform to plan requirements.

628.2.7 Silt Screen

(1)Furnish fabric and submit a certificate of compliance certifyi ng that the fabric conforms to the following:

Thickness ..................................................... ............................................................... ............................. 15 mils Minimum grab tens ile strength ................................. ............................................................... .................... 120 lb Minimum equiva lent opening .................................... ............................................................... ........ No.170 sieve

(2)Heat seal or sew all fabric seams.
(3)For flotation, use an 8-inch d iameter solid expanded polystyre ne log, or engineer-approved equal, with

a buoyancy of approxim ately 20 pounds per foot. Do not use poly styrene beads or chips.

(4)For the main load line, use 5/16-inch cable. For ballast, use a 1/4-inch chain.

628.2.8 Sand Bags

(1)Furnish bags made of canvas, burlap, nylon, or other engineer- approved material filled with concrete

sand or other engineer-approved granular material. 628.2.9 Polyethylene Sheeting

(1)Furnish 6 mil or thicker polyethylene sheeting conforming to ASTM D4397 .

628.2.10 Turbidity Barriers

(1)Furnish barrier made of coated impervious fabric capable of co ntaining all sediment at the location

placed. It shall have a cable, with a 5/16 inch or larger diame ter, capable of supporting the barrier at the required height above the water. It shall have a self-conta ined ballast that weighs at least 0.7 pound per foot. The ballast may be either chain or flexible cable. Barrier ends shall have grommets to lace together adjoining sections. For anchor posts use one of t he following: steel fence posts, steel pipes, or steel channels.

(2)Submit a certificate of complia nce certifying that the turbidi ty barrier fabric conforms to the following:

TEST REQUIREMENT METHOD VALUE[1] Minimum grab tensile strength ASTM D4632 200 lb Minimum puncture strength ASTM D4833 90 lb Maximum permeability ASTM D4491 1x10-7 cm/s Minimum ultraviolet stability ASTM D4355 70% (strength retained at 500 hrs of exposure) [1] All numerical values represent m inimum or maximum average roll values. Average test results from all rolls in a lot must conform the tabulated values. 628.2.11 Soil Stabilizer

(1)Soil stabilizer type A is one of the following: a cementitious soil binder added to wood cellulose fiber

mulch, or a bonded fiber matrix . Soil stabilizer type B is a po lyacrylimide.

(2)Furnish soil stabilizer products from the department's PAL .

628.2.12 Inlet Protection

(1)Use a type FF geotextile conforming to 645.2.2.1 except use a woven polypropylene fabric. Furnish

type FF geotextiles, or bags man ufactured from type FF geotexti les, from the department's PAL .

Effective with the December 2018 Letting 383 2019 Standard Spec ifications 628.2.13 Rock Bags

(1)Furnish rock bags made of a por ous, ultraviolet resistant, hig h-density polyethylene or geotextile that

will retain 70 percent of its original strength after 500 hours of exposure according to ASTM D4355 and a minimum in-place filled size of 18 inches long by 12 inches wide by 6 inches high. Ensure that the fabric conforms to the following: TEST REQUIREMENT METHOD VALUE Minimum Tensile ASTM D4632 Machine direction 70 lb minimum Cross direction 40 lb minimum Elongation ASTM D4632 Machine direction 20% minimum Cross direction 10% min Puncture ASTM D4833 65 lbs minimum Minimum Apparent Opening 0.0234 inches (No. 30 sieve) Maximum Apparent Opening 0.0787 inches (No. 10 sieve)

(2)Fill the bags with a clean, sou nd, hard, durable, engineer-app roved coarse aggregate conforming by

visual inspection to the gradation specified for No. 2 coarse a ggregate for concrete in 501.2.5.4.5 . 628.2.14 Tracking Pads

(1)Furnish tracking pad aggregate conforming to 312.2 for select crushed material except the material

shall be substantially free of particles passing the No. 10 sie ve. Furnish type R geotextile conforming to 645.2.2.6 .

628.3Construction

628.3.1 General

(1)Arrange to have available a sufficient quantity of contract-re quired temporary erosion control materials

to protect the project site from erosion at all times during construction. Includeer osion mat, erosion bales, silt fence, manufactured alternative materials for temporary ditch checks, and other temporary erosion control materials the contract requires.

(2)Ensure that erosion control pr oducts selected from the departm ent's PAL are properly installed and

maintained to remain in place and functioning as the contracts pecifies. 628.3.2 Erosion Mat

(1)Provide protective covering ma ts or soil retention mats for er osion control on prepared planting areas

of slopes, ditches, channels, or shorelines, at locations the p lans show or the engineer directs. Conform to the seasonal limitations designated in the departmen t's PAL for photodegradable products.

(2)Install as the manufacturer sp ecifies except as follows:
1.Do not use single roll material less than 6 feet wide in ch annels.
2.Entrench mats approximately 3 inches deep along the edge fa cing traffic for all installations within 5 feet of

active traffic lanes.

3.Overlap mats by 3 inches or less and anchor with anchoring devices selected from the department's PAL

for all mats the department's PAL designates as urban.

(3)Cover TRM's immediately after installation with materials from the department's PAL as follows:
1.On slopes use either an EC RM or a type A soil stabilizer. I f using a soil stab ilizer, apply at the

manufacturer’s recommended rate unless the contract or engineer specifies otherwise.

2.In channels use an ECRM of a class and type the department' s PAL allows for channel applications.
(4)Remove all stones, clods, roots, sticks, or other foreign mate rial that prevent the mat from bearing

completely on the surfac e before placing the mat.

(5)Reseed any seeded areas damaged or destroyed during placement of the erosion mat as specified for

the original seeding.

(6)Dispose of all surplus excavation or materials, and all stones , clods, or other foreign material removed

in preparing for placing the mat.

(7)Apply water uniformly after placing the mat over a seeded area to sufficiently moisten the seedbed to a

depth of 2 inches and in a way that precludes washing or erosio n.

(8)Maintain the erosion mat and repair any damaged areas until th e work is accepted.
(9)The contractor shall not overlap type urban erosion mat with type urban or other type erosion mat.

Effective with the December 2018 Letting 384 2019 Standard Spec ifications 628.3.3 Erosion Bales

(1)Furnish bales of straw, hay, or other suitable baled material to form erosion contro l structures other

than ditch checks. Install at loc ations the plans show or as th e engineer directs.

(2)Maintain the bales as required including removing and disposin g of sediment deposits. Remove

erosion bales after slopes and di tches are stable and turf develops enough to make future erosion unlikely. The engineer will determine when the contractor meets these criteria satisfactorily. The contractor may use bales as mulch. Dispose of bales not used as mulch in a manner acceptable to the engineer. Reshape ditches; fill sumps and trenches; dispose of excess eroded material; and topsoil, fertilize, and seed the affected area. 628.3.4 Silt Fence 628.3.4.1 Installation and Removal

(1)Erect the silt fence before star ting a construction operation that might cause sedimentation or siltation

at the site of the proposed silt fence.

(2)If possible, construct the sil t fence in an arc or horseshoes hape with its ends pointing up slope.

Construct the silt fenc e to the dimensions , and according to th e details the plans show. Remove silt fences, as the engineer determines, after stabilizing the slopes and ditches and developing the turf to the extent that future erosion i s unlikely. Clean up and restor e the surface after removal. The contractor owns all materials re maining after removal and is re sponsible for their disposal off the right- of-way. 628.3.4.2 Inspection and Maintenance

(1)Inspect all silt fences immediat ely after each rainfall and at least daily during prolonged rainfall.

Correct any deficiencies immediately. Additionally, review the locations for silt fences and filter barriers in areas that construction activity changed the earth contour a nd drainage runoff on a daily basis to ensure that the silt fences are p roperly and effectively locate d. If deficiencies exis t, install additional silt fences as the engineer directs or approves.

(2)Remove sediment deposits when t he build-up exceeds approximately 1/2 the volume capacity of the

silt fence. The engineer may order the contractor to remove dep osits if the engineer determines deposits exceed 1/2 the volume c apacity of the silt fence. The contractor shall dress, to the existing grade, sediment deposits remaini ng in place after the silt fenc e is no longer requi red, this includes topsoiling, fertilizing, and seeding the affected area. 628.3.5 Silt Screen

(1)Install the silt screen to pre vent drift shoreward or downstre am. Securely attach the flotation log to the

fabric in both the horizontal and vertical direction.

(2)Attach the 5/16-inch cable at the flotation members and extend along the entire length of each section

of silt screen. Seal a 1/4-inch chain in the lower hem for ballast.

(3)Use connectors to join the main load line and ballast chain to carry all tensile pressure. Join the fabric

for its entire height with grommets and lacing rope.

(4)Ensure the silt screen extends fr om the water surface to a max imum 10 foot depth.
(5)Install anchorages or stakes on both shore and stream side to maintain stability. Use a post with

deadman or engineer-approved equal fo r shore anchors. Ensure st ream anchors are of sufficient size, type, and strength to stabilize the barrier bey ond the construction area.

(6)Buoy anchors to prevent pulling the barrier under water. Use Danforth-type anchors in sandy bottom

and heavy kedge type or mushroo m anchors on mud bottoms.

(7)Maintain the barrier throughout construction operations.
(8)After completing the work, remov e the barrier in a way that pr events siltation of the river.

628.3.6 Cleaning Sediment Basins

(1)Clean sediment basins when the engineer determines the sedimen t has accumulated to an extent that

impairs the effectiveness of the sediment basin.

(2)Dispose of the surplus material according to 205.3.12 for disposal of surplus o r unsuitable material.

628.3.7 Mobilizations for Erosion Control

(1)Move personnel, equipment, and ma terials to the project site f or constructing erosion control items at

the stages the contract indic ates or the engineer directs.

(2)Submit for approval an ECIP required in 107.20 for accomplishing temporary and permanent erosion

control work. Stage the ECIP erosion control wor k to conform to the number of Mobilizations Erosion Control bid items the contract plans show. The department will not allow any deviation from approved

Effective with the December 2018 Letting 385 2019 Standard Spec ifications staging without the engineer’s w ritten approval. The engineer w ill direct each of the mobilizations. Mobilize with sufficient personnel, equipment, supplies, and incidentals, within 72 hours of the engineer’s written order. 628.3.8 Mobilizations Emergency Erosion Control

(1)Move personnel, equipment, and ma terials to the project site t o install temporary erosion control items

on an emergency basis as the engineer directs.

(2)Mobilize with sufficient personnel, equipment, materials, and incidentals on the j ob site within 8 hours

the engineer’s written order to install temporary erosion contr ol items on an emergency basis.

(3)An emergency is a sudden occurre nce of a serious and urgent na ture, beyond normal maintenance of

erosion control items and mobiliz ations the ECIP includes. Unde r this definition, an emergency mobilization requires immediate action to move necessary person nel, equipment, and materials to the emergency site followed by immediate installation of temporary erosion control measures.

(4)Unless the engineer directs otherwise, replenish stockpiled ma terial delivered as specified for plan

quantities in 628.3.1 and subsequently used for emergen cy erosion control to the pre -emergency totals of these stockpiles. 628.3.9 Polyethylene Sheeting

(1)Install polyethylene sheeting at locations the plans show or a s the engineer directs.
(2)Secure the sheeting from wind and water dislocation. Before pl acing, remove stones, roots, sticks, and

other materials that interfere w ith the sheeting bearing completely on the soil. Overlap adjacent sheets a minimum of 3 feet in the di rection of flow; and seal the edges with waterproof tape or other engineer- approved method. Patch damaged ar eas with sheeting overlapped a minimum of 3 feet and seal the joints with waterproof tape or other engineer-approved method. Maintain the sheeting and make satisfactory repairs of damaged areas.

(3)Upon completing the work, remo ve the polyethylene sheeting. Th e contractor shall assume ownership

of all removed material. 628.3.10 Turbidity Barriers

(1)Install turbidity barriers at locations the plans show or as t he engineer directs.
(2)Place all barriers, before begi nning adjacent construction, in a way that causes minimum disturbance

of the streambed and banks. Extend the barrier into the stream banks far enough to preclude washing out or erosion around the ends. D rive posts securely into the s treambed at 10 foot intervals along the line of the barrier installation. Fasten the barrier to the pos ts and securely anchor the barrier load lines at the barrier ends and at 10 foo t intervals between the barrie r ends, unless the engineer directs otherwise. Provide additional anc horing if necessary to maintai n the barrier location during construction operations. Install sand bags as the plans show to anchor the barrier to the streambed. The engineer may require additional sand bags to ensure adequat e performance. The contractor, as required by permit under 107.19 , shall provide and anchor both danger buoys and navigational markers.

(3)Maintain the integrity of the ba rrier as necessary to contain erosion from adjacent construction

operations. Promptly correct all deficiencies. Barrier maintena nce includes removing and disposing of accumulations of soil and ot her detrimental material.

(4)Remove the barrier after completing the adjacent work. Delay r emoval until removi ng and disposing of

accumulated soils and other susp ended materials, and all suspen ded materials settle. Minimize disturbing the streambed and banks during removal operations.

(5)If the engineer approves, the contractor may substitute sheet pile installed as a part of their

construction operation for all or part of the turbidity barrier the plans show. 628.3.11 (Vacant) 628.3.12 Soil Stabilizer 628.3.12.1 General

(1)Provide soil stabilizer as a soil bonding agent to prevent or minimize erosion. Install on exposed soil

surfaces of temporary or permanen t slopes as the plans show or as the engineer directs. 628.3.12.2 Soil Stabilizer Type A

(1)Apply soil stabilizer with conventional hydraulic seeding equipment. Ensure that surrounding surfaces,

structures, signs, trees, and shr ubs are not over-sprayed. The engineer will not accept the work until the contractor cleans over-spr ayed surfaces. Provide a finished application 3/16 to 1/4 inches thick.

Effective with the December 2018 Letting 386 2019 Standard Spec ifications (2) For permanent slope applicatio ns, sow seed separately, before applying the soil stabilizer, to ensure that the seed has direct contact with the soil. 628.3.12.3 Soil Stabilizer Type B

(1)Apply soil stabilizer with conventional hydraulic seeding equi pment or by dry spreading. Apply the

material at the manufacturer's recommended rate unless the engi neer directs otherwise.

(2)For permanent slope applications, apply a department-approved mulch when applying the soil

stabilizer or after applying it to protect the seed. 628.3.13 Inlet Protection

(1)Furnish, install, maintain, and remove type FF geotextile, and fabric hold down and support systems

for inlet protection where the plans show or the engineer direc ts. The contractor may provide manufactured alternatives selected from the department's PAL.

(2)For type A inlet protection, ins tall around field inlets until establishing permanent soil stabilization; and

around pavement inlets before pla cing curb, gutter, or curb & g utter.

(3)For type B inlet protection, ins tall on curb, gutter, curb & g utter, and pavement inlets after placing the

surrounding pavement surfaces.

(4)For type C inlet protection use a wooden 2 x 4, wrapped and se cured in type FF geotextile, installed in

front of the curb head as the plans show. The wood shall not bl ock the entire opening of the curb box.

(5)For type D inlet protection, the contractor may make the bag from type FF geotextile or choose a

manufactured type FF bag from the department's PAL. Ensure that the device is designed to fit the size and shape of the inlet. At a m inimum, inspect and maintain after every precipitation event. 628.3.14 Temporary Ditch Checks

(1)Provide suitable ditch check m aterials, installed and maintained at locations the plans show or as the

engineer directs.

(2)Construct temporary ditch chec ks using a double row of erosion bales or a manufactured alternative

from the department's PAL. Place temporary ditch checks ac ross ditches at locations the plans show or as the engineer directs immediat ely after shaping the ditches or slopes. Excavate upstream sumps as the engineer directs.

(3)Remove sediment deposits when t he build-up exceeds approximately 1/2 the erosion bale structures

volume capacity. The engineer may order the contractor to remov e deposits if the engi neer determines that sediment deposits exceed 1/2 the erosion bale structures v olume capacity. Dispose of excess sediment as the engineer directs.

(4)Remove ditch checks after the slopes and ditches are stable and the turf develops enough to make

future erosion unlikely. The engineer will determine when the c ontractor meets these criteria. The contractor may use bales as mulch. Dispose of bales not used as mulch in a manner acceptable to the engineer. Reshape the ditch; fill sumps and trenches; dispose of excess eroded material; and topsoil, fertilize, and seed the affected area. 628.3.15 Culvert Pipe Checks

(1)Install rock bag culvert pipe ch ecks as the plans show and as the engineer directs. Place bags

immediately after installing new culverts and before beginning earth disturbing activities in areas drained by existing culverts. P lace rock bags on the inlet end of the culvert only. Leave rock bags in place until slopes and ditches are stable and turf develops eno ugh to make future erosion unlikely. Periodically remove sediment to m aintain effective function. Re move and dispose o f the bags and rock filler when they are no longer n eeded to control erosion. Dispose of accumulated sediment and restore the site. The contractor may spread accumulated sediment to for m a surface suitable for seeding. 628.3.16 Tracking Pads

(1)Install tracking pads at the locations the plans show, locations consistent with an engineer-approved

ECIP, or where the engineer direc ts before allowing constructio n traffic to leave the site. Ensure that the pad is wide enough to cover t he full width of the egress po int. Design the inst allation to divert surface water flow away from the pad and, if field conditions d ictate, provide a culvert to channel flow under the pad.

(2)Replace or rework material in the surface of the pad to minimi ze material tracked onto public roads.

Maintain the driving surface in a clean and safe operating cond ition. Remove the pad and restore the site upon completion of contract work.

Effective with the December 2018 Letting 387 2019 Standard Spec ifications 628.3.17 Rock Bags

(1)Install rock bags as the plans show or the engineer directs ei ther in conjunction with work done under

other contract bid items or as s tand-alone erosion control devi ces. Periodically remove sediment to maintain effective function. Rem ove and dispose of the bags and rock filler when they are no longer needed to control erosion. Dispose of accumulated sediment and restore the site. The contractor may spread accumulated sediment to fo rm a surface suitable for seeding.

628.4Measurement

628.4.1 General 628.4.1.1 Borrow Sites and Material Disposal Sites

(1)The department will measure work acceptably completed underse lected bid items placed on borrow

sites and material disposal sites if that work is consistent wi th an engineer-approved ECIP. The department will measure only the following bid items using the methods described in their respective measurement subsections: Erosion Mat (type) Soil Stabilizer (type) Mulching Erosion Bales Culvert Pipe Checks Seeding Temporary Ditch Checks Polyethylene Sheeting Seeding Temporary Silt Fence Tracking Pads Fertilizer Type (type) Silt Fence Maintenance Rock Bags Inlet Protection (type) Mobilizations Emergency Erosion Control 628.4.1.2 Sand Bags

(1)The department will not measure sand bags. Sand bags are incid ental to the bid items that use sand

bags. 628.4.2 Erosion Mat

(1)The department will measure the Erosion Mat bid items by the s quare yard acceptably completed. The

department will not make allowanc e for portions of the mat that must be entrenched in the soil for any end or junction slot, or for required overlaps. 628.4.3 (Vacant) 628.4.4 Erosion Bales

(1)The department will measure Erosion Bales as each individual bale acceptably completed.

628.4.5 (Vacant) 628.4.6 Silt Fence

(1)The department will measure Sil t Fence by the linear foot acce ptably completed. The department will

measure along the base of the f ence, center-to-center of end po st, for each section of fence. 628.4.7 (Vacant) 628.4.8 Silt Fence Maintenance

(1)The department will measure Sil t Fence Maintenance by the line ar foot acceptably completed. The

department will measure along the base of the fence, end-to-end of the section maintained, for each time a section of fence is cleaned and repaired. 628.4.9 Silt Screen

(1)The department will measure Sil t Screen by the linear foot acc eptably completed.

628.4.10 Cleaning Sediment Basins

(1)The department will measure Cleani ng Sediment Basins by the cubic yard acceptably completed,

measured in the vehicle. 628.4.11 Mobilizations Erosion Control

(1)The department will measure Mob ilizations Erosion Control by e ach individual mobilization acceptably

completed. The department will not include the following:

1.Delivering and installing mat erials provided for in specifi c contract bid items.
2.Work specified under the Mob ilizations Emergency Erosion Co ntrol bid item, or the work and operations

necessary for normal contractor maintenance of erosion control items.

3.The movement of personnel, equipment, and materials to the work site to accomplish installing additional

erosion control items the engineer deems necessary to control e rosion between the stages contained in the department-approved plan of operations, unless the engineer directs otherwise in writing.

Effective with the December 2018 Letting 388 2019 Standard Spec ifications 628.4.12 Mobilizations Emergency Erosion Control

(1)The department will measure Mob ilizations Emergency Erosion Co ntrol by each individual mobilization

acceptably completed. The department will not include deliverin g and installing te mporary erosion control materials provided for in specific contract bid items. 628.4.13 Polyethylene Sheeting

(1)The department will measure Polyethylene Sheeting by the square yard acceptably completed.

628.4.14 Turbidity Barriers

(1)The department will measure Turbid ity Barrier by the square ya rd acceptably completed. The

department will make no allowance for portions of the turbidity barrier considered as part of the anchorages, required overlaps, or having a bottom flap greater than 48 inches.

(2)If the contractor substitutes sheet pile for turbidity barrier as allowed in 628.3.10 , the department will

measure that turbidity barrier a s the plan quantity in square y ards of material replaced. 628.4.15 Soil Stabilizer

(1)The department will measure the Soil Stabilizer bid items by t he acre acceptably completed within the

limits the contract designates or as the engineer directs. 628.4.16 Inlet Protection

(1)The department will measure the In let Protection bid items as each individual location and type

acceptably completed. 628.4.17 Temporary Ditch Checks

(1)The department will measure Temp orary Ditch Ch ecks by the line ar foot acceptably completed. If

using erosion bales, the departm ent will only measure the length across the ditch, not the length of each row of bales. The departm ent will not measure ditch checks constructed with a single row of bales. 628.4.18 (Vacant) 628.4.19 Culvert Pipe Checks

(1)The department will measure Culvert Pipe Checks as each indivi dual rock bag acceptably completed.

628.4.20 Tracking Pads

(1)The department will measure Tracking Pads as each individual l ocation acceptably completed

measured only at the locations the plans show, consistent with an engineer-approved ECIP, and where the engineer directs. 628.4.21 Rock Bags

(1)The department will measure Rock Bags as each individual bag a cceptably completed.

628.5Payment

628.5.1 General

(1)The department will pay for measured quantities at the contrac t unit price under the following bid

items: ITEM NUMBER DESCRIPTION UNIT

628.1104 Erosion Bales EACH

628.1504 Silt Fence LF

20 Silt Fence Maintenance LF

50 Silt Screen LF

628.1905 Mobilizations Erosion Control EACH

10 Mobilizations Emergency Erosion Control EACH

20 Cleaning Sediment Basins CY

628.2000 - 2099 Erosion Mat (class) (type) SY

628.5505 Polyethylene Sheeting SY

628.6005 Turbidity Barriers SY

628.6500 - 6599 Soil Stabilizer (type) ACRE

628.7000 - 7099 Inlet Protection (type) EACH

628.7504 Temporary Ditch Checks LF

55 Culvert Pipe Checks EACH

60 Tracking Pads EACH

Effective with the December 2018 Letting 389 2019 Standard Spec ifications 628.7570 Rock Bags EACH

(2)The department will pay for measured quantities at the contrac t unit price under selected bid items

placed on borrow sites and mater ial disposal sites if that work is consistent with an engineer-approved ECIP. The department will pay for only the following bid items using the methods described in their respective payment subsections: Erosion Mat (type) Soil Stabilizer (type) Mulching Erosion Bales Culvert Pipe Checks Seeding Temporary Ditch Checks Polyethylene Sheeting Seeding Temporary Silt Fence Tracking Pads Fertilizer Type (type) Silt Fence Maintenance Rock Bags Inlet Protection (type) Mobilizations Emergency Erosion Control 628.5.2 Erosion Mat

(1)Payment for the Erosion Mat bid items is full compensation for providing, protecting, and storing

erosion mat materials on the project; for placing and anchoring the mat, including staples; for preparing the seeded areas; for installing end and junction slots; for repairing an d reseeding damaged areas; for providing and applying water; and for disposing of a ll surplus and waste materials.

(2)The department will pay separatel y for covering class III types B, C, and D mats with an ECRM under

the applicable Erosion Mat bid i tem, or with type A soil stabilizer under the Soil Stabilizer Type A bid item. 628.5.3 (Vacant) 628.5.4 Erosion Bales

(1)Payment for Erosion Bales is fu ll compensation for providing, protecting, and storing erosion bales on

the project; for placing materials, including stakes; for ancho ring the bales; for all excavating, including trenches and sumps; for removing excess sedim ent during constru ction; for removing and disposing of the bales and all waste or surpl us materials, including eroded materials; and for shaping and restoring ditches.

(2)The department will pay separatel y for any required topsoiling, fertilizing, or seeding under the

applicable bid item. 628.5.5 (Vacant) 628.5.6 Silt Fence

(1)Payment for Silt Fence is full compensation for providing, pro tecting, and storin g silt fence on the

project; for erecting fence, including all excavating, placing posts, backfilling, and attaching geotextile; and for removing the fence at project completion. 628.5.7 (Vacant) 628.5.8 Silt Fence Maintenance

(1)Payment for Silt Fence Maintenance is full compensation for al l required cleaning and repairing; for

removing or spreading the accumu lated sediment to form a surfac e suitable for seeding; and for replacing silt fence and all damages caused by overloading sediment material or ponding water adjacent to the silt fence. 628.5.9 Silt Screen

(1)Payment for Silt Screen is full compensation for providing, assembling, erecting, maintaining, and

removing the silt screen barrier. 628.5.10 Cleaning Sediment Basins

(1)Payment for Cleaning Sediment B asins is full compensation for all excavating; and for disposing of

surplus material. 628.5.11 Mobilizations Erosion Control

(1)Payment for Mobilizations Erosi on Control is full compensation for the staged moving of personnel,

moving equipment, and moving mate rials. The department will pay separately for delivery and installation of erosion control devices under the other bid ite ms in this section.

(2)Failure to mobilize within 72 hours of the engineer’s written order will result in a $300 per calendar day

deduction from money due under the contract, for ea ch calendar day of delay. The engineer may extend the 72-hour period for del ays not the contractor's fault .

Effective with the December 2018 Letting 390 2019 Standard Spec ifications 628.5.12 Mobilizations Emergency Erosion Control

(1)Payment for Mobilizations Emerg ency Erosion Control is full co mpensation for the staged moving of

personnel, moving equipment, and mo ving materials. The departme nt will pay separately for delivery and installation of temporaryer osion control devices under the other bid items in this section.

(2)Failure to mobilize within 8 hours, will result in a $300 per calendar day deduction from money due

under the contract, for each cal endar day of del ay. The enginee r may extend the 8-hour period for delays not the contractor's fault. 628.5.13 Polyethylene Sheeting

(1)Payment for Polyethylene Sheeti ng is full compensation for fur nishing and delivering the polyethylene

sheeting to the project site; fo r storing on the project; for i nstalling the sheeting; for all excavating and backfilling; for securing the shee ting and seali ng the edges of the sheeting; and for removing and disposing of the sheeting and surplus materials. 628.5.14 Turbidity Barriers

(1)Payment for Turbidity Barriers is full compensation for furnis hing, assembling, installing, maintaining,

and removing the turbidity barrier; and for sandbags, buoys, na vigational markers, anchors, and anchor ropes.

(2)If the contractor substitutes sheet pile for turbidity barrier as allowed in 628.3.10 , the department will

pay for the plan quantity of tu rbidity barrier replaced. 628.5.15 Soil Stabilizer

(1)Payment for the Soil Stabilizer b id items is full compensation for furnishing, mixing, and applying soil

stabilizer. 628.5.16 Inlet Protection

(1)Payment for the Inlet Protecti on bid items is full compensatio n for furnishing, tr ansporting, and

installing materials; and for maintaining and removing the inle t protection devices. 628.5.17 Temporary Ditch Checks

(1)Payment for Temporary Ditch Ch ecks is full compensation for pr oviding, protecting, and storing ditch

check materials on the projec t; for installing and removing dit ch checks at project completion or as the engineer directs; for repairing and reseeding damaged areas; an d for disposing of all surplus and waste material.

(2)The department will not pay for in stalling ditch checks if con structed of a single row of erosion bales.

628.5.18 (Vacant) 628.5.19 Culvert Pipe Checks

(1)Payment for Culvert Pipe Checks is full compensation for provi ding rock bags; for periodic sediment

removal; for removing and disposing of rock bags and rock fille r; for disposing of surplus eroded materials; and for restoring the site. 628.5.20 Tracking Pads

(1)Payment for Tracking Pads is fu ll compensation for providing tracking pads including aggregate and

geotextile; for replacing or rewor king material as required to maintain performance; and for removing the pad and restoring the site. 628.5.21 Rock Bags

(1)Payment for Rock Bags is full compensation for providing rock bags; for periodics ediment removal; for

removing and disposing of rock bags and rock f iller; for disposing of surplus eroded materials; and for restoring the site.

Effective with the December 2018 Letting 391 2019 Standard Spec ifications Section 629 Fertilizer and Agricultural Limestone

629.1Description

(1)This section describes furnis hing and incorporating fertilizin g material in the soil on areas of proposed

seeding or proposed sodding.

(2)This section also describes fu rnishing and incorporating agricultural limestone in the soil.

629.2Materials

629.2.1 Fertilizers 629.2.1.1 General

(1)Use fertilizers for seeding, sodding, or other planting that a re standard commercial packaged or bulk

products in granular or liquid fo rm conforming to Wisconsin sta tutes and the Wisconsin administrative code chapter ATCP 40. Ensure that each container of packaged fe rtilizer is plainly marked with the analysis of the contents showing m inimum percentages of total n itrogen, available phosphoric acid, and soluble potash. If furnishing the fertilizer in bulk, include an invoice in each shipment indicating the minimum percentages of total nitrogen, available phosphoric aci d, and soluble potash in the contents. http://docs.legis.wi.gov /statutes/statutes/ http://docs.legis.wi.gov/code/ admin_code/atcp/020/40.pdf

(2)If using fertilizer with a total of nitrogen, phosphoric acid, and potash greater than 32 percent for type A

or 50 percent for type B, apply t hem at a rate that provides eq ual nitrogen, phosphoric acid, and potash. 629.2.1.2 Type A

(1)Type A fertilizer shall conform to the following minimum requi rements:

Nitrogen, not l ess than ....................................... ............................................................... ............................. 16% Phosphoric Acid, not less than ................................ ............................................................... ......................... 6% Potash, not l ess than ......................................... ............................................................... ............................... 6%

(2)The total of nitrogen, phosphoric acid, and potash shall equal at least 32 percent.
(3)Total nitrogen shall at lea st equal the sum of the phosphoric acid and soluble potash.

629.2.1.3 Type B

(1)Type B fertilizer shall conform to the following minimum requi rements:

Nitrogen, not l ess than ....................................... ............................................................... ............................. 16% Phosphoric Acid, not less than ................................ ............................................................... ......................... 6% Potash, not l ess than ......................................... ............................................................... ............................. 24%

(2)The total of nitrogen, phosphoric acid, and potash shall equal at least 50 percent.

629.2.2 Agricultural Limestone

(1)Conform to chapter 94.66 of the Wisconsin statutes and of the Wisconsin administrative code chapter

ATCP 41. Furnish limestone with a neutralizing index of not less than 40 or more than 109. http://docs.legis.wi.gov /statutes/statutes/94 http://docs.legis.wi.gov/code/ admin_code/atcp/020/41.pdf

(2)Before using, furnish a statem ent to the engineer indicating t he index zone or grade of the limestone

for each deposit.

629.3Construction

629.3.1 Fertilizer 629.3.1.1 General

(1)Uniformly apply the fertilizers elected for the seeding areas and incorporate into the soil by light

discing or harrowing. If applying granular fertilizer, ensure i t is well pulverized and free from lumps.

(2)If incorporating fertilizer int o topsoiled areas, the contract or may apply it just before, and in conjunction

with, final discing or harrowing, o r if hand manipulating the t opsoil, apply it just before final raking and leveling.

(3)If placing fertilizer on surfaces with no topsoil, prepare the soil by discing or har rowing to at least 6

inches deep and then incorporate the fertilizer as specified ab ove.

(4)If sowing seeding areas by pressure sprayer, then fertilize by placing the required quantity of fertilizer

in the tank, mixing with the water and the seed, agitating constantly, and apply during the seeding operation. If applying fertilizer th is way then the department will not require discing and harrowing after placement.

Source: Wisconsin Standard Specifications for Highway and Structure Construction, 2019 Edition. Pages 390399 of 601.