Effective with the December 2018 Letting 212 2019 Standard Spec ifications Section 502 Concrete Bridges
502.2.8 Preformed Elastomer ic Compression Joint Sealer
1.Use preformed elastomeric compression joint sealer conforming to AASHTO M297.
2.If installing the preformed join t sealer, use a lubricant-adhe sive that is a one-part moisture curing polyurethane and hydrocarbon solven t mixture with the following physical properties: Effective with the December 2018 Letting 213 2019 Standard Spec ifications Average weigh t per gallon ..................................... ............................................................... .... 7.2 to 8.8 pounds Solids conten t percent ........................................ ............................................................... ... 72 to 74% by weight Adhesive to remai n fluid from ................................. ........................................................................... 5 F to 120 F Film strength ( ASTM D412 ) ............................................................. ....................................................... 120 0 psi Elongation .................................................... ............................................................... ................................. 350%
3.Ensure the viscosity of the lubr icant-adhesive performs suitab ly with the application equipment. The engineer will reject any lubricant-adhesive not used within 9 m onths of manufacture.
4.Ensure the lubricant-adhesive consistency works well at the te mperatures the seals are installed, is compatible with the seals and t he concrete, and is relatively u naffected by the normal moisture in the concrete.
5.Deliver the lubricant-adhesive in containers plainly marked wi th the manufacturer's name or trademark, lot number, and manufacture date.
6.Use a joint sealer compatible w ith concrete, or steel and resi stant to abrasion, oxidation, oils, gasoline, salt, and other materials spill ed on or applied to the surface.
7.Shape the sealer so that in its compressed condition the top c enter of the exposed surface is depressed below the ed ges of the installed sealer. At the joints maximum opening, the minimum unit pressure on the sides of the joint sealer shall be 3 psi.
8.Mark the top surface of the s eal at one-foot intervals clearly , in a manner durable enough to make length determinations of the seal after installing in the pavem ent joints.
9.Mark shipping containers for se als clearly, with the manufactu rer’s name, the size of the seal, the lot number, and the manufacture date.
502.3.2 3 Erection
1.Build falsework on foundations adequate to suppo rt the load wi thout appreciable settlement. Drive an ample quantity of falsework p iling to support the falsework unl ess there is firm foundation material for the support of mud sills that i s not subject to undermining or softening. Construct mud sills of a size and thickness to support the load at the soil’s safe bearing va lue. Generally, found mud sills only on rock, firm sand, gravel, or very firm, silty, sands or clays in their natural beds. Place mud sills founded on well-compacted slopes of berm fills or natural slopes on ben ches, with the edge o f the sill not closer than one foot from the intersec tion of the bench and the surfac e of the slope, except if the engineer allows placing sills on slope paving. The safe design bearing v alue for foundation material, other than rock, under mud sills shall not e xceed 2 tons per square foot. Unless supporting the excavation for footings adequately wi th sheeting, place the edge of the falsew ork sill no closer than 4 feet from the excavation edge.
2.If supporting falsework by mud sills placed on paved, well-com pacted slopes of berm fills, then the contractor shall not strut the fa lsework to columns, unless fou nding the column on rock or supporting by piling.
3.Set falsework at the proper elev ation to produce, in conjuncti on with engineer-approved wedges, shims, or jacks, the specified per manent camber plus a construc tion camber covering allowance for settlement. Construct slabs and gi rder spans to provide a perma nent camber as the plans show.
4.If extending existing concrete b ridges, then extend the falsew ork and forms for the new construction one foot under the edge of the exis ting structure and make the existing structure bear on the falsework by driving wedges between the falsework and the forms.
5.If the plans show, brace and tie the exterior girders supporti ng bridge decks to the interior girders as necessary to preclude rotation o f the exterior girders if suppo rting the deck overhang by knee braces bearing against the ex terior girders.
6.If the plans do not show the abov e requirement, t he contractor shall determine the need for any bracing or stabilizat ion necessary to prev ent girder rotation a nd overhang settlement.
7.The contractor’s responsibility i ncludes obtaining satisfactory results whether or not the plans show a requirement for bracing or stab ilizing the exterior girders.
8.If building falsework over a s tream or lake subject to boating use, construct it to provide ample horizontal and vertical clearanc e for rowboats and small powerb oats to pass. If building falsework over a highway or street used by traffi c provide a minimum clearance , unless the plans show otherwise or special provisions specify ot herwise, of 22 feet horizontal and 13 1/2 feet vertical. Ensure that no part of the falsework protrudes into the clear areas reserved for water or highway traf fic. For signing, conform to plan details or contract provision requirements.
502.3.3 4 Timber Forms
1.Use forms for exposed surfaces made of dressed lumber, of unif orm thickness and make mortar-tight.
2.Fillet the forms with triangular molding chamfer strips at exp osed, sharp corners and at the edges of the concrete. Unless specified otherwise, use triangular moldin g that measures 3/4 inch on the sides.
3.Construct forms for railing, copings, and ornamental work to s tandards equivalent to first-class millwork. Make moldings, panel work, and bevel strips, straight and true, with neatly mitered joints, and design so that the finished work is true, sharp, and clean cut. Exercise special care to secure smooth and tight fitting forms, hold the forms rigidly to line and grade, and remove without injuring the concrete.
4.In forming copings, offsets, and recesses, give the forms suff icient taper to allow removal without damaging the concrete. The maxim um draft shall equal one inch per foot.
5.Use bolts or rods to hold forms in place. Construct metal appl iances used inside forms to hold them to correct alignment and location so that, after removing the form s, removal of the metal to a depth of at least one inch from the surface of the concrete does not injure the surface. Hold bolts or rods in place by attaching devices to the wales that develop the strength of the rod. Fill cavities left by removing bolts and rods with cement mortar conforming to 502.3.7.1 and leave a sound, smooth, and even surface uniform in color. If exposing the completed concrete, u se tie rods of a diame ter, or fitted with cones, or other means to provide cavities large enough to allow filling and finishing with cement mortar.
6.The contractor shall not use spr eaders for metal pipe, precast concrete, or rolled sections unless it removes them while placing the concrete.
7.Secure forms for exposed surface s to the studs or uprights with true horizontal joints.
8.If reusing forms or form lumber m aintain them in clean and goo d condition as to accuracy, shape, strength, rigidity, tightness, and smoothness of surface. Do no t reuse any split, w arped, bulged, or marred lumber, or use lumber with defects that may produce infe rior work.
9.If possible, daylight columnar fo rms at vertical intervals and with sufficient openings to allow free access to forms for inspecting and working the concrete.
502.3.3 8 Lined Forms
1.Use lined forms for the exposed surfaces of endwalls, substruc ture units, retaining walls, rigid frames, underside surfaces of superstruct ures, except slabs between bea ms or girders, the outside surfaces of superstructures, and all railing and parapet surfaces.
2.Ensure lined form surfaces completely contact the concrete fac ed with metal, plywood, composition, or other engineer-approved material to the engineer’s satisfaction . Submit samples, specifications, and other pertinent information on these forms to the engineer if r equested and secure the engineer’s permission to use the contemplated form lining.
3.Form lining material shall not bulge, warp or blister, or stai n the concrete. Keep the number of pieces of material used line forms to a minimum. Make splices in form lining material neatly and break joints with the form material.
4.The contractor may use forms constructed of metal, plywood, or other engineer-approved material that satisfactorily produces the desired surface finish for the conc rete instead of lined forms.
502.3.4 2 Removing Falsework
1.Do not remove falsework and form supports without the engineer 's approval. Remove supports in a way that allows the concrete to uniformly and gradually take th e stresses due to its own mass.
2.In determining the removal time of falsework, consider the loc ation and character o f the structure, the weather, the materials used in t he mix, and other conditions in fluencing the concrete setting.
3.The engineer may determine when to remove falsework or form su pports by using test cylinders or by using the minimum requirements specified below: 1. If not controlling field operations by cylinder tests, keep falsework supporting concrete in bridges, including slabs, beams, girders, a rches, or concrete slabs on steel or co ncrete girders in place according to the minimum requirements for equivalent curing days specified in 502.3.10.1. Except do not remove falsework from cast in place bridge slab decks or box girder spans until at least 7 days elapse, fo r deflection control, exclude days that the concrete s urface was subjected to tempera tures below 40 F. 2. If controlling field operations by cylinder tests, remove f alsework or form supports, with the engineer's approval, when the tests of cylinders show a concrete compressi ve strength of not less than 2000 psi for spans 12 feet or less; and not l ess than 2500 psi for spans ove r 12 feet. Except, do not remove falsework from cast-in-place bridge slab decks or box girder spans until at least 7 days elapse, fo r deflection control; exclude days that the concrete s urface was subjected to tempera tures below 40 F.
4.Double the length of the horizont al projection of cantilevered portions of piers, abutments, and similar sections for determining span length for falsework removal.
5.Test at least 2 cylinders to det ermine the attained strength o f concrete for falsew ork removal. Use the average test results for the 2 cylinders to determine complianc e, except that both cylinders must be no less than 10 percent below the requ ired strength. Cure the cylinders under conditions that at best equal the most unfavorable conditi ons for concrete sampled that the cylinders represent. Effective with the December 2018 Letting 217 2019 Standard Spec ifications (6) Remove falsework piles down to at least 24 inches below stream bed or finished ground line. Remove temporary mud sills and footings.
7.For multiple concrete spans of continuous design, do not remov e the falsework from any one span until the concrete in an entire unit of continuous span cures f or the required time. If providing a longitudinal joint in the roadwa y of any one span, do not remov e the falsework from any portion of the span until the entire span cures for the required time.
502.3.5 1 General
1.Notify the engineer before placin g concrete to allow inspectio n of the forms, reinforcement, and placement preparations.
2.Before placing any concrete in a given pour, have sufficient l abor, material, and equipment at the work site to complete the pour. Use equipment that is adequate for t he work and in first-class working order.
3.Complete the forming and placing reinforcement before placing the concrete in any unit. Place and rigidly support in the correct position all bar steel reinforce ment extending into a subsequent pour before placing the first concrete in a given pour, unless the plans show otherwise. Complete adjacent pile driving and other operations detrimental to freshly placed concrete before placing concrete.
4.Before placing concrete, remov e sawdust, chips, nails, wire, o ther construction debris, and extraneous matter from the forms interior. C lean the contact surfaces of s tructural steel members embedded in the placed concrete to ensure they are free from oil, grease, loose rust scale, or other materials that would affect the bond between the concrete and the steel.
5.The contractor shall not support c onstruction equipment on rei nforcement steel or bar chairs.
6.Place the concrete in a way tha t avoids segregating the aggreg ate or displacing the reinforcement. If the engineer finds any defective concrete section, remove and r eplace it, as the engineer directs, at no expense to the department.
7.Arrange and use chut es, troughs, belts, and pipes as aids in p lacing concrete so no separation of the concrete ingredients occur. Provide enough chutes, troughs, or pipes to carry the concrete up at a uniform level without shifting them. Keep chutes, troughs, belt s, and pipes clean and free from coatings of hardened concrete. Discharge water used for flushin g away from the concrete in place.
8.If placing concrete in structur es, the distance from the disch arge ends to the point of deposit for chutes, troughs, pipes, belts, and buckets shall not exceed 4 f eet.
9.If using conveyor belt systems , equip the belts with suitable hoods or chutes to control the discharge.
10.If conveying or placing concrete by pumping, use suitable equi pment with adequate capacity for the work. Arrange the equipment so tha t any resulting vibrations do not damage freshly placed concrete. Operate the pump in a way that p roduces a continuous stream of concrete without air pockets. After pumping is complete, if using the concrete remaining in the pip eline, eject it so there is no concrete contamination or ingredients sep aration. After this operation, thoroughly clean the equipment.
11.If placing concrete by pumping, take measures to minimize entr ained air loss. The point of discharge from the flexible hose at the end of the boom shall be higher than the lowest point of the flexible hose. If using an extended boom, the contractor may lay part of the f lexible hose on the deck. If completely suspending the flexible hose fr om the boom, tie the discharge e nd of the flexible hose back toward the end of the rigid boom to form a partial loop. The engineer may approve alternate methods if the contractor can demonstrate that the air loss in the concrete created by the pumping process does not exceed 1.0 percent in any boom orientation.
12.The contractor shall not use a luminum pipes, chutes, troughs, spouts, or tremies for pumping, conveying, or placing concrete.
13.If placing operations involve placing concrete through the com pleted forms, as for , piers, columns, and retaining walls over 5 feet in height, with the exception of ca st in place concrete piles and walls less than 10 inches thick, deposit concrete through sheet metal or o ther engineer-approved pipes. Assemble these pipes in section s to facilitate adjusting outlets to proper heights during pouring operations. The distance from t he bottom of these pipes to the point of deposit shall not exceed 4 feet at any time.
14.If using troughs or chutes, extend them down inside the forms, or through holes left in the forms, to within 2 feet of the point of deposit unless they end in vertic al downspouts that extend to within 4 feet of the point of deposit. Equip steep chutes with baffle boards or assemble them in short lengths that reverse the direction of movem ent. The contractor shall not use long chutes for conveying concrete from the mixing plant to the forms. Effective with the December 2018 Letting 218 2019 Standard Spec ifications (15) Place concrete in continuous hor izontal layers approximately 12 inches thick, except that the engineer may allow increasing this thickn ess to 24 inches. Place each la yer in a continuous pour and consolidate before the concrete i n the preceding layer takes in itial set.
16.Make construction joints only at locations the plans show, unless the engineer dir ects otherwise. In case of an emergency, place construction joints at the engineer ’s direction. Use shear keys or inclined reinforcement at necessary points to transmit shear, or bond th e 2 sections together.
17.Regulate placing the concrete so that the pressure of the conc rete does not exceed that of the form design.
18.Take special care to fill each part of the forms by depositing concrete directly as near the final position as possible, to work the coarse aggregate back from the face, a nd to force the concrete under and around the reinforcement bars wi thout displacing them. Also, tr y to prevent spattering the forms or reinforcement bars so that the sp attered concrete does not dry or harden before incorporating into the mix. Clean foreign material from reinforcement bars before the succeeding pour.
19.Remove all removable form spread ers before placing concrete at the spreader elevation.
20.Take care to avoid accumulating laitance or foreign matter ins ide forms, recesses, or corners. Provide openings in forms for removing any accumulations, as the engine er directs.
21.After the concrete takes initia l set, avoid jarring the forms or placing any strain on the ends of projecting reinforcement.
22.Use mechanical vibration to consolidate the concrete for super structures. Consolidate other concrete for structures by vibrating unless using other methods the engi neer finds satisfactory. Use vibrators capable of operating at frequencies sufficient to achieve thoro ugh and uniform consolidation, but at not less than 7000 impulses per minute. Make available at least one spare vibrator, in working order and of sufficient frequency, on the wo rk site before pouring concre te.
23.Apply vibration to the freshly deposited concrete by slowly in serting and withdrawing the vibrator. Perform this procedure at enough locations and for as long as n ecessary to uniformly and thoroughly consolidate the entire weight of fresh concrete without causing aggregate segregation, or forming localized areas of mortar.
24.Consolidate each concrete laye r thoroughly before placing the next layer on top. Ensure that the vibrator penetrates through each successive layer and sufficiently into the preceding layer to uniformly blend the 2 concrete layers together.
25.The contractor shall not perform vibration directly to or thro ugh the reinforcement of sections or layers that harden so that they are no longer plastic under vibration. The contractor shall not use the vibrator to transport, or to flow , the concrete within the forms to the extent of causing segregation.
26.Supplement vibration with as mu ch spading as necessary, to ens ure smooth surfaces and dense concrete, along form surfaces and in corners and locations impo ssible to reach with the vibrator.
27.If required to continue mixing, p lacing, or finishing concrete after daylight hours, employ artificial light at the work site to the engineer’s satisfaction.
502.3.5 3 Depositing Concrete Underwater
1.Deposit concrete unde rwater only if the engi neer orders, the p lans show, or the contract specifies.
2.Provide concrete as specified in 501, except increase the slump to 5 - 9 inches without exceeding t he maximum mix water allowed for that grade. Effective with the December 2018 Letting 219 2019 Standard Spec ifications (3) For concrete deposited underwate r, place it carefully in a compacted weight in its final position using a tremie. The tremie consists of a tube that has a diameter of no t less than 10 inches and constructed in sections having flanged couplings fitted with gaskets. The trem ie support shall allow free movement of the discharge end over the entire work surface and allow its ra pid lowering if neces sary to choke off or retard the flow. Keep the dischar ge end sealed at all times and the tremie tube full to the bottom of the hopper. If dumping a batch into the hopper, raise the tremie sl ightly, but not out of the concrete at the bottom, until the batch discharges to the bottom of the hopper. Then stop the flow by lowering the tremie. Ensure a continuous unint errupted flow until the work i s complete. The contractor may use a tremie equipped with a suitable mechanical seal or valve at the discharge point instead of the open tube tremie, if the engineer appr oves of the design, method of operation, and control of the device.
4.Exercise special care not to disturb concrete deposited underw ater and to maintain still water at the deposit point. The contractor s hall not place concrete in runni ng water. Ensure watertight formwork.
5.Place the concrete in a way tha t precludes developing a cold joint between successive layers or placement stages. Accomplish this by either placing the concret e layers deep enough to accommodate satisfactory tremie operation, while ensuring that the previously layer does not take initial set by pouring at a rat e sufficient to raise the concrete level between 1 1/2 to 2 feet per hour; or by placing the concrete full depth in one continuous operation and completing the work to grade progressively from one end of the coffe rdam to the other.
6.Design cofferdams to accommodat e appropriate and planned pour rates. The contractor may place underwater concrete by pumping, if the engineer approves.
7.The contractor shall not dewat er the cofferdam until at least 3 days pass from the time placed and not before the concrete hardens and is strong enough to withstand t he hydrostatic pressure.
8.After dewatering, remove laitance or other unsatisfactory material on the top of seals and underlying proposed substructure units by scraping, chipping, or other mea ns.
502.3.5 4 Superstructures
1.Except for parapets or similar pours, the contractor shall not place concrete in bridge decks if housing is required at time of placement, unless the engineer specifically allows or requires in writing. Except for rigid frame bridges, remove the forms for the substructure units that support any proposed superstructure before placing the superstructure.
2.Ensure continuous concrete place ment in superstructures betwee n joints the plans show.
3.Exercise care to minimize honeycombed concrete. The engineer m ay require the removal and replacement of honeycombed concrete at no expense to the depart ment.
4.Do not place concrete parapets, sidewalks, and medians on cast in place structures until the falsework is released for that superstruct ure unit. The contractor may pl ace those portions o f the railings directly attached to substructure units w hile the falsework is in place.
5.The contractor may form and place concrete parapets, sidewalks and medians on steel girder, I-beam, or pre-stressed girder structures after 48 hours following deck placement, provided it uses no heavy equipment on the deck and it properly cures the deck adjacent t o the pours.
6.Place floor drains, conduits, e xpansion joints, and other fittings as the plans show. Place and securely fastened them before placing the concrete.
7.Before placing concrete floors on steel superstructures, release the falsework and swing the span free on its supports.
502.3.6 3.2 Preformed Elastomeric Compression Joint Sealer
1.Use preformed elastomeric compression joint sealer conforming to 502.2.8 and install in the joint with a lubricant-adhesive.
2.Clean joint faces to ensure they are free of laitance, oils, g reases, dirt, free water, and other foreign matter immediately before inst alling the seal. The engineer will direct the method of cleaning the joints.
3.Install the seals, in the pro perly prepared joint, using tools designed for installin g joint seals. Remove and replace any seal damaged du ring installation with an undama ged seal. Remove and reinstall any seal improperly positioned in the joint at the proper elevation .
4.Before placement, cut the seal s to the lengths of the joints o r as much longer as needed for proper installation. Measure each seal b efore and after installing as a check against stretch. Remove and reinstall any installed seal sho wing more than 5 percent stretc h.
5.Install the seals so they are s ecure and free from any objectionable curling or twisting in the joint groove. Use a lubricant to facilit ate installation and to cover both sides of the seal over the full area in contact with the sides of the joint. The contractor may apply t he lubricant to the joint faces, or the seal, or both. Install the seals in a highly compress ed state and ens ure the top of the seal is below the pavement surface by approximately 1/8 inch but not more than 3/ 8 inch. Install the seal in one piece, without field or factory splicing, for the full length of each transverse joint.
6.Observe the manufacturer-specif ied temperature limitations.
502.3.7 1 General
1.After removing forms, remove me tal devices used to tie forms t ogether in a way that leaves no metal within less than one inch of the concrete sur face and does not injure the concrete surface. The contractor shall not burn off r ods, bolts, or other metal devic es. After removing the ties, roughen the opening and remove concrete containing any oil.
2.Immediately after removing forms, saturate cavities produced, and other holes, depressions, and honeycomb spots with water and carefully point with a cement an d fine aggregate mortar mixed in the same proportions as the concrete being treated and of as dry a consistency as possible to use. For exposed surfaces, add as much whit e cement as necessary to prov ide a mortar the approximate color of the concrete. Use mortar in pointing that is not more than one hour old.
3.Clean open joints in the comple ted work to make them free of m ortar and concrete.
4.If using insulated forms or if a llowed to leave forms in place more than 72 hours, poi nt holes, cavities, depressions, and honeycomb areas and apply a sack rubbed or rub bed surface finish as soon after removing the forms as weather and curing conditions allow.
502.3.7 5 Sack Rubbed Surface Finish
1.If the plans show, or specifications indicate, provide a sack rubbed finish on concrete surfaces.
2.Before applying the sack-rubbe d finish fill tie rod holes and large cavities and re move or correct fins and irregularities as specified in 502.3.7.1 and 502.3.7.2 .
3.Produce a sack rubbed surface finish by rubbing the concrete s urface with a clean rubber float or wad of burlap and mortar. Use mortar made of one part cement and 2 parts, by volume, sand passing a Effective with the December 2018 Letting 222 2019 Standard Spec ifications No. 16 sieve, mixed with suffici ent water to provide a consiste ncy equal to that of thick cream. Use the same type and brand cement as used in the concrete. If necessar y, blend white cement into the cement to match the surrounding concrete surface.
4.Thoroughly wet the surface of t he concrete and then perform sa ck rubbing while the surface is damp but not wet. Thoroughly rub the mo rtar over the area with a rubber float or wad of burlap, filling pits. While the mortar is still plasti c in the pits, rub the surface with the rubber float or burlap using a dry mix of the above proportions, removi ng excess plastic material and placing enough dry material in the pits to stiffen and solidify the mort ar, then finish the mortar fillings flush with the surface. At the end of the rubbing, no mortar or material s hall remain on the surface othe r than that within the pits.
5.Ensure the completed surface is free of surface voids and blem ishes, and is uniform in appearance and texture, except for the difference in texture between the f illed voids and the remainder of the surface.
502.3.7 8 Floors
1.Prepare the concrete for bridge floors, if and as required in 501.3.2.4.3, with a retarding admixture. Deliver the mixed concrete at a uniform rate to provide a conti nuous placing operation for each pour section. Handle and place the co ncrete by methods and equipment that minimize segregating the ingredients. Deposit it as clos ely as possible to its final pos ition without forming piles and so that it requires a minimum of rehandling. 2.Immediately after depositing the concrete, consolidate, strike off, screed, and finish it to the required grade, section, and surface tolerance. Uniformly consolidate th e concrete by internal vibratory methods as specified in 502.3.5.1 , except that, the contractor may use a vibratory screed for consolidating and finishing in conjunction with internal vibration. Operate the internal vibrators or the vibratory screed, or both, in a way that avoids over-vibration.
3.Unless the contract specifies o therwise, construct concrete br idge floors with self-propelled machine finishers.
4.Use a machine finisher designed for finishing bridge floors. I t shall consist of a rig id supporting frame mounted on wheels that ride on re movable tracks or rails and is equipped with the necessary screeding apparatus to strike o ff and finish the concrete to re quired crown and grade. It shall have one or more power-driven oscillating , rotating or vibratory screeds . The screeds may suspend from the machine either transversely or longitudinally with the bridge c enterline, except as required for skew angles of 20 degrees or greater. Use a finishing machine capable of propelling itsel f both forward and backward to allow repeated passe s of the screed in order to cor rect surface irregularities. Adjust its screed or screeds and operate in manner that finishes the concr ete to required grade and crown and requires a minimum of cutting or filling in any subsequent floa t-finishing operations.
5.The contractor shall set the ra ils or tracks, that the machine finisher rides on, to t he required elevation; and ensure they adjus t to allow for settlement under load. If t he rail supports are located in the Effective with the December 2018 Letting 223 2019 Standard Spec ifications concrete, ensure their removal without disturbing the concrete, or partially remove so that no piece remains less than 2 inches below the finished concrete surface. Remove these supports, fill the resulting holes with concrete, and finish flush with the deck c oncrete before it hardens.
6.Ensure the rails or tracks ex tend beyond each end of the floor or deck sufficien tly to support the finishing machine a t the correct grade and entirely free of the floor or deck area.
7.Finish floor areas inaccessibl e to machine operation by hand m ethods.
8.On bridge decks supported on pr estressed concrete or steel girders and having skew angles of 20 degrees or greater, operate the finishing machine so that its l ongitudinal axis is within 20 degrees of the centerline of bearing of the substructure units. Make trans verse screeds parallel to the longitudinal axis of the machine.
9.If using hand-operated strike-off screeds, design , construct, and operate them to provide the required crown and grade in the finished floor. The contractor may use v ibratory or nonvibratory type screeds that operate on forms or temporary guides set and maintained at the required elevation. Use sectioned, temporary guides that remain rigid an d unyielding un der screed operation and, if located within the pour limits, can be removed as the work progresses. If using vibratory screeds to supplement required internal vibration, operate them so they do not over vibrate the concrete.
10.Hand finish gutter lines and areas around floor drains not rea ched by the templates and finishing equipment to the grade an d section needed to i nsure proper drai nage.
11.Strike off and remove the la itance from floor areas that will receive concrete for sidewalks or similar items.
12.Following screeding, unless obtaining a satisfactory surface w ith a self-propelled finishing machine, float the surface as needed to produce a uniform surface.
13.While the concrete is still plas tic and following screeding op erations, and float finishing if performed, work laitance, surplus water, and inert material off the floor and make it smooth. Test for smoothness by dragging the entire floor surf ace with a 10-foot straightedge as specified in 415.3.6.1 for straightedging concret e pavement. Use bridges to facilitate str aightedge operations on pour sections wider than 2 lanes. Revise 502.3.7.8(14) to require transverse tining for bridge decks unless specified otherwise. This change was implemented in ASP 6 effective with the December 2017 letting. 14.Unless specified otherwise, transversely tine finish the floors of struc tures with approach pavements designed for speeds of 40 mph or greater as specified in 415.3.8.3 , except make the tining 1/8 inch in depth and do not perform tining within 12 inches of gutters. Th e contractor may apply a broom finish, described below, instead of the ar tificial turf drag finish req uired before tining. The contractor may perform tining manually, if it obtains a finish satisfactory to the engineer. Perform tining within 20 degrees of the centerline of bearing of the su bstructure units on bridge decks havi ng skew angles of 20 degrees or greater. 15.Unless specified otherwise, provide a turf drag finish on floo rs of structures wit h approach pavements designed for speeds of less than 40 mph as specified in 415.3.8.2 or provide a broom finish. If providing a broom finish, draw the broom transversely across the full width of the pavement with adjacent strokes slightly overlapping. Perform brooming to produce uniform corrugations and approximately 1/8 inch in depth. C omplete brooming before the c oncrete hardens and this operation tears or roughens the surface. Bro oming shall provide a surface free from rough or porous areas, irregularities, and depressions that result from improper broom handling. Furnish br ooms of a sufficient quality, size, and construction, and operate them to produce a surface finish the engineer approves. Provided the contractor obtains satisfactory re sults, the engin eer will allow manual brooming instead of mechanical brooming. 16.The finished bridge floor shall conform to the surface test sp ecified in 415.3.10 . The engineer will not direct corrective grinding without authorization from the depar tment’s bureau of structures. 17.Make available suitable platfo rms to use, as required, over steel reinforcement projecting from previously placed concrete, duri ng the period necessary for the concrete to achieve sufficient strength to preclude damage from contract or's operations on the unprotec ted reinforcement.
18.Make available adequate bridges , if and as the engineer requir es, for inspecting and testing the placed concrete, and furnish bridges, i f necessary, to perform work op erations that follow the screeding operations. Effective with the December 2018 Letting 224 2019 Standard Spec ifications 502.3.8 Curing
502.3.8 1.1 Impervi ous Coating Method
1.After finishing operations, and as soon as the free water disa ppears, spray the concrete surface with a uniform coating of curing compound conforming to 502.2.6. Seal moisture in the concrete by applying a continuous water-impermeable film on exposed concrete surface s.
2.Provide sufficient agitation of pigment within the curing comp ound during spraying to ensure uniform consistency and dispersion as applied.
3.Apply the curing com pound with spraying equipment that produce s a continuous, uniform film that does not run or sag.
4.Apply the curing compound unifo rmly at a minimum rate of one g allon per 150 squar e feet. Apply the membrane curing material in 2 applications at the rate of not l ess than one gallon per 300 square feet.
5.If damage to the curing compound coating occurs before the con crete conforms to the opening criteria specified in 502.3.10 , recoat the affected area immedi ately. If removing forms befor e the concrete conforms to the opening criteria specified in 502.3.10 , coat newly exposed surfaces within 30 minutes after form removal. 502.3.8.1.2 Impervious Sheeting Method
1.As soon as the concrete receives a finish and hardens sufficie ntly to prevent excess ive marring, cover exposed concrete surfaces with one or a combination of the foll owing impervious sheeting materials: 1. Polyethylene sheeting confor ming to the curing materials sp ecified in 501.2.9. 2. Polyethylene-coated burlap conforming to the curing materia ls specified in 501.2.9 . Pre-wet the polyethylene-coated burlap and pl ace with the uncoated side aga inst the concrete. 3. Insulated curing blankets with an impervious coating, with the engineer's approval. 4. Alternate impervious sheeti ng materials, with the engineer' s approval. 2.Provide sheeting material sufficient to cover exposed surfaces and edges, with enough excess to hold the material securely in place b y weighting or an alternate anc horing method. Provide a minimum of 12 inches overlap between adjacent pieces of sheeting. Place th e sheeting material so that it is in direct contact with exposed concrete surfaces.
3.Maintain the sheeting material in place until the concrete con forms to the opening criteria specified in
502.3.8 2.1 General
1.Do not use reinforcing steel to s upport or attach covering mat erials.
2.If curing formed concrete by t he impervious coating method, ap ply the first application immediately after form removal and surface finish application. If the surfa ce is dry, wet the concrete thoroughly with water and apply the curing compo und just as the surface film of water disappears. Apply the second application as soon as the first application sets.
3.Do not apply impervious coati ng curing material to constructio n joints, or to surfaces being bonded to other concrete, or to surfaces being waterproofed, or to which applying sealants. Ensure that steel reinforcement, anchors, watersto ps, and similar devices are fre e of compound before placing concrete.
4.Do not use the impervious coating method on concrete before applying the required surface finish. Use other allowed curing procedur es before applying the surface finish.
5.The contractor may delay applying the required surface finish, if the engineer approves, until after completing curing with wetted burlap or polyethylene-coated bur lap, in order to allow uniform and continuous finish application. P rovide at least 4 hours of an e ngineer-approved moisture cure to prevent the finish from sanding-out.
6.If the structure or any portion of it is enclosed, and artific ial heat is provided for protection, this does not waive the above requirements for moisture for curing. The c ontractor may use steam for heating and to produce an adequate supply of moisture within the enclos ure.
7.The contractor may leave forms in place instead of using burla p or membrane curing.
502.3.9 1 General
1.Maintain the quality of the conc rete placed in cold weather. P rovide the protection necessary to prevent concrete freezing until it develops sufficient strength to conform to the opening criteria specified in 502.3.10 . Remove and replace frozen or frost damaged concrete at no exp ense to the department.
2.Unless the engineer directs otherwise, protect concrete under both of the following conditions: 1. The air temperature is 40 F or less. 2. The air temperature is predicted to be 40 F or less within 24 hours.
3.Ensure that forms, reinforcem ent, base, and subgrade are free of ice, snow, and frost during pouring. If the atmospheric temperature is below 40 F, preheat the inter ior surfaces of forms, all reinforcement, and the concrete surface adjac ent to the pour to 40 F or higher .
4.Adjust forms or insulation, as necessary, to control the tempe rature of the concrete. Unless the engineer allows otherwise, ensur e the temperature of the concrete does not exceed 120 F, or fall below 40 F during the protection period.
502.4.1 General
1.The department will measure the quantities of the various bid items that constitute the completed and accepted structure according to the contract provision for thos e bid items, in the units provided. All work included in the scope of the contract, but not listed as b id items in the propos al are incidental to the cost of the work. Effective with the December 2018 Letting 231 2019 Standard Spec ifications 502.4.2 Concrete for Bridges
1.The department will measure the Co ncrete Masonry Bridges bid i tems by the cubic yard acceptably completed. The department will not measure work or material for forms, falsework, c offerdams, unless specified otherwise, pumping, bra cing, or other incidentals nec essary to complete the work as required in these specifications.
2.If measuring floor slabs, the department will deduct the volume of the flanges of I-beams and precast concrete beams projecting into concrete floor slabs from the vo lume of the floor slab.
3.The department will deduct from t he quantity of concrete, as c omputed above, the actual volume displaced by the projection of c ast-in-place concrete piling in to the footing, pile cap, or abutment; and 0.8 cubic foot of volume for each linear foot of timber piling projecting into the footing, pile cap, or abutment. The department will meas ure this net quantity for pay ment.
4.If the contractor pours footi ngs wholly, or in part without fo rms, the department will only measure material placed within the footing dimensions the plans show.
503.2.2 Concrete
1.Furnish concrete as specified in 501. If the design ultimate stress, f' c, the plans show is 8000 psi or higher for a prestressed concrete I-type girder, extend 28-day strength requirements within 503 for that girder to 56 days.
2.Ensure concrete attains a minimum 28-day compressive strength of 6000 psi for prestressed I-type girders. Base tests on 6-inch b y 12-inch cylinders, or 4-inch b y 8-inch cylinders, provided the engineer develops and approves a correlati on factor. Mold concrete cylin ders in steel or plastic molds. Cure concrete cylinders according to AASHTO T23, except cure the cyl inders with the member until release strength is obtained, then cure the cylinders according to AASH TO T23. Maintain laboratory facilities and equipment according to AASHTO M201. Make 3 cylinders for ea ch line of prestressed members poured and test each cy linder according to AASHTO T22. Calibrat e cylinder-testing equipment at least annually according to AASHTO T67. Average the strengths of the 2 cylinders with the highest test results for each line and use the average to determine complian ce with the 28-day strength requirement. Ensure that neither of the 2 cylinders with the highest test results h as a strength less than 10 percent below the required strength.
3.Instead of the above acceptance procedure, the engineer will a llow early acceptance of the prestressed units, before the 28-day test, if 2 successive laboratory tests on standard test specimens, cured continuously with and in the same manner as the units, in dicate compressive strength in excess of the required 28-da y strength. Test the 28-day strength cylin ders and record the results to maintain continuity of the contractor's quality control records.
4.Have an HTCP-certified PCC Technician I sample concrete, perfo rm fresh concrete testing, and fabricate and cure cylinders. Hav e an HTCP-certified Concrete S trength Tester, working in a department-qualified laboratory, perform cylinder and core comp ression tests. Determine the compressive strength in psi fo r each cylinder according to AASH TO T22. Test each cylinder to failure. Use a compression machine that automatically records the date, time, rate of loading on a load vs. time plot, and maximum load for each cylinder. Include a printo ut of this information with the strength documentation for each cylinder tested. Notify the engineer imm ediately if concrete cylinder compressive strengths are less than the required 28-day strength. Keep neatly documented records of all cylinder testing on the day of the test and make them avail able to the engineer.
5.Furnish prestressed concrete me mbers cast from air-entrained c oncrete, except I-type girders may use non-air-entrained concrete. Use type I, IL, IS, IP, IT, II, or III cement. The contractor may replace up to 30 percent of type I, I L, II, or III cement with an equal weight of fly ash, slag, or a combination of fly ash and slag. Ensure th at fly ash conforms to 501.2.6 and slag conforms to 501.2.7 . Use only one source and replacement rate for work under a single bid item. U se a department-approved air- entraining admixture conforming to 501.2.2 for air-entrained concrete. Use only size No. 1 coarse aggregate conforming to 501.2.5.4 . 6.The contractor shall determine pr oportions for the mix within the following limitations: Water cementitious mat erial ratio, w/cm ....................... ............................................................... .... 0.45 or less[1] Cementitious mat erial content ................................. ............................................ 610-800 pounds per cubic yard Air content: Prestressed I- type girders .................................... ........................................................ 6.0 pe rcent maximum Other com ponents .............................................. ............................................................... ... 4.5 - 7.5 percent Slump ......................................................... ............................................................... .......... 8 inches maximum[2]
Source: Wisconsin Standard Specifications for Highway and Structure Construction, 2019 Edition. Pages 221–241 of 601.
View official source ↗