301 — CLASS 3 EXCAVATION FOR INCIDENTAL CONSTRUCTION 2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 300 DRAINAGE SECTION 301 — CLASS 3 EXCAVATION FOR INCIDENTAL CONSTRUCTION
301.01 Description
Excavate below the specified elevation when unsuitable subgrade material is encountered.
301.02 Materials
Not applicable.
301.03 Construction
Excavate to the length, width, and depth at authorized locations. Handle excavated material as specified in 402.03.01.
301.04 Measurement and Payment
Class 3 Excavation for Incidental Construction will be measured and paid for at the Contract unit price per cubic yard. The payment will be full compensation for all material, labor, equipment, tools, and incidentals necessary to complete the work.