Effective with the December 2018 Letting 212 2019 Standard Spec ifications Section 502 Concrete Bridges
502.1Description
502.2Materials
502.2.1 General
modified for class I structure concrete in 715. Provide QMP for class I structure concrete as specified in 715.
materials for hardware incorporated into the structure. Repair cuts and other damage to galvanized or epoxy coatings according to ASTM A780. Do not use galvanized hardwa re where it is in contact with weathering steel. 502.2.2 Concrete Composition
high early strength concrete.
contract requires it, or if the engineer allows t he contractor, in writing, to use high early strength concrete to expedite the work.
502.2.3 Falsework
Use material that is in good condition, sound, and free from de fects that might impair its strength. Use reasonably straight piling capable of withstanding pile driving .
502.2.4 Forms
engineer will not require the use of new, unused material. Use material in good condition, of adequate strength, and of a shape suitable for the purpose intended. 502.2.5 Waterstops
rubberized membrane waterstops. Use polyvinyl chloride waterstops that are a dense, homogeneous material, free from holes and ot her imperfections, extruded fro m an elastomeric plastic compound. If using PVC waterstops, conform to the Corps of Engineers' Specif ication CRD-C 572.
waterstop products. Use membrane with a minimum thickness of 60 mils. 502.2.6 Concrete Curing Compound
dye, except as modified in 501.2.9 for testing. 502.2.7 Preformed Joint Filler Revise 502.2.7(1) to include foam expansion joint materials. This change was implemented in ASP 6 effective with the December 2017 letting.
502.2.8 Preformed Elastomer ic Compression Joint Sealer
polyurethane and hydrocarbon solven t mixture with the following physical properties:
Effective with the December 2018 Letting 213 2019 Standard Spec ifications Average weigh t per gallon ..................................... ............................................................... .... 7.2 to 8.8 pounds Solids conten t percent ........................................ ............................................................... ... 72 to 74% by weight Adhesive to remai n fluid from ................................. ........................................................................... 5 F to 120 F Film strength ( ASTM D412 ) ............................................................. ....................................................... 120 0 psi Elongation .................................................... ............................................................... ................................. 350%
engineer will reject any lubricant-adhesive not used within 9 m onths of manufacture.
compatible with the seals and t he concrete, and is relatively u naffected by the normal moisture in the concrete.
trademark, lot number, and manufacture date.
salt, and other materials spilled on or applied to the surface.
depressed below the ed ges of the installed sealer. At the joints maximum opening, the minimum unit pressure on the sides of the joint sealer shall be 3 psi.
length determinations of the seal after installing in the pavem ent joints.
number, and the manufacture date. 502.2.9 Non-Bituminous Joint Sealer
T, and either single-componen t typeS, or multi-component type M. 502.2.10 Hot-Poured Elastic Joint Sealer
502.2.11 Crack and Surface Sealers
- Crack sealer: Low Viscosity Crack Sealers for Bridge Decks li st. - Protective surface treatment: C oncrete Protective Surface Tre atment list. - Pigmented surface sealer: Cur e and Seal Compound for Non-traf ficked Surfaces for Structural Masonry list. 502.2.12 Adhesive Anchors
studs, nuts, and washers. Ensure that galvanized materials are either hot dipped according to ASTM A153 supplemented by ASTM F2329 or mechanically zinc coated according to ASTM B695. If the plans show using reinforcing bars, use grade 60 bars conforming to AASHTO M31 and to 505.2.
anchors. Do not use adhesive anchors in overhead applications w ith sustained tensile loads. 502.2.13 Clear Protective Coating
MATERIAL MINIMUM PERCENT BY WEIGHT Vinyl resin[1] ............................................................................................................................. ...................... 25.0 Methyl ethyl k etone solv ent ................................... ............................................................... ......................... 37.0 Toluene so lvent ............................................... ............................................................... ............................... 37.0 [1] Use resin of an engineer-approved vinyl chloride-acetate copol ymer containing 86 percent vinyl chloride and 14 percent vinyl acetate. Ensure a viscosity of 250-500 centipo ises for a 22 percent by weight solution or resin in a solvent, consisting of equal parts of methyl iso-butyl ket one and toluene at 77 F. COATING PROPERTY Weight per gal lon at 77 F ..................................... ............................................................... . 7.6 pounds minimum Viscosity a t 77 F ............................................. ............................................................... ........... 60-70 Krebs units Color ......................................................... ............................................................... .............. Clear and colorless Drying time ................................................... ............................................................... ........... 1/2 hour maximum
Effective with the December 2018 Letting 214 2019 Standard Spec ifications 502.3 Construction 502.3.1 General
not slip-form parapets unless the department explicitly allows by special provision. 502.3.2 Falsework 502.3.2.1 Detailed Plans
and computations for falsework, as specified in 105.2 , and place on file. If t he engineer re quests, submit 2 additional copies of p lans for review. Revise the plans as the engineer directs. Understand that whether or not the engineer requests submission of these plans or concurs in the use of the submitted or corrected plans, t he contractor is responsible for obtaining satisfactory results. 502.3.2.2 Design
allowance of not less than 10 pou nds per square foot of horizon tal projection of forms; and must also provide the necessary rigidity and support for the loads withou t appreciable settlement or deformation. Consider the potential effects of high wind and high water in t he design. 502.3.2.3 Erection
ample quantity of falsework p iling to support the falsework unl ess there is firm foundation material for the support of mud sills that i s not subject to undermining or softening. Construct mud sills of a size and thickness to support the load at the soil’s safe bearing va lue. Generally, found mud sills only on rock, firm sand, gravel, or very firm, silty, sands or clays in their natural beds. Place mud sills founded on well-compacted slopes of berm fills or natural slopes on ben ches, with the edge o f the sill not closer than one foot from the intersection of the bench and the surfac e of the slope, except if the engineer allows placing sills on slope paving. The safe design bearing v alue for foundation material, other than rock, under mud sills shall not e xceed 2 tons per square foot. Unless supporting the excavation for footings adequately wi th sheeting, place the edge of the falsew ork sill no closer than 4 feet from the excavation edge.
contractor shall not strut the fa lsework to columns, unless fou nding the column on rock or supporting by piling.
shims, or jacks, the specified per manent camber plus a construction camber covering allowance for settlement. Construct slabs and gi rder spans to provide a perma nent camber as the plans show.
one foot under the edge of the exis ting structure and make the existing structure bear on the falsework by driving wedges between the falsework and the forms.
necessary to preclude rotation o f the exterior girders if suppo rting the deck overhang by knee braces bearing against the ex terior girders.
bracing or stabilization necessary to prev ent girder rotation a nd overhang settlement.
requirement for bracing or stab ilizing the exterior girders.
horizontal and vertical clearanc e for rowboats and small powerb oats to pass. If building falsework over a highway or street used by traffi c provide a minimum clearance , unless the plans show otherwise or special provisions specify ot herwise, of 22 feet horizontal and 13 1/2 feet vertical. Ensure that no part of the falsework protrudes into the clear areas reserved for water or highway traf fic. For signing, conform to plan details or contract provision requirements. 502.3.3 Forms 502.3.3.1 Detailed Plans
place concrete until all this w ork is complete. If the engineer directs, submit detailed plans and computations for forms to the engi neer for examination. Revise the plans as the engineer directs.
Effective with the December 2018 Letting 215 2019 Standard Spec ifications Understand that whether or no t the engineer reque sts submission of these plans or concurs in the use of the submitted or corrected pl ans, the contractor is responsi ble for obtaining satisfactory results. 502.3.3.2 Design
weighing 160 pounds per cubic foo t plus a live load allowance of not less than 10 pounds per square foot of horizontal projection of forms. Use substantial and uny ielding forms designed so that the finished concrete conforms to t he proper dimensions and contours. Design forms to account for vibration forces. 502.3.3.3 Erection
loads that occur due to constru ction operations. Construct and maintain forms to p revent warping and joint openings due to lumber shrinkage, and so they remain true to the lines designated until the concrete hardens sufficiently. F orms shall remain in place for the periods specified below in 502.3.4.
the work stopped until correction of the defects. If the engineer orders, the contractor shall remove and replace the concrete within the defective area at no expense to the department. 502.3.3.4 Timber Forms
the concrete. Unless specified otherwise, use triangular moldin g that measures 3/4 inch on the sides.
millwork. Make moldings, panel work, and bevel strips, straight and true, with neatly mitered joints, and design so that the finished work is true, sharp, and clean cut. Exercise special care to secure smooth and tight fitting forms, hold the forms rigidly to line and grade, and remove without injuring the concrete.
damaging the concrete. The maxim um draft shall equal one inch per foot.
correct alignment and location so that, after removing the forms, removal of the metal to a depth of at least one inch from the surface of the concrete does not injure the surface. Hold bolts or rods in place by attaching devices to the wales that develop the strength of the rod. Fill cavities left by removing bolts and rods with cement mortar conforming to 502.3.7.1 and leave a sound, smooth, and even surface uniform in color. If exposing the completed concrete, u se tie rods of a diame ter, or fitted with cones, or other means to provide cavities large enough to allow filling and finishing with cement mortar.
removes them while placing the concrete.
strength, rigidity, tightness, and smoothness of surface. Do no t reuse any split, w arped, bulged, or marred lumber, or use lumber with defects that may produce infe rior work.
access to forms for inspecting and working the concrete. 502.3.3.5 Metal Forms
loading. Use metal forms thick enough so they remain true to sh ape. Countersink bolt and rivet heads in the form face. Use clamps, pin s, or other connection devices designed to hold the forms rigidly together and to allow removal without injuring the concrete. Th e contractor shall not use metal forms that do not present a smooth su rface or line up properly. Exerc ise special care to keep metal forms free from rust, grease, or other foreign matter that tends to d iscolor concrete. 502.3.3.6 Clean Outs
provide adequate clean-out openings. Ensure forms are clean and entirely free from chips, dirt, sawdust, nails, wire, and other extraneous matter during concre te placement.
Effective with the December 2018 Letting 216 2019 Standard Spec ifications 502.3.3.7 Oiling and Wetting
with other engineer-approved bond -inhibiting materials that wil l not discolor or injuriously affect the concrete surface. Perform oiling before placing the reinforceme nt. Thoroughly wet forms with water immediately before placing concrete. 502.3.3.8 Lined Forms
underside surfaces of superstructures, except slabs between bea ms or girders, the outside surfaces of superstructures, and all railing and parapet surfaces.
other engineer-approved material to the engineer’s satisfaction . Submit samples, specifications, and other pertinent information on these forms to the engineer if r equested and secure the engineer’s permission to use the contemplated form lining.
of material used line forms to a minimum. Make splices in form lining material neatly and break joints with the form material.
satisfactorily produces the desired surface finish for the conc rete instead of lined forms. 502.3.3.9 Cylindrical Column Forms
and with adequate strength to supp ort the concrete. Ensure that the surfaces of the tube are waterproof with a treated interior surface that prevents adhesi on of the tube to the concrete and after finishing, does not leave protruding seams or fins. The tube sh all provide a smooth and true column surface, free from discoloration. 502.3.4 Removing Forms and Falsework 502.3.4.1 Removing Forms
requirements for falsework specified below in 502.3.4.2 . The contractor may remove all other forms 12 hours after casting concrete if t he concrete is sufficientlyse t to be self-supporting.
weather, use water, as the engi neer directs, to cool the concrete within the forms.
502.3.4.2 Removing Falsework
way that allows the concrete to uniformly and gradually take th e stresses due to its own mass.
weather, the materials used in t he mix, and other conditions in fluencing the concrete setting.
using the minimum requirements specified below:
slabs, beams, girders, a rches, or concrete slabs on steel or co ncrete girders in place according to the minimum requirements for equivalent curing days specified in 502.3.10.1. Except do not remove falsework from cast in place bridge slab decks or box girder spans until at least 7 days elapse, fo r deflection control, exclude days that the concretes urface was subjected to tempera tures below 40 F.
approval, when the tests of cylinders show a concrete compressi ve strength of not less than 2000 psi for spans 12 feet or less; and not l ess than 2500 psi for spans ove r 12 feet. Except, do not remove falsework from cast-in-place bridge slab decks or box girder spans until at least 7 days elapse, fo r deflection control; exclude days that the concretes urface was subjected to tempera tures below 40 F.
sections for determining span length for falsework removal.
average test results for the 2 cylinders to determine complianc e, except that both cylinders must be no less than 10 percent below the requ ired strength. Cure the cylinders under conditions that at best equal the most unfavorable conditi ons for concrete sampled that the cylinders represent.
Effective with the December 2018 Letting 217 2019 Standard Spec ifications (6) Remove falsework piles down to at least 24 inches below stream bed or finished ground line. Remove temporary mud sills and footings.
until the concrete in an entire unit of continuous span cures f or the required time. If providing a longitudinal joint in the roadwa y of any one span, do not remov e the falsework from any portion of the span until the entire span cures for the required time. 502.3.5 Handling and Placing Concrete 502.3.5.1 General
placement preparations.
site to complete the pour. Use equipment that is adequate for t he work and in first-class working order.
rigidly support in the correct position all bar steel reinforcement extending into a subsequent pour before placing the first concrete in a given pour, unless the plans show otherwise. Complete adjacent pile driving and other operations detrimental to freshly placed concrete before placing concrete.
matter from the forms interior. C lean the contact surfaces of s tructural steel members embedded in the placed concrete to ensure they are free from oil, grease, loose rust scale, or other materials that would affect the bond between the concrete and the steel.
the engineer finds any defective concrete section, remove and r eplace it, as the engineer directs, at no expense to the department.
concrete ingredients occur. Provide enough chutes, troughs, or pipes to carry the concrete up at a uniform level without shifting them. Keep chutes, troughs, belts, and pipes clean and free from coatings of hardened concrete. Discharge water used for flushin g away from the concrete in place.
chutes, troughs, pipes, belts, and buckets shall not exceed 4 f eet.
work. Arrange the equipment so tha t any resulting vibrations do not damage freshly placed concrete. Operate the pump in a way that p roduces a continuous stream of concrete without air pockets. After pumping is complete, if using the concrete remaining in the pip eline, eject it so there is no concrete contamination or ingredients sep aration. After this operation, thoroughly clean the equipment.
from the flexible hose at the end of the boom shall be higher than the lowest point of the flexible hose. If using an extended boom, the contractor may lay part of the f lexible hose on the deck. If completely suspending the flexible hose fr om the boom, tie the discharge e nd of the flexible hose back toward the end of the rigid boom to form a partial loop. The engineer may approve alternate methods if the contractor can demonstrate that the air loss in the concrete created by the pumping process does not exceed 1.0 percent in any boom orientation.
conveying, or placing concrete.
retaining walls over 5 feet in height, with the exception of ca st in place concrete piles and walls less than 10 inches thick, deposit concrete through sheet metal or o ther engineer-approved pipes. Assemble these pipes in sections to facilitate adjusting outlets to proper heights during pouring operations. The distance from t he bottom of these pipes to the point of deposit shall not exceed 4 feet at any time.
within 2 feet of the point of deposit unless they end in vertical downspouts that extend to within 4 feet of the point of deposit. Equip steep chutes with baffle boards or assemble them in short lengths that reverse the direction of movem ent. The contractor shall not use long chutes for conveying concrete from the mixing plant to the forms.
Effective with the December 2018 Letting 218 2019 Standard Spec ifications (15) Place concrete in continuous hor izontal layers approximately 12 inches thick, except that the engineer may allow increasing this thickn ess to 24 inches. Place each la yer in a continuous pour and consolidate before the concrete i n the preceding layer takes in itial set.
case of an emergency, place construction joints at the engineer ’s direction. Use shear keys or inclined reinforcement at necessary points to transmit shear, or bond th e 2 sections together.
design.
as possible, to work the coarse aggregate back from the face, a nd to force the concrete under and around the reinforcement bars wi thout displacing them. Also, tr y to prevent spattering the forms or reinforcement bars so that the sp attered concrete does not dry or harden before incorporating into the mix. Clean foreign material from reinforcement bars before the succeeding pour.
openings in forms for removing any accumulations, as the engineer directs.
projecting reinforcement.
for structures by vibrating unless using other methods the engi neer finds satisfactory. Use vibrators capable of operating at frequencies sufficient to achieve thoro ugh and uniform consolidation, but at not less than 7000 impulses per minute. Make available at least one spare vibrator, in working order and of sufficient frequency, on the wo rk site before pouring concre te.
Perform this procedure at enough locations and for as long as n ecessary to uniformly and thoroughly consolidate the entire weight of fresh concrete without causing aggregate segregation, or forming localized areas of mortar.
vibrator penetrates through each successive layer and sufficiently into the preceding layer to uniformly blend the 2 concrete layers together.
that harden so that they are no longer plastic under vibration. The contractor shall not use the vibrator to transport, or to flow , the concrete within the forms to the extent of causing segregation.
concrete, along form surfaces and in corners and locations impo ssible to reach with the vibrator.
at the work site to the engineer’s satisfaction. 502.3.5.2 Substructures
forms and fill the entire exca vation with concrete, if the mate rial type encountered in excavation for structures allows placing concrete for footings wholly or in part without forms, and if the engineer approves.
show otherwise. Allow the concrete to set at least 12 hours bef ore placing the concrete in the cap, cross girder, or superstructure.
retaining walls, and abutments by placing weep holes in conjunction with the construction specified in 206.3.12 . Discharge the drainage water th rough the abutment, the wall o f the culvert, or through the retaining wall in a manner and at locations that do not cause d iscoloration of exposed masonry surfaces. Form weep holes and, i f necessary, fit with suitable screens or gratings to protect the intake against clogging. Constructing we ep holes the plans show is inc idental to the work.
502.3.5.3 Depositing Concrete Underwater
maximum mix water allowed for that grade.
Effective with the December 2018 Letting 219 2019 Standard Spec ifications (3) For concrete deposited underwate r, place it carefully in a compacted weight in its final position using a tremie. The tremie consists of a tube that has a diameter of no t less than 10 inches and constructed in sections having flanged couplings fitted with gaskets. The trem ie support shall allow free movement of the discharge end over the entire work surface and allow its ra pid lowering if neces sary to choke off or retard the flow. Keep the dischar ge end sealed at all times and the tremie tube full to the bottom of the hopper. If dumping a batch into the hopper, raise the tremie sl ightly, but not out of the concrete at the bottom, until the batch discharges to the bottom of the hopper. Then stop the flow by lowering the tremie. Ensure a continuous unint errupted flow until the work i s complete. The contractor may use a tremie equipped with a suitable mechanical seal or valve at the discharge point instead of the open tube tremie, if the engineer appr oves of the design, method of operation, and control of the device.
deposit point. The contractors hall not place concrete in runni ng water. Ensure watertight formwork.
placement stages. Accomplish this by either placing the concret e layers deep enough to accommodate satisfactory tremie operation, while ensuring that the previously layer does not take initial set by pouring at a rat e sufficient to raise the concrete level between 1 1/2 to 2 feet per hour; or by placing the concrete full depth in one continuous operation and completing the work to grade progressively from one end of the coffe rdam to the other.
underwater concrete by pumping, if the engineer approves.
before the concrete hardens and is strong enough to withstand t he hydrostatic pressure.
proposed substructure units by scraping, chipping, or other mea ns. 502.3.5.4 Superstructures
is required at time of placement, unless the engineer specifically allows or requires in writing. Except for rigid frame bridges, remove the forms for the substructure units that support any proposed superstructure before placing the superstructure.
replacement of honeycombed concrete at no expense to the department.
is released for that superstructure unit. The contractor may pl ace those portions o f the railings directly attached to substructure units w hile the falsework is in place.
or pre-stressed girder structures after 48 hours following deck placement, provided it uses no heavy equipment on the deck and it properly cures the deck adjacent t o the pours.
fastened them before placing the concrete.
on its supports. 502.3.6 Joints 502.3.6.1 General
joints are those joints that pro vide for movement by sliding or by deflection. Contraction joints are those joints that provide for ac commodating movement resulting from contraction, and control cracking.
show, except upon the engineer’s written authorization. If cons tructing joints not as the plans show, but required due to emergency, use shear keys or inclined reinf orcement at locations necessary to transmit shear, or to bond the 2 sections together.
show otherwise, make joints nor mal to the forms. Provide bulkhe ads for all except horizontal joints. Ensure that joints are true to alignment and uniform in width.
Effective with the December 2018 Letting 220 2019 Standard Spec ifications (5) If the plans show, seal expansion joints with a hot-poured ela stic joint sealer, conforming to 502.2.10. Seal contraction joints with a non-bituminous joint sealer conf orming to 502.2.9 . 502.3.6.2 Construction Joints
insert and remove the template that avoids chipping, breaking, or damaging the concrete.
matter from the previously set c oncrete surface and keep the su rface saturated with water until the new concrete is placed. Immediat ely before placing the new conc rete, draw forms tightly against the previously set concrete. 502.3.6.3 Expansion Joints 502.3.6.3.1 Preformed Joint Filler
concrete. Take special care to p revent displacing the joint fil ler during concrete placing and to prevent forming concrete fins under or between the sections of material . Do not assemble a series of small pieces of joint filler to produce a shape that could be cut fro m a single piece. Edge or chamfer exposed concrete edges adjacent to prefo rmed fillers, as the plans show . 502.3.6.3.2 Preformed Elastomeric Compression Joint Sealer
a lubricant-adhesive.
matter immediately before inst alling the seal. The engineer will direct the method of cleaning the joints.
and replace any seal damaged du ring installation with an undama ged seal. Remove and reinstall any seal improperly positioned in the joint at the proper elevation .
installation. Measure each seal b efore and after installing as a check against stretch. Remove and reinstall any installed seal sho wing more than 5 percent stretc h.
groove. Use a lubricant to facilitate installation and to cover both sides of the seal over the full area in contact with the sides of the joint. The contractor may apply t he lubricant to the joint faces, or the seal, or both. Install the seals in a highly compressed state and ensure the top of the seal is below the pavement surface by approximately 1/8 inch but not more than 3/ 8 inch. Install the seal in one piece, without field or factory splicing, for the full length of each transverse joint.
502.3.6.3.3 Expansion Device
will not allow welding in the steel extrusion’s internal sectio n where the neoprene ex trusion is located. Weld splices conforming to the following: For steel: AWS D 1.5, Bridge Welding Code. For stainless steel: AWS D 1.6, Structural Welding Code - Stain less Steel. Revise 502.3.6.3.3(3) to require an inspector from the c ontractor's current field welding plan described in (DT2337).
1 . Designate an inspector listed in the current contractor field w elding plan described in department form DT2337.
in the permanent project record.
that all surfaces are dry, free from dirt, grease, and contamin ants before installing the neoprene extrusion and cover or fill this internal section before placin g concrete, to preve nt concrete from entering. 502.3.6.4 Waterstops
polyvinyl chloride waterstops. Make the field splices for rubbe rized membrane or polyvinyl chloride
Effective with the December 2018 Letting 221 2019 Standard Spec ifications waterstops watertight. Install r ubberized membrane waterstops a s specified for rubberized membrane in 516.3.3 . Install polyvinyl waterstops as the plans show.
sufficiently strong to w ithstand that force. 502.3.7 Surface Finish of Concrete 502.3.7.1 General
within less than one inch of the concrete sur face and does not injure the concrete surface. The contractor shall not burn off r ods, bolts, or other metal devices. After removing the ties, roughen the opening and remove concrete containing any oil.
honeycomb spots with water and carefully point with a cement an d fine aggregate mortar mixed in the same proportions as the concrete being treated and of as dry a consistency as possible to use. For exposed surfaces, add as much whit e cement as necessary to prov ide a mortar the approximate color of the concrete. Use mortar in pointing that is not more than one hour old.
depressions, and honeycomb areas and apply a sack rubbed or rub bed surface finish as soon after removing the forms as weather and curing conditions allow. 502.3.7.2 Ordinary Surface Finish
vibrators or spading implements. Force coarse aggregate from the surface, and thoroughly work the mortar against the forms to produce as smooth a finish as possi ble, free from water pockets, air bubbles, and honeycomb.
irregularities. If the engineer det ermines the final surface is not satisfactory and that an ordinary surface finish was not provided, apply a rubbed surface finish conforming to 502.3.7.3 to the affected exposed areas. There is no requirement to extend the rubbed surface finish into nondefective areas solely to obtain a uniform texture. 502.3.7.3 Rubbed Surface Finish
brick immediately after removing the forms. Begin by moistening the surface with water and then immediately rubbing it with the carborundum brick, using light pressure and a circular motion. Continue rubbing until filling air holes and small depressions and a thi n, uniform coating of mortar is on the surface and until obtaining a smooth surface, free from lumber marks and irregularities.
approves.
material as specified in 502.3.8 .
502.3.7.4 Float Surface Finish
excess with a wooden template, forcing the coarse aggregate bel ow the mortar surface. After striking off the concrete, work the surfac e thoroughly with a wooden flo at. Before this last finish sets, lightly stripe surfaces finished this way and exposed in the finished w ork with a fine brush to remove the surface cement film and leave a fine-grained, smooth, but sande d texture.
502.3.7.5 Sack Rubbed Surface Finish
and irregularities as specified in 502.3.7.1 and 502.3.7.2 .
of burlap and mortar. Use mortar made of one part cement and 2 parts, by volume, sand passing a
Effective with the December 2018 Letting 222 2019 Standard Spec ifications No. 16 sieve, mixed with suffici ent water to provide a consiste ncy equal to that of thick cream. Use the same type and brand cement as used in the concrete. If necessar y, blend white cement into the cement to match the surrounding concrete surface.
but not wet. Thoroughly rub the mo rtar over the area with a rubber float or wad of burlap, filling pits. While the mortar is still plasti c in the pits, rub the surface with the rubber float or burlap using a dry mix of the above proportions, removi ng excess plastic material and placing enough dry material in the pits to stiffen and solidify the mort ar, then finish the mortar fillings flush with the surface. At the end of the rubbing, no mortar or materials hall remain on the surface othe r than that within the pits.
and texture, except for the difference in texture between the f illed voids and the remainder of the surface. 502.3.7.6 Substructures
surfaces of parapets built integrally with substructure units t he same surface finish specified for similar work on superstructures in 502.3.7.7 . Rubbed or special surface finish is not required for any formed faces of substructure units unle ss the plans or special provisi ons require, or as specified in 502.3.7.2 for applying a rubbed surface finish.
tops of piers with a wooden floa t as specified for float surfac e finish. Before this last finish sets, steel trowel the entire area. If finishin g areas to receive bearing p lates, secure a true plane at the correct elevation. 502.3.7.7 Superstructures
well as to exposed side surfaces of superstructures, including the outer face of outside pre-stressed girders as specified in 503.3.3.4 , unless the special provisions specify otherwise.
unless the plans or special provisions require it, except if, t he engineer determines the sack rubbed finish provided is unsatisfact ory, then the contractor shall ap ply a rubbed surface finish conforming to 502.3.7.3 to the affected exposed areas.
completed structure with a woo den float as specified for float surface finish. Before this last finish sets, steel trowel these areas and then brush them. 502.3.7.8 Floors
Deliver the mixed concrete at a uniform rate to provide a conti nuous placing operation for each pour section. Handle and place the co ncrete by methods and equipment that minimize segregating the ingredients. Deposit it as clos ely as possible to its final pos ition without forming piles and so that it requires a minimum of rehandling.
grade, section, and surface tolerance. Uniformly consolidate th e concrete by internal vibratory methods as specified in 502.3.5.1 , except that, the contractor may use a vibratory screed for consolidating and finishing in conjunction with internal vibration. Operate the internal vibrators or the vibratory screed, or both, in a way that avoids over-vibration.
finishers.
mounted on wheels that ride on re movable tracks or rails and is equipped with the necessary screeding apparatus to strike o ff and finish the concrete to re quired crown and grade. It shall have one or more power-driven oscillating , rotating or vibratory screeds . The screeds may suspend from the machine either transversely or longitudinally with the bridge c enterline, except as required for skew angles of 20 degrees or greater. Use a finishing machine capable of propelling itsel f both forward and backward to allow repeated passes of the screed in order to cor rect surface irregularities. Adjust its screed or screeds and operate in manner that finishes the concr ete to required grade and crown and requires a minimum of cutting or filling in any subsequent floa t-finishing operations.
and ensure they adjus t to allow for settlement under load. If t he rail supports are located in the
Effective with the December 2018 Letting 223 2019 Standard Spec ifications concrete, ensure their removal without disturbing the concrete, or partially remove so that no piece remains less than 2 inches below the finished concrete surface. Remove these supports, fill the resulting holes with concrete, and finish flush with the deck c oncrete before it hardens.
finishing machine a t the correct grade and entirely free of the floor or deck area.
degrees or greater, operate the finishing machine so that its l ongitudinal axis is within 20 degrees of the centerline of bearing of the substructure units. Make trans verse screeds parallel to the longitudinal axis of the machine.
crown and grade in the finished floor. The contractor may use v ibratory or nonvibratory type screeds that operate on forms or temporary guides set and maintained at the required elevation. Use sectioned, temporary guides that remain rigid an d unyielding un der screed operation and, if located within the pour limits, can be removed as the work progresses. If using vibratory screeds to supplement required internal vibration, operate them so they do not over vibrate the concrete.
equipment to the grade an d section needed to i nsure proper drai nage.
items.
float the surface as needed to produce a uniform surface.
work laitance, surplus water, and inert material off the floor and make it smooth. Test for smoothness by dragging the entire floor surf ace with a 10-foot straightedge as specified in 415.3.6.1 for straightedging concret e pavement. Use bridges to facilitate str aightedge operations on pour sections wider than 2 lanes. Revise 502.3.7.8(14) to require transverse tining for bridge decks unless specified otherwise. This change was implemented in ASP 6 effective with the December 2017 letting.
designed for speeds of 40 mph or greater as specified in 415.3.8.3 , except make the tining 1/8 inch in depth and do not perform tining within 12 inches of gutters. Th e contractor may apply a broom finish, described below, instead of the ar tificial turf drag finish req uired before tining. The contractor may perform tining manually, if it obtains a finish satisfactory to the engineer. Perform tining within 20 degrees of the centerline of bearing of the su bstructure units on bridge decks havi ng skew angles of 20 degrees or greater.
designed for speeds of less than 40 mph as specified in 415.3.8.2 or provide a broom finish. If providing a broom finish, draw the broom transversely across the full width of the pavement with adjacent strokes slightly overlapping. Perform brooming to produce uniform corrugations and approximately 1/8 inch in depth. C omplete brooming before the c oncrete hardens and this operation tears or roughens the surface. Bro oming shall provide a surface free from rough or porous areas, irregularities, and depressions that result from improper broom handling. Furnish br ooms of a sufficient quality, size, and construction, and operate them to produce a surface finish the engineer approves. Provided the contractor obtains satisfactory re sults, the engin eer will allow manual brooming instead of mechanical brooming.
direct corrective grinding without authorization from the depar tment’s bureau of structures.
previously placed concrete, duri ng the period necessary for the concrete to achieve sufficient strength to preclude damage from contract or's operations on the unprotec ted reinforcement.
concrete, and furnish bridges, i f necessary, to perform work op erations that follow the screeding operations.
Effective with the December 2018 Letting 224 2019 Standard Spec ifications 502.3.8 Curing 502.3.8.1 General
develops sufficient strength to open it to service. Cure concre te by one or a combination of the following methods:
concrete placement operations. 502.3.8.1.1 Impervi ous Coating Method
uniform coating of curing compound conforming to 502.2.6. Seal moisture in the concrete by applying a continuous water-impermeable film on exposed concrete surfaces.
consistency and dispersion as applied.
does not run or sag.
membrane curing material in 2 applications at the rate of not l ess than one gallon per 300 square feet.
specified in 502.3.10 , recoat the affected area immedi ately. If removing forms befor e the concrete conforms to the opening criteria specified in 502.3.10 , coat newly exposed surfaces within 30 minutes after form removal. 502.3.8.1.2 Impervious Sheeting Method
exposed concrete surfaces with one or a combination of the foll owing impervious sheeting materials:
polyethylene-coated burlap and pl ace with the uncoated side aga inst the concrete.
the material securely in place b y weighting or an alternate anc horing method. Provide a minimum of 12 inches overlap between adjacent pieces of sheeting. Place th e sheeting material so that it is in direct contact with exposed concrete surfaces.
502.3.10 . If temporary removal is required, to remove forms or perform other necessary work, re-cover exposed concrete as quickly as practicable, or as the engineer directs.
502.3.8.1.3 Continuous Wet Cure Method
or fog the exposed surfaces of t he concrete to keep it moist un til the concrete conforms to the opening criteria specified in 502.3.10 . Apply a layer of thoroughly wetted burlap to protect the surf ace from the mechanical impact of the spray.
suspend the spraying or fogging. R emedy the conditions causing erosion or switch to another cure method that does not involve continuous wet cure.
wet curing and switch to another curing method.
Effective with the December 2018 Letting 225 2019 Standard Spec ifications 502.3.8.1.4 Alternate Curing Methods
Supply technical specifications , test results, or performance r ecords to support its proposed alternative method, if the engineer requests. 502.3.8.2 Curing Requirements 502.3.8.2.1 General
after form removal and surface finish application. If the surface is dry, wet the concrete thoroughly with water and apply the curing compo und just as the surface film of water disappears. Apply the second application as soon as the first application sets.
other concrete, or to surfaces being waterproofed, or to which applying sealants. Ensure that steel reinforcement, anchors, watersto ps, and similar devices are fre e of compound before placing concrete.
Use other allowed curing procedures before applying the surface finish.
completing curing with wetted burlap or polyethylene-coated bur lap, in order to allow uniform and continuous finish application. P rovide at least 4 hours of an e ngineer-approved moisture cure to prevent the finish from sanding-out.
not waive the above requirements for moisture for curing. The c ontractor may use steam for heating and to produce an adequate supply of moisture within the enclosure.
502.3.8.2.2 Substructures
footings as specified in 502.3.8.1 or by submersion, if the enginee r approves. If necessary to re move wetted burlap to allow form setti ng, keep the exposed concrete surface thoroughly damp. 502.3.8.2.3 Decks
7 days with polyethylene-coated bu rlap or other coated material conforming to 501.2.9 . As soon as the concrete sets sufficiently to s upport the covering, place the c oated burlap with the coated side up; or perform an initial cure of the co ncrete by using wetted burlap for at least 12 hours and then apply the coated burlap to a thoroughly we tted concrete surface. Place ea ch strip or sheet of coated burlap so that it overlaps the preceding sheet by at least 12 inches. Secure the coated burlap covering in place. Ensure adequate moisture is present on the surface of the floor , wearing surfaces, or sidewalks beneath the curing material for the 7-day curing period.
following method. Begin curing the horizontal concrete surfaces by fogging within 15 minutes of finishing and tining. Apply the fog or fine water spray so that no water marks re sult and no mortar washes from the concrete surface . Keep the concrete surface continuously wet by fogging until applying the burlap strips to the finished concrete. Wet the bu rlap immediately afte r placement. During the first day, until placing the soaker hose system, keep the b urlap continuousl y wet. Through the remainder of the curing period, k eep the burlap continuously wet with soaker hoses hooked up to a continuous water source. Inspec t the burlap on a daily basis to ensure that the enti re surface is moist. If necessary, alter the soaker h ose system as needed to ensure the entire surface is moist. Do not use white polyethylene sheeting or p lastic coated burlap blankets. Continue moist curing at least 7 days. 502.3.8.2.4 Parapets
after form removal and surface finish application. Keep the bur lap thoroughly wet for at least 4 days; or by covering for the same period with thoroughly wetted polyethy lene-coated burlap conforming to 501.2.9 .
structure by one of t he following methods:
Effective with the December 2018 Letting 226 2019 Standard Spec ifications 1. Apply impervious coating cu ring material immediately after removing the forms and applying the required surface finish.
keeping the burlap thoroughly wet for at least 4 days.
502.3.9 Cold Weather Protection 502.3.9.1 General
prevent concrete freezing until it develops sufficient strength to conform to the opening criteria specified in 502.3.10 . Remove and replace frozen or frost damaged concrete at no exp ense to the department.
If the atmospheric temperature is below 40 F, preheat the inter ior surfaces of forms, all reinforcement, and the concrete surface adjac ent to the pour to 40 F or higher .
engineer allows otherwise, ensur e the temperature of the concrete does not exceed 120 F, or fall below 40 F during the protection period. 502.3.9.2 Mixing
80 F, unless otherwise directed.
502.3.9.3 Heating
the curing period by the impervious coating method or the imper vious sheeting method specified in 502.3.8 .
concrete to ensure a temperature of the forms and reinforcings teel of not less than 40 F. Ensure a reasonably uniform temperature throughout the enclosure.
in water inside the cofferdam. 502.3.9.4 Temperature Records
conditions that the concrete is subjected to. At a minimum, pro vide high/low thermo meters that retain the minimum and maximum temperature readings for each measureme nt period. Provide facilities suitable to the engineer to verify the temperature inside and o utside the insulation, and within the mass of the concrete at various l ocations in the unit. Make tem perature recordings at least every 24 hours. Make outside air temperature recordings at the same time making the recordings within the enclosure. Provide a copy of the temperature record to the engi neer at the close of each day's work. 502.3.9.5 Cessation of Heating or Cold Weather Protection
the enclosure to avoid a sudden temperature c hange of the new concrete. Make this decrease by loosening the forms and other ins ulating layers in a manner to allow the whole mass of concrete to gradually approach the outside air temperature at the end of th e curing period. Ensure the average rate of decrease does not excee d 5 F in any hour, or 40 F in any 24-hours, until reaching the outside air temperature. Allow the concrete surface to dry while equalizing the temperatures. 502.3.9.6 Bridge Decks
similar pours, according to the following requirements:
Effective with the December 2018 Letting 227 2019 Standard Spec ifications 1. Do not place concrete for br idge decks or other superstructure elements when t he national weather service forecast for the constr uction area predic ts temperatures to fall below 32 F within 24 hours, unless the engineer specifically allows or requires in writing.
the construction area predicts temperatures to fall below 20 F during the cold weather protection period. 502.3.10 Applying Loads to Concrete 502.3.10.1 Opening to Service 502.3.10.1.1 General
strength to open it to service . The engineer will use the same criteria to allow the opening of structural masonry concrete items to service as is used to allow the openi ng of bridge superstructures to traffic.
to construction and public traffic when the concrete attains a verified compressive strength of 3500 psi. Without compressive strength information, the engineer may allo w the contractor to open the affected structural masonry after the fo llowing minimum times as adjuste d for concrete surface temperature. APPLICATION EQUIVALENT CURING DAYS High early strength concrete 4 General purpose concrete: grade A 5 General purpose concrete: grades A-FA, A-S, A-T, A-IS, A-IP, an d A-IT 7
the daily average concrete surface temperature by taking the av erage of the high and low temperatures at the least favorable location of the affected co ncrete unit, as verified by the engineer, for each day. If this daily average concrete surface temperatur e falls below 60 F, then equivalent curing days accumulate at a reduced rate. Use the following gui delines to calculate equivalent curing days; for a daily average concre te surface temperature of:
502.3.10.1.2 Exceptions 502.3.10.1.2.1 General
complete and the strength or equi valent curing day requirements are met.
criteria as specified in 502.3.10.1.2.2 and 502.3.10.1.2.3 . The engineer may suspend or delay operations that injure the surfac e or otherwise damage the conc rete. Clean the surface before allowing any traffic to use the structure. 502.3.10.1.2.2 Substructures
immediately after dewatering t he cofferdam and preparing the su rface of the seal. Unless the engineer directs otherwise, the contract or may set the column and wall f orms on the day after placing the concrete in the footing; and may place the concrete in columns and walls after the concrete footing for the column or wall cures for at least 24 hours over 40 F.
502.3.10.1.2.2(1) , to concrete substructure units until the concrete in the unit cures for at least 48 hours. Do not apply loads to the beams of open-type substructur e units until after the required falsework support period. 502.3.10.1.2.3 Superstructures
decks that result from storing sm all articles, and operating co ncrete buggies and other necessary light equipment, if applied in a way that causes no injury to the con crete.
necessary to perform subsequent pours on that structure. Do not operate or park hauling equipment outside of the centerline of an ex terior girder until at least 24 hours after placing the parapet.
Effective with the December 2018 Letting 228 2019 Standard Spec ifications 502.3.10.1.3 Opening Strength 502.3.10.1.3.1 General
strength by one or a combination of the following methods:
conforming to the following criteria:
estimate compressive strength ba sed on test results of concrete of the same mix design placed adjacent to and under similar co nditions on the same project. 502.3.10.1.3.2 Compressive Strength Testing of Cylinders
strength as the average of compr essive strength test results fo r 2 cylinders. If the strength of a cylinder is less than 90 percent of the re quired strength , the engineer will reject the resulting average. Field cure cylinders under conditionss imilar to those prevailing for the structural masonry unit they represent. Fabricate cylinders according to AASHTO T23 and test the cylinders according to AASHTO T22. 502.3.10.1.3.3 Maturity Method
strength of cylinders from concre te incorporated into the work. Submit the maturity data to the engineer for approval before placi ng more concrete using that m ix design. Develop a new strength/maturity relationship every time the mix changes or if engineer verificati on cylinder strength varies more than 10 percent from the required opening strength when tested at the calibrated opening maturity.
curves, and maturity testing. Use a default datum temperature o f 32 F or use a mix-specific datum temperature determined according to Annex A1 of ASTM C1074 . Develop data points for the strength/maturity relationship up to 120 percent of the require d opening strength. Revise 502.3.10.1.3.3(3) to allow co ntractor determination of maturity pr obe placement based on their operations.
each 100 cubic yards of concrete placed under non-pavement bid items. The resulting maturity, after engineer verification, will apply to concrete on the same proje ct conforming to the following:
calibration curve currently in use on the project. The engineer will designate the sa mpling location for these verification cylinders. Pr ovide 2 cylinders for compressi ve strength testing and one with a data- encrypted sensor embedded in its c enter for maturity evaluation . Cast and cure these cylinders on-site as the engineer directs and conf orming to the requirements of ASTM C31 for field curing. Deliver the 2 compressive strength cylinders to the engineer after attaining 50 percent of their opening maturity. Notify the engineer promptly when t he instrumented cylinder rea ches the opening maturity so the engineer can perform verification testing as closely as possibl e to that opening maturity level. 502.3.11 Name Plates
lugs in the concrete. Except fo r survey benchmarks, do not atta ch other permanent p lates or markers to a structure. 502.3.12 Bridge Seat Protection
and any piers beneath transverse joints.
Effective with the December 2018 Letting 229 2019 Standard Spec ifications (2) Use the type of epoxy resin the manufacturer recommends for se aling exterior concrete surfaces, subject to the engineer’s approval.
the engineer directs otherwise.
below 60 F unless the engineer specifically allows.
loose material.
manufacturer’s written instru ctions. If no application rate is recommended, apply the epoxy at approximately one gallon per 100 square feet. 502.3.13 Concrete Crack and Surface Sealing 502.3.13.1 Crack Sealing
viscosity crack sealer. Conduct an initial crack survey with th e engineer within 7 days after wet curing is complete, or when the deck d ries enough to expose cracks req uiring sealing. Seal the cracks identified in the survey. Seal c rack areas only. Do not flood seal the deck unless the engineer allows as a part of overseeding with aggregate.
except as follows:
particles.
and subsequently applying surface sealer, before opening to public traffic. Seal additional cracks identified in the follow-up surv ey before applying protective surface treatment. 502.3.13.2 Protective Surface Treatment
and sidewalks After dec k crack sealing is completed, apply surf ace treatment to the top of new bridge decks. Do not apply to surfaces w here the contract requires sta ining or other treatment.
blast over the surface to remov e dust and any loose particles. Ensure that application equipment is clean inside before filling and that the equipment is functioni ng properly.
period has expired. Apply according to manufacturer recommendations, except ensure the concrete is surface dry for a minimum of 2 consecutive days before applying . Ensure that the crack sealer is dry to the touch before applying surf ace treatment. Apply at the manufacturer's recommended rate. If application in a single coat cau ses ponding, use two lighter co ats allowed to dry between coats.
not open the bridge deck to tra ffic until the surface treatment is dry enough to sustain traffic without causing damage to the surface treatment or creating a hazard to traffic. 502.3.13.3 Pigmented Surface Sealer
including parapets on abutment wings. Use gray sealer unless the contract specifies a different color. Do not seal surfaces where the contract requires staining or ot her treatment.
to remove dust and any loose par ticles. Ensure that application equipment is clean inside before filling and that the equipment is functioning properly.
recommended application procedures and coverage rate. If applic ation in a single coat causes running, use two lighter coats a llowed to dry between coats.
Effective with the December 2018 Letting 230 2019 Standard Spec ifications 502.3.14 Adhesive Anchors 502.3.14.1 General
before installing anchors. Do not install anchors before 21 days after concrete placement. Notify the engineer if reinforcement is encountered during drilling.
Follow additional cleaning procedures and temperature restricti ons the adhesive manufacturer recommends.
following the adhesive manufacturer's installation recommendati ons. Fill holes completely with adhesive.
- Installation by or under the direct supervision of an ACI/CRSI certified installer. - Field-verified by n on-destructive pullou t testing according t o ASTM E488 . 502.3.14.2 ACI/CRSI Certified Installer
is directly viewing installation of 2 or more anchors per insta ller. Submit department form DT1641 to the engineer certifying that anc hor installation conforms to th e contract.
procedures and may direct the c ontractor to perform pull-out te sting conforming to 502.3.14.3 . 502.3.14.3 Non-Destructive Pullout Testing
ASTM E488 for the first 3 anchors of each rebar size installed under the contract. Do not proceed with production installation without the engineer's approval. Do not test before 28 days after concrete placement.
to the embedment depth the plans show. Test anchors to a proof load of 80 percent of the anchor yield strength unless the pl ans show otherwise. If an anchor fa ils, modify installation procedures or use a different anchor system and retest.
placed during production insta llation whichever is greater. Pro vide an approximate installation schedule to the engineer and imm ediately notify the engineer if a test fails. The engineer will increase testing frequency by one perc ent for each failed anchor. Submit test reports and specification sheets prescribed under ASTM E488 to the engineer upon request.
testing procedures and may dir ect the contractor to perform additional pull-out testing. 502.3.15 Clear Protective Coating
temperatures lower than the manufacturer recommends.
backwalls and the ends of the body wall to remove dust and dirt .
concrete. Apply the coating at the rate of one gallon per 200 s quare feet. If the coating runs or sags when applied in one coat, apply t he material in 2 approximately equal coats of thickness. Apply the second coat within 10 minutes of the first.
starting steel erection, prote ct the above-mentioned areas from staining until applying the coating. Obtain the engineer's approval for the met hod of temporary prot ection.
502.4Measurement
502.4.1 General
accepted structure according to the contract provision for thos e bid items, in the units provided. All work included in the scope of the contract, but not listed as b id items in the proposal are incidental to the cost of the work.
Effective with the December 2018 Letting 231 2019 Standard Spec ifications 502.4.2 Concrete for Bridges
completed. The department will not measure work or material for forms, falsework, c offerdams, unless specified otherwise, pumping, bra cing, or other incidentals nec essary to complete the work as required in these specifications.
concrete beams projecting into concrete floor slabs from the vo lume of the floor slab.
displaced by the projection of c ast-in-place concrete piling in to the footing, pile cap, or abutment; and 0.8 cubic foot of volume for each linear foot of timber piling projecting into the footing, pile cap, or abutment. The department will measure this net quantity for payment.
material placed within the footing dimensions the plans show. 502.4.3 Concrete for Seals
department will only measure material the engineer orders, the plans show, or the contract specifies.
dimensions of the area and thickness of the seal the plans show , or the engineer orders. The department will deduct the volume displaced by piles, if any, f rom this quantity and the department will measure this net quantity for payment. If using cast in place c oncrete piling, deduct the actual volume displaced by the piling; and in the case of timber piling, deduct the quantity based on 0.8 cubic foot of volume for each linear foot of p iling projecting into or throug h the seal. 502.4.4 Preformed Elastomer ic Compression Joint Sealers
linear foot acceptably completed, measured along the centerline of the joint. 502.4.5 Expansion Devices
structure accept ably completed. 502.4.6 Surface Sealing
items by the square yard accept ably completed, measured as the net area treated with no additional area measured where re-sealing a fter applying pavement marking as required under 646.3.1.1 . 502.4.7 Adhesive Anchors
completed. 502.4.8 Clear Protective Coatings
quantity measured equals the actual number of gallons used to t reat the abutments and piers.
502.5Payment
502.5.1 General
items: ITEM NUMBER DESCRIPTION UNIT
502.0100 Concrete Masonry Bridges CY
502.0200 Concrete Masonry Bridges HES CY
502.1100 Concrete Masonry Seal CY
502.2000 Compression Joint Sealer Preformed Elastomeric (width) L F
502.3100 Expansion Device (structure) LS
502.3200 Protective Surface Treatment SY
10 Pigmented Surface Sealer SY
502.4100 - 4199 Adhesive Anchors (inch) EACH
502.4200 - 4299 Adhesiv e Anchors (bar) EACH
502.6500 Protective Coating Clear GAL
Effective with the December 2018 Letting 232 2019 Standard Spec ifications (2) Perform miscellaneous work tha t the plans show or the contract specifies, but not listed as bid items, as a part of and included in the c ontract price for other bid i tems. 502.5.2 Concrete for Bridges
falsework; for placing, finishing, curing, protecting, and heating concrete; for measuring concrete opening strength, including fabric ating and testing cylinders, and evaluating maturity; for treating joints, including sealing, providing preformed joint filler and waterpr oofing; for sealing de ck cracks identified in the initial crack survey; for providing bridge seat protecti on; and for providing nameplates.
material placed within the footing dimensions the plans show.
allowed under 502.2.2 , the contractor will bear the ad ditional costs associated with that substitution.
sealing additional deck cracks i dentified in the follow-up crac k survey at the fixed price of $3.00 per linear foot of crack acceptably sealed. The department willals o pay separately for traffic control required for the follow-up sealing operations. 502.5.3 Concrete for Seals
placing, curing, protecting, and pumping.
the department will pay for this work as extra work. 502.5.4 Preformed Elastomer ic Compression Joint Sealers
providing the seal, including lubricant-adhesive. 502.5.5 Expansion Devices
502.5.6 Surface Sealing
compensation for treating and sealing surfaces including surface preparation and color-matching as required. Resealing after pavement marking is incidental to the applicable pavement marking bid item under 646.5 . 502.5.7 Adhesive Anchors
for pullout testing including addi tional engineer-directed veri fication testing.
HS bid item as specified in 505.5 . 502.5.8 Clear Protective Coatings
temporary protection, and surface preparation.
Effective with the December 2018 Letting 233 2019 Standard Spec ifications Section 503 Prestressed Concrete Members
503.1Description
or other prestressed concrete members.
method, stress the reinforcing tendons initially, then place an d cure the concrete and release the stress from the anchorages to the concrete after developing spe cified concrete strength.
503.2Materials
503.2.1 General
incorporated into the finished structure. 503.2.2 Concrete
higher for a prestressed concrete I-type girder, extend 28-day strength requirements within 503 for that girder to 56 days.
girders. Base tests on 6-inch b y 12-inch cylinders, or 4-inch b y 8-inch cylinders, provided the engineer develops and approves a correlati on factor. Mold concrete cylin ders in steel or plastic molds. Cure concrete cylinders according to AASHTO T23, except cure the cyl inders with the member until release strength is obtained, then cure the cylinders according to AASH TO T23. Maintain laboratory facilities and equipment according to AASHTO M201. Make 3 cylinders for ea ch line of prestressed members poured and test each cy linder according to AASHTO T22. Calibrat e cylinder-testing equipment at least annually according to AASHTO T67. Average the strengths of the 2 cylinders with the highest test results for each line and use the average to determine compliance with the 28-day strength requirement. Ensure that neither of the 2 cylinders with the highest test results h as a strength less than 10 percent below the required strength.
prestressed units, before the 28-day test, if 2 successive laboratory tests on standard test specimens, cured continuously with and in the same manner as the units, in dicate compressive strength in excess of the required 28-da y strength. Test the 28-day strength cylin ders and record the results to maintain continuity of the contractor's quality control records.
fabricate and cure cylinders. Hav e an HTCP-certified ConcreteS trength Tester, working in a department-qualified laboratory, perform cylinder and core comp ression tests. Determine the compressive strength in psi fo r each cylinder according to AASH TO T22. Test each cylinder to failure. Use a compression machine that automatically records the date, time, rate of loading on a load vs. time plot, and maximum load for each cylinder. Include a printo ut of this information with the strength documentation for each cylinder tested. Notify the engineer imm ediately if concrete cylinder compressive strengths are less than the required 28-day strength. Keep neatly documented records of all cylinder testing on the day of the test and make them available to the engineer.
use non-air-entrained concrete. Use type I, IL, IS, IP, IT, II, or III cement. The contractor may replace up to 30 percent of type I, I L, II, or III cement with an equal weight of fly ash, slag, or a combination of fly ash and slag. Ensure th at fly ash conforms to 501.2.6 and slag conforms to 501.2.7 . Use only one source and replacement rate for work under a single bid item. U se a department-approved air- entraining admixture conforming to 501.2.2 for air-entrained concrete. Use only size No. 1 coarse aggregate conforming to 501.2.5.4 .
Water cementitious mat erial ratio, w/cm ....................... ............................................................... .... 0.45 or less[1] Cementitious mat erial content ................................. ............................................ 610-800 pounds per cubic yard Air content: Prestressed I- type girders .................................... ........................................................ 6.0 pe rcent maximum Other com ponents .............................................. ............................................................... ... 4.5 - 7.5 percent Slump ......................................................... ............................................................... .......... 8 inches maximum[2]