Effective with the December 2018 Letting 106 2019 Standard Spec ifications Section 210 Structure Backfill
210.1Description
culverts, retaining walls, and structural plate pipes and pipe arches.
210.2Materials
210.2.1 General Requirements
particles or sand-sized particles mixed with gravel, crushed gr avel, or crushed stone. Do not use crushed concrete or reclaimed asphalt.
than or equal to 6. The contract or may substitute type A for type B material. 210.2.2 Gradation
- For the entire sample, conform to the following gradation lim its: PERCENT PASSING BY WEIGHT SIEVE TYPE A TYPE B 3-inch 100 100 No. 4 25 - 100 25 - 100 - For the portion of the sample passing the No. 4 sieve, confor m to the following gradation limits: PERCENT PASSING BY WEIGHT SIEVE TYPE A TYPE B No. 4 100 100 No. 40 0 - 75 ___ No. 100 0 - 15 ___ No. 200 0 - 8.0 0 - 15.0 210.2.3 Sampling and Testing
Sampling[1] ............................................................................................................................. ........... AASHTO T2 Percent passing t he 200 sieve ................................. ............................................................... ........ AASHTO T11 Gradation[1] ............................................................................................................................. ........ AASHTO T27 Liquid l imit .................................................. ............................................................... ...................... AASHT O T89 Plasticity index and plastic limit ............................ ............................................................... ........... AASHTO T90 [1] As modified in CMM 8-60. 210.2.4 Source
responsible for negotiating with property owners to obtain gran ular material.
material disposal under 104.9 and 208.3 .
passing the No. 200 sieve before excavating the granular material.
are neatly constructed.
210.3Construction
place and compact as specified for those applications. 210.4 Measurement
completed. The department will only include material placed within the limits and in the places the plans show, the contract desig nates, or the engineer directs. F or minor quantities, the engineer may measure by the cubic yard in t he vehicle. The department may co nvert the measurement between weight and volume as specified in 109.1 .
Effective with the December 2018 Letting 107 2019 Standard Spec ifications (3) For measurement by the ton, the department will determine weig ht based on contractor-provided tickets submitted daily. Submit a ticket for each load showing the material, net weight, date, and project ID. For material with mor e than 7 percent moisture, the department will reduce the ticket weight by the weight of water exceeding 7 percent. The department will determine moisture content as a percent of dry weight.
210.5Payment
items: ITEM NUMBER DESCRIPTION UNIT
210.1100 Backfill Structure Type A CY
210.1500 Backfill Structure Type A TON
210.2100 Backfill Structure Type B CY
210.2500 Backfill Structure Type B TON
department will pay for the Backfill Structure bid items as spe cified in 209.5 for Backfill Granular except; if the contractor substitutes type A for type B material as allowed under 210.2 , the department will pay at the contract unit price for Backfill Structure Type B.
Effective with the December 2018 Letting 108 2019 Standard Spec ifications Section 211 Preparing the Foundation
211.1Description
foundation to a condition suitabl e for constructing and supporting a subbase, base, or surface course. Perform the work described in this section whether or not the c ontract contains the applicable Prepare Foundation bid items.
supporting subbase, bas e, or surface course. 211.2 (Vacant)
211.3Construction
211.3.1 General
required alignment and cross-section with equipment and methods adapted for the purpose. After shaping and compacting, provide a smooth foundation, at require d density, and at the proper elevation and contour, to receive the next course.
stability or density, scarify the area forming the foundation t o a uniform depth.
similar to those existing in t he foundation. Excavate and remov e high places to the required lines, grade, and section.
characteristics of a stabilized foundation by minimizing cutting into, or filling ov er the stabilized foundation, provided these adjustments do not impair the riding qualities, drainage, or appearance of the finished pavement or cause , in effect, a deviation from a g rade established by appropriate municipal ordinance.
course constructed. 211.3.2 Earth Subgrade
prepare or restore the foundation by removing vegetation; excavating and removing materials of any nature encountered above the required elevations; filling depre ssions occurring below the required elevations; and smoothing, shaping, and compacting the subgrade to the required grade, section, and density.
the subgrade to the required li nes, grade, cross-section, and u niform density. Remove stones over 6 inches in greatest dimension en countered during the operations.
presume that the previously com pleted work conforms to the requirements under this section. 211.3.3 Foundation for Non-Rigid Base
to the required grade, cross-section, and density. Shape and co mpact the foundation for the full width of the roadbed, to the required lines, grade, cross -section, an d density for at least 1000 feet in advance of base laying operations. Unless specified otherwise, uniformly compact the foundation to not less than the density for st andard compaction of the partic ular material existing in the foundation. Maintain the prepared foundati on ahead of the base laying operations in a smooth condition and at not less than specified density. Remove any ruts or surface irregul arities produced by hauling or other equipment or other traffic. Corre ct soft or yielding areas, holes, or other defects that occur due to traffic, hauling, poor drainage, u nstable materials, or from an y other cause before placing the base. Remove snow or ice, if any, from the foundation before placing the base.
designed specifically for trimmi ng foundations. The machine sha ll utilize automatics ensors to trim to the required grade and cross-section. If trimmed material consi sts of crushed aggregate, salvage and use this material in the aggregat e base for shoulder constructi on.