gp-3Award and Execution of Contract

MD · 2026 Standard Specifications✓ Full text on BuildSpecBook pages 33–34 Save this section

Ask about Section gp-3

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

GP-3.01AWARD OF CONTRACT (SEE GP-2.19)

Written notice of award shall be sent to the successful bidder. A Notice of Award may be rescinded at any time prior to execution of the Contract by the Administrator.

GP-3.02RETURN OF PROPOSAL GUARANTY

All proposal guaranties, except those of the three lowest bidders, will be returned immediately following opening and the review of the proposals. The guaranty of the three lowest bidders will be returned following the execution of the Contract and approval by the Board, if required. The Contractor has the right to substitute a bid bond for other bid security at any time prior to return of the proposal guaranty.

GP-3.03PERFORMANCE BOND AND PAYMENT BOND

REQUIREMENTS

(a)Acceptable security for performance and payment shall be as stated in

COMAR 21.06.07.01B.

(b)Performance and Payment Bonds. A performance and payment bond is required for

all construction Contracts in excess of $100,000 each in the amount equal to at least 100 percent of the Contract price. The bonds shall be delivered by the bidder to the Administration no later than the time the Contract is to be executed. If the bidder fails to deliver the required bonds, the bid shall be rejected, the bid security shall be enforced, and award of the Contract may be made to the next lowest responsive and responsible bidder.

(1)The required performance bond shall be in the form specified in

COMAR 21.07.02.10, Exhibit A.

(2)The required payment bond shall be in the form specified in

COMAR 21.07.02.10, Exhibit B.

GP-3.04EXECUTION OF CONTRACT

(a)The Contract shall be effective only upon receipt by the Administration of the proper,

executed Contract form, and performance and payment bonds (if required), approval by the Board of Public Works, (if required), and execution of the Contract by the Administration.

(b)After a Notice of Award, as provided in GP-3.01, has been issued to a bidder, the

Administration shall forward the formal Contract form and the appropriate forms for the payment and performance bonds (if any) to the bidder for execution. The bidder will execute the Contract form and return same, together with fully executed payment and performance bonds (if any), to the Administration within 10 days after receipt of same. After receipt of properly executed Contract form and payment and performance bonds, (if any), the Administration will execute the Contract within 60 days and forward the bidder a copy; provided, however, that the Board has approved the Contract if such approval is required. If the Administration fails to execute the Contract and the period of irrevocability has expired, the bidder may, as its sole remedy, withdraw its bid.

GP-3.05FAILURE TO EXECUTE CONTRACT

Failure of the bidder to execute the Contract and file acceptable security as defined in GP-3.03 within the time aforesaid shall be just cause for the annulment of the award and the forfeiture of the proposal guaranty which shall become the property of the State of Maryland, not as a penalty but in liquidation of damages sustained. Award may then be made to the next lowest responsive, responsible bidder or the work may be readvertised and constructed under Contract or otherwise, as the Administration may decide.

Get an email when gp-3 changes

Maryland revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Construction and Materials, 2026 Edition. Pages 33–34 of 1,138. View official source ↗