Movable Bridges
820.01 DESCRIPTION. Provide all material, equipment, tools, measuring
devices, and labor to purchase/fabricate, shop test, transport, install/erect, align/adjust, paint, lubricate, field test, and setup a Movable Bridge as specified herein. These specification govern both new construction projects and rehabi litation/ repair projects.
820.01.1 Structural Specifications: All specifications for bridges in other
sections that are applicable to the structure of a Movable Bridge shall apply, unless otherwise specified herein or shown on the plans.
820.01.2 Mechanical System Speci fications: See Section 821 for
Mechanical System specifications.
820.01.3 Electrical System Specifications: See Section 822 for
Electrical System specifications.
820.01.4 Operator’s House/Machinery House Specifications: See
Section 823 for Operator’s House/Machinery House specifications.
820.02 ACRONYMS AND ABBREVI ATIONS. See 101.02 , 801.02 , 821.02 ,
and 822.02 for acronyms and abbreviations.
820.03 DEFINITIONS. See 101.03 , 801.03 , 821.03 , and 822.03 for additional
definitions. Balance Blocks . Concrete blocks that can be added or removed from a counterweight to adjust the counterbalance of a movable span, usually weighing approximately 80 pounds. Bobtail Swing Span Bridge. A swing span bridge where the length of the movable span on the channel side of the pivot girder is longer than the opposite length. Balancing the span requires a counterweight. Movable Bridges
820.01 DESCRIPTION. Provide all material, equipment, tools, measuring
devices, and labor to purchase/fabricate, shop test, transport, install/erect, align/adjust, paint, lubricate, field test, and setup a Movable Bridge as specified herein. These specification govern both new construction projects and rehabi litation/ repair projects.
820.01.1 Structural Specifications: All specifications for bridges in other
sections that are applicable to the structure of a Movable Bridge shall apply, unless otherwise specified herein or shown on the plans.
820.01.2 Mechanical System Speci fications: See Section 821 for
Mechanical System specifications.
820.01.3 Electrical System Specifications: See Section 822 for
Electrical System specifications.
820.01.4 Operator’s House/Machinery House Specifications: See
Section 823 for Operator’s House/Machinery House specifications.
820.02 ACRONYMS AND ABBREVI ATIONS. See 101.02 , 801.02 , 821.02 ,
and 822.02 for acronyms and abbreviations.
820.03 DEFINITIONS. See 101.03 , 801.03 , 821.03 , and 822.03 for additional
definitions. Balance Blocks . Concrete blocks that can be added or removed from a counterweight to adjust the counterbalance of a movable span, usually weighing approximately 80 pounds. Bobtail Swing Span Bridge. A swing span bridge where the length of the movable span on the channel side of the pivot girder is longer than the opposite length. Balancing the span requires a counterweight. Movable Bridges
820.01 DESCRIPTION. Provide all material, equipment, tools, measuring
devices, and labor to purchase/fabricate, shop test, transport, install/erect, align/adjust, paint, lubricate, field test, and setup a Movable Bridge as specified herein. These specification govern both new construction projects and rehabi litation/ repair projects.
820.01.1 Structural Specifications: All specifications for bridges in other
sections that are applicable to the structure of a Movable Bridge shall apply, unless otherwise specified herein or shown on the plans.
820.01.2 Mechanical System Speci fications: See Section 821 for
Mechanical System specifications.
820.01.3 Electrical System Specifications: See Section 822 for
Electrical System specifications.
820.01.4 Operator’s House/Machinery House Specifications: See
Section 823 for Operator’s House/Machinery House specifications.
820.02 ACRONYMS AND ABBREVI ATIONS. See 101.02 , 801.02 , 821.02 ,
and 822.02 for acronyms and abbreviations.
820.03 DEFINITIONS. See 101.03 , 801.03 , 821.03 , and 822.03 for additional
definitions. Balance Blocks . Concrete blocks that can be added or removed from a counterweight to adjust the counterbalance of a movable span, usually weighing approximately 80 pounds. Bobtail Swing Span Bridge. A swing span bridge where the length of the movable span on the channel side of the pivot girder is longer than the opposite length. Balancing the span requires a counterweight. Movable Bridges
820.01 DESCRIPTION. Provide all material, equipment, tools, measuring
devices, and labor to purchase/fabricate, shop test, transport, install/erect, align/adjust, paint, lubricate, field test, and setup a Movable Bridge as specified herein. These specification govern both new construction projects and rehabi litation/ repair projects.
820.01.1 Structural Specifications: All specifications for bridges in other
sections that are applicable to the structure of a Movable Bridge shall apply, unless otherwise specified herein or shown on the plans.
820.01.2 Mechanical System Speci fications: See Section 821 for
Mechanical System specifications.
820.01.3 Electrical System Specifications: See Section 822 for
Electrical System specifications.
820.01.4 Operator’s House/Machinery House Specifications: See
Section 823 for Operator’s House/Machinery House specifications.
820.02 ACRONYMS AND ABBREVI ATIONS. See 101.02 , 801.02 , 821.02 ,
and 822.02 for acronyms and abbreviations.
820.03 DEFINITIONS. See 101.03 , 801.03 , 821.03 , and 822.03 for additional
definitions. Balance Blocks . Concrete blocks that can be added or removed from a counterweight to adjust the counterbalance of a movable span, usually weighing approximately 80 pounds. Bobtail Swing Span Bridge. A swing span bridge where the length of the movable span on the channel side of the pivot girder is longer than the opposite length. Balancing the span requires a counterweight. Movable Bridges
820.01 DESCRIPTION. Provide all material, equipment, tools, measuring
devices, and labor to purchase/fabricate, shop test, transport, install/erect, align/adjust, paint, lubricate, field test, and setup a Movable Bridge as specified herein. These specification govern both new construction projects and rehabi litation/ repair projects.
820.01.1 Structural Specifications: All specifications for bridges in other
sections that are applicable to the structure of a Movable Bridge shall apply, unless otherwise specified herein or shown on the plans.
820.01.2 Mechanical System Speci fications: See Section 821 for
Mechanical System specifications.
820.01.3 Electrical System Specifications: See Section 822 for
Electrical System specifications.
820.01.4 Operator’s House/Machinery House Specifications: See
Section 823 for Operator’s House/Machinery House specifications.
820.02 ACRONYMS AND ABBREVI ATIONS. See 101.02 , 801.02 , 821.02 ,
and 822.02 for acronyms and abbreviations.
820.03 DEFINITIONS. See 101.03 , 801.03 , 821.03 , and 822.03 for additional
definitions. Balance Blocks . Concrete blocks that can be added or removed from a counterweight to adjust the counterbalance of a movable span, usually weighing approximately 80 pounds. Bobtail Swing Span Bridge. A swing span bridge where the length of the movable span on the channel side of the pivot girder is longer than the opposite length. Balancing the span requires a counterweight. Movable Bridges
820.01 DESCRIPTION. Provide all material, equipment, tools, measuring
devices, and labor to purchase/fabricate, shop test, transport, install/erect, align/adjust, paint, lubricate, field test, and setup a Movable Bridge as specified herein. These specification govern both new construction projects and rehabi litation/ repair projects.
820.01.1 Structural Specifications: All specifications for bridges in other
sections that are applicable to the structure of a Movable Bridge shall apply, unless otherwise specified herein or shown on the plans.
820.01.2 Mechanical System Speci fications: See Section 821 for
Mechanical System specifications.
820.01.3 Electrical System Specifications: See Section 822 for
Electrical System specifications.
820.01.4 Operator’s House/Machinery House Specifications: See
Section 823 for Operator’s House/Machinery House specifications.
820.02 ACRONYMS AND ABBREVI ATIONS. See 101.02 , 801.02 , 821.02 ,
and 822.02 for acronyms and abbreviations.
820.03 DEFINITIONS. See 101.03 , 801.03 , 821.03 , and 822.03 for additional
definitions. Balance Blocks . Concrete blocks that can be added or removed from a counterweight to adjust the counterbalance of a movable span, usually weighing approximately 80 pounds. Bobtail Swing Span Bridge. A swing span bridge where the length of the movable span on the channel side of the pivot girder is longer than the opposite length. Balancing the span requires a counterweight. Movable Bridges
820.01 DESCRIPTION. Provide all material, equipment, tools, measuring
devices, and labor to purchase/fabricate, shop test, transport, install/erect, align/adjust, paint, lubricate, field test, and setup a Movable Bridge as specified herein. These specification govern both new construction projects and rehabi litation/ repair projects.
820.01.1 Structural Specifications: All specifications for bridges in other
sections that are applicable to the structure of a Movable Bridge shall apply, unless otherwise specified herein or shown on the plans.
820.01.2 Mechanical System Speci fications: See Section 821 for
Mechanical System specifications.
820.01.3 Electrical System Specifications: See Section 822 for
Electrical System specifications.
820.01.4 Operator’s House/Machinery House Specifications: See
Section 823 for Operator’s House/Machinery House specifications.
820.02 ACRONYMS AND ABBREVI ATIONS. See 101.02 , 801.02 , 821.02 ,
and 822.02 for acronyms and abbreviations.
820.03 DEFINITIONS. See 101.03 , 801.03 , 821.03 , and 822.03 for additional
definitions. Balance Blocks . Concrete blocks that can be added or removed from a counterweight to adjust the counterbalance of a movable span, usually weighing approximately 80 pounds. Bobtail Swing Span Bridge. A swing span bridge where the length of the movable span on the channel side of the pivot girder is longer than the opposite length. Balancing the span requires a counterweight. Counterweight . A large heavy concret e and/or steel structure used to counterbalance the weight of a movable span or a movable barrier. Equal Arm Swing Span Bridge. A swing span bridge where the length of the movable span on the channel side of the pivot girder is equal to the opposite leng th. Lift Tower . Towers on a vertical lift bridge that facilitate lifting of the movable span. Machinery Deck . Platform on top of a vertical lift bridge lift tower where the span drive machinery is located. Movable Barrier . A barrier that is lowered p erpendicular to the roadway to provide a physical barrier to vehicular traffic when a movable bridge is open to marine traffic. Movable Bridge . A bridge, usually crossing a navigable waterway that has a span that can be moved to open the waterway for mar ine navigation. Movable Bridge ( Bascule Span ). A movable bridge that has a cantilevered movable span which rotates vertically about a horizontal axis to allow marine navigation of the waterway with unlimited vertical clearance. Movable Bridge (Pontoon Span ). A movable bridge that has a floating movable span which rotates horizontally about a pivot point to allow marine navigation of the waterway with unlimited vertical clearance. The floating span becomes part of the fender system when the span is in t he open position. Movable Bridge ( Swing Span ). A movable bridge that has a cantilevered movable span which rotates horizontally about a vertical axis to allow marine navigation of the waterway with unlimited vertical clearance. Movable Bridge ( Vertical Lift Span ). A movable bridge that has a counterweighted movable span which lifts vertically between two towers to allow marine navigation of the waterway with limited vertical clearance. Movable Span . The span on a movable bridge that can move by means of permanently installed mechanical and electrical systems to allow marine navigation of the waterway. Pivot Girder . Girder on a swing span bridge that is located on the center pivot bearing and supports the entire weight of the movable span during operation. Sheave . Large pulley located on top the lift towers of a vertical lift bridge which support the counterweight, counterweight wire ropes, and the movable span. Sheaves facilitate counterbalancing and movement of the movable span. Sheave Trunn ion. Large axle on which a sheave rotates . Span Trunnion . Large axle on which a bascule span rotates. System Integrator . A designated representative of the contractor that has the knowledge, experience, responsibility, and authority to integrate the work of all engineering disciplines related to the project. Traffic Gate . A gate that is lowered perpendicular to the roadway to provide a visual warning to vehicular traffic when a movable bridge is open to marine traffic. Trunnion . Large axle on whic h any heavy movable structure or component rotates. (e.g. bascule span, sheave, counterweight, etc.) Trunnion Bearings . Large sleeve or roller bearings that facilitate rotation of a trunnion. Unequal Arm Swing Span Bridge. See “Bobtail Swing Span .”
820.04 Materials.
Structural Concrete 805.02 Reinforcing Steel 806.02 Structural Metals 807.02 Steel Grid Flooring 808.02 Bridge Railings, Hand Railings and Permanent Roadway Barriers 810.02 Painting and Protective Coatings 811.03 Treated Timber 812.02 Concrete Approach Slabs 813.02 Bearings 814.02 Joints 815.02 Drainage Systems 816.02 Mechanical Systems 821.04 Electrical Systems 822.04 Facilities 823.04 Portland Cement Concrete 901.02 Epoxy Resin Systems Section 1017 All material for fabricated items and all construction material for movable bridges shall be new.
820.05 General Requirements .
820.05.1 Federal, State, and Local Codes and Laws: Providing work in
accordan ce with Federal, State, and local codes, laws, ordinances, and codes listed in 821.05.1 is a minimum requirement. Work specified in the Contract that is more Trunnion . Large axle on whic h any heavy movable structure or component rotates. (e.g. bascule span, sheave, counterweight, etc.) Trunnion Bearings . Large sleeve or roller bearings that facilitate rotation of a trunnion. Unequal Arm Swing Span Bridge. See “Bobtail Swing Span .”
820.04 Materials.
Structural Concrete 805.02 Reinforcing Steel 806.02 Structural Metals 807.02 Steel Grid Flooring 808.02 Bridge Railings, Hand Railings and Permanent Roadway Barriers 810.02 Painting and Protective Coatings 811.03 Treated Timber 812.02 Concrete Approach Slabs 813.02 Bearings 814.02 Joints 815.02 Drainage Systems 816.02 Mechanical Systems 821.04 Electrical Systems 822.04 Facilities 823.04 Portland Cement Concrete 901.02 Epoxy Resin Systems Section 1017 All material for fabricated items and all construction material for movable bridges shall be new.
820.05 General Requirements .
820.05.1 Federal, State, and Local Codes and Laws: Providing work in
accordan ce with Federal, State, and local codes, laws, ordinances, and codes listed in 821.05.1 is a minimum requirement. Work specified in the Contract that is more Trunnion . Large axle on whic h any heavy movable structure or component rotates. (e.g. bascule span, sheave, counterweight, etc.) Trunnion Bearings . Large sleeve or roller bearings that facilitate rotation of a trunnion. Unequal Arm Swing Span Bridge. See “Bobtail Swing Span .”
820.04 Materials.
Structural Concrete 805.02 Reinforcing Steel 806.02 Structural Metals 807.02 Steel Grid Flooring 808.02 Bridge Railings, Hand Railings and Permanent Roadway Barriers 810.02 Painting and Protective Coatings 811.03 Treated Timber 812.02 Concrete Approach Slabs 813.02 Bearings 814.02 Joints 815.02 Drainage Systems 816.02 Mechanical Systems 821.04 Electrical Systems 822.04 Facilities 823.04 Portland Cement Concrete 901.02 Epoxy Resin Systems Section 1017 All material for fabricated items and all construction material for movable bridges shall be new.
820.05 General Requirements .
820.05.1 Federal, State, and Local Codes and Laws: Providing work in
accordan ce with Federal, State, and local codes, laws, ordinances, and codes listed in 821.05.1 is a minimum requirement. Work specified in the Contract that is more Trunnion . Large axle on whic h any heavy movable structure or component rotates. (e.g. bascule span, sheave, counterweight, etc.) Trunnion Bearings . Large sleeve or roller bearings that facilitate rotation of a trunnion. Unequal Arm Swing Span Bridge. See “Bobtail Swing Span .”
820.04 Materials.
Structural Concrete 805.02 Reinforcing Steel 806.02 Structural Metals 807.02 Steel Grid Flooring 808.02 Bridge Railings, Hand Railings and Permanent Roadway Barriers 810.02 Painting and Protective Coatings 811.03 Treated Timber 812.02 Concrete Approach Slabs 813.02 Bearings 814.02 Joints 815.02 Drainage Systems 816.02 Mechanical Systems 821.04 Electrical Systems 822.04 Facilities 823.04 Portland Cement Concrete 901.02 Epoxy Resin Systems Section 1017 All material for fabricated items and all construction material for movable bridges shall be new.
820.05 General Requirements .
820.05.1 Federal, State, and Local Codes and Laws: Providing work in
accordan ce with Federal, State, and local codes, laws, ordinances, and codes listed in 821.05.1 is a minimum requirement. Work specified in the Contract that is more stringent than that required by the Federal, State, and local codes, laws, and ordinances shall also be provided. Work that does not meet the requirements of the Federal , State, and local codes, laws, and ordinances, and/or the Contract documents shall be corrected at no additional cost or time to the Department.
820.05.2 Specifications and Standards: Comply with 821.05.2 unless
otherwise specified.
820.05.3 Workmanship: Unless otherwise directed, use best industry
practices at all times during th e fabrication, transportation, erection, installation, alignment, adjustment, and testing of the movable bridge structure and performance of all related work.
820.05.4 Personnel: Provide construction personnel who are
knowledgeable and experienced in the constr uction of movable bridges or other similar heavy movable structures. Although the plans are of sufficient detail and quality to convey the intent of the design to an experienced contractor, they do not necessarily depict every detail or specify every incid ental or ancillary item required for the movable bridge to be properly fabricated, transported, erected, aligned, adjusted, tested, painted, and to function in accordance with the intent of the Contract. Provide a “System Integrator” to perform the followi ng:
820.05.2 Specifications and Standards: Comply with 821.05.2 unless
otherwise specified.
820.05.3 Workmanship: Unless otherwise directed, use best industry
practices at all times during th e fabrication, transportation, erection, installation, alignment, adjustment, and testing of the movable bridge structure and performance of all related work.
820.05.4 Personnel: Provide construction personnel who are
knowledgeable and experienced in the constr uction of movable bridges or other similar heavy movable structures. Although the plans are of sufficient detail and quality to convey the intent of the design to an experienced contractor, they do not necessarily depict every detail or specify every incid ental or ancillary item required for the movable bridge to be properly fabricated, transported, erected, aligned, adjusted, tested, painted, and to function in accordance with the intent of the Contract. Provide a “System Integrator” to perform the followi ng:
820.05.2 Specifications and Standards: Comply with 821.05.2 unless
otherwise specified.
820.05.3 Workmanship: Unless otherwise directed, use best industry
practices at all times during th e fabrication, transportation, erection, installation, alignment, adjustment, and testing of the movable bridge structure and performance of all related work.
820.05.4 Personnel: Provide construction personnel who are
knowledgeable and experienced in the constr uction of movable bridges or other similar heavy movable structures. Although the plans are of sufficient detail and quality to convey the intent of the design to an experienced contractor, they do not necessarily depict every detail or specify every incid ental or ancillary item required for the movable bridge to be properly fabricated, transported, erected, aligned, adjusted, tested, painted, and to function in accordance with the intent of the Contract. Provide a “System Integrator” to perform the followi ng:
820.05.2 Specifications and Standards: Comply with 821.05.2 unless
otherwise specified.
820.05.3 Workmanship: Unless otherwise directed, use best industry
practices at all times during th e fabrication, transportation, erection, installation, alignment, adjustment, and testing of the movable bridge structure and performance of all related work.
820.05.4 Personnel: Provide construction personnel who are
knowledgeable and experienced in the constr uction of movable bridges or other similar heavy movable structures. Although the plans are of sufficient detail and quality to convey the intent of the design to an experienced contractor, they do not necessarily depict every detail or specify every incid ental or ancillary item required for the movable bridge to be properly fabricated, transported, erected, aligned, adjusted, tested, painted, and to function in accordance with the intent of the Contract. Provide a “System Integrator” to perform the followi ng:
820.06 Movable Bridge Submi Ttals.
Movable Bridge submittals shall comply with Section 105.02.2 , 801.05 , 821.06 , and 822.06 . They include shop drawings, cut sheets, field measurements, calculations, manuals, and any other document that the contractor is required by the Contr act to produce and submit to the Bridge Engineer for review or record. The purchase or fabrication of any item prior to the completion of the submittal process is at the contractor’s risk. Said items that are later determined to be unacceptable for use on the project, will be rejected by the Department at the contractor’s expense, even if the items purchased or fabricated are identical to that shown on the contract documents (plan error). Always copy the Project Engineer whenever transmitting submittals.
820.06.1 Lubrication and Equipment Setting Drawings: Prepare and
submit lubrication and equipment setting drawings to the Bridge Engineer for review. Lubrication and equipment setting drawings shall show the layout of all mechanical and electrical items on the br idge structure. Identify each lubrication point with an arrow and list lubricant type and frequency of lubrication. Lubrication of manufactured items shall be based on the manufacturer's recommendations. Point to, and identify, mechanical and electrical it ems with pertinent set points, and list the set point values (e.g. Relief Valve, 1,500 psi). These sheets should not be prepared until the final setup of the bridge has been completed.
820.06 Movable Bridge Submi Ttals.
Movable Bridge submittals shall comply with Section 105.02.2 , 801.05 , 821.06 , and 822.06 . They include shop drawings, cut sheets, field measurements, calculations, manuals, and any other document that the contractor is required by the Contr act to produce and submit to the Bridge Engineer for review or record. The purchase or fabrication of any item prior to the completion of the submittal process is at the contractor’s risk. Said items that are later determined to be unacceptable for use on the project, will be rejected by the Department at the contractor’s expense, even if the items purchased or fabricated are identical to that shown on the contract documents (plan error). Always copy the Project Engineer whenever transmitting submittals.
820.06.1 Lubrication and Equipment Setting Drawings: Prepare and
submit lubrication and equipment setting drawings to the Bridge Engineer for review. Lubrication and equipment setting drawings shall show the layout of all mechanical and electrical items on the br idge structure. Identify each lubrication point with an arrow and list lubricant type and frequency of lubrication. Lubrication of manufactured items shall be based on the manufacturer's recommendations. Point to, and identify, mechanical and electrical it ems with pertinent set points, and list the set point values (e.g. Relief Valve, 1,500 psi). These sheets should not be prepared until the final setup of the bridge has been completed.
820.06 Movable Bridge Submi Ttals.
Movable Bridge submittals shall comply with Section 105.02.2 , 801.05 , 821.06 , and 822.06 . They include shop drawings, cut sheets, field measurements, calculations, manuals, and any other document that the contractor is required by the Contr act to produce and submit to the Bridge Engineer for review or record. The purchase or fabrication of any item prior to the completion of the submittal process is at the contractor’s risk. Said items that are later determined to be unacceptable for use on the project, will be rejected by the Department at the contractor’s expense, even if the items purchased or fabricated are identical to that shown on the contract documents (plan error). Always copy the Project Engineer whenever transmitting submittals.
820.06.1 Lubrication and Equipment Setting Drawings: Prepare and
submit lubrication and equipment setting drawings to the Bridge Engineer for review. Lubrication and equipment setting drawings shall show the layout of all mechanical and electrical items on the br idge structure. Identify each lubrication point with an arrow and list lubricant type and frequency of lubrication. Lubrication of manufactured items shall be based on the manufacturer's recommendations. Point to, and identify, mechanical and electrical it ems with pertinent set points, and list the set point values (e.g. Relief Valve, 1,500 psi). These sheets should not be prepared until the final setup of the bridge has been completed.
820.06.2 Manuals: For all movable bridge projects, prepare and submit the
following manuals. Cost of preparing and submitting the manuals shall be included in th e pay items of Sections of 821, 822, and 823. The Department will withhold 5 percent of the bid price of all mechanical, electrical, and facility items (821, 822, and 823 items) until all manuals have been reviewed and accepted, and final paper reproductio ns have been received by the Department.
820.06.2 Manuals: For all movable bridge projects, prepare and submit the
following manuals. Cost of preparing and submitting the manuals shall be included in th e pay items of Sections of 821, 822, and 823. The Department will withhold 5 percent of the bid price of all mechanical, electrical, and facility items (821, 822, and 823 items) until all manuals have been reviewed and accepted, and final paper reproductio ns have been received by the Department.
820.07 Construction Require Ments.
820.07.1 Position of Movable Span during Construction: For new
construction, the movable span(s) may be erected in the “open to navigation” or “closed to navigation” positions as allowed by the plans and the Project Engineer. At all times, construction must comply with the United States Coast Guard (USCG) permit or negotiated agreement with the USCG. Maintain marine and vehicular traffic requirem ents and closures as specified in the plans.
820.07.2 Survey of Structural Elements: Perform all survey
measurements of structural bridge elements that may be affected by temperature and sunlight in the early morning prior to development of a temperature differential in the structure.
820.07.3 Shop Assembly of Structural Steel: Shop assemble the
structural steel for all movable spans in accordance with 807.04.10 and mark for reassembly in accordance with 807.04.24 .
820.07.4 Construction Sequence: Adhere to construction sequencing
specified herein unless otherwise specified on the plans. Any deviation from the construction sequencing must be submitted to the Bridge Engineer for review.
820.07.5 Concrete Test Blocks: Provide test blocks to determine the
exact density (weight) of the concrete individually for the movable span deck (if applicable), the counterweight, and the balance blocks. All concrete shall be Class A unless otherwise noted on the plans. Cast test blocks early enough in the construction period such that the test data will be available when it is time for the contractor to perform counterweight calculations. If the paper reproductions of the Bridge Operation Manual are rejected after review, the title sheet of both copies will be stamped “Returned for Correction,” and both copies will be returned to the contractor with instructions for corrections. Correct errors and resubmit to the Bridge Engineer for review. This process will repeat until the Department has no comments. The title sheet will then be stamped “Accepted in accordance with LSSRB 105.02 ,” initialed and dated by the reviewer, and distributed by the Department.
820.07 Construction Require Ments.
820.07.1 Position of Movable Span during Construction: For new
construction, the movable span(s) may be erected in the “open to navigation” or “closed to navigation” positions as allowed by the plans and the Project Engineer. At all times, construction must comply with the United States Coast Guard (USCG) permit or negotiated agreement with the USCG. Maintain marine and vehicular traffic requirem ents and closures as specified in the plans.
820.07.2 Survey of Structural Elements: Perform all survey
measurements of structural bridge elements that may be affected by temperature and sunlight in the early morning prior to development of a temperature differential in the structure.
820.07.3 Shop Assembly of Structural Steel: Shop assemble the
structural steel for all movable spans in accordance with 807.04.10 and mark for reassembly in accordance with 807.04.24 .
820.07.4 Construction Sequence: Adhere to construction sequencing
specified herein unless otherwise specified on the plans. Any deviation from the construction sequencing must be submitted to the Bridge Engineer for review.
820.07.5 Concrete Test Blocks: Provide test blocks to determine the
exact density (weight) of the concrete individually for the movable span deck (if applicable), the counterweight, and the balance blocks. All concrete shall be Class A unless otherwise noted on the plans. Cast test blocks early enough in the construction period such that the test data will be available when it is time for the contractor to perform counterweight calculations. If the paper reproductions of the Bridge Operation Manual are rejected after review, the title sheet of both copies will be stamped “Returned for Correction,” and both copies will be returned to the contractor with instructions for corrections. Correct errors and resubmit to the Bridge Engineer for review. This process will repeat until the Department has no comments. The title sheet will then be stamped “Accepted in accordance with LSSRB 105.02 ,” initialed and dated by the reviewer, and distributed by the Department.
820.07 Construction Require Ments.
820.07.1 Position of Movable Span during Construction: For new
construction, the movable span(s) may be erected in the “open to navigation” or “closed to navigation” positions as allowed by the plans and the Project Engineer. At all times, construction must comply with the United States Coast Guard (USCG) permit or negotiated agreement with the USCG. Maintain marine and vehicular traffic requirem ents and closures as specified in the plans.
820.07.2 Survey of Structural Elements: Perform all survey
measurements of structural bridge elements that may be affected by temperature and sunlight in the early morning prior to development of a temperature differential in the structure.
820.07.3 Shop Assembly of Structural Steel: Shop assemble the
structural steel for all movable spans in accordance with 807.04.10 and mark for reassembly in accordance with 807.04.24 .
820.07.4 Construction Sequence: Adhere to construction sequencing
specified herein unless otherwise specified on the plans. Any deviation from the construction sequencing must be submitted to the Bridge Engineer for review.
820.07.5 Concrete Test Blocks: Provide test blocks to determine the
exact density (weight) of the concrete individually for the movable span deck (if applicable), the counterweight, and the balance blocks. All concrete shall be Class A unless otherwise noted on the plans. Cast test blocks early enough in the construction period such that the test data will be available when it is time for the contractor to perform counterweight calculations. If the paper reproductions of the Bridge Operation Manual are rejected after review, the title sheet of both copies will be stamped “Returned for Correction,” and both copies will be returned to the contractor with instructions for corrections. Correct errors and resubmit to the Bridge Engineer for review. This process will repeat until the Department has no comments. The title sheet will then be stamped “Accepted in accordance with LSSRB 105.02 ,” initialed and dated by the reviewer, and distributed by the Department.
820.07 Construction Require Ments.
820.07.1 Position of Movable Span during Construction: For new
construction, the movable span(s) may be erected in the “open to navigation” or “closed to navigation” positions as allowed by the plans and the Project Engineer. At all times, construction must comply with the United States Coast Guard (USCG) permit or negotiated agreement with the USCG. Maintain marine and vehicular traffic requirem ents and closures as specified in the plans.
820.07.2 Survey of Structural Elements: Perform all survey
measurements of structural bridge elements that may be affected by temperature and sunlight in the early morning prior to development of a temperature differential in the structure.
820.07.3 Shop Assembly of Structural Steel: Shop assemble the
structural steel for all movable spans in accordance with 807.04.10 and mark for reassembly in accordance with 807.04.24 .
820.07.4 Construction Sequence: Adhere to construction sequencing
specified herein unless otherwise specified on the plans. Any deviation from the construction sequencing must be submitted to the Bridge Engineer for review.
820.07.5 Concrete Test Blocks: Provide test blocks to determine the
exact density (weight) of the concrete individually for the movable span deck (if applicable), the counterweight, and the balance blocks. All concrete shall be Class A unless otherwise noted on the plans. Cast test blocks early enough in the construction period such that the test data will be available when it is time for the contractor to perform counterweight calculations. If the paper reproductions of the Bridge Operation Manual are rejected after review, the title sheet of both copies will be stamped “Returned for Correction,” and both copies will be returned to the contractor with instructions for corrections. Correct errors and resubmit to the Bridge Engineer for review. This process will repeat until the Department has no comments. The title sheet will then be stamped “Accepted in accordance with LSSRB 105.02 ,” initialed and dated by the reviewer, and distributed by the Department.
820.07 Construction Require Ments.
820.07.1 Position of Movable Span during Construction: For new
construction, the movable span(s) may be erected in the “open to navigation” or “closed to navigation” positions as allowed by the plans and the Project Engineer. At all times, construction must comply with the United States Coast Guard (USCG) permit or negotiated agreement with the USCG. Maintain marine and vehicular traffic requirem ents and closures as specified in the plans.
820.07.2 Survey of Structural Elements: Perform all survey
measurements of structural bridge elements that may be affected by temperature and sunlight in the early morning prior to development of a temperature differential in the structure.
820.07.3 Shop Assembly of Structural Steel: Shop assemble the
structural steel for all movable spans in accordance with 807.04.10 and mark for reassembly in accordance with 807.04.24 .
820.07.4 Construction Sequence: Adhere to construction sequencing
specified herein unless otherwise specified on the plans. Any deviation from the construction sequencing must be submitted to the Bridge Engineer for review.
820.07.5 Concrete Test Blocks: Provide test blocks to determine the
exact density (weight) of the concrete individually for the movable span deck (if applicable), the counterweight, and the balance blocks. All concrete shall be Class A unless otherwise noted on the plans. Cast test blocks early enough in the construction period such that the test data will be available when it is time for the contractor to perform counterweight calculations. If the paper reproductions of the Bridge Operation Manual are rejected after review, the title sheet of both copies will be stamped “Returned for Correction,” and both copies will be returned to the contractor with instructions for corrections. Correct errors and resubmit to the Bridge Engineer for review. This process will repeat until the Department has no comments. The title sheet will then be stamped “Accepted in accordance with LSSRB 105.02 ,” initialed and dated by the reviewer, and distributed by the Department.
820.07 Construction Require Ments.
820.07.1 Position of Movable Span during Construction: For new
construction, the movable span(s) may be erected in the “open to navigation” or “closed to navigation” positions as allowed by the plans and the Project Engineer. At all times, construction must comply with the United States Coast Guard (USCG) permit or negotiated agreement with the USCG. Maintain marine and vehicular traffic requirem ents and closures as specified in the plans.
820.07.2 Survey of Structural Elements: Perform all survey
measurements of structural bridge elements that may be affected by temperature and sunlight in the early morning prior to development of a temperature differential in the structure.
820.07.3 Shop Assembly of Structural Steel: Shop assemble the
structural steel for all movable spans in accordance with 807.04.10 and mark for reassembly in accordance with 807.04.24 .
820.07.4 Construction Sequence: Adhere to construction sequencing
specified herein unless otherwise specified on the plans. Any deviation from the construction sequencing must be submitted to the Bridge Engineer for review.
820.07.5 Concrete Test Blocks: Provide test blocks to determine the
exact density (weight) of the concrete individually for the movable span deck (if applicable), the counterweight, and the balance blocks. All concrete shall be Class A unless otherwise noted on the plans. Cast test blocks early enough in the construction period such that the test data will be available when it is time for the contractor to perform counterweight calculations. If the paper reproductions of the Bridge Operation Manual are rejected after review, the title sheet of both copies will be stamped “Returned for Correction,” and both copies will be returned to the contractor with instructions for corrections. Correct errors and resubmit to the Bridge Engineer for review. This process will repeat until the Department has no comments. The title sheet will then be stamped “Accepted in accordance with LSSRB 105.02 ,” initialed and dated by the reviewer, and distributed by the Department.
820.07 Construction Require Ments.
820.07.1 Position of Movable Span during Construction: For new
construction, the movable span(s) may be erected in the “open to navigation” or “closed to navigation” positions as allowed by the plans and the Project Engineer. At all times, construction must comply with the United States Coast Guard (USCG) permit or negotiated agreement with the USCG. Maintain marine and vehicular traffic requirem ents and closures as specified in the plans.
820.07.2 Survey of Structural Elements: Perform all survey
measurements of structural bridge elements that may be affected by temperature and sunlight in the early morning prior to development of a temperature differential in the structure.
820.07.3 Shop Assembly of Structural Steel: Shop assemble the
structural steel for all movable spans in accordance with 807.04.10 and mark for reassembly in accordance with 807.04.24 .
820.07.4 Construction Sequence: Adhere to construction sequencing
specified herein unless otherwise specified on the plans. Any deviation from the construction sequencing must be submitted to the Bridge Engineer for review.
820.07.5 Concrete Test Blocks: Provide test blocks to determine the
exact density (weight) of the concrete individually for the movable span deck (if applicable), the counterweight, and the balance blocks. All concrete shall be Class A unless otherwise noted on the plans. Cast test blocks early enough in the construction period such that the test data will be available when it is time for the contractor to perform counterweight calculations. Casting and weighing test blocks must be per formed in the presence of the Project Engineer. Notify the Project Engineer at least three working days in advance. Test blocks shall be of known volume, and shall contain at least one cubic foot (0.03 cu
820.07.6 Construction of Counterweight:
820.07.6 Construction of Counterweight:
820.07.7 Installation of Alignment Critical Mechanical Equipment:
Alignment critical mechanical equipment such as trunnion bearings, gears, drive shafts, gearboxes, brakes, shaft couplings, etc., shall be installed by millwrights experienced in the installation of the specified equipment. Use industry standard alignment equipment and techniques. Alignments shall meet tolerances specified in the Contract, or the manufacturer’s minimum requirements, whichever is more stringent.
820.07.8 Temporary Operation and Maintenance of Movable Span:
Provide qualified personnel to operate a nd maintain the movable bridge as directed below. All bridge operations shall be in accordance with the United States Coast Guard (USCG) permit or negotiated agreement with the USCG. While operating the movable bridge, the contractor is responsible for mai ntenance of the structure. In addition to 107.19 , damages that are the result of either negligent operation or negligent maintenance are the responsibility of the c ontractor.
820.07.9 Final Setup, and Field Testing of Mechanical and Electrical
Systems: Notify the Bridge Engineer 14 calendar days prior to final setup and field testing so the EOR may be present. After installation of all mechanical an d electrical systems has been completed and all weight that will remain on the movable span during operation is in place, adjust and test all mechanical and electrical systems as directed by the plans.
820.07.7 Installation of Alignment Critical Mechanical Equipment:
Alignment critical mechanical equipment such as trunnion bearings, gears, drive shafts, gearboxes, brakes, shaft couplings, etc., shall be installed by millwrights experienced in the installation of the specified equipment. Use industry standard alignment equipment and techniques. Alignments shall meet tolerances specified in the Contract, or the manufacturer’s minimum requirements, whichever is more stringent.
820.07.8 Temporary Operation and Maintenance of Movable Span:
Provide qualified personnel to operate a nd maintain the movable bridge as directed below. All bridge operations shall be in accordance with the United States Coast Guard (USCG) permit or negotiated agreement with the USCG. While operating the movable bridge, the contractor is responsible for mai ntenance of the structure. In addition to 107.19 , damages that are the result of either negligent operation or negligent maintenance are the responsibility of the c ontractor.
820.07.9 Final Setup, and Field Testing of Mechanical and Electrical
Systems: Notify the Bridge Engineer 14 calendar days prior to final setup and field testing so the EOR may be present. After installation of all mechanical an d electrical systems has been completed and all weight that will remain on the movable span during operation is in place, adjust and test all mechanical and electrical systems as directed by the plans.
820.07.7 Installation of Alignment Critical Mechanical Equipment:
Alignment critical mechanical equipment such as trunnion bearings, gears, drive shafts, gearboxes, brakes, shaft couplings, etc., shall be installed by millwrights experienced in the installation of the specified equipment. Use industry standard alignment equipment and techniques. Alignments shall meet tolerances specified in the Contract, or the manufacturer’s minimum requirements, whichever is more stringent.
820.07.8 Temporary Operation and Maintenance of Movable Span:
Provide qualified personnel to operate a nd maintain the movable bridge as directed below. All bridge operations shall be in accordance with the United States Coast Guard (USCG) permit or negotiated agreement with the USCG. While operating the movable bridge, the contractor is responsible for mai ntenance of the structure. In addition to 107.19 , damages that are the result of either negligent operation or negligent maintenance are the responsibility of the c ontractor.
820.07.9 Final Setup, and Field Testing of Mechanical and Electrical
Systems: Notify the Bridge Engineer 14 calendar days prior to final setup and field testing so the EOR may be present. After installation of all mechanical an d electrical systems has been completed and all weight that will remain on the movable span during operation is in place, adjust and test all mechanical and electrical systems as directed by the plans.
820.07.7 Installation of Alignment Critical Mechanical Equipment:
Alignment critical mechanical equipment such as trunnion bearings, gears, drive shafts, gearboxes, brakes, shaft couplings, etc., shall be installed by millwrights experienced in the installation of the specified equipment. Use industry standard alignment equipment and techniques. Alignments shall meet tolerances specified in the Contract, or the manufacturer’s minimum requirements, whichever is more stringent.
820.07.8 Temporary Operation and Maintenance of Movable Span:
Provide qualified personnel to operate a nd maintain the movable bridge as directed below. All bridge operations shall be in accordance with the United States Coast Guard (USCG) permit or negotiated agreement with the USCG. While operating the movable bridge, the contractor is responsible for mai ntenance of the structure. In addition to 107.19 , damages that are the result of either negligent operation or negligent maintenance are the responsibility of the c ontractor.
820.07.9 Final Setup, and Field Testing of Mechanical and Electrical
Systems: Notify the Bridge Engineer 14 calendar days prior to final setup and field testing so the EOR may be present. After installation of all mechanical an d electrical systems has been completed and all weight that will remain on the movable span during operation is in place, adjust and test all mechanical and electrical systems as directed by the plans. Prior to the inspection by the EOR, all mechanical and electrical systems shall be successfully adjusted and tested to the satisfaction of the Systems Integrator and the Project Engineer. On the day of the inspection, have personnel and equipment available to make any adjustments to the span that may be neces sary such as troubleshooting and correcting the electrical system, and adjusting limit switches, buffers, span locks, brakes, time delay relays, balance blocks, relief valves, etc. The cost of any additional inspections beyond one final and one follow -up inspection will be back -charged to the contractor.
820.07.10 Training: After the final inspection, setup, and testing of the
mechanical and electrical systems have been completed, have experienced personnel provide the following training:
820.08 Construction Require Ments for Swing Span
BRIDGES.
820.08.1 Construction of Approach Spans: Approach spans
immediately adjacent to the movable span shall not be constructed until “End Lift Reactions and Elevations,” 820.08.9 has been completed. Each approach span must match the elevation and profile of the movable span across the entire width of the roadway to within plus or minus 1/8 inch.
820.08.2 Installation of Center P ivot Bearing:
Prior to the inspection by the EOR, all mechanical and electrical systems shall be successfully adjusted and tested to the satisfaction of the Systems Integrator and the Project Engineer. On the day of the inspection, have personnel and equipment available to make any adjustments to the span that may be neces sary such as troubleshooting and correcting the electrical system, and adjusting limit switches, buffers, span locks, brakes, time delay relays, balance blocks, relief valves, etc. The cost of any additional inspections beyond one final and one follow -up inspection will be back -charged to the contractor.
820.07.10 Training: After the final inspection, setup, and testing of the
mechanical and electrical systems have been completed, have experienced personnel provide the following training:
820.08 Construction Require Ments for Swing Span
BRIDGES.
820.08.1 Construction of Approach Spans: Approach spans
immediately adjacent to the movable span shall not be constructed until “End Lift Reactions and Elevations,” 820.08.9 has been completed. Each approach span must match the elevation and profile of the movable span across the entire width of the roadway to within plus or minus 1/8 inch.
820.08.2 Installation of Center P ivot Bearing:
Prior to the inspection by the EOR, all mechanical and electrical systems shall be successfully adjusted and tested to the satisfaction of the Systems Integrator and the Project Engineer. On the day of the inspection, have personnel and equipment available to make any adjustments to the span that may be neces sary such as troubleshooting and correcting the electrical system, and adjusting limit switches, buffers, span locks, brakes, time delay relays, balance blocks, relief valves, etc. The cost of any additional inspections beyond one final and one follow -up inspection will be back -charged to the contractor.
820.07.10 Training: After the final inspection, setup, and testing of the
mechanical and electrical systems have been completed, have experienced personnel provide the following training:
820.08 Construction Require Ments for Swing Span
BRIDGES.
820.08.1 Construction of Approach Spans: Approach spans
immediately adjacent to the movable span shall not be constructed until “End Lift Reactions and Elevations,” 820.08.9 has been completed. Each approach span must match the elevation and profile of the movable span across the entire width of the roadway to within plus or minus 1/8 inch.
820.08.2 Installation of Center P ivot Bearing:
Prior to the inspection by the EOR, all mechanical and electrical systems shall be successfully adjusted and tested to the satisfaction of the Systems Integrator and the Project Engineer. On the day of the inspection, have personnel and equipment available to make any adjustments to the span that may be neces sary such as troubleshooting and correcting the electrical system, and adjusting limit switches, buffers, span locks, brakes, time delay relays, balance blocks, relief valves, etc. The cost of any additional inspections beyond one final and one follow -up inspection will be back -charged to the contractor.
820.07.10 Training: After the final inspection, setup, and testing of the
mechanical and electrical systems have been completed, have experienced personnel provide the following training:
820.08 Construction Require Ments for Swing Span
BRIDGES.
820.08.1 Construction of Approach Spans: Approach spans
immediately adjacent to the movable span shall not be constructed until “End Lift Reactions and Elevations,” 820.08.9 has been completed. Each approach span must match the elevation and profile of the movable span across the entire width of the roadway to within plus or minus 1/8 inch.
820.08.2 Installation of Center P ivot Bearing:
Prior to the inspection by the EOR, all mechanical and electrical systems shall be successfully adjusted and tested to the satisfaction of the Systems Integrator and the Project Engineer. On the day of the inspection, have personnel and equipment available to make any adjustments to the span that may be neces sary such as troubleshooting and correcting the electrical system, and adjusting limit switches, buffers, span locks, brakes, time delay relays, balance blocks, relief valves, etc. The cost of any additional inspections beyond one final and one follow -up inspection will be back -charged to the contractor.
820.07.10 Training: After the final inspection, setup, and testing of the
mechanical and electrical systems have been completed, have experienced personnel provide the following training:
820.08 Construction Require Ments for Swing Span
BRIDGES.
820.08.1 Construction of Approach Spans: Approach spans
immediately adjacent to the movable span shall not be constructed until “End Lift Reactions and Elevations,” 820.08.9 has been completed. Each approach span must match the elevation and profile of the movable span across the entire width of the roadway to within plus or minus 1/8 inch.
820.08.2 Installation of Center P ivot Bearing:
820.08.3 Erection of Bobtail Swing Span with Combination
Concrete and Grid Deck: The following is a suggested sequence of constructi on that complies with the design of the movable span. Prior to construction, submit detailed erection drawings to the Bridge Engineer for review. As a minimum, the submittal shall show the sequence of construction, falsework construction, and counterweight /balance block calculations. Each time the erection blocking is adjusted, submit the blocking ordinates of the movable span to the Bridge Engineer for review. Note that the movable span will not be balanced until the end of the erection process. All erecti on blocking adjustments to the movable span will be made in an unbalanced condition. Maintain stability of the movable span during construction, but allow vertical deflection as required by the erection process.
820.08.3 Erection of Bobtail Swing Span with Combination
Concrete and Grid Deck: The following is a suggested sequence of constructi on that complies with the design of the movable span. Prior to construction, submit detailed erection drawings to the Bridge Engineer for review. As a minimum, the submittal shall show the sequence of construction, falsework construction, and counterweight /balance block calculations. Each time the erection blocking is adjusted, submit the blocking ordinates of the movable span to the Bridge Engineer for review. Note that the movable span will not be balanced until the end of the erection process. All erecti on blocking adjustments to the movable span will be made in an unbalanced condition. Maintain stability of the movable span during construction, but allow vertical deflection as required by the erection process.
820.08.4 Erection of Bobtail Swing Span with All Concrete Deck:
The following is a suggested sequence of const ruction that complies with the design of the movable span. Prior to construction, submit detailed erection drawings to the Bridge Engineer for review. As a minimum, the submittal shall show the sequence of construction, falsework construction, and counterw eight/balance block calculations. Each time the erection blocking is adjusted, submit the blocking ordinates of the movable span to the Bridge Engineer for review. Note that the movable span will not be balanced until the end of the erection process. All e rection blocking adjustments to the movable span will be made in an unbalanced condition. Maintain stability of the movable span during construction, but allow vertical deflection as required by the erection process.
820.08.4 Erection of Bobtail Swing Span with All Concrete Deck:
The following is a suggested sequence of const ruction that complies with the design of the movable span. Prior to construction, submit detailed erection drawings to the Bridge Engineer for review. As a minimum, the submittal shall show the sequence of construction, falsework construction, and counterw eight/balance block calculations. Each time the erection blocking is adjusted, submit the blocking ordinates of the movable span to the Bridge Engineer for review. Note that the movable span will not be balanced until the end of the erection process. All e rection blocking adjustments to the movable span will be made in an unbalanced condition. Maintain stability of the movable span during construction, but allow vertical deflection as required by the erection process.
820.08.5 Erection of Equal Arm Swing Span with All Concrete Deck:
The following is a suggested sequence of construction that complies with the design of the movable span. Prior to construction, su bmit detailed erection drawings to the Bridge Engineer for review. As a minimum, the submittal shall show the sequence of construction, falsework construction, and balance block calculations. Each time the erection blocking is adjusted, submit the blocking ordinates of the movable span to the Bridge Engineer for review. Maintain stability of the movable span during construction, but allow vertical deflection as required by the erection process.
820.08.5 Erection of Equal Arm Swing Span with All Concrete Deck:
The following is a suggested sequence of construction that complies with the design of the movable span. Prior to construction, su bmit detailed erection drawings to the Bridge Engineer for review. As a minimum, the submittal shall show the sequence of construction, falsework construction, and balance block calculations. Each time the erection blocking is adjusted, submit the blocking ordinates of the movable span to the Bridge Engineer for review. Maintain stability of the movable span during construction, but allow vertical deflection as required by the erection process.
820.08.6 Erection of Equa l Arm Swing Span with Grid Deck: The
following is a suggested sequence of construction that complies with the design of the movable span. Prior to construction, submit detailed erection drawings to the Bridge Engineer for review. As a minimum, the submi ttal shall show the sequence of construction, falsework construction, and balance block calculations. Each time the erection blocking is adjusted, submit the blocking ordinates of the movable span to the Bridge Engineer for review. Maintain stability of th e movable span during construction, but allow vertical deflection as required by the erection process.
820.08.6 Erection of Equa l Arm Swing Span with Grid Deck: The
following is a suggested sequence of construction that complies with the design of the movable span. Prior to construction, submit detailed erection drawings to the Bridge Engineer for review. As a minimum, the submi ttal shall show the sequence of construction, falsework construction, and balance block calculations. Each time the erection blocking is adjusted, submit the blocking ordinates of the movable span to the Bridge Engineer for review. Maintain stability of th e movable span during construction, but allow vertical deflection as required by the erection process.
820.08.7 Rack and Pinion Installation (Swing Span): For swing span
bridges with rack and pinion gears, installation requirements are similar to the requirements for vertical lift bridge rack and pinion gears.
820.08.8 Span Balancing (S wing Span): Perform span balancing in the
morning when the effects of temperature on the main girders are at a minimum. Do not perform span balancing during wind that could cause the balance wheels to contact with the track. After the movable span is fu lly constructed, including all mechanical and electrical equipment, and deflected under dead load, adjust the balance wheels to have a 1/2 -to 3/4 -inch gap between the balance wheels and the track. Check the vertical profile ordinates of both main girders a nd compare with the ordinates shown in the plans for the span swinging freely with equal end lifts. Adjust balance blocks, swing the span open and closed, and recheck ordinates. Repeat until the ordinates match the ordinates shown on the plans as close as achievable. Operate the span multiple times and recheck ordinates to ensure the results are repeatable. Adjust balance wheels to have a minimum 1/16 -inch gap with the track at all times during the operation of the span. Swing the span open and closed. If a t any point the gap between the balance wheels and the track exceeds 3/16 inch, that portion of the track must be re -leveled.
820.08.9 End Lift Reactions and Elevations (Swing Span):
Notify the Bridge Engineer 14 calendar days prior to measuring the end lift reactions so the EOR or a designated representative may be present. Measurement of end lift reactions and elevations shall be performed after span balancing has been completed. Submit cut sheets to the Bridge Engineer for review of hydraulic jacks and pressure gauges. Select jack size so that the expected load will register between 2,000 and 4,000 psi. Use 0 -5,000 psi digital pressure gauges with an accuracy of ± 0.25 percent full scale. New gauges shall come with NIST certification. Used gauges shall be newly certified. Power units shall be capable of holding the load for the duration of the measurement process without significant leakage of hydraulic fluid.
820.08.7 Rack and Pinion Installation (Swing Span): For swing span
bridges with rack and pinion gears, installation requirements are similar to the requirements for vertical lift bridge rack and pinion gears.
820.08.8 Span Balancing (S wing Span): Perform span balancing in the
morning when the effects of temperature on the main girders are at a minimum. Do not perform span balancing during wind that could cause the balance wheels to contact with the track. After the movable span is fu lly constructed, including all mechanical and electrical equipment, and deflected under dead load, adjust the balance wheels to have a 1/2 -to 3/4 -inch gap between the balance wheels and the track. Check the vertical profile ordinates of both main girders a nd compare with the ordinates shown in the plans for the span swinging freely with equal end lifts. Adjust balance blocks, swing the span open and closed, and recheck ordinates. Repeat until the ordinates match the ordinates shown on the plans as close as achievable. Operate the span multiple times and recheck ordinates to ensure the results are repeatable. Adjust balance wheels to have a minimum 1/16 -inch gap with the track at all times during the operation of the span. Swing the span open and closed. If a t any point the gap between the balance wheels and the track exceeds 3/16 inch, that portion of the track must be re -leveled.
820.08.9 End Lift Reactions and Elevations (Swing Span):
Notify the Bridge Engineer 14 calendar days prior to measuring the end lift reactions so the EOR or a designated representative may be present. Measurement of end lift reactions and elevations shall be performed after span balancing has been completed. Submit cut sheets to the Bridge Engineer for review of hydraulic jacks and pressure gauges. Select jack size so that the expected load will register between 2,000 and 4,000 psi. Use 0 -5,000 psi digital pressure gauges with an accuracy of ± 0.25 percent full scale. New gauges shall come with NIST certification. Used gauges shall be newly certified. Power units shall be capable of holding the load for the duration of the measurement process without significant leakage of hydraulic fluid.
820.08.7 Rack and Pinion Installation (Swing Span): For swing span
bridges with rack and pinion gears, installation requirements are similar to the requirements for vertical lift bridge rack and pinion gears.
820.08.8 Span Balancing (S wing Span): Perform span balancing in the
morning when the effects of temperature on the main girders are at a minimum. Do not perform span balancing during wind that could cause the balance wheels to contact with the track. After the movable span is fu lly constructed, including all mechanical and electrical equipment, and deflected under dead load, adjust the balance wheels to have a 1/2 -to 3/4 -inch gap between the balance wheels and the track. Check the vertical profile ordinates of both main girders a nd compare with the ordinates shown in the plans for the span swinging freely with equal end lifts. Adjust balance blocks, swing the span open and closed, and recheck ordinates. Repeat until the ordinates match the ordinates shown on the plans as close as achievable. Operate the span multiple times and recheck ordinates to ensure the results are repeatable. Adjust balance wheels to have a minimum 1/16 -inch gap with the track at all times during the operation of the span. Swing the span open and closed. If a t any point the gap between the balance wheels and the track exceeds 3/16 inch, that portion of the track must be re -leveled.
820.08.9 End Lift Reactions and Elevations (Swing Span):
Notify the Bridge Engineer 14 calendar days prior to measuring the end lift reactions so the EOR or a designated representative may be present. Measurement of end lift reactions and elevations shall be performed after span balancing has been completed. Submit cut sheets to the Bridge Engineer for review of hydraulic jacks and pressure gauges. Select jack size so that the expected load will register between 2,000 and 4,000 psi. Use 0 -5,000 psi digital pressure gauges with an accuracy of ± 0.25 percent full scale. New gauges shall come with NIST certification. Used gauges shall be newly certified. Power units shall be capable of holding the load for the duration of the measurement process without significant leakage of hydraulic fluid.
820.08.7 Rack and Pinion Installation (Swing Span): For swing span
bridges with rack and pinion gears, installation requirements are similar to the requirements for vertical lift bridge rack and pinion gears.
820.08.8 Span Balancing (S wing Span): Perform span balancing in the
morning when the effects of temperature on the main girders are at a minimum. Do not perform span balancing during wind that could cause the balance wheels to contact with the track. After the movable span is fu lly constructed, including all mechanical and electrical equipment, and deflected under dead load, adjust the balance wheels to have a 1/2 -to 3/4 -inch gap between the balance wheels and the track. Check the vertical profile ordinates of both main girders a nd compare with the ordinates shown in the plans for the span swinging freely with equal end lifts. Adjust balance blocks, swing the span open and closed, and recheck ordinates. Repeat until the ordinates match the ordinates shown on the plans as close as achievable. Operate the span multiple times and recheck ordinates to ensure the results are repeatable. Adjust balance wheels to have a minimum 1/16 -inch gap with the track at all times during the operation of the span. Swing the span open and closed. If a t any point the gap between the balance wheels and the track exceeds 3/16 inch, that portion of the track must be re -leveled.
820.08.9 End Lift Reactions and Elevations (Swing Span):
Notify the Bridge Engineer 14 calendar days prior to measuring the end lift reactions so the EOR or a designated representative may be present. Measurement of end lift reactions and elevations shall be performed after span balancing has been completed. Submit cut sheets to the Bridge Engineer for review of hydraulic jacks and pressure gauges. Select jack size so that the expected load will register between 2,000 and 4,000 psi. Use 0 -5,000 psi digital pressure gauges with an accuracy of ± 0.25 percent full scale. New gauges shall come with NIST certification. Used gauges shall be newly certified. Power units shall be capable of holding the load for the duration of the measurement process without significant leakage of hydraulic fluid. Use two identical hydraulic jacks with known bore sizes for the long arm, and two identical hydraulic ja cks with known bore sizes for the short arm. All four jacks shall be the same size for an equal arm span. Locate the jacks at the end lift locations as shown on the plans. Each jack shall be connected to a separate power unit. Pressure gauges should be mou nted directly to the jacks, if possible. Otherwise, pressure gauges shall be located as close to the jacks as practical. Jacks must be completely free of air before measurement. Measure end lift reactions in the morning when the effects of temperature on t he main girders are at a minimum. Jack all four corners of the span simultaneously until design reactions are achieved. Allow time for pressure readings to stabilize. Monitor elevations to ensure that each corner is lifting correctly. Survey roadway surfac e elevations at each gutter line, the profile grade line at each end of the span, and at the pivot girder location. Tolerances between survey and plan elevations are ± 1/4 inch at span ends and ± 3/8 inch at the pivot girder location. If elevations are not within tolerances, adjust spacer plate under the pivot girder while weighing the span under 820.08.10 and repeat the process until tolerance is achieved. After end lift elevations have been determined, construct risers for end wedge shoes and install/shim the end wedge shoes to meet elevations. At this point, approach spans adjacent to the movable span may be constructed to match movable span elevations.
820.08.10 Weighing the Movable Span (Swing Span): Notify the
Bridge Engineer 14 calendar days prior to weighing the movable span so the EOR or a designated representative may be pre sent. Weighing of the movable span shall be performed after measurement of end lift reactions has been completed. Spacer plate under the pivot girder can be adjusted at this time if required. Submit Cut Sheets for hydraulic jacks and pressure gauges to the Bridge Engineer for review. Select jack size so that the expected load will register between 6,000 and 8,000 psi. Use 0 -10,000 psi digital pressure gauges with an accuracy of ± 0.25 percent full scale. New gauges shall come with NIST certification. Used g auges shall be newly certified. Use two identical hydraulic jacks with known bore sizes, and locate them under the pivot girder where shown on the plans. Each jack should be connected to a separate power unit. Power units shall be capable of holding the lo ad for the duration of the weighing process without significant leakage of hydraulic fluid. Pressure gauges should be mounted directly to the jacks if possible. Otherwise, pressure gauges shall be located as close to the jacks as practical. Jacks shall be completely free of air before measurement. Use two identical hydraulic jacks with known bore sizes for the long arm, and two identical hydraulic ja cks with known bore sizes for the short arm. All four jacks shall be the same size for an equal arm span. Locate the jacks at the end lift locations as shown on the plans. Each jack shall be connected to a separate power unit. Pressure gauges should be mou nted directly to the jacks, if possible. Otherwise, pressure gauges shall be located as close to the jacks as practical. Jacks must be completely free of air before measurement. Measure end lift reactions in the morning when the effects of temperature on t he main girders are at a minimum. Jack all four corners of the span simultaneously until design reactions are achieved. Allow time for pressure readings to stabilize. Monitor elevations to ensure that each corner is lifting correctly. Survey roadway surfac e elevations at each gutter line, the profile grade line at each end of the span, and at the pivot girder location. Tolerances between survey and plan elevations are ± 1/4 inch at span ends and ± 3/8 inch at the pivot girder location. If elevations are not within tolerances, adjust spacer plate under the pivot girder while weighing the span under 820.08.10 and repeat the process until tolerance is achieved. After end lift elevations have been determined, construct risers for end wedge shoes and install/shim the end wedge shoes to meet elevations. At this point, approach spans adjacent to the movable span may be constructed to match movable span elevations.
820.08.10 Weighing the Movable Span (Swing Span): Notify the
Bridge Engineer 14 calendar days prior to weighing the movable span so the EOR or a designated representative may be pre sent. Weighing of the movable span shall be performed after measurement of end lift reactions has been completed. Spacer plate under the pivot girder can be adjusted at this time if required. Submit Cut Sheets for hydraulic jacks and pressure gauges to the Bridge Engineer for review. Select jack size so that the expected load will register between 6,000 and 8,000 psi. Use 0 -10,000 psi digital pressure gauges with an accuracy of ± 0.25 percent full scale. New gauges shall come with NIST certification. Used g auges shall be newly certified. Use two identical hydraulic jacks with known bore sizes, and locate them under the pivot girder where shown on the plans. Each jack should be connected to a separate power unit. Power units shall be capable of holding the lo ad for the duration of the weighing process without significant leakage of hydraulic fluid. Pressure gauges should be mounted directly to the jacks if possible. Otherwise, pressure gauges shall be located as close to the jacks as practical. Jacks shall be completely free of air before measurement. Retract wedges and raise the span until all load has been removed from the pivot bearing. Allow time for pressure readings to stabilize. Record readings and repeat two more times. Measurements are good if they ar e within 1 percent of each other. Submit pressure readings to the Bridge Engineer for review. Actual span weight shall not differ from the design weight by more than ± 5 percent. If an adjustment needs to be made to the pivot girder elevation during this procedure, remove the existing spacer plate while jacking the span and replace with a single spacer plate machined to the required thickness.
820.09 Construction Require Ments for Vertical L Ift Span
BRIDGES.
820.09.1 Construction of Approach Spans: Approach spans
immedia tely adjacent to the movable span shall not be constructed until “Installation of Bearing Shoes,” 820.09.10 has been completed. Each approach span must match the elevation and profile of the movable span across the entire width of the roadway to within ± 1/8 inch.
820.09.2 Tolerances for Lift Towers: For either concrete or steel to wer
vertical lift bridges, all lines, surfaces, corners, arises, and elements of the lift towers shall be within ± 1/4 inch in any 10 foot section and not more than ± 1/2 inch for the entire length of the tower for towers less than 100 feet and ± 3/4 inch for towers greater than 100 feet of the plan dimension. For concrete lift towers, survey towers after each placement and before any further construction on that leg occurs. If at any point the tower does not meet the required tolerances, submit a contracto r proposal with recommendations for remediation which may include removal and replacement of the tower. For steel lift towers, survey towers continually during construction. If at any point during construction the tower does not meet the required tolerance s, submit a contractor proposal with recommendations for remediation, which may include removal and re -fabrication of structural members.
820.09.3 Installation of Sheave Assemblies (Concrete Towers):
Do not transport sheave assemblies to the project site until it is time to install them in their permanent locations on the sheave pedestals. Sheave assemblies shall come from the shop complete with trunnions, trunnion bearings, and sheave gear installed. Sheave gears shall come from the shop coated with a dry, rust -inhibiting grease. Do not remove this grease until installation of the pinion gear. Retract wedges and raise the span until all load has been removed from the pivot bearing. Allow time for pressure readings to stabilize. Record readings and repeat two more times. Measurements are good if they ar e within 1 percent of each other. Submit pressure readings to the Bridge Engineer for review. Actual span weight shall not differ from the design weight by more than ± 5 percent. If an adjustment needs to be made to the pivot girder elevation during this procedure, remove the existing spacer plate while jacking the span and replace with a single spacer plate machined to the required thickness.
820.09 Construction Require Ments for Vertical L Ift Span
BRIDGES.
820.09.1 Construction of Approach Spans: Approach spans
immedia tely adjacent to the movable span shall not be constructed until “Installation of Bearing Shoes,” 820.09.10 has been completed. Each approach span must match the elevation and profile of the movable span across the entire width of the roadway to within ± 1/8 inch.
820.09.2 Tolerances for Lift Towers: For either concrete or steel to wer
vertical lift bridges, all lines, surfaces, corners, arises, and elements of the lift towers shall be within ± 1/4 inch in any 10 foot section and not more than ± 1/2 inch for the entire length of the tower for towers less than 100 feet and ± 3/4 inch for towers greater than 100 feet of the plan dimension. For concrete lift towers, survey towers after each placement and before any further construction on that leg occurs. If at any point the tower does not meet the required tolerances, submit a contracto r proposal with recommendations for remediation which may include removal and replacement of the tower. For steel lift towers, survey towers continually during construction. If at any point during construction the tower does not meet the required tolerance s, submit a contractor proposal with recommendations for remediation, which may include removal and re -fabrication of structural members.
820.09.3 Installation of Sheave Assemblies (Concrete Towers):
Do not transport sheave assemblies to the project site until it is time to install them in their permanent locations on the sheave pedestals. Sheave assemblies shall come from the shop complete with trunnions, trunnion bearings, and sheave gear installed. Sheave gears shall come from the shop coated with a dry, rust -inhibiting grease. Do not remove this grease until installation of the pinion gear. Retract wedges and raise the span until all load has been removed from the pivot bearing. Allow time for pressure readings to stabilize. Record readings and repeat two more times. Measurements are good if they ar e within 1 percent of each other. Submit pressure readings to the Bridge Engineer for review. Actual span weight shall not differ from the design weight by more than ± 5 percent. If an adjustment needs to be made to the pivot girder elevation during this procedure, remove the existing spacer plate while jacking the span and replace with a single spacer plate machined to the required thickness.
820.09 Construction Require Ments for Vertical L Ift Span
BRIDGES.
820.09.1 Construction of Approach Spans: Approach spans
immedia tely adjacent to the movable span shall not be constructed until “Installation of Bearing Shoes,” 820.09.10 has been completed. Each approach span must match the elevation and profile of the movable span across the entire width of the roadway to within ± 1/8 inch.
820.09.2 Tolerances for Lift Towers: For either concrete or steel to wer
vertical lift bridges, all lines, surfaces, corners, arises, and elements of the lift towers shall be within ± 1/4 inch in any 10 foot section and not more than ± 1/2 inch for the entire length of the tower for towers less than 100 feet and ± 3/4 inch for towers greater than 100 feet of the plan dimension. For concrete lift towers, survey towers after each placement and before any further construction on that leg occurs. If at any point the tower does not meet the required tolerances, submit a contracto r proposal with recommendations for remediation which may include removal and replacement of the tower. For steel lift towers, survey towers continually during construction. If at any point during construction the tower does not meet the required tolerance s, submit a contractor proposal with recommendations for remediation, which may include removal and re -fabrication of structural members.
820.09.3 Installation of Sheave Assemblies (Concrete Towers):
Do not transport sheave assemblies to the project site until it is time to install them in their permanent locations on the sheave pedestals. Sheave assemblies shall come from the shop complete with trunnions, trunnion bearings, and sheave gear installed. Sheave gears shall come from the shop coated with a dry, rust -inhibiting grease. Do not remove this grease until installation of the pinion gear. Retract wedges and raise the span until all load has been removed from the pivot bearing. Allow time for pressure readings to stabilize. Record readings and repeat two more times. Measurements are good if they ar e within 1 percent of each other. Submit pressure readings to the Bridge Engineer for review. Actual span weight shall not differ from the design weight by more than ± 5 percent. If an adjustment needs to be made to the pivot girder elevation during this procedure, remove the existing spacer plate while jacking the span and replace with a single spacer plate machined to the required thickness.
820.09 Construction Require Ments for Vertical L Ift Span
BRIDGES.
820.09.1 Construction of Approach Spans: Approach spans
immedia tely adjacent to the movable span shall not be constructed until “Installation of Bearing Shoes,” 820.09.10 has been completed. Each approach span must match the elevation and profile of the movable span across the entire width of the roadway to within ± 1/8 inch.
820.09.2 Tolerances for Lift Towers: For either concrete or steel to wer
vertical lift bridges, all lines, surfaces, corners, arises, and elements of the lift towers shall be within ± 1/4 inch in any 10 foot section and not more than ± 1/2 inch for the entire length of the tower for towers less than 100 feet and ± 3/4 inch for towers greater than 100 feet of the plan dimension. For concrete lift towers, survey towers after each placement and before any further construction on that leg occurs. If at any point the tower does not meet the required tolerances, submit a contracto r proposal with recommendations for remediation which may include removal and replacement of the tower. For steel lift towers, survey towers continually during construction. If at any point during construction the tower does not meet the required tolerance s, submit a contractor proposal with recommendations for remediation, which may include removal and re -fabrication of structural members.
820.09.3 Installation of Sheave Assemblies (Concrete Towers):
Do not transport sheave assemblies to the project site until it is time to install them in their permanent locations on the sheave pedestals. Sheave assemblies shall come from the shop complete with trunnions, trunnion bearings, and sheave gear installed. Sheave gears shall come from the shop coated with a dry, rust -inhibiting grease. Do not remove this grease until installation of the pinion gear. Retract wedges and raise the span until all load has been removed from the pivot bearing. Allow time for pressure readings to stabilize. Record readings and repeat two more times. Measurements are good if they ar e within 1 percent of each other. Submit pressure readings to the Bridge Engineer for review. Actual span weight shall not differ from the design weight by more than ± 5 percent. If an adjustment needs to be made to the pivot girder elevation during this procedure, remove the existing spacer plate while jacking the span and replace with a single spacer plate machined to the required thickness.
820.09 Construction Require Ments for Vertical L Ift Span
BRIDGES.
820.09.1 Construction of Approach Spans: Approach spans
immedia tely adjacent to the movable span shall not be constructed until “Installation of Bearing Shoes,” 820.09.10 has been completed. Each approach span must match the elevation and profile of the movable span across the entire width of the roadway to within ± 1/8 inch.
820.09.2 Tolerances for Lift Towers: For either concrete or steel to wer
vertical lift bridges, all lines, surfaces, corners, arises, and elements of the lift towers shall be within ± 1/4 inch in any 10 foot section and not more than ± 1/2 inch for the entire length of the tower for towers less than 100 feet and ± 3/4 inch for towers greater than 100 feet of the plan dimension. For concrete lift towers, survey towers after each placement and before any further construction on that leg occurs. If at any point the tower does not meet the required tolerances, submit a contracto r proposal with recommendations for remediation which may include removal and replacement of the tower. For steel lift towers, survey towers continually during construction. If at any point during construction the tower does not meet the required tolerance s, submit a contractor proposal with recommendations for remediation, which may include removal and re -fabrication of structural members.
820.09.3 Installation of Sheave Assemblies (Concrete Towers):
Do not transport sheave assemblies to the project site until it is time to install them in their permanent locations on the sheave pedestals. Sheave assemblies shall come from the shop complete with trunnions, trunnion bearings, and sheave gear installed. Sheave gears shall come from the shop coated with a dry, rust -inhibiting grease. Do not remove this grease until installation of the pinion gear.
820.09.4 Installation of Sheave Assemblies (Steel Towers): Use the
same installation procedure as 820.09.3 “Installation of Sheave Assemblies (Concrete Towers)” except as follows:
820.09.5 Construction of Counterweight (Vertical Lift): Construct the
counterweights in accordance with the plans and 820.07.6 , “Construction of
820.09.4 Installation of Sheave Assemblies (Steel Towers): Use the
same installation procedure as 820.09.3 “Installation of Sheave Assemblies (Concrete Towers)” except as follows:
820.09.5 Construction of Counterweight (Vertical Lift): Construct the
counterweights in accordance with the plans and 820.07.6 , “Construction of
820.09.4 Installation of Sheave Assemblies (Steel Towers): Use the
same installation procedure as 820.09.3 “Installation of Sheave Assemblies (Concrete Towers)” except as follows:
820.09.5 Construction of Counterweight (Vertical Lift): Construct the
counterweights in accordance with the plans and 820.07.6 , “Construction of Counterweight.” Construct forms and place the counterweight concrete. Remove forms after the counterweight has met requirements for form removal.
820.09.6 Installation of Counterweight Wire Ropes (Vertical Lift):
At all times during the installation process, handle counterweight wire ropes (CWR’s) in accord ance with the wire rope manufacturer’s recommendations. Kinks in the CWR’s will be cause for rejection. Orient CWR’s on the sheave as shown on the plans and without twisting.
820.09.7 Installation of Span Drive Machinery and Pinion Gears.
(Vertical Lift): Install the span drive machinery on the machinery deck as shown on the plans. All machinery shall be installed by a millwright and shall be aligned to within tolerances shown on the plans and industry standards for equipment of this type, whichever is more stringent. Do not begin to install span drive machinery until the movable span nears completion. Turned bolts/fitted pins for pinion shaft bearings shall not be installed until the sheave is fully loaded with the weight of the completed movable span and counterweight. Counterweight.” Construct forms and place the counterweight concrete. Remove forms after the counterweight has met requirements for form removal.
820.09.6 Installation of Counterweight Wire Ropes (Vertical Lift):
At all times during the installation process, handle counterweight wire ropes (CWR’s) in accord ance with the wire rope manufacturer’s recommendations. Kinks in the CWR’s will be cause for rejection. Orient CWR’s on the sheave as shown on the plans and without twisting.
820.09.7 Installation of Span Drive Machinery and Pinion Gears.
(Vertical Lift): Install the span drive machinery on the machinery deck as shown on the plans. All machinery shall be installed by a millwright and shall be aligned to within tolerances shown on the plans and industry standards for equipment of this type, whichever is more stringent. Do not begin to install span drive machinery until the movable span nears completion. Turned bolts/fitted pins for pinion shaft bearings shall not be installed until the sheave is fully loaded with the weight of the completed movable span and counterweight. Counterweight.” Construct forms and place the counterweight concrete. Remove forms after the counterweight has met requirements for form removal.
820.09.6 Installation of Counterweight Wire Ropes (Vertical Lift):
At all times during the installation process, handle counterweight wire ropes (CWR’s) in accord ance with the wire rope manufacturer’s recommendations. Kinks in the CWR’s will be cause for rejection. Orient CWR’s on the sheave as shown on the plans and without twisting.
820.09.7 Installation of Span Drive Machinery and Pinion Gears.
(Vertical Lift): Install the span drive machinery on the machinery deck as shown on the plans. All machinery shall be installed by a millwright and shall be aligned to within tolerances shown on the plans and industry standards for equipment of this type, whichever is more stringent. Do not begin to install span drive machinery until the movable span nears completion. Turned bolts/fitted pins for pinion shaft bearings shall not be installed until the sheave is fully loaded with the weight of the completed movable span and counterweight.
820.09.8 Weighing of Counterweight and Movable Span (Vertical
Lift): After th e turned bolts/fitted pins have been installed in the pinion bearings, use the following procedure to weigh the counterweight and the movable span or submit an alternate method to the Bridge Engineer for review. Notify the Bridge
820.09.8 Weighing of Counterweight and Movable Span (Vertical
Lift): After th e turned bolts/fitted pins have been installed in the pinion bearings, use the following procedure to weigh the counterweight and the movable span or submit an alternate method to the Bridge Engineer for review. Notify the Bridge Engineer 14 calendar days prior to weighing the counterweight and the movable span so the EOR or a designated representative may be present. Weighing of the counterweight and movable span shall be performed after construction of both is fully complete. Submit cut sheets for hydraul ic jacks and pressure gauges to the Bridge Engineer for review. Select jack size so that the expected load will register between 6,000 and 8,000 psi. Use 0 -10,000 psi digital pressure gauges with an accuracy of ± 0.25 percent full scale. New gauges shall c ome with N.I.S.T. certification. Used gauges shall be newly certified.
820.09.9 Balance Movable Span (Vertical Lift): Using the weights
measured for the movable span and the counterweight, adjust the balance blocks so that the movable span is 1,500 pounds span heavy per corner. This is a starting Engineer 14 calendar days prior to weighing the counterweight and the movable span so the EOR or a designated representative may be present. Weighing of the counterweight and movable span shall be performed after construction of both is fully complete. Submit cut sheets for hydraul ic jacks and pressure gauges to the Bridge Engineer for review. Select jack size so that the expected load will register between 6,000 and 8,000 psi. Use 0 -10,000 psi digital pressure gauges with an accuracy of ± 0.25 percent full scale. New gauges shall c ome with N.I.S.T. certification. Used gauges shall be newly certified.
820.09.9 Balance Movable Span (Vertical Lift): Using the weights
measured for the movable span and the counterweight, adjust the balance blocks so that the movable span is 1,500 pounds span heavy per corner. This is a starting point. Further adjustments to the span balance may need to be made to achieve proper performance. Maintain a record of all balance block adjustments.
820.09.10 Installation of Bearing Shoes (Vertical Lift): Lower the
movable span so that the bearing feet contact the main piers. Mark location for bearing shoes on the main pier, and drill in place anchor bolts as shown on the plans. Use a template to space anchor bolts and to hold anchor bolts vertical. Using a non -shrink epoxy grout, form up and install grout pads under bearing s hoes as shown on the plans, and in a similar manner as for the sheave pedestals, level bearing shoes with a machinist level. Bearing shoe elevations shall be accurate to within ± 1/16 inch. Entire length of bearing feet shall contact the bearing shoes. Grind bearing feet and repaint as required.
820.09.11 Installation of Span and Counterweight Guide Rails
(Vertical Lift): Install span and counterweight guide rails as shown on the plans. Guide rails shall be vertical to within ± 1/8 inch along the entire length of the rail. Guide rail splices shall mate flush. Roller guides shall not ride on guide rails during operation when there is no wind.
820.09.12 Installation of Span Locks (Vertical Lift): Span lock catch
shall have already been installed on the movable span. Locate span lock base and drill in place anchor bolts as shown on the plans. Use a template to space anchor bolts and to hold anchor bolts vertical. Using an epoxy grout from the Approved Materials List, form up and install grout pads under span lock bases as sho wn on the plans, and in a similar manner as the sheave pedestals. Level span lock bases with a machinist level. Span lock base elevations shall be accurate to within ± 1/16 inch. Locate span lock on base such that the center of the latch, when extended, is over the center of the catch when the latch is horizontal. Shim span lock so that there is a 1/16 -inch gap between the latch and the catch when the latch is extended. Adjust limit switches so that the span lock latch is fully inside the enclosure when retracted and horizontal when extended.
820.09.13 Installation of Air Buffers (Vertical Lift): Install air buffers
as shown on the plans and thoroughly lubricate. Provide air pressure gauges (0 - 300psi) and install in place of the oilers. Operate span and adjust air valves until the span seats gently and all buffers see approximately the same maximum pressure. This should be between 75 and 100 psi. Be prepared to demonstrate pressure settings during final setup and inspection, and have personnel and tools available to make additional adjustments at that time. After air buffer operation has been accepted, match mark the air valve position and install oilers. point. Further adjustments to the span balance may need to be made to achieve proper performance. Maintain a record of all balance block adjustments.
820.09.10 Installation of Bearing Shoes (Vertical Lift): Lower the
movable span so that the bearing feet contact the main piers. Mark location for bearing shoes on the main pier, and drill in place anchor bolts as shown on the plans. Use a template to space anchor bolts and to hold anchor bolts vertical. Using a non -shrink epoxy grout, form up and install grout pads under bearing s hoes as shown on the plans, and in a similar manner as for the sheave pedestals, level bearing shoes with a machinist level. Bearing shoe elevations shall be accurate to within ± 1/16 inch. Entire length of bearing feet shall contact the bearing shoes. Grind bearing feet and repaint as required.
820.09.11 Installation of Span and Counterweight Guide Rails
(Vertical Lift): Install span and counterweight guide rails as shown on the plans. Guide rails shall be vertical to within ± 1/8 inch along the entire length of the rail. Guide rail splices shall mate flush. Roller guides shall not ride on guide rails during operation when there is no wind.
820.09.12 Installation of Span Locks (Vertical Lift): Span lock catch
shall have already been installed on the movable span. Locate span lock base and drill in place anchor bolts as shown on the plans. Use a template to space anchor bolts and to hold anchor bolts vertical. Using an epoxy grout from the Approved Materials List, form up and install grout pads under span lock bases as sho wn on the plans, and in a similar manner as the sheave pedestals. Level span lock bases with a machinist level. Span lock base elevations shall be accurate to within ± 1/16 inch. Locate span lock on base such that the center of the latch, when extended, is over the center of the catch when the latch is horizontal. Shim span lock so that there is a 1/16 -inch gap between the latch and the catch when the latch is extended. Adjust limit switches so that the span lock latch is fully inside the enclosure when retracted and horizontal when extended.
820.09.13 Installation of Air Buffers (Vertical Lift): Install air buffers
as shown on the plans and thoroughly lubricate. Provide air pressure gauges (0 - 300psi) and install in place of the oilers. Operate span and adjust air valves until the span seats gently and all buffers see approximately the same maximum pressure. This should be between 75 and 100 psi. Be prepared to demonstrate pressure settings during final setup and inspection, and have personnel and tools available to make additional adjustments at that time. After air buffer operation has been accepted, match mark the air valve position and install oilers. point. Further adjustments to the span balance may need to be made to achieve proper performance. Maintain a record of all balance block adjustments.
820.09.10 Installation of Bearing Shoes (Vertical Lift): Lower the
movable span so that the bearing feet contact the main piers. Mark location for bearing shoes on the main pier, and drill in place anchor bolts as shown on the plans. Use a template to space anchor bolts and to hold anchor bolts vertical. Using a non -shrink epoxy grout, form up and install grout pads under bearing s hoes as shown on the plans, and in a similar manner as for the sheave pedestals, level bearing shoes with a machinist level. Bearing shoe elevations shall be accurate to within ± 1/16 inch. Entire length of bearing feet shall contact the bearing shoes. Grind bearing feet and repaint as required.
820.09.11 Installation of Span and Counterweight Guide Rails
(Vertical Lift): Install span and counterweight guide rails as shown on the plans. Guide rails shall be vertical to within ± 1/8 inch along the entire length of the rail. Guide rail splices shall mate flush. Roller guides shall not ride on guide rails during operation when there is no wind.
820.09.12 Installation of Span Locks (Vertical Lift): Span lock catch
shall have already been installed on the movable span. Locate span lock base and drill in place anchor bolts as shown on the plans. Use a template to space anchor bolts and to hold anchor bolts vertical. Using an epoxy grout from the Approved Materials List, form up and install grout pads under span lock bases as sho wn on the plans, and in a similar manner as the sheave pedestals. Level span lock bases with a machinist level. Span lock base elevations shall be accurate to within ± 1/16 inch. Locate span lock on base such that the center of the latch, when extended, is over the center of the catch when the latch is horizontal. Shim span lock so that there is a 1/16 -inch gap between the latch and the catch when the latch is extended. Adjust limit switches so that the span lock latch is fully inside the enclosure when retracted and horizontal when extended.
820.09.13 Installation of Air Buffers (Vertical Lift): Install air buffers
as shown on the plans and thoroughly lubricate. Provide air pressure gauges (0 - 300psi) and install in place of the oilers. Operate span and adjust air valves until the span seats gently and all buffers see approximately the same maximum pressure. This should be between 75 and 100 psi. Be prepared to demonstrate pressure settings during final setup and inspection, and have personnel and tools available to make additional adjustments at that time. After air buffer operation has been accepted, match mark the air valve position and install oilers. point. Further adjustments to the span balance may need to be made to achieve proper performance. Maintain a record of all balance block adjustments.
820.09.10 Installation of Bearing Shoes (Vertical Lift): Lower the
movable span so that the bearing feet contact the main piers. Mark location for bearing shoes on the main pier, and drill in place anchor bolts as shown on the plans. Use a template to space anchor bolts and to hold anchor bolts vertical. Using a non -shrink epoxy grout, form up and install grout pads under bearing s hoes as shown on the plans, and in a similar manner as for the sheave pedestals, level bearing shoes with a machinist level. Bearing shoe elevations shall be accurate to within ± 1/16 inch. Entire length of bearing feet shall contact the bearing shoes. Grind bearing feet and repaint as required.
820.09.11 Installation of Span and Counterweight Guide Rails
(Vertical Lift): Install span and counterweight guide rails as shown on the plans. Guide rails shall be vertical to within ± 1/8 inch along the entire length of the rail. Guide rail splices shall mate flush. Roller guides shall not ride on guide rails during operation when there is no wind.
820.09.12 Installation of Span Locks (Vertical Lift): Span lock catch
shall have already been installed on the movable span. Locate span lock base and drill in place anchor bolts as shown on the plans. Use a template to space anchor bolts and to hold anchor bolts vertical. Using an epoxy grout from the Approved Materials List, form up and install grout pads under span lock bases as sho wn on the plans, and in a similar manner as the sheave pedestals. Level span lock bases with a machinist level. Span lock base elevations shall be accurate to within ± 1/16 inch. Locate span lock on base such that the center of the latch, when extended, is over the center of the catch when the latch is horizontal. Shim span lock so that there is a 1/16 -inch gap between the latch and the catch when the latch is extended. Adjust limit switches so that the span lock latch is fully inside the enclosure when retracted and horizontal when extended.
820.09.13 Installation of Air Buffers (Vertical Lift): Install air buffers
as shown on the plans and thoroughly lubricate. Provide air pressure gauges (0 - 300psi) and install in place of the oilers. Operate span and adjust air valves until the span seats gently and all buffers see approximately the same maximum pressure. This should be between 75 and 100 psi. Be prepared to demonstrate pressure settings during final setup and inspection, and have personnel and tools available to make additional adjustments at that time. After air buffer operation has been accepted, match mark the air valve position and install oilers. point. Further adjustments to the span balance may need to be made to achieve proper performance. Maintain a record of all balance block adjustments.
820.09.10 Installation of Bearing Shoes (Vertical Lift): Lower the
movable span so that the bearing feet contact the main piers. Mark location for bearing shoes on the main pier, and drill in place anchor bolts as shown on the plans. Use a template to space anchor bolts and to hold anchor bolts vertical. Using a non -shrink epoxy grout, form up and install grout pads under bearing s hoes as shown on the plans, and in a similar manner as for the sheave pedestals, level bearing shoes with a machinist level. Bearing shoe elevations shall be accurate to within ± 1/16 inch. Entire length of bearing feet shall contact the bearing shoes. Grind bearing feet and repaint as required.
820.09.11 Installation of Span and Counterweight Guide Rails
(Vertical Lift): Install span and counterweight guide rails as shown on the plans. Guide rails shall be vertical to within ± 1/8 inch along the entire length of the rail. Guide rail splices shall mate flush. Roller guides shall not ride on guide rails during operation when there is no wind.
820.09.12 Installation of Span Locks (Vertical Lift): Span lock catch
shall have already been installed on the movable span. Locate span lock base and drill in place anchor bolts as shown on the plans. Use a template to space anchor bolts and to hold anchor bolts vertical. Using an epoxy grout from the Approved Materials List, form up and install grout pads under span lock bases as sho wn on the plans, and in a similar manner as the sheave pedestals. Level span lock bases with a machinist level. Span lock base elevations shall be accurate to within ± 1/16 inch. Locate span lock on base such that the center of the latch, when extended, is over the center of the catch when the latch is horizontal. Shim span lock so that there is a 1/16 -inch gap between the latch and the catch when the latch is extended. Adjust limit switches so that the span lock latch is fully inside the enclosure when retracted and horizontal when extended.
820.09.13 Installation of Air Buffers (Vertical Lift): Install air buffers
as shown on the plans and thoroughly lubricate. Provide air pressure gauges (0 - 300psi) and install in place of the oilers. Operate span and adjust air valves until the span seats gently and all buffers see approximately the same maximum pressure. This should be between 75 and 100 psi. Be prepared to demonstrate pressure settings during final setup and inspection, and have personnel and tools available to make additional adjustments at that time. After air buffer operation has been accepted, match mark the air valve position and install oilers.
820.10 Construction Require Ments for Bascule Sp An
BRIDGES.
820.10.1 Construction of Approach Spans: Approach spans
immediately adjacent to the movable span shall not be constructed until construction of the movable spans is completed. Each approach span must match the elevation and profile of the movable span across the entire width of the roadway to within ± 1/8 inch.
820.10.2 Alignment of Span Trunnion Bearings (Bascule): Span
trunnion bearing supports must have a surface flatness of 0.010 inches under the entire footprint of the span trunnion bearing housing and must be level to the accuracy of a machinist’s level. Field machine, if necessary, to meet these requirements. Shim the span trunnion bearings to the design elevations and align using a piano wire, laser, or other approved method.
820.10.3 Alignment of Movable Span(s) (Bascule): Hold trusses or
girders of bascule span(s) erected in the open position to the correct alignment by the use of struts, braces, guy -wires or other approved methods. Drilling and reaming of bolt holes for lateral bracing may be performed after lowering the bascule span(s) to allow adjustment of alignment in the closed position. For double leaf bascule spans, the two spans must be aligned to within the allowable tolerances of the span locks in the closed position, and the two spans must match the elevation and profile of each other across the entire width of the roadway to within ± 1/8 inch. Do not install the turned bolts/fitted pins in the span trunnion bearings until alignment of the bascule span(s) in the open and closed positions has been verified.
820.10.4 Balancing of the Movable Span (Bascule): Use the strain
gauge balancing method to balance the movable span(s). Adjust balance blocks to achieve a balance condition of 3,000 pounds “toe” or “tip” heavy in the closed position and neutral in the open position.
820.11 MEASUREMENT. Except as defined below, measurement for movable
bridge components shall be made in accordance with its respective Section. Measurement includes all equipment, materials, labor, tools, and incidentals necessary to complete this item.
820.10 Construction Require Ments for Bascule Sp An
BRIDGES.
820.10.1 Construction of Approach Spans: Approach spans
immediately adjacent to the movable span shall not be constructed until construction of the movable spans is completed. Each approach span must match the elevation and profile of the movable span across the entire width of the roadway to within ± 1/8 inch.
820.10.2 Alignment of Span Trunnion Bearings (Bascule): Span
trunnion bearing supports must have a surface flatness of 0.010 inches under the entire footprint of the span trunnion bearing housing and must be level to the accuracy of a machinist’s level. Field machine, if necessary, to meet these requirements. Shim the span trunnion bearings to the design elevations and align using a piano wire, laser, or other approved method.
820.10.3 Alignment of Movable Span(s) (Bascule): Hold trusses or
girders of bascule span(s) erected in the open position to the correct alignment by the use of struts, braces, guy -wires or other approved methods. Drilling and reaming of bolt holes for lateral bracing may be performed after lowering the bascule span(s) to allow adjustment of alignment in the closed position. For double leaf bascule spans, the two spans must be aligned to within the allowable tolerances of the span locks in the closed position, and the two spans must match the elevation and profile of each other across the entire width of the roadway to within ± 1/8 inch. Do not install the turned bolts/fitted pins in the span trunnion bearings until alignment of the bascule span(s) in the open and closed positions has been verified.
820.10.4 Balancing of the Movable Span (Bascule): Use the strain
gauge balancing method to balance the movable span(s). Adjust balance blocks to achieve a balance condition of 3,000 pounds “toe” or “tip” heavy in the closed position and neutral in the open position.
820.11 MEASUREMENT. Except as defined below, measurement for movable
bridge components shall be made in accordance with its respective Section. Measurement includes all equipment, materials, labor, tools, and incidentals necessary to complete this item.
820.10 Construction Require Ments for Bascule Sp An
BRIDGES.
820.10.1 Construction of Approach Spans: Approach spans
immediately adjacent to the movable span shall not be constructed until construction of the movable spans is completed. Each approach span must match the elevation and profile of the movable span across the entire width of the roadway to within ± 1/8 inch.
820.10.2 Alignment of Span Trunnion Bearings (Bascule): Span
trunnion bearing supports must have a surface flatness of 0.010 inches under the entire footprint of the span trunnion bearing housing and must be level to the accuracy of a machinist’s level. Field machine, if necessary, to meet these requirements. Shim the span trunnion bearings to the design elevations and align using a piano wire, laser, or other approved method.
820.10.3 Alignment of Movable Span(s) (Bascule): Hold trusses or
girders of bascule span(s) erected in the open position to the correct alignment by the use of struts, braces, guy -wires or other approved methods. Drilling and reaming of bolt holes for lateral bracing may be performed after lowering the bascule span(s) to allow adjustment of alignment in the closed position. For double leaf bascule spans, the two spans must be aligned to within the allowable tolerances of the span locks in the closed position, and the two spans must match the elevation and profile of each other across the entire width of the roadway to within ± 1/8 inch. Do not install the turned bolts/fitted pins in the span trunnion bearings until alignment of the bascule span(s) in the open and closed positions has been verified.
820.10.4 Balancing of the Movable Span (Bascule): Use the strain
gauge balancing method to balance the movable span(s). Adjust balance blocks to achieve a balance condition of 3,000 pounds “toe” or “tip” heavy in the closed position and neutral in the open position.
820.11 MEASUREMENT. Except as defined below, measurement for movable
bridge components shall be made in accordance with its respective Section. Measurement includes all equipment, materials, labor, tools, and incidentals necessary to complete this item.
820.10 Construction Require Ments for Bascule Sp An
BRIDGES.
820.10.1 Construction of Approach Spans: Approach spans
immediately adjacent to the movable span shall not be constructed until construction of the movable spans is completed. Each approach span must match the elevation and profile of the movable span across the entire width of the roadway to within ± 1/8 inch.
820.10.2 Alignment of Span Trunnion Bearings (Bascule): Span
trunnion bearing supports must have a surface flatness of 0.010 inches under the entire footprint of the span trunnion bearing housing and must be level to the accuracy of a machinist’s level. Field machine, if necessary, to meet these requirements. Shim the span trunnion bearings to the design elevations and align using a piano wire, laser, or other approved method.
820.10.3 Alignment of Movable Span(s) (Bascule): Hold trusses or
girders of bascule span(s) erected in the open position to the correct alignment by the use of struts, braces, guy -wires or other approved methods. Drilling and reaming of bolt holes for lateral bracing may be performed after lowering the bascule span(s) to allow adjustment of alignment in the closed position. For double leaf bascule spans, the two spans must be aligned to within the allowable tolerances of the span locks in the closed position, and the two spans must match the elevation and profile of each other across the entire width of the roadway to within ± 1/8 inch. Do not install the turned bolts/fitted pins in the span trunnion bearings until alignment of the bascule span(s) in the open and closed positions has been verified.
820.10.4 Balancing of the Movable Span (Bascule): Use the strain
gauge balancing method to balance the movable span(s). Adjust balance blocks to achieve a balance condition of 3,000 pounds “toe” or “tip” heavy in the closed position and neutral in the open position.
820.11 MEASUREMENT. Except as defined below, measurement for movable
bridge components shall be made in accordance with its respective Section. Measurement includes all equipment, materials, labor, tools, and incidentals necessary to complete this item.
820.10 Construction Require Ments for Bascule Sp An
BRIDGES.
820.10.1 Construction of Approach Spans: Approach spans
immediately adjacent to the movable span shall not be constructed until construction of the movable spans is completed. Each approach span must match the elevation and profile of the movable span across the entire width of the roadway to within ± 1/8 inch.
820.10.2 Alignment of Span Trunnion Bearings (Bascule): Span
trunnion bearing supports must have a surface flatness of 0.010 inches under the entire footprint of the span trunnion bearing housing and must be level to the accuracy of a machinist’s level. Field machine, if necessary, to meet these requirements. Shim the span trunnion bearings to the design elevations and align using a piano wire, laser, or other approved method.
820.10.3 Alignment of Movable Span(s) (Bascule): Hold trusses or
girders of bascule span(s) erected in the open position to the correct alignment by the use of struts, braces, guy -wires or other approved methods. Drilling and reaming of bolt holes for lateral bracing may be performed after lowering the bascule span(s) to allow adjustment of alignment in the closed position. For double leaf bascule spans, the two spans must be aligned to within the allowable tolerances of the span locks in the closed position, and the two spans must match the elevation and profile of each other across the entire width of the roadway to within ± 1/8 inch. Do not install the turned bolts/fitted pins in the span trunnion bearings until alignment of the bascule span(s) in the open and closed positions has been verified.
820.10.4 Balancing of the Movable Span (Bascule): Use the strain
gauge balancing method to balance the movable span(s). Adjust balance blocks to achieve a balance condition of 3,000 pounds “toe” or “tip” heavy in the closed position and neutral in the open position.
820.11 MEASUREMENT. Except as defined below, measurement for movable
bridge components shall be made in accordance with its respective Section. Measurement includes all equipment, materials, labor, tools, and incidentals necessary to complete this item.
820.10 Construction Require Ments for Bascule Sp An
BRIDGES.
820.10.1 Construction of Approach Spans: Approach spans
immediately adjacent to the movable span shall not be constructed until construction of the movable spans is completed. Each approach span must match the elevation and profile of the movable span across the entire width of the roadway to within ± 1/8 inch.
820.10.2 Alignment of Span Trunnion Bearings (Bascule): Span
trunnion bearing supports must have a surface flatness of 0.010 inches under the entire footprint of the span trunnion bearing housing and must be level to the accuracy of a machinist’s level. Field machine, if necessary, to meet these requirements. Shim the span trunnion bearings to the design elevations and align using a piano wire, laser, or other approved method.
820.10.3 Alignment of Movable Span(s) (Bascule): Hold trusses or
girders of bascule span(s) erected in the open position to the correct alignment by the use of struts, braces, guy -wires or other approved methods. Drilling and reaming of bolt holes for lateral bracing may be performed after lowering the bascule span(s) to allow adjustment of alignment in the closed position. For double leaf bascule spans, the two spans must be aligned to within the allowable tolerances of the span locks in the closed position, and the two spans must match the elevation and profile of each other across the entire width of the roadway to within ± 1/8 inch. Do not install the turned bolts/fitted pins in the span trunnion bearings until alignment of the bascule span(s) in the open and closed positions has been verified.
820.10.4 Balancing of the Movable Span (Bascule): Use the strain
gauge balancing method to balance the movable span(s). Adjust balance blocks to achieve a balance condition of 3,000 pounds “toe” or “tip” heavy in the closed position and neutral in the open position.
820.11 MEASUREMENT. Except as defined below, measurement for movable
bridge components shall be made in accordance with its respective Section. Measurement includes all equipment, materials, labor, tools, and incidentals necessary to complete this item.
820.10 Construction Require Ments for Bascule Sp An
BRIDGES.
820.10.1 Construction of Approach Spans: Approach spans
immediately adjacent to the movable span shall not be constructed until construction of the movable spans is completed. Each approach span must match the elevation and profile of the movable span across the entire width of the roadway to within ± 1/8 inch.
820.10.2 Alignment of Span Trunnion Bearings (Bascule): Span
trunnion bearing supports must have a surface flatness of 0.010 inches under the entire footprint of the span trunnion bearing housing and must be level to the accuracy of a machinist’s level. Field machine, if necessary, to meet these requirements. Shim the span trunnion bearings to the design elevations and align using a piano wire, laser, or other approved method.
820.10.3 Alignment of Movable Span(s) (Bascule): Hold trusses or
girders of bascule span(s) erected in the open position to the correct alignment by the use of struts, braces, guy -wires or other approved methods. Drilling and reaming of bolt holes for lateral bracing may be performed after lowering the bascule span(s) to allow adjustment of alignment in the closed position. For double leaf bascule spans, the two spans must be aligned to within the allowable tolerances of the span locks in the closed position, and the two spans must match the elevation and profile of each other across the entire width of the roadway to within ± 1/8 inch. Do not install the turned bolts/fitted pins in the span trunnion bearings until alignment of the bascule span(s) in the open and closed positions has been verified.
820.10.4 Balancing of the Movable Span (Bascule): Use the strain
gauge balancing method to balance the movable span(s). Adjust balance blocks to achieve a balance condition of 3,000 pounds “toe” or “tip” heavy in the closed position and neutral in the open position.
820.11 MEASUREMENT. Except as defined below, measurement for movable
bridge components shall be made in accordance with its respective Section. Measurement includes all equipment, materials, labor, tools, and incidentals necessary to complete this item.
820.12 Payment.
Payment will be made at the Contract unit price which includes all equi pment, materials, labor, tools, and incidentals necessary to complete the item. Cost of preparing and submitting the manuals shall be included in the pay items of Sections of 821, 822, and 823. The Department will withhold 5 percent of the bid price of all mechanical, electrical, and facility items (821, 822, and 823 items) until all manuals have been reviewed and accepted, and final paper reproductions have been received by the Department. Payment will be made under: Item No. Pay Item Pay Unit 820-01 Temporary Operation & Maintenance of Movable Span Lump Sum 820-02 Temporary Operation & Maintenance of Movable Span Day 820-03 Weighing and Balancing of Movable Span Lump Sum 820-04 Final Setup and Field Testing Lump Sum 820-05 Training Lump Sum
820.12 Payment.
Payment will be made at the Contract unit price which includes all equi pment, materials, labor, tools, and incidentals necessary to complete the item. Cost of preparing and submitting the manuals shall be included in the pay items of Sections of 821, 822, and 823. The Department will withhold 5 percent of the bid price of all mechanical, electrical, and facility items (821, 822, and 823 items) until all manuals have been reviewed and accepted, and final paper reproductions have been received by the Department. Payment will be made under: Item No. Pay Item Pay Unit 820-01 Temporary Operation & Maintenance of Movable Span Lump Sum 820-02 Temporary Operation & Maintenance of Movable Span Day 820-03 Weighing and Balancing of Movable Span Lump Sum 820-04 Final Setup and Field Testing Lump Sum 820-05 Training Lump Sum Section 821 Mechanical Systems
821.01 DESCRIPTION. Provide all material, equipment, tools, measuring
devices, and labor to purchase/fabricate, shop test, transport, install/erect, align/adjust, paint, lubricate, field test, and set -up all Mechanical Items/Systems as speci fied herein. These specification govern both new construction projects and rehabilitation/ repair projects.
821.02 ACRONYMS AND ABBREVI ATIONS. See 101.02 and 801.02 for
additional acronyms and abbreviations. ASJ All Service Jacket BOD Biological Oxygen Demand BTU British Thermal Unit CFM Cubic Feet per Minute CMU Concrete Masonry Unit CWP Cold Working Pressure GPM Gallons per Minute EPDM Ethylene Propylene Diene Monomer EEIPS Double Extra Improved Plow Steel EIPS Extra Improved Plow Steel FKM Fluorocarbon Elastomer FSK Foil-Scrim Kraft HFC Hard Fiber Core HPU Hydraulic Powe r Unit HVAC Heating, Ventilation, and Air Conditioning IWRC Independent Wire Rope Core MDFT Minimum Dry Film Thickness MERV Minimum Efficiency Reporting Value NIST National Institute of Standards and Technology NPS Nominal Pipe Size NRTL Nationally Recognized Testing Laboratories PE Polyethylene PVC Polyvinyl Chloride PVDF Polyvinylidene Diflouride