3-21 FULL DEPTH RECYCLED PAVEMENT (With Foamed Asphalt)
309.01 Description This work shall consist of pulverizin g a portion of the existing
roadway structure into a homogenous mass, treating the pulveriz ed material with the foamed asphalt process, and placing and compacting this material to th e lines, grades, and dimensions shown on the plans or established by the Resident. MATERIALS 309.020 Pulverized Material Pulverized material shall co nsist of the existing asphalt pavement and one inch or more as specified of the underlying gr avel, pulverized and blended into a homogenous mass. Pulverized material will be pr ocessed to 100 percent passing a 2 in square mesh sieve. 309.021 New Aggregate and Additional Recycled Material New aggregate, if required by the contract, shall meet the requirements of Sectio n 703.10 - Aggregate for Untreated Surface Course and Leveling Course, Type A. Aggregate Subbase Course Gravel Type D processed to 100 percent passing a 2 inch square mesh si eve and meeting the requirements of 703.06 – Aggregate for Base and Subbase may be used in areas requiring depths greater than 2 inches. New aggregate required to restor e grade and/or cross-slope shall be measured and paid for under the appropriate item. Crus her dust required as part of the job mix shall be considered part of the 309 item and will n ot be measured for payment. Recycled material, if required, shall consist of salvaged aspha lt material from the project or from off-site stockpiles that has been processed, prior to u se to 100 percent passing a 2 in square mesh sieve. Recycled material shall be conditionally ac cepted at the source by the Resident. It shall be free of winter sand, granular fill, const ruction debris, and other materials not generally considered asphalt pavement. Recycled material generated and salvaged from the project shall be used within the roadway limits to the extent it is available as described in 30 9.06. No additional payment will be made for material salvaged from the project. Recycled material supplied from off-site stockpiles shall be p aid for as described in the contract, or by contract modification. 309.022 Asphalt Binder The asphalt binder used in the f oamed asphalt process shall be Performance Grade 64-28 or 58-28 meeting the requirements of AASHTO M320. 309.023 Portland Cement The Portland Cement shall be Ty pe I or II meeting the requirements of AASHTO M85. 309.024 Hydrated Lime Hydrated Lime shall meet the requ irements of AASHTO M216. 3-22 309.025 Crusher Dust Crusher dust, if required by the m ix design, shall be free from friable or deleterious material, including excessive mica, and shall meet the following gradation requirements: Sieve Size Percent Passing 12.5 mm [½ in] 100 0.075 mm [No. 200] 10 - 20 309.026 Water Water shall be clean and free from delete rious concentrations of acids, alkalis, salts or other organic or chemical substances. EQUIPMENT 309.030 Pulverizer The modified milling or recycling mach ine shall, as a minimum, have the following features: EHT*** a. A minimum power capability of 600 horsepower. b. Two microprocessor-controlled systems, complete with 2 indep endent pumping systems and spray bars, to regulate the application of foamed a sphalt stabilizing agent, separate from water (for increas ing the moisture content of the recycled material), in relation to the forward speed and mass of the material being recycled.
309.04 Pulverizing The entire depth of existing pavement shall be pulverized
together with approximately 1 i nch or more of the underlying gr avel into a homogenous mass. All pulverizing shall be done with equipment that will p rovide a homogenous mass of pulverized material, processed in-place, which will pass a 2 in square mesh sieve.
309.05 Weather Limitations When foamed asphalt is used, full depth recycled work
shall be performed when; a Foaming operations will be allowed between May 15th and September 15th inclusive in Zone 1 - Areas north of US Rout e 2 from Gilead to Bangor and north of Route 9 from Bangor to Calais. Foaming operations will be allowed betwe en May 1st and September 30th inclusive in Zone 2 - Areas s outh of Zone 1 including the US R oute 2 and Route 9 boundaries. b The atmospheric temperature, as determined by an approved the rmometer placed in the shade at the recycling location, is 50°F and rising. c When there is no standing water on the surface. d During generally dry conditions, or when weather conditions a re such that proper pulverizing, adding, mixing, and c uring can be obtained using p roper procedures, and when compaction can be accomplished as determined by the Reside nt. e When the surface is not frozen and when overnight temperature s are expected to be above 32°F. f Wind conditions as such that the spreading of lime or cement on the roadway ahead of the recycling machine will not adversely affect the operatio n.
309.06 Full Depth Recycling Procedure New aggregate or r ecycled material meeting
the requirements of Section 309.021 - New Aggregate, and Recycl ed Material shall be added as necessary to restore cross-slope and/or grade before i nitial pulverizing. Locations will be shown on the plans or described in the construction not es; the Resident may add other locations while construction of the project is in progres s. The Contractor will use recycled material to the extent it is available, in lieu of new aggregate. The material shall then be pulverized, processed, and blended into a homogeneous m ass passing a 2 in square mesh sieve. Material found not pulverized down to a 2 in size w ill be required to be reprocessed by the recycler with successive passes until approv ed by the Resident. Should the Contractor be require d to add new aggregate or recyc led material to restore cross-slope and/or grade after the initial pulverizing process, those areas will require re- processing to blend into a homogenous mass passing a 2 in squa re mesh sieve. The resultant material from the initial pulverizing processes s hall be graded and compacted to the cross-slope and profile shown on the plans or as directed by the Resident. The Contractor will also be responsible for re-establishing the existing profile grade. The 3-25 completed surface of the full depth recycled course shall be sh aped and maintained to a tolerance, above or below the required cross sectional shape, o f ⅜ inch. The initial pulverizing process density requirements will be the same as Se ction 309.08 unless otherwise directed by the Resident. Following completion of the initial pulverizing and blending pr ocess the dry stabilizing agents (lime or cement) shall be spread uniformly over the full width of roadway to be recycled prior to each pass of the foaming operation, and in a continuous process by means of a mechanical spreader. Dry stabilizing agents shall be sprea d at the prescribed rate of application provided by the Department. If required by the mix design, a uniform layer of crusher dust or other aggregate specified shall be spread over th e full width of the roadway ju st prior to the foaming procedure. Foamed asphalt shall be incorporated into the materi al to a depth determined by the pavement design. These additives shall then be uniformly bl ended into a homogeneous mass until an apparent uniform distribution has occurred. The Resident may adjust the rate of application as necessary. Asphalt binder shall be added to the milling or recycling proce ss by pumping from a mobile bulk tanker that is pushed from behind by the recycling machine. Tankers shall be equipped with a built-in thermometer to ensure that the bitumin ous stabilizing agent is maintained at 375 F + 10F. The system employed to add the foamed asphalt to the recycling process shall conform to the equipment requirements s pecified in this Section. Sufficient water shall be added through the recycler head durin g the recycling process to ensure thorough blending to meet the optimum moisture for compa ction as specified. Water shall be added only by means of a controlled system on the recy cling machine. Care shall be taken to prevent excessive wetting. A second water truck may be required during recycling operations to assist in the compaction and water cont rol efforts. The rate of water supplied shall be kept constant unless changed due to project m aterial changes. The resultant material shall be graded and compacted to the cro ss-slope and profile shown on the plans or as directed by the Resident. The Contract or will also be responsible for re-establishing the existing profile grade. The completed s urface of the full depth recycled course shall be shaped and maintained to a tolerance, above or below the required cross sectional shape, of ⅜ in. Areas not meeting this toleranc e will be repaired as described in Section 309.061. After compaction, the roadway surface shall be treated with a l ight application of water, and rolled with pneumatic-tired rollers to create a close-knit texture. The finished layer shall be free from:
309.07 Quality Control The Contractor shall operate in ac cordance with the
approved Quality Control Plan (QCP) to assure a product meeting the contract requirements. The QCP shall meet the requirements of Section 106.4 - Quality Control and this Section. The Contractor shall not begin recycling operations until the D epartment approves the QCP in writing. Prior to performing any recycling process, the Department and t he Contractor shall hold a Pre-recycle conference to discuss the recycling schedule, typ e and amount of equipment to be used, sequence of operations, and traffic control. A copy o f the QC random numbers to be used on the project shall be provided to the Resident. All field and plant supervisors including the responsible onsite recycling process supervisor s hall attend this meeting. The QCP shall address any items that affect the quality of the Recycling Process including, but not limited to, the following:
309.08 Test Strip The contractor shall assemble all item s of equipment for the
recycling operation on the first day of the foamed asphalt work . The Contractor shall construct a test strip for the project at a location approved b y the Resident. The Responsible onsite Recycling Supervisor will work with Department personnel to determine the 3-28 suitability of the mixed material, bitumen dispersion within th e mixed material, moisture control within the mixed material, and compaction and surface f inish. Thetest strip section is required to:
309.09 Miscellaneous No new pavement shall be placed on the full depth recycled
pavement until a curing period of 48 hours has elapsed. If inc lement weather occurs, the Department reserves the right to extend the curing period.
309.10 Method of Measurement Full Depth recycled materia l (with Foamed
Asphalt) will be measured by the yd2. 3-29
309.11 Basis of Payment The accepted quantity of Full De pth Recycled Pavement
with Foamed Asphalt shall be paid for at the contract unit pric e per yd2, complete in-place to the specified limits, which price shall be full compensation fo r furnishing all equipment and labor for pulverizing, blending, placing, grading, compacting a nd for all incidentals necessary to complete the work i ncluding asphalt binder, water, Portland Cement, lime, and crusher dust. The addition of materials to restore profile grade and/or cross -slope in areas shown on the plans or described in the construction notes will be paid s eparately under designated pay items within the contract. No additional payment will be made f or materials salvaged from the project. Payments will be made under: P a y I t e m Pay Unit
309.35 Full Depth Recycled Pavement with Foamed Asphalt 5 in de pth Square Yard
309.36 Full Depth Recycled Pavement with Foamed Asphalt 6 in de pth Square Yard
SECTION 310 - PLANT MIXED RECYCLED ASPHALT PAVEMENT
310.01 Description This work shall consist of the removal of a ll bituminous pavement
from the existing roadway, hauling the bituminous pavement to a n approved location, and processing as per Section 310.020. The gravel base of the exis ting roadway shall be regraded and compacted to the tolerances shown on the typicals, or as directed by the Resident. All plant mixed recycled asphalt pavement shall be placed in on e or more courses on an approved base and in accordance with these specifications, and in reasonably close conformity with the lines, grades and thicknesses indicated on the plans, or as established by the Resident. Excess recycled material not used in the PMRAP p rocess will become the property and responsibility of the contractor. 310.020 Composition of Mixture The mixture shall be composed a s directed in the job mix formula. The recycled asphalt pavement shall be processed b y the Contractor so all material will be no larger than 1 ½ inch and stockpiled so as t o minimize segregation. The stockpile shall be free of any materials not generally consider ed to be asphalt pavement. If additional material is required, the material will be supplied by the Department or acquired from the Contractor through the C ontract Modification process. A job mix formula shall be furnished by the Department establis hing the percentage of emulsified asphalt cement, Portland Cement, aggregate, and wate r to be used in the mixture. The JMF additive proportions will be verified by taking a secon d recycled material sample once the stockpiles have been constructed.