Division 800 — Incidental Construction

837Pavement Widening, Shouldering and Pavement Edge Wedgefor Hma Overlay Projects

KS · 2015 Standard Specifications✓ Full text on BuildSpecBook pages 588–589 Save this section

Ask about Section 837

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

837 - PAVEMENT WIDENING, SHOULDERING AND PAVEMENT EDGE WEDGE FOR HMA OVERLAY PROJECTS 800-97 PAVEMENT WIDENING, SHOULDERING AND PAVEMENT EDGE WEDGE

837.1 Description

Widen the existing pavement, construct shoulders or construct the transition from the pavement edge to the ditch as shown in the Contract Documents. BID ITEMS UNITS Shoulders (Earth) (HMA Widening) Station Shoulders (Aggregate) (HMA Widening) Station Pavement Edge Wedge (Earth) Station Pavement Edge Wedge (Rock) Ton Aggregate for Shoulders (AS-1) Ton Common Excavation (Contractor-Furnished) Cubic Yard Water for Earthwork Compaction (Set Price) M Gallon

837.2 Materials

a. Material for Earth Shoulders and Pavement Edge Wedge (Earth). Use earthen material obtained from the locations shown in the Contract Documents. Do not use material containing roots, sod and other perishable and deleterious matter. When required, provide Contractor-Furnished earthen material that complies with Contractor-Furnished Common Excavation, SECTION 205. Earthen material will be accepted by the Engineer on the basis of visual inspection at the point of usage. b. Material for Aggregate Shoulders and Pavement Edge Wedge (Aggregate). Use existing aggregate that is free of roots, sod and other perishable and deleterious matter. If the project does not have existing aggregate for reuse, or if additional material is required, provide aggregate that complies with aggregate for shoulder construction (AS-1), DIVISION 1100. The Engineer will accept this material on the basi s of visual inspection at the point of usage. c. Water for Earthwork Compaction. Provide water that complies with DIVISION 2400. d. HMA Materials. Provide the designated HMA that complies with DIVISION 600.

837.3 Construction Requirements

a. Excavation for HM A Pavement Widening. Excavate along the edge of the existing pavement to the depth and width shown in the Contract Documents. Compact the bottom of the trench according to Type B (MR-90) compaction, SECTION 205 . If material unsuitable for proper compaction is encountered in the bottom of the trench, remove the unsuitable material and replace it with suitable earthen material. Dispose of the unsuitable material by scattering it at locations on the right-of-way as directed by the Engineer. Before placing any HMA material in the tren ch, clean the trench of all loose material. Provide for drainage of the trench, as necessary. b. Placing the Asphalt Material Pavement Widening.

1.Plant Mix HMA Construction. Clean the edge of the existing pavement. Paint or spray a thin coat of asphalt tack on the pavement edge. Place the HMA in the trench in 2 or more lifts. Place and compact the HMA by the method that produces the best results. Place the top lift of the HMA widening conc urrently with the roadway surfacing. Compact the top lift of HMA to comply with the density requirements of HMA Overlay, SECTION 602.
2.Cold Recycled Asphalt Construction. Place the cold recycled asphalt materi al in 1 lift. Place the material in the widening concurrently with the roadway material. Place and compact the cold recycled asphalt material by the method that produces the best results. Compact the mixture to comply with the density requirements specified for the Cold Recycled Asphalt Construction, DIVISION 600. 837 - PAVEMENT WIDENING, SHOULDERING AND PAVEMENT EDGE WEDGE FOR HMA OVERLAY PROJECTS 800-98 c. Shouldering the Asphalt or Concrete Pavement Widening. After the surface course is in place, construct the shoulders as shown in th e Contract Documents. Do not damage the pavement surfaces. Do not dump or mix material on the pavement surfaces.
1.Earth Shoulders. Use material obtained from the widening trench excavation, or Contractor-furnished material, if required, to construct the earthen shoulders. Dispose of excess earthen material (obtained from the widening trench excavation), if any, at locations on the right-of way as directed by the Engineer. Construct the earth shoulders according to SECTION 205.
2.Aggregate Shoulders. Use existing aggregate obtain ed from the project, or ag gregate provided by the Contractor, when required, to construct the aggregate shoulders. Stockpile any excess aggregate (obtained from the widening trench excavation at locations shown in the Contract Documents or locations on the project as directed by the Engineer. Construct the aggregate shoulders according to SECTION 305, except the compacti on shall comply with Type B compaction and MR-3-3 Moisture Content, SECTION 205. d. Earthen and Aggregat e Pavement Edge Wedge. After the surface course is in place, construct edge wedges as shown in the Contract Documents. Do not da mage the pavement surfaces. Do not dump or mix material on the pavement surfaces. Use the type of material indicated in the Co ntract Documents to construct the wedges. Place the material for the pavement edge wedge in a uniform layer. The maximum compacted thickness of any layer of earthen or aggregate pavement edge wedge is 6 inches. If the thickness is greater than 6 inches, spread and compact the aggregate base in multiple lifts of equal thickness with a maximum lift thickness of 6 inches. Compact the wedges to comply with Type B (MR-90) Compaction, SECTION 205.

837.4 Measurement and Payment

The Engineer will measure shoulder for asphalt widenings on each side of the roadway by the station. The excavation for the asphalt widenings is not meas ured for separate payment. The HMA quantities for the HMA widenings are included in the roadway surfacing quantities. The Engineer will measure earth pavement edge wedg e on each side of the roadway by the station. The Engineer will measure the aggregate pavement edge wedge by the ton. The Engineer will measure the ag gregate for shoulders by the ton. The Engineer will measure Contractor-furnished common excavation according to SECTION 205. The Engineer will measure water for earthwork compaction according to SECTION 205. Payment for "Shoulders (Earth) (HMA Widening)", "Shoulders (Aggregate) (HMA Widening)", "Pavement Edge Wedge (Earth)", "Pavement Edge Wedge (Rock)", "Aggregate for Shoulders (AS-1)" and "Common Excavation (Contractor-Furnished)" at the contract unit pr ices, and for "Water for Ea rthwork Compaction" at the contract unit set price is full compensation for the specified work.

Get an email when 837 changes

Kansas revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for State Road and Bridge Construction, 2015 Edition. Pages 588–589 of 978. View official source ↗