B
HomeLibrariesCopilotSearchProjectsBookmarks
FeedbackHelp Desk
Libraries
Building Codes
Code LibraryIBC — BuildingIRC — ResidentialIFC — FireIPC — PlumbingIMC — MechanicalIFGC — Fuel GasIECC — EnergyNEC — ElectricalModel Codes
Specifications
CSI SpecificationsDOT SpecsTransit SpecsUSACE
Standards
TransportationRailroadFire SafetyAccessibilityStructural
Tools & References
DiagramsAssembliesProductsCalculatorsChecklistsPermits
PricingLog in
General Provisions (00100-00999)

210801 — Concrete Foundations

MD · 2025 Standard SpecificationsBook pages 872873View official source ↗

CATEGORY 800 TRAFFIC SECTION 801 — CONCRETE FOUNDATIONS

801.01 Description

Construct concrete foundations for installing traffic signals, highway lighting, and signs.

801.02 Materials

Curing Materials 902.07 Portland Cement Concrete 902.10, Mix No. 3 Corrugated Metal Pipe Section 905 Reinforcement Steel Section 908 Anchor Bolts 909.08 Conduit 950.10 Galvanizing for Hardware A153

801.03 Construction

801.03.01 Excavation. Excavate to the dimensions specified. Ensure that all excavation work is

inspected and approved before proceeding with construction.

801.03.02 Galvanized parts that have been cut or chipped to bare metal shall be repaired according

to A780. 801.03.03 Concrete Placement. Place concrete against undisturbed earth wherever possible. However, where the existing ground shows a tendency to cave in or otherwise will not retain its shape during or after excavation provide, install, and leave in place a corrugated steel pipe. Mix, place, and test concrete as specified in Section 420. Construct footings, including reinforcement and bolt circle data, as specified in the Contract Documents and in conformance with the approved working drawings. Use suitable and accurately placed templates to set the anchor bolts plumb. Leave the templates in place until the concrete attains initial set. Apply a level trowel finish to the top of the foundation. Apply a liquid membrane forming compound to all exposed surfaces. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS.

801.03.04 Unusual Soil Conditions. When unexpected subsurface conditions are encountered,

modify the excavation depth as directed. If rock or boulders cannot be removed by ordinary means, remove them to the levels and dimensions specified, or to a depth necessary to obtain the required stability.

801.03.05 Backfill. Use material that is free of topsoil, organic, frozen, and other undesirable

materials. Keep spaces to be backfilled free of trash. Clean the space before placing backfill. Use suitable material from the excavation or other sources as specified in Section 204. Place in layers not more than 8 in. loose thickness. Use mechanical or vibratory compaction equipment to obtain at least 92 percent of maximum density at a moisture content within 2 percent of the optimum according to T 180, Method C.

801.04 Measurement and Payment

Concrete foundations for installing traffic signals, highway lighting, and signs will be measured and paid for at the Contract unit price per cubic yard for the pertinent Concrete Foundation item. The payment will be full compensation for all concrete, excavation, corrugated metal pipe or forms, reinforcement steel, anchor bolts, backfill, and for all material, labor, equipment, tools, and incidentals necessary to complete the work. Where concrete barrier transitions, grounding, and conduit are required, they will be measured and paid for as specified in Section 604, Section 804, and Section 805 respectively. 802 — GALVANIZED STEEL BEAM SIGN POSTS 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 800 TRAFFIC SECTION 802 — GALVANIZED STEEL BEAM SIGN POSTS

802.01 Description

Furnish and install galvanized steel beam sign posts.

802.02 Materials

Bolts, Nuts and Washers 909.07 Galvanizing for Beams A123 Galvanizing for Hardware A153 Steel Beams A709

802.03 Construction

Stake each location for approval. Upon approval, submit working drawings. Show the highest elevation of the traveled roadway and the shoulder elevation at each post location. Upon approval of the working drawings, materials may be ordered. Galvanized parts that have been cut or chipped to bare metal shall be repaired according to A780. Install posts plumb and to the lateral orientation specified.

802.04 Measurement and Payment

Galvanized Steel Beam Sign Posts will be measured and paid for at the Contract unit price per linear foot for the various sizes of posts specified. The payment will be full compensation for stakeout, and for all material, labor, equipment, tools, and incidentals necessary to complete the work. Breakaway Base Support Systems will be measured and paid for as specified in Section 821.

Source: Maryland Standard Specifications for Construction and Materials, 2025 Edition. Pages 872873 of 1,113.