SECTION 619 - MULCH
619.01 Description This work shall consist of furnishing and applying hay, straw,
bark, erosion control mix, or cellulose fiber for covering slopes and other areas with a mulch as shown on the plans or authorized.
619.02 Mulch Material shall conform to the requirements specified in the following
Sections of Division 700 - Materials: M u l c h 717.04 M u l c h B i n d e r 717.05
619.03 General Cellulose fiber mulch shall be used with Seedi ng Method 1 and may
be used with Seeding Method 2 in approved areas, which may include, but are not limited to, lawns adjacent to developed property, areas subject to high air blasts created by moving vehicles, and areas where hay mulch would create a hazard. 6-59
619.04 Applying Mulch Mulch sha ll be any of the following types of material.
619.05 Maintenance The Contractor shall maintain the hay, str aw, or fiber mulch by
repairing all damaged mulch and by correcting all shifting of the mulch due to wind, water, or other causes, until an acceptable growth of grass has been achieved. If cellulose fiber mulch is used, any reseeding will require a dditional cellulose fiber mulch. Bark mulch and erosion control mix will be accepted upon compl etion. Upon acceptance of each area, the Contractor will be relieved of further responsibility for maintaining that area or repairing damage except that resulting from their own or subcontractor's operations. If water spray is used as a temporary binder, it shall be main tained in a manner acceptable to the Resident. 6-60
619.06 Method of Measurement The Department will measure Mulc h for payment
by the area of surface in Units of 1000 ft2 along the slope of the ground. The quantity of bark mulch and erosion control mix measured an d accepted for payment will be the number of cubic yards each, delivered and installed to the required depth as shown on the plans or as directed. Measurement will be parallel with the slope of the ground.
619.07 Basis of Payment The accepted areas mulched will be paid for at the
contract price per unit; Bark Mulch and Erosion Control Mix will be paid for by the Cubic Yard; which shall be full compensation for furnishing and spreading the hay or straw and mulch binder, cellulose fiber mulch, bark mulch or erosion control mix. When mulch is measured by bales, each bale will be paid for at 60% of the contract price per unit. Payment will be made under: P a y I t e m P a y U n i t
619.12 Mulch Unit
619.13 Bark Mulch Cubic Yard
619.14 Erosion Control Mix Cubic Yard