Effective with the December 2018 Letting 273 2019 Standard Spec ifications Section 509 Concrete Overlay and Structure Repair
509.1Description
removing and disposing any remaining asphaltic patches or unsou nd concrete from those areas; the furnishing, placing and curing concrete overlays; and full dept h deck, surface, curb and joint repairs, as required.
509.2Materials
equal to 5 gallons of water per 94 pounds of cement.
repairs. The contractor may incre ase the slump for grade E conc rete to a maximum of 4 inches. The contractor may apply an engineer- approved commercial grout or s urface coating to surfaces being repaired instead of the grades of concrete designated above if it is impracticable to apply that masonry, if the engineer specifi cally approves in writing.
repairs, and full-depth deck r epairs; except as follows:
509.3Construction 509.3.1 General
or damaged by the contractor's operations. Use engineer-approved patching or repair material compatible with the existing coating and inert in concrete. 509.3.2 Equipment
vibratory screed with a variabl e frequency the operator can adj ust. Provide enough ident ical vibrators to provide at least 2 vibrators fo r each 5 feet of screed length. Ensure that the bottom face of each screed is at least 7 inches wide with a rounded leading edge. Each screed shall have an effective weight of at least 75 pounds per square foot of botto m face area. Provide each scr eed with the capability to positively control of the vertical pos ition, the angle of t ilt and the shape of th e crown.
width of the machine.
for raising the screeds to clear the screeded surface for trave ling in reverse.
machine next to the completed lane, to travel on the lane. 509.3.3 Cleaning
pavements before placing the concrete overlay.
suitable mechanical scarifyer. A ccomplish this in a way that pr events hooking or tearing the reinforcing steel and that removes at least one inch of concrete from the deck or pavement surface but not more than the maximum depth the plans show.
sound material by using chippers conforming to 509.3.4 for chippers.
patches and unsound concrete as specified for preparation in 509.3.4.
steel, the vertical faces of cur bs, sidewalks and parapets to the depth of the adjoini ng concrete overlay after completing preparation.
Effective with the December 2018 Letting 274 2019 Standard Spec ifications 5. Clean the surface receiving the new concrete by mechanicall y dislodging contami nation or debris and removing loose particles and dust with high-pressure water or a ir. Ensure that no free-standing water remains before placing grout and that cleaning water conforms t o 501.2.4 . 509.3.4 Preparation
unsound or disintegrated areas o f concrete decks and approach p avements as the plans show, or as the engineer directs.
deck concrete only to a depth t hat exposes 1/2 of the periphera l area of the t op or bottom bar steel in the top mat of reinforcement.
limit of the type 1 removal desc ribed above. One inch below the bottom of the top or bottom bar steel in the top mat of reinforcement is the minimum depth of type 2 rem oval. The engineer will direct any further removal.
the bridge floor. If chipping ex poses the existing bar steel re inforcement for more than 1/2 of its peripheral area, and where bond between exi sting concrete and reinforcing bar has been destroyed, remove the adjacent concrete to provide a minimum one-inch clearance aroun d the bar.
and are equipped with flat, chise l-type points with a cutting e dge not less than 3/4 inch or greater than 3 inches wide.
of the steel.
procedures to minimize debris dropping into the stream, streambed, roadway, or right-of-way below. 509.3.5 Joint Repair
piers, abutments and deck ends and other locations, and form ne w joints as the plans show, and the engineer directs.
directs. Place a 1/2 inch deep saw cut at the line of removal on the bottom edge of t he deck to control concrete breakout or cover the line of removal with a 1 1/2 inc h thick layer of concrete to cover all reinforcing steel exposed duri ng joint repair. Use removal equi pment that causes no damage to the portion of the concrete floor, curbs, and reinforcing steel remaining i n place. Do not use tractor-mounted rams for removal operations within 9 inc hes of the edge, or within the d epth of the slab from t he edge, whichever is less.
and retie, as the eng ineer considers nece ssary. If additional reinforcement is required, use grade 60 steel conforming to AASHTO M31, and to 505.2 .
nozzle to remove loose particles and dust.
neat cement as specified fo r concrete overlays in 509.3.9.2 .
509.3.6 Curb Repair
concrete curbs and fo rm new curb faces, top or back as the plans show.
steel. Clean, realign, and retie e xisting reinforcing steel, as the engineer considers necessary.
show and the engineer directs.
Effective with the December 2018 Letting 275 2019 Standard Spec ifications 5. Clean the surface against which placing the new concrete to remove loose particles and dust, and keep continuously wet for 2 hours before placing new concrete. Immed iately before placing concrete, coat the surfaces of old concrete with neat cement as specified in 509.3.9.2.
509.3.7 Concrete Surface Repair
other elements that the plans show, and the engineer directs, a nd replace those portions with concrete.
Clean, realign, and retie existing reinforcing steel, as the en gineer considers necessary.
greater, at locations the plans show or as the engineer directs .
deteriorated concrete.
continuously wet for a period of 2 hours be fore placing new con crete. 509.3.8 Full Depth Deck Repair
locations on the deck as the engineer directs, and then prepare and form these areas.
significant damage to that portion of the structure remaining i n place. The contractor shall preserve and utilize the required existing reinforcing steel.
the department.
necessary.
particles and dust, and keep cont inuously wet for 2 hours befor e placing concrete . Immediately before placing concrete in the full dep th deck replacement, coat the e ntire surface receiving the new concrete with neat cement as specified in 509.3.9.2 .
509.3.9 Concrete 509.3.9.1 General
construct a concrete overlay course on concrete deck and approa ch pavement to the lines, grades, thickness, and cross-section the plans show, or the engineer di rects.
overlay.
tops, and backs.
deck elevation before placing the overlay. 509.3.9.2 Placing Concrete Overlays
depth deck repair areas.
pavement being overlaid, and all ve rtical joints with a neatce ment mixture. Ensure the surface of the existing deck is moist without any standing water before coatin g with the neat cement mixture. Brush the neat cement over the prepared concrete surface to ensureal l parts receive an even coating and do not allow excess neat cement to collect in pockets. Apply th e neat cement at a rate that ensures the cement does not dry out before covering with the new concre te.
Effective with the December 2018 Letting 276 2019 Standard Spec ifications (3) Place concrete for deck prepar ation immediately in front of th e overlay course and vibrate internally in addition to surface screed vibration. Place concrete in a single operation, with no construction joints in the overlay section except as the plan show or the engineer directs. Do not place concrete if the ambient air temperature is above 88 F.
of the structure. Conduct bridge deck finishing operations so t hat the elapsed time between depositing the concrete on the deck and fi nal screeding does not exceed 10 minutes.
at the locations the plan show, and true to the alignments the plan show.
pavements with design speeds of 40 mph or greater, except there is no requirement for the turf drag or broom finish.
plans show. Begin sawing joints within 6 hours after placing th e concrete, unless the engineer directs otherwise, and complete within 12 hours. 509.3.9.3 Curing Concrete Overlays
502.3.8 , including fogging, and allow to cure for 3 days. 509.3.9.4 Opening to Traffic
may extend this time if conditions warrant. 509.4 Measurement
square yard acceptably comple ted. The department will not subtract areas of type 2 removal from areas of type 1 removal. The depa rtment will subtract areas of full-depth deck repair, the engineer directs before beginning the type 1 or type 2 deck removals, fr om the areas of the type 1 or type 2 removals. The department will no t subtract areas of full-depth deck repair, the engineer directs after type 1 or type 2 deck removals a re underway, from the areas of the type 1 or type 2 removals. The department will not measure areas of joint repair under these bid items.
Deck Repair by the square y ard acceptably completed.
measured as the exposed surface area, following removal, as del ineated by the saw cuts.
completed. The department will in clude the volume of concrete u sed in associated approach and deck preparation, joint repair, curb repair, and in full-depth deck repair as part of the Concrete Masonry Overlay bid items. The department will compute yardage based on the nominal cubic yard of concrete defined in 501.3.2.2 . The department will not measure wasted concrete.
509.5Payment
509.5.1 General
items: ITEM NUMBER DESCRIPTION UNIT
509.0200 Preparation Approaches SY
509.0300 - 0399 Preparation Decks (type) SY
509.0500 Cleaning Decks SY
509.0600 Cleaning Approaches SY
509.1000 Joint Repair SY
509.1200 Curb Repair LF
509.1500 Concrete Surface Repair SF
509.2000 Full-Depth Deck Repair SY
509.2500 Concrete Masonry Overlay Decks CY
509.2600 Concrete Masonry Overlay Approaches CY
Effective with the December 2018 Letting 277 2019 Standard Spec ifications (2) Repairing damage to existing reinforcement is incidental to the contract. 509.5.2 Preparation
removing asphaltic patches and unsound concrete; and for disposing of waste materials.
Overlay bid items. 509.5.3 Cleaning
cleaning the deck or approaches; and for blast cleaning the ent ire deck or approaches, including all exposed existing reinforcing steel. 509.5.4 Joint Repair
and for forming new joints.
Overlay bid items.
509.5.5 Curb Repair
forming; and for disposi ng of waste material.
Overlay Decks bid item. 509.5.6 Concrete Surface Repair
disposing of deterio rated concrete; for cl eaning reinforcing st eel; and for the volume of concrete used in the surface repair. 509.5.7 Full Depth Deck Repair
concrete areas; for disposing o f waste material; for forming; a nd for salvaging and using the existing bar steel reinforcement. The depa rtment will pay for this bid i tem at the contract unit price regardless of whether the engineer directs i t before or after beginning the type 1 or type 2 removals.
Overlay Decks bid item. 509.5.8 Concrete Overlays
the concrete used including the volume needed to complete the w ork done under the associated Preparation Approaches, Preparati on Decks, Join t Repair , Curb Repair, and Full-Depth Deck Repair bid items; and for sawing and sealing joints.
Effective with the December 2018 Letting 278 2019 Standard Spec ifications Section 511 Temporary Shoring
511.1Description
511.2Materials
AASHTO Load and Resistance Factor Design Specifications and the WisDOT Bridge Manual. Design to address all limit states using a design life of 36 months or the project specific duration, whichever is greater. Have a professional engi neer, registered in the state of Wisconsin and knowledgeable of the specific site conditions and requirements, verify the adequacy of the design. Submit one copy of each shoring design, signed and sealed by the same professional engi neer verifying the design, to the engineer for incorporation into the permanent project record.
511.3Construction
location as follows: Under the Temporary Shoring bid item: for all temporary shoring locations the contract shows. Under the Temporary Shoring (str ucture) bid items: for temporar y shoring associated with structure ID numbers identified in the bid item supplemental descriptions . Under the Temporary Shoring (loc ation) bid items: for temporary shoring associated with roadway locations identified in the bid item supplemental descriptions.
the left-in-place bid items, leav e the shoring in place as the special provisions specify or as the plans show. Place backfill conforming to 206.3.13 in excavated space not occupied by the new permanent construction.
511.4Measurement
completed at locations the plans show, measured as the area of exposed face in the plane of the shoring from the ground line in front of the shoring to a maximum of one foot above the retained grade. Shoring used for staged construction in multiple configu rations without removal and reinstallation will be measured on ce based on the configuration with the largest area of exposed face.
511.5Payment
items: ITEM NUMBER DESCRIPTION UNIT
511.1100 Temporary Shoring SF
511.1200 Temporary Shoring (structure) SF
511.1300 Temporary Shoring (location) SF
511.2200 Temporary Shoring Left In Place (structure) SF
511.2300 Temporary Shoring Left In Place (location) SF
for providing a signed and sealed copy of the design; for removal or additional work required to leave in place; and for backfilling.