SECTION 604 - MANHOLES, INLETS, AND CATCH BASINS
604.01 Description Construct manholes, inlets, and catch basins.
604.02 Materials Materials shall meet the requirements specified in the following
Sections of Division 700 - Materials: Portland Cement 701.01 Clay or Shale Brick 704.01 C o n c r e t e M a s o n r y B l o c k s 704.03 J o i n t M o r t a r 705.02 6-14 Reinforcing Steel 709.01 Stone Curbing and Edging 712.04 Precast Concrete Units 712.06 Tops and Traps 712.07 C o r r u g a t e d M e t a l U n i t s 712.08 Catch Basin and Manhole Steps 712.09 Except as otherwise provided on the plans, concrete for these structures shall meet the requirements of Section 502 - Structural Concrete. Catch basin grates shall be either the type of grate shown on the Standard Details or an approved equal. The corners shall be notched by the Contractor at the project site by grinding the corner to fit the cast iron frames.
604.03 Construction Requirements Concrete catch basins and manholes shall be
constructed of precast units, except that concrete blocks may be used around inlet and outlet pipes. Joints for precast concrete units shall be of Portland cement mortar, rubber gaskets, flexible plastic rings, mastic joint filler or other approved types to form a watertight joint. Joints for concrete blocks shall be of Portland cement mortar, not more than ½ inch wide, completely filled and neatly tooled on the inside of the structure. Metal catch basins shall be corrugated metal pipe units mounte d on a Portland cement concrete foundation. Catch basins and manholes shall be placed to the required grad e on a compacted foundation of uniform density. Inlet and outlet pipe elevations may vary from the elevations shown on the plans depending upon field conditions. Pipe sections entering catch basins shall be firmly connected to the structure wall with no part of the pipe projecting more than 6 inches inside the wall. When a section of culvert is cut, the end shall be finished in a skillful manner. Metal frames and traps, when called for, shall be set in a bed of clay bricks or shale bricks and mortar, or otherwise secured as shown on the plans. Castings shall be set to the correct elevation before the next final course of paving material has been placed. Upon completion, each catch basin and manhole shall be cleaned of all accumulation of silt, debris, or foreign matter and shall be kept clean until final acceptance of the work.
604.04 Altering, Adjusting, and Rebuilding Catch Basins and Manholes Existing catch
basins and manholes shall be dismantled sufficiently to allow altering, adjusting, or rebuilding in accordance with the applicable requirements as shown on the Standard Detail plans for complete catch basins and manholes. When existing frames, covers, and grates are used, they shall be thoroughly cleaned of existing mortar before placing to the new grade. 6-15
604.05 Method of Measurement Catch basins, manholes, and accessories of the
respective types will be measured by the number of units, measured as follows, complete, and accepted in place.
604.06 Basis of Payment The accepted quantities of catch basins, manholes, altered
grates, traps, and steps, will be paid for at the contract unit price each of the respective types complete in place. Payment for rebuilding, adjusting or altering catch basins and manholes shall include furnishing all materials including new blocks, bricks, mortar, metal tops, covers, and curb inlets when required. Frames, grates, and covers for new or rebuilt catch basins or manholes shall be considered part of the structure and no separate payment will be made. Payment for cleaning existing catch basins and manholes will be paid for at the contract unit price each. There will be no payment for cleaning new, altered, adjusted, or rebuilt catch basins and manholes. Payment will be full compensation for supplying all equipment and labor to clean the basins and manholes and to dispose of the waste. Excavation and backfill will be considered incidental, except as provided in Section 206 - Structural Excavation. Payment will be made under: P a y I t e m P a y U n i t 604.072 Catch Basin Type A1-C Each 604.082 Catch Basin Type A2-C Each
604.09 Catch Basin Type B1 Each
604.092 Catch Basin Type B1-C Each 604.096 60”Catch Basin Type B1-C Each 604.097 72”Catch Basin Type B1-C Each
604.10 Catch Basin Type B2 Each
604.102 Catch Basin Type B2-C Each
604.11 Catch Basin Type C1 Each
604.12 Catch Basin Type C2 Each
604.13 24 inch Catch Basin Type E Each
604.14 30 inch Catch Basin Type E Each
604.15 Manhole Each
604.16 Altering Catch Basin to Manhole Each
604.161 Altering Catch Basin Each 604.164 Rebuilding Catch Basin Each 604.166 Rebuilding Manhole Each 604.167 ChangeCatch Basin Grate to Cascade Grate Each
604.17 Altering Manhole to Catch Basin Each
604.18 Adjusting Manhole or Catch Basin to Grade Each
604.182 Cleaning Existing Catch Basin and Manhole Each
604.19 8 inch Trap Each
604.20 12 inch Trap Each
604.21 15 inch Trap Each
604.22 18 inch Trap Each
6-18
604.23 Step Each
604.242 Catch Basin Type F3 Each 604.243 Catch Basin Type F3-C Each 604.244 Catch Basin Type F4 Each 604.245 Catch Basin Type F4-C Each 604.246 Catch Basin Type F5 Each 604.247 Catch Basin Type F5-C Each 604.248 Catch Basin Type F6 Each 604.249 Catch Basin Type F6-C Each
604.25 Catch Basin Type A5 Each
604.252 Catch Basin Type A5-C Each
604.26 Catch Basin Type B5 Each
604.262 Catch Basin Type B5-C Each
Manholes, Inlets, and Catch Basins in other states
Get an email when 604 changes
Maine revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.