- PILING PILING
704.1DESCRIPTION
Drive the specified types of piles to the penetration and bearing values shown in the Contract Documents. B I D I T E M S U N I T S P i l e s ( * ) ( * * ) L i n e a r F o o t Test Piles (*) (**) Linear Foot Test Piles (Special) (*) (**) Linear Foot Cast Steel Pile Points Each Pre-Drilled Pile Holes Linear Foot *Type: Cast-In-Place Concrete, Prestressed Concrete, Steel or Steel Sheet, Corrugated Metal Sheet + **Size +Black or Galvanized
704.2MATERIALS
Provide materials that comply with the applicable requirements. Concrete ................................................................................................................ SECTIONS 401 & 402 Aggregates for Concrete Not On Grade ................................................................ SECTIONS 1102 Prestressed Concrete Piles ..................................................................................... DIVISION 700 Steel Bars for Concrete Reinforcement ................................................................. DIVISION 1600 Steel Piling and Steel Pile Points ........................................................................... DIVISION 1600 Type B Preformed Expansion Joint Filler ............................................................. DIVISION 1500 Paint Materials ....................................................................................................... DIVISION 1800
704.3PILE DRIVING EQUIPMENT
energy required to drive piles at a penetration rate of not less than 0.10 inches per blow at the minimum driving resistance according to the appropriate pile driving formula in TABLE 704-1. In addition to all other requirements, single and doubl e acting diesel hammers and air/steam hammers require the following.
such as rings on the ram or a scale (jump stick) extending a bove the ram cylinder, to permit the Engineer to visually determine hammer stroke at all times during pile driving operation. Also, provide the Engineer a chart from the hammer manufacturer equating stroke and blows per minute for the open-end diesel hammer to be used.
bounce chamber pressure gauge, mounted near ground level so as to be easily read by the Engineer. Also, provide the Engineer a chart, calibrated to actual hammer performance, equating bounce chamber pressure to either equivalent energy or stroke for the closed-end diesel hammer to be used.
pile and drive cap, and in no case shall the striking part have a weight less than 2,750 pounds.
hammer is used for driving steel piles, steel sheet and shells for cast-in-place concre te piles, use one with a minimum weight of 3,500 pounds. In no case may the weight of the gravity hammer be less than the pile being driven plus the weight of the driving cap. In lieu of weighing the hammer, a certification may be provided by the Contractor. Equip all gravity hammers with hammer guides to maintain concentric impact on the drive head or pile cushion. Regulate the fall to avoid injury to the piles. The fall shall be a maximum of 12 feet. If diesel or air/steam hammers are used, the maximum fall shall be 90% of the maximum fall recommended by the hammer manufacturer. - PILING If steam or diesel hammers are used, its rated gross energy in foot-pounds shall be a minimum of 2 ½ times the weight of the pile in pounds. The hammer shall develop a minimum of 6,000 foot-pounds of energy per blow.
piles with a diesel or air/steam hammer that can develop an energy per blow at each full stroke of the piston of a minimum of 1 foot-pound for each pound of weight driven. The hammer shall develop a minimum of 6,000 foot- pounds of energy per blow.
Documents or in writing by the Engineer. If approved, vibratory hammers shall be used in combination with pile load testing and re-tapping with an impact hammer. In addition, 1 of every 10 piles driven with a vibratory hammer shall be re-tapped with an impact hammer of suitable energy to verify that acceptable load capacity was achieved.
capacity to maintain, under working conditions, the pressure at the hammer specified by the manufacturer. In case the required penetration or bearing is not obtained by the use of a hammer complying with the above minimum requirements, provide a hammer of greater energy or when permitted, resort to jetting or pre-drilling at Contractor expense. Use of the pile driving analyzer may be required when minimum requirements are not obtained or results are doubtful.
position with guys or stiff braces to sup port the pile during drivin g. Except where piles ar e driven through water, use leads of sufficient length that the use of a follower shall not be necessa ry. Leads shall be of sufficient length to allow them to be spiked into the ground at the onset of driving.
thickness of hammer cushion material to prevent damage to the hammer or pile and to maintain uniform driving behavior. Use hammer cushions made of durable, manufactured material that shall retain uniform properties during driving. Wire rope and asbestos hammer cushions are pr ohibited. Place a striking plat e on the hammer cushion to maintain uniform compression of the cushion material. In spect the hammer cushion in the presence of the Engineer when beginning pile driving at each stru cture or after each 100 hours of pile dr iving, whichever is more frequent. Replace the hammer cushion whenever there is a reduction of hammer cushion thickness exceeding 25% of the original thickness, or when the cushion begins deteriorating, tearing, etc., before continuing driving. The following are acceptable types of p ile cap material. Other materials may be used with approval of the Bureau of Construction and Materials.
when it starts to powderize or when it disintegrates into various layers.
the cushion develops horizontal cracks.
equipment.
aluminum is deformed or broken.
the hammer blow to the pile head. Axially align the driving head with the hammer and the pile. The driving head is guided by the leads and shall not be free swinging. The driving head shall fit around the pile head in a manner that prevents transfer of torsional force during driving while maintaining proper alignment of hammer and pile.
nozzle shall be sufficient to freely erode the material adjacent to the pile. Use a plant with sufficient capacity to deliver a minimum of 100 pounds per square inch pressure at ¾-inch jet nozzles at all times. At a minimum of 5 feet before the desired penetr ation is reached, withdraw the jets and driv e the piles to secure the final penetration with an approved hammer. - PILING
704.4CONSTRUCTION REQUIREMENTS
length of piles) shown in the Contract Documents. For piles and test piles, provide the Engineer with the completed "Pile and Driving Equipment Data" sheet a minimum of 3 weeks before the scheduled date of drivin g piling. The Engineer will forward this information for Test Pile (Special) to the Chief Geologist. When a restrike is required by the Engineer, follow subsection 704.4e. for restrike procedures. Provide piles for the structure according to the order list (number and length of piles) prepared by the Engineer. Drive the specified test piles at the locations shown in the Contract Documents. The Engineer will use the test pile information to determine the pile tip elevation. If multiple hammers are used on a project requiring test pile or test pile (special), drive a test pile or test pile (special), whichever is specified, with each hammer.
driving of the test piles (special). Provide the Engineer with the completed "Pile and Driving Equipment Data" sheet a minimum of 3 weeks before the scheduled date of drivi ng piling. The Engineer will forward this information to the Chief Geologist. In order to mobilize the PDA, notify the Engineer a minimum of 5 working days before driving the test piles (special). Prior to driving the test pile (special), the Engineer will require approximately 1½ hours to prepare the test piling (special) and install the dynamic measuring eq uipment. If with prior approval, the piles are to be welded prior to the Engineer attaching the testing equipment, provide the Engineer with safe and reasonable means of access to the pile for preparing the pile and attaching the instruments. When a restrike is required by the Engineer, follow subsection 704.4e.(3). for restrike procedures. To obtain the estimated ultimate loads, the Engineer will use the PDA to take dynamic measurements as the test pile (special) is driven to the required driving resistance. If non-axial driving is indicated by dynamic test equipment measurements, immediately realign the driving system. The Engineer will use the PDA results to provide the Contractor with a blow count for production driving.
combination of pre-drilled holes or water jetting an d a hammer. Use equipment that complies with subsection 704.3. Drive the piles at the locations and to the vertical or battered lines shown in the Contract Documents. Use leads of sufficient length to allow them to be spiked into the ground at the onset of driving the pile. Do not drive piles until the footing, webwall or abutment excavation is completed. Drive all of the piles required for the footing or abutment before placing any concrete in the footing or abutment, unless the foundation is a minimum of 20 feet away or has cured a minimum of 24 hours. When specified, drill pile holes before driving the piles. Drill the holes accurately so that the piles are set as shown in the Contract Documents. The maximum size of the pre-drilled holes is equal to the diameter of the pile plus 3 inches. The depth of pre-drilled pile holes is show n in the Contract Documents. If pre-drilled pile holes are not specified, the Contractor may choose to pre-drill pile holes, provided the Engineer approves the Contractor’s method and limits. After the piles are driven to their fina l positions in the pre-drilled holes, fill the holes with loose sand or material specified in the Cont ract Documents. If concrete is specified, allow sufficient concrete slump and provide vibration to fill all voids around the pile. Drive all pile heads perpendicular to the longitudinal axis of the piles to prevent eccentric impacts from the drive head of the hammer. Use pile caps on all piles during the pile driving operations. For pile caps of concrete piles and prestressed concrete piles, use a suitable cushion next to the pile head that fits into a casting that supports a timber shock block. On pile caps for steel piles and steel sheet piles, provide grooves in the bottom of the cap to accommodate the shape of the piles to hold the axis of piles in line with the axis of the hammer. On pipe pile, use a helmet with a minimum interior guide of 6 inches. If specified, use the type of cast steel pile points shown in the Contract Documents. Use pile points that provide full bearing for the piles. Provide an experienced welder to attach the cast steel pile points to the piles. Use full-length piles where practicable. It is preferred that steel piling is not spliced. Splices may be made with the permission of the Engineer, or when shown in the Contract Documents. Make splices as shown in the Contract Documents. Use an approved welding process as provided in DIVISION 700 to make the splices. Provide an experienced welder qualified under SECTION 713 to make the welded splices for structural steel piling and shell piling. Correct or replace any failure in the splice at own expense. - PILING Avoid extensions, splices or build-ups on prestressed concrete piles whenever possible. When splicing is necessary, make them as shown in the Contract Documents. If the pile driving procedure causes crushing or spallin g of the prestressed concrete piles, or deformation of the steel piles, remove and replace the damaged piles with new, longer piles. A second p ile may be driven adjacent to the damaged pile, when approved by the Engineer and can be accomplished without detriment to the structure. Do not force misaligned piles into proper position. Re move and replace piles driven out of their proper location with new, longer piles. If the driven pile is 35 feet or less in length, the maximum allowable variation from the vertical or battered lines shown in the Contract Documents is ¼ inch per foot of length. If the driven pile is greater than 35 feet in length, the maximum allowable variation from the vertical or battered lines shown in the Contract Documents is ⅛ inch per foot of length. The maximum allowable variation on the head of the driven pile from the position shown on the Contract Documents is 2 inches for piles used in bents, and 6 inches for foundation piles. Drive all piles in the orientation shown on the Plans. If the axial orientation of the pile rotates or twists by more than 10°, the Field Engineer will contact the Bureau of Structures and Geotechnical Services. Re-drive all piles pushed up by the driving of adjacent piles, or by any other cause.
bearing value, penetration and pile tip elevation. Stop dr iving the piling (regardless of the penetration) if 1½ times the specified minimum driving resistance is attained. Stop driving the piling if, in the opinion of the Engineer, the specified minimum driving resistance, penetration and pile tip elevation can not be attained without damage to the piling. If the specified minimum driving resistance is not attained with the specified number and length of piling, the Engineer may allow additional piling be driven so that the maximum load on any pile does not exceed its safe carrying capacity. In the absence of loading tests, determine the sa fe bearing values of piles by the formulas in TABLE 704- 1. - PILING TABLE 704-1: PILE FORMULAS Hammer Pile Type Formula Gravity Timber 1.0S HW2P Gravity Steel Steel Shell Steel Sheet )XW( W 35.0S HW3P Air/Steam (Single Acting) All Types 1.0S HW2P Air/Steam (Double Acting) All Types 1.0S E2P Delmag and McKierman-Terry* All Types W **X1.0S HW6.1P Link-Belt* All Types W **X1.0S E6.1P *diesel hammers ** For diesel hammers, the quantity X/W shall not be less than 1. P = safe bearing power in pounds W = weight in pounds, of striking part of hammer H = height of fall in feet E = energy of ram in foot-pounds per blow S = the average penetration in inches per blow for th e last 5 blows for gravity hammers and the last 20 blows for air/steam or diesel hammers X = weight in pounds of the pile plus the weight of any cap and/or anvil used on the pile during driving The above formulas are applicable only when: The hammer has a free fall; The penetration is reasonably quick and uniform; and There is no appreciable bounce after the blow. If water jets are used in connection with the driving, determine the bearing capacity by the formulas above from the results of driving after the jets have been withdrawn, or a load test may be applied. The energy rating used to determine if any type or brand of diesel hammer is of adequate size other than those shown in TABLE 704-1, is 80% of the energy rating as listed by the manufacturer. Use an energy rating of 100% of the energy rating listed by the manufacturer for computing bearing values and to determine if an air/steam is of adequate size. If the number of blows per minute for an air/steam hammer deviates significantly from the number designated by the manufacturer, take corrective action as directed by the manufacturer.
If a pile does not attain the minimum driving resistance within a few feet of the plan elevation, the pile restrike procedure may be used. Contact the Regional Geology Office for guidance before using the restrike procedure. Restrike procedures differ depending on whether a Test Pile, Test Pile (Special) or neither is called for in the Contract Documents. When a PDA is used, the restrike procedure will be as directed by the Regional Geologist.
Contract Documents, and the PDA is not available. The following procedure shall be used. Drive all of the piling in a group to within 2 feet of plan elevation; A group of piling is defined as all piles contained within a single footing. All of the piling in the pile group shall sit undisturbed for a minimum of 24 hours; Prior to starting the restrike procedure, warm the hammer up at a location as far away from the pile group as practical, preferably in another substructure member or pile group; - PILING Using the warmed up hammer, immediately restrike 20% of the piles in a group, with a minimum of 2 in a group restruck. Of these, restrike the piles in a single group with the furthest spacing away from each other. When possible, restrike those with the lowest resistance during driving. Restrike for 30 blows or until the pile penetrates an additional 4 inches, whichever comes first. Record the penetration for every 5 blows. In the event the pile movement is less than ½ inch during the restrike, the restrike may be terminated after 20 blows. Restrike additional (the 20% or 2 minimum specified above) pile in the group as directed by the Engineer. The driving resistance of the piling is computed based on the average penetration, if any, for the first 5 blows. The driving resistance of each piling is the driving resistance computed for the pile that was restruck. If the computed driving resistance is less than the design pile load, splice additiona l length onto each piling in the group and resume driving each piling until the required driving resistance is achieved.
not available. The following procedure must be used. Drive the Test Pile to within 2 feet of plan elevation; The Test Pile shall sit undisturbed for a minimum of 24 hours; Prior to starting the restrike procedure, warm the hammer up at a location as far away from the Test Pile as practical, preferably in another substructure member or pile group; The Test Pile is then immediately restruck with the warmed-up hammer for 30 blows or until the pile penetrates an additional 4 inches, whichever comes firs t. Record the penetration for every 5 blows. In the event the pile movement is less than ½ inch during the restrike, the restrike may be terminated after 20 blows. The driving resistance of the Test Pile is computed ba sed on the average penetration, if any, for the first 5 blows. If the computed driving resi stance is less than the design pile load, splice additional length and resume driving until the minimum driving resistance is achieved.
of the Regional Geologist for the Restrike Procedure.
required, make the connection as shown in the Contract Documents. Pile cut-off material becomes the property of KDOT, if the Engineer determines the pile cut-off material is worth salvaging. Store the salvageable material at the site selected by the Engineer. Pile cut-off material determined to not be salvageable becomes the property of the Contractor.
concrete piles. Unless otherwise noted in the Contract Documents, apply the paint in the field. Use the same kind of paint and total number of coats as specified for the stru ctural steel on the structure. If a paint system is not specified for the structure, use a prim e coat of inorganic zinc as required for the shop coat and an acrylic or polyurethane finish coat, as specified in DIVISION 700 for the final coat. Apply the paint to the pile for a distance of 1 foot below the bottom of the channel, top of the embankment, natural ground or normal low water elevation.
from inside the steel shell. Unless specified otherwise in th e Contract Documents, use Grad e 3.5 concrete to fill the steel shells. Do not place concrete in the steel shell until the driving of all steel shells within a radius of 15 feet from the pile is completed, or until all the piles for any one bent are driven. If this can not be done, discontinue all driving within the above limits until the concrete in the last pile cast is a minimum of 7 days old. Remove accumulations of water from inside the steel shells before concrete is placed. Consolidate the concrete in the upper 15 feet of the steel shell by internal vibration.
while driving the sheet piling. - PILING
704.5MEASUREMENT AND PAYMENT
The Engineer will measure the length of steel pile, steel sheet pile, cast-in-place concrete pile and prestressed concrete pile remaining in the structure, by the linear foot. The Engineer will measure the length of prestressed concrete from the tip of the pile to the point that concrete is removed to provide the connection with the cap or footing. This measurement does not include the length of reinforcing steel extending beyond the pile and into the cap or footing. The Engineer will measure the actual length of ordered a nd accepted test pile and test pile (special) by the linear foot. The Engineer will measure each cast steel pile point used. If after driving the ordered and accepted length of pile, plan bearing is not achieve d and additional pile is required, the Engineer will measure for payment each pile splice needed to lengthen the pile to achieve bearing. The Engineer will not measure for payment pile splices shown in the Contract Documents or pile splices approved for the Contractor’s convenience. The Engineer will measure pre-drilled pile holes by th e linear foot. The Engineer will measure pre-drilled pile holes from the elevation at the bottom of the hole to the bottom of the footing or abutment elevation shown in the Contract Documents. If the Contractor drills the pile holes to an elevation below that shown in the Contract Documents for bottom of hole, the additional drilling below the elevation shown in the Contract Documents is not measured for payment. Pre-drilled p ile holes not specified, but drilled for the Contractor’s convenience are not measured for payment. The Engineer will measure pile cut-off by the linear fo ot for Pile (*) (**). Pile cut-off is the difference between the length of pile ordered and accepted and the actual length of pile remaining in the structure. If the Contractor (for convenience or method of operation) uses a length of pile that exceeds the length of pile ordered and accepted, the excess length is not measured as pile cut-off. The Engineer will not measure pile cut-off of Test P ile (*) (**) and Test Pile (Special) (*) (**) for payment. If the pile for these items is cutoff and used /spliced on the project, the pile will not be measured for separate payment. Splices will be paid for according to this subsection. The Pile Restrike procedure shall not be paid for separately, but shall be subsidiary to the bid item "Piling", "Test Pile" and "Test Pile (Special)". Payment for the various types of "Piles" and "Test P iles", "Cast Steel Pile Poin ts" and "Pre-Drilled Pile Holes" at the contract unit prices is full compensation for the specified work. Payment for pile splices at 4 times the contract unit price of the type of pile spliced is full compensation for the specified work. Payment for pile cut-off per linear foot as shown in TABLE 704-2 is full compensation for the specified work. TABLE 704-2: PILE CUT-OFF PAYMENT Pile Type % of Contract Unit Price Paid Cast-in-place (Shell) 60 Pre-stressed concrete 75 Steel 75 Steel Sheet 75 The costs of all load tests ordered by the Engineer will be paid for as Extra Work as shown in SECTION 104.
Piling in other states
Get an email when 704 changes
Kansas revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.