301Class 3 Excavation for Incidental Construction

MD · 2026 Standard Specifications✓ Full text on BuildSpecBook pages 317–317 Save this section

Ask about Section 301

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

301 — CLASS 3 EXCAVATION FOR INCIDENTAL CONSTRUCTION 2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 300 DRAINAGE SECTION 301 — CLASS 3 EXCAVATION FOR INCIDENTAL CONSTRUCTION

301.01 Description

Excavate below the specified elevation when unsuitable subgrade material is encountered.

301.02 Materials

Not applicable.

301.03 Construction

Excavate to the length, width, and depth at authorized locations. Handle excavated material as specified in 402.03.01.

301.04 Measurement and Payment

Class 3 Excavation for Incidental Construction will be measured and paid for at the Contract unit price per cubic yard. The payment will be full compensation for all material, labor, equipment, tools, and incidentals necessary to complete the work.

Get an email when 301 changes

Maryland revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Construction and Materials, 2026 Edition. Pages 317–317 of 1,138. View official source ↗