205 — TEST PIT EXCAVATION 2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 200 GRADING SECTION 205 — TEST PIT EXCAVATION

205.01 Description

Excavate and backfill test pits to determine the location of underground structures and utilities.

205.02 Materials

Not applicable.

205.03 Construction

Determine the location of underground structures and utilities by test pit excavation prior to excavation operations. Excavate test pits at the location and to the size and depth authorized. Backfill test pits as specified in Section 210.

205.04 Measurement and Payment

Test Pit Excavation will be measured and paid for at the Contract unit price per cubic yard for the material actually removed from within the limits specified. The payment will be full compensation for all excavation, tamped backfill, and all material, labor, equipment, tools, and incidentals necessary to complete the work. Any pavement to be replaced will be measured and paid for as specified in Section 106.

Get an email when 205 changes

Maryland revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Construction and Materials, 2026 Edition. Pages 304–304 of 1,138. View official source ↗

Ask about this section

Scoped to Maryland Standard Specifications for Construction and Materials, Section 205 — Test Pit Excavation. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.