302 — SELECTED BACKFILL 2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 300 DRAINAGE SECTION 302 — SELECTED BACKFILL
302.01 Description
Place selected backfill material and compact.
302.03 Construction
Place selected backfill on suitable subgrade material that has been prepared in as specified in Section 208 and compact the selected backfill as specified in Section 210. When unsuitable subgrade material is encountered, notify the Engineer to inspect the material. Excavate unsuitable material as specified in 208.03.01 and Section 301 before placing selected backfill.
302.04 Measurement and Payment
Selected Backfill using No. 57 Aggregate or Selected Backfill using Crusher Run Aggregate CR-6 will be measured and paid for at the Contract unit price per cubic yard. The payment will be full compensation for all material, labor, equipment, tools, and incidentals necessary to complete the work.
Get an email when 302 changes
Maryland revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.