1-37 Section 104. Control of the Work
104.01. Authority of Department The Contractor must not construe approvals, reviews, or inspections by the Department or its officers, agents, and employees as a warranty or assumption of liability on the part of the Department. The Contractor understands and agrees that approvals, reviews, and inspections are for the sole and exclusive purposes of the Department, whic h is acting in a governmental capacity under the contract. Department approvals, reviews, and inspections do not relieve the Contractor of its contractual obligations. The Contractor understands that approvals, reviews, and inspections are undertaken for t he sole use and information of the Department and will not act as a warranty as to the propriety of the Contractor ’s performance.
A.General Authority of the Engineer. The Engineer will decide questions that arise concerning the interpretation of the contract and its acceptable fulfillment. The Engineer will also decide questions regarding the quality and acceptability of materials provided, work performed, manner of performance, and rate of progress of the work. If either party discovers any errors, uncertainties, inconsistencies, omissions, or conflicts in the contract, the Engineer will clarify and determine the true intent of the contract.
B.Authority of the Engineer to Suspend Work. The Engineer may suspend the work, or a portion of the work, for the followi ng reasons :
1.Failure by the Contractor to correct conditions that are unsafe for the worker s or the public ;
3.Conditions considered unfavorable for the prosecution of the work ; or
4.Any other condition or reason deemed to be in the interest of the public. Upon written notice of a suspension, the Contractor must put the work in a satisfactory condition and protect the work, as directed by the Engineer. The suspended w ork must not adversely affect the safety or mobility of the public. The Contr actor must not resume the suspended work until directed, in writing, by the Engineer. MDOT Standard Specifications for Construction Section 104
1-38 C. Authority of the Engineer to Direct the Acceleration of the Work. The
Engineer may order the Contractor to accelerate the work or portions of the work to avoid user delay costs or to complete the project early.
D.Authority and Duties of Inspectors. The Department may appoint Inspectors to inspect the work and test materials. These duties may extend to all parts of the work and preparation or manufacture of materials for use in the work. The Department does not authorize an Inspector to revoke or change the contract. If a dispute arises between the Contractor and the Inspector regarding the materials provided or performance of the work, the Inspector may, by submitting written notice to the Contractor, reject materials or suspend the work until the Engineer makes a determination regarding the dispute. The Department considers work performed contrary to the Inspector ’s directions or work performed while suspended by the Inspector as unauthorized work. The Engineer may direct the Contractor to remove and replace unauthorized work at no additional cost to the Department in accordance with subsection 104.05. Actions or omissions of the Inspector will not relieve the Contractor of the responsibility of completing the work as required by the contract.
E.Authority to Inspect. The Contractor must provide the Department and its authorized representatives safe access to the work at all times. The Contractor must provide the Department an d its authorized representatives with the information and assistance necessary for them to make complete and detailed inspections. The Department may also perform inspections at mill s, plant s, laborator ies, shops, or other locations outside the project lim its. The Contractor is not entitled to a time extension or compensation for reasonable delays, inconvenience, or any other cause attributed to the Department ’s reasonable inspection of the work.
F.Authority to Inspect Scales. The Contractor must enlist the s ervices of a Michigan Registered Service Agency to certify the calibration and working order of the weighing system. The Department may inspect or verify scale systems, private scale inspectors, and inspection agencies. The Contractor must immediately correct any failure to meet the requirements of this subsection. The Contractor must ensure at all times that scales are installed, maintained, and used in accordance with the Weights and Measures Act, MCL 290.601 et seq., and the requirements of the NIST Handbook 44, Specifications, Tolerances and Other Technical Requirements for Weighing and Measuring Devices . The Contractor is responsible for all costs incurred for the inspection of scale systems, and no additional compensation will be allowed. The Contractor is not entitled to an extension of time or compensation for MDOT Standard Specifications for Construction Section 104
1-39 reasonable delays, inconvenience, or any other cause attributed to the
Department ’s inspection of scale systems. 104.02. Plans and Working Drawings The Department will provide plans showing details of the work required by the contract. If the plans omit dimensions necessary to complete the work, the Engineer will provide the Contractor with the omitted dimensions upon request. The Contractor is responsible for all dimensions he or she scales from the pl ans. The Contractor must submit , for review , all working drawings not furnished by the Department for all parts of the work as required by the c ontract. The working drawings must call attention to deviations from the plans, specifications, and contract. If deviations have not been clearly identified, they will not be considered as part of the working drawing approval. If the contract requires w orking drawings and design calculations that are not part of the finished structure, the Contractor must submit these working drawings and design calculations to the Engineer for Department review. If the contract does not require these working drawings and design calculations, but the Engineer directs the Contractor to submit them, the Department will pay for these working drawings and design calculations as extra work. The Contractor must ensure that a Professional Engineer, licensed in the State of Michigan, seals all working drawings and design calculations submitted. The Contractor is responsible for t he correctness of the working drawings and design calculations and ensuring that the design complies with any permit requirements. The Contractor will submit a complete set of w orking drawings and design calculations , and the Department will have up to 14 calendar days to review for approval or provide comments for revisions required to obtain approval unless noted otherwise in the contract. Should approval not be granted per the first review, the Contractor is required to submit revised working drawings and design calculations, and the Department may require up to 7 calendar days for each additional review cycle. To ensure timely response and review time frames, the Contractor and Department will communicate directly to address and resolve all outstanding c omments on all subsequent submittals. If, for reasons not attributed to the Contractor, additional time is required beyond 28 calendar days of Department review time to obtain approval for the working drawings, this additional time will be considered for an extension of time in accordance with sub section 108.07 or 108.08. The Contractor is responsible for costs associated with obtaining approval of w orking drawings and design calculations. MDOT Standard Specifications for Construction Section 104
1-40 The Department ’s review and approval does not relieve the Contractor of full
responsibility for all negligence in the construction of the project resulting from the working drawings. The Department ’s review and approval of the working drawings and design calculations are not a warranty of the adequacy and correctness of t he design. The Contractor may arrange for the Department to communicate directly with the fabricator or supplier to review the working drawings for the following or similar items:
A.Fabricated structural elements ;
C.Electrical equipment and circuitry ; and
D.Water mains. Prior to development of working drawings , the Contractor must check the dimensions and locations of the exposed features on existing structures to verify that its relationship to the proposed work is as shown on the plans. The Contractor must notify the Engineer of differences between the actual dimensions and locations of exposed existing features and those shown on the plans. The cost of verifying the dimensions and locations of exposed existing features is included in the c ontract unit price for mobilization in accordance with section 1 10. After completing the work, the Contractor must provide the Department with one complete set of working drawings on a medium approved by the Department. The Contractor must provide copies of catalogue cuts, parts lists, operating procedures, and instructions as deemed necessary for the project by the Engineer. 104.03. Deviations from the Plans The Contractor must not deviate from the plans or from Department -approved working drawings and design calculations unless the deviation is approved by the Engineer in writing. If the Engineer approves deviations from the plans or Department -approved working drawings, the Contractor must submit to the Engineer revised plans, working drawings, and des ign calculations sealed by a Professional Engineer, licensed in the State of Michigan, for review by the Department. The Contractor is responsible for the correctness of these revised plans, working drawings, and design calculations and for ensuring that t he revised design complies with any permit requirements. MDOT Standard Specifications for Construction Section 104
1-41 104.04. Conformity with the Contract
The Contractor must perform the work as required by the contract. The Engineer may reject work that does not meet the contract requirements. If the Engineer accepts work that does not meet the contract requirements, the Engineer will document the basis of acceptance by contract modification. The Engineer will determine whether a reduction in the contract unit price or a guaranty bond is appropriate and will properly docume nt its determination. The Contractor must remove and replace or correct rejected work as directed by the Engineer at no additional cost to the Department. 104.05. Removal of Unauthorized Work If the Contractor performs unauthorized work (work performed without the inspections required by the contract, extra work performed without Department approval, work performed contrary to the I nspectors ’ direction, or work performed while under suspension by the I nspector), the Engineer may direct the Contractor to remove and replace the unauthorized work at no additional cost to the Department. 104.06. Coordination of Drawing Dimensions and the Contract In case of a conflict in the contract, the following establishes the order of precedence:
A.All proposal material except the materials listed in subsections 104.06.B through 104.06.F ;
C.Supplemental specifications ;
D.Project plans and approved working drawings ;
E.MDOT Standard Plans; and
F.Standard Specifications . Plan dimensions take precedence over calculated dimensions; calculated dimensions take precedence over scaled dimensions. The Contractor must not take advantage of errors or omissions in the c ontract and must immediately notify the Engineer when errors or omis sions are discovered. If any errors, uncertainties, inconsistencies, omissions, or conflicts are discovered in the contract, the Engineer will determine the true intent of the contract. MDOT Standard Specifications for Construction Section 104
1-42 104.07. Contractor Obligations
The Contractor must obtain and provide sufficient materials, equipment, tools, labor, and incidentals to complete the project as required by the contract. The Contractor, its suppliers, and its subcontractors must allow the Department access to relevant records, accounts, and other project -related documentation and to their facilities as necessary for the Department to determine compliance with the contract requirements. Except for safety issues or as required by the contract, the Contractor must not suspend work unless approved by the Engineer in writ ing. The Contractor must notify the Engineer within 24 hours of suspending the work.
A.Project Supervisor. The Contractor must provide a Project Supervisor to manage the work. Before beginning the work, the Contractor must submit to the Engineer the name of the Project Supervisor in writing. As the primary representative of the Contractor on the project, the Project Supervisor must be available at all times and must:
1.Have access to the contract at all times;
2.Ensure that each subcontractor has access to the contract covering the subcontractor’s work at the project at all times;
3.Communicate in English;
4.Be capable of reading, interpreting, and implementing the contract;
5.Communicate with subcontractors in a manner that ensures that the Department ’s directions are carried out;
6.Be familiar with, and competent in, the management of projects involving the type of work being performed;
7.Act as agent for the Contractor and be responsible for subcontractors;
8.Anticipate construction impacts to property owners and businesses and work with these parties before the impacts occur to minimize conflict;
9.Handle delays or quality issues for the Contractor; and
10.Receive and implement the direction of the Engineer. When the Contractor or its subcontractors are performi ng work, the Project Supervisor must be present at the project unless otherwise approved by the Engineer. When the Contractor and subcontractors are not performing work at the project , the Contractor must designate a Contractor representative to receive an d execute directions from the Engineer at all times. The representative must be available at all times to receive and sign work orders. MDOT Standard Specifications for Construction Section 104
1-43 B. Safety and Health Requirements. The Contractor is responsible for
protecting the life and health of all personnel on the project , the safety and health of the public , and property during the construction of the project. The Contractor must comply with all local, state, and federal laws and regulations governing construction methods and the furnishing and use of safeguards, safety devices, protective equipment, and environmental and hazardous materials controls. The Contractor must provide the following prior to the commencement of construction:
1.Safety Supervisor. The Contractor must appoint a Safety Supervisor, and an alternate, with the authority and responsibility to administer the Construction Safety Program on the project. The Contractor must provide written notification to the Engineer of the names, addresses, and telephone numbers of the Safety Supervisor and the alternate.
2.Construction Safety Program. Before beginning w ork on the p roject, the Contractor must submit a written Construction Safety Program that outlines the plan and procedures for preventing and mitigating incidents and fires on the p roject and meeting all health and safety requirements of the contract . The Construction Safety Program must include provisions for meeting the requirements of subsection 812.03 and details for the materials and equipment that will be used to prevent construction-related debris or materials from entering the open lanes of traffic and the actions, including traffic control measures, that will be taken to immediately and safely remove the debris or material from the roadway. The Engineer may request a meeting with the Contractor to discuss the Construction Safety Program and to develop mutual understandings to govern the administration and enforcement of the program.
3.Emergency Control. The Contractor or alternate must remain on call for notification of em ergencies that may arise during periods when construction operations are not in progress. The Contractor must be available to assist local emergency response efforts by addressing any contract work involved in, or affected by , the emergency as directed by the Engineer. The Contractor must meet periodically with the Engineer as the work progresses to review the contract and the Construction Safety Program and to consider necessary changes to the program for traffic protection and incident prevention. If the Contractor is not reasonably available to take protective or corrective action, the Department will authorize others to take the MDOT Standard Specifications for Construction Section 104
1-44 protective or corrective action. The Contractor will be responsible for
the itemized cost associated with protective or correct ive action required for traffic protection and incident prevention and completed by others at the Department ’s direction .
4.High -Visibility Safety Apparel. All workers must wear high -visibility safety apparel as specified in the MMUTCD.
C.Maintenance During Construction
1.Routine Maintenance by the Department. Except as specified in subsection 104.07.C.2, the Department will assume routine maintenance of roads , bridges , and other facilities open to traffic or used by the public during periods of approved seasonal suspensions. The Department defines routine maintenance as the repair of damage to roads, bridges , and other facilities from normal wear and tear due to traffic and weather. Routine maintenance does not include damage resulting from t he Contractor ’s vehicles or equipment. The Department will perform snow plowing and ice control work on roads and facilities open to traffic. The Contractor is not entitled to compensation for delays, inconvenience, or any other cause attributed to the Department ’s performance of routine maintenance.
2.Routine Maintenance by the Contractor. If the Contractor maintains through-traffic on the project, the Contractor must perform necessary routine maintenance, as directed by the Engineer, on that portion of the roadbed surface on which construction operations have begun. The Contractor must perform routine maintenance outside the area of construction operations but within project limits only if directed to do so by the Engineer in writing. The Department will pay the Contractor for all routine maintenance directed by the Engineer as extra work. The Contractor must perform routine maintenance on Contractor - constructed temporary facilities not open to traffic or in use by the public (including during periods of appr oved seasonal suspensions) at no additional cost to the Department, unless otherwise required by the contract. The Contractor must provide access for local traffic to property along the project even during seasonal suspension at no additional cost to the D epartment unless otherwise provided for in the contract. Sweep pavements in the construction area, including service roads and cross streets, as directed by the Engineer. Paved surfaces must be swept as often as necessary and as directed by the Engineer. Paved roadbeds must be given a final cleaning within 7 days prior to MDOT Standard Specifications for Construction Section 104
1-45 opening the pavement surface to traffic or notification by the
Contractor that the w ork is completed, whichever occurs first. The work of sweeping will not be paid for separatel y, but payment will be considered as having been included in other contract items.
3.Damage Repair by the Contractor. Except as specified in subsection 107.11, the Contractor must repair damage to highway facilities caused by defective materials, faulty work manship, Contractor operations, and work not protected properly from naturally occurring events at no additional cost to the Department. The Contractor is responsible, at no additional cost to the Department , to provide the necessary materials and equipment to prevent construction -related debris or materials from entering the open lanes of traffic. This includes protecting traffic controls, remov ing spilled materials or debris from the roadbed or drainage courses, and repair ing damaged facilities necessary for public travel and safety. The Contractor must provide, install, and operate traffic control devices required to warn traffic of and protect traffic from Contractor -damaged facilities and repair operations at no additional cost to the Department. If the Department determines that the Contractor is not reasonably available to take protective or corrective actions, the Department will authorize others to complete the protective or corrective actions. The itemized cost associated with protective or correct ive action that is required due to Contractor -damaged facilities and repair operations and completed by others at the Department ’s direction will be the responsibility of the Contractor.
D.Final Clean up. Unless otherwise required by the contract, the cost of final cleanup is included in the cont ract unit price for other pay items. Before final acceptance by the Engineer , the Contractor must complete all of the following:
1.Remove the following from the project limits, unless otherwise required by the contract or directed by the Engineer:
c.Temporary erosion control devices;
e.Temporary bridges, approaches, and buildings;
f.Equipment; and MDOT Standard Specifications for Construction Section 104
1-46 g. Temporary traffic control devices.
2.Restore areas occupied during the project to a condition at least equal to the condition existing before the Contractor began performing work, as determined by the Engineer.
3.Restore property that was used or damaged during the performance of the work, including property outside the project limits.
4.Provide the Department with written notification that all property that was used or damaged during performance of the work, including property outside the project limits, has been restored in accordance with applicable local, state, and federal requirements.
5.Clean paved roadbeds and sidewalks within 7 days before opening the pavement surface to traffic . Take precautions so as not to produce airborne dust when cleaning roadbeds in residential and urban areas. 104.08. Cooperation by the Contractor The Contractor must conduct operations to cooperate with and interfere as little as possible with activities of other contractors, the Department, utilities, or public authorities on or near the p roject or as directed by the Engineer. The Department may perform other work and al low public utility companies and others to do work on or near the project. The Contractor is not entitled to compensation or extension of time for delays or costs incurred as a result of complying with this requirement, except as allowed in subsection 108. 08 or subsection 108.09.B . If a dispute arises between two or more contractors or others as to the respective rights of each under these specifications, the Engineer will determine the matters at issue and will define the respective rights of the various interests involved in order to secure the completion of all parts of the work in general harmony and with satisfactory results. The Engineer ’s decision will be final and binding on all parties concerned. The Contractor, or any other party, is not entitled to an extension of time or compensation for delays, inconvenience, or any other cause attributed to the Engineer ’s decision, except as allowed in subsection 108.08 or subsection 109.05. 104.09. Lines, Grades, and Elevations The Contractor must provide, place, prot ect, and maintain staking necessary for proper prosecution, inspection, and final measurements of the w ork in accordance with section 824 and the contract. The Contractor must determine and lay out detail dimensions and elevations. The Engineer may check to determine whether the Contractor ’s work meets the contract requirements in accordance with subsection 104.01. MDOT Standard Specifications for Construction Section 104
1-47 104.10. Claim for Extra Compensation or Extension of Time
The Contractor must sign and submit a claim for extra compensation or time extension to the Department, whether on behalf of the C ontractor or any tier subcontractor. If the Contractor fails to submit a claim in accordance with the Department ’s written claim procedure in effect at the time the Contractor files the claim and this subsection, the Contractor waives its rights to compensation or an extension of time for the claim. This waiver applies whether or not, as a result of the Contractor ’s failure to comply with these requirements, the Department ’s rights were prejudiced. The Contractor and Department will use the following procedure for claims:
A.Notice of Claim. The Contractor must sign all notices of intent to file a claim and ensure that the written notice includes a concise description of the claim and identifies the co ntract requirement in dispute. If seeking extra compensation for any reason not specifically covered elsewhere in the contract, the Contractor must notify the Engineer in writing in accordance with following time requirements:
1.Before beginning the work or upon encountering the circumstance that is the basis of the claim.
2.Within 3 calendar days after the beginning of a delay, for which the Contractor intends to seek compensation. If the Contractor fails to provide written notice, the Contractor waives all rights to a claim for compensation or a n extension of time except if the Department prepared records that substantiate the claims with regard to liability and amount, and claims are for extra costs that were unforeseeable. If the Contractor fails to provide proper written notice for extra compensation or if the Contractor fails to allow the Engineer to record accounts of actual costs, the Department ’s claims process decision regarding extra compensation will be considered final and binding. The Department wil l not consider the Contractor ’s refusal to sign a written contract modification or work order, or the Contractor ’s signing of a contract modification or work order under protest, as the required written notice.
B.Keeping Records. If submitting a written notice of intent to file a claim, the Contractor must:
1.Keep accurate records of the costs of the work or delay;
2.Allow the Engineer every facility for keeping records regarding the costs of the work or delay related to the claim; and
3.Compare records with the Engineer and bring them into agreement at the end of each day. MDOT Standard Specifications for Construction Section 104
1-48 C. Validity of Claim. The notice of intent to file a claim or the Engineer ’s
cost recordkeeping does not establish the validity of a claim.
D.Timing for Filing of Claim. The Contractor mus t file a claim with the Engineer within the following time frames, whichever occurs first:
1.No later than 60 calendar days after the work involved in the claim is completed, or the delay, loss of efficiency, loss of productivity, or similar event is terminated; or
2.No later than 60 calendar days after the final acceptance of all contract work. The Department may grant extensions of the above time requirements in accordance with the Department ’s current claim procedure.
E.Claim Content and Certification. The Contractor ’s claim must include a completed MDOT Form 1953 Claim Content and Certification that contains the following information, as applicable:
1.A detailed factual statement of the claim providing necessary dates, locations, and items of work related to and included in the claim.
2.The date or dates on which actions resulting in the claim occurred or conditions resulting in the claim became evident.
3.Identification of documents substantiating the Contractor ’s claim.
4.Identification of the provisions of the contract that support the claim and a statement of the reasons these provisions support the claim.
5.A detailed compilation and a breakdown of the amount of additional compensation sought as follows:
a.Documented additional labor costs;
b.Documented additional material costs;
c.List of additional equipment costs, including each piece of equipment and the rental rate claimed for each;
d.Markups for items a . through c . per subsection 109.05.D ; and
e.Other additional direct costs or damages and associated supporting documentation.
6.For a claim related to an extension of time, a detailed compilation of the specific dates and the exact number of calendar days sought for the extension of time , the basis for entitlement to time for each day, all documentation of the delay, and all impacts of the delay to the progress schedule and critical path. MDOT Standard Specifications for Construction Section 104
1-49 Subcontractors must document and certify their claim(s) as described in
subsection 104.10.E. If the Contractor has a claim item related to a subcontractor ’s claim, the C ontractor must document and certify their claim as described in subsection 104.10.E.
F.Consistency of Claim and Exhaustion of Administrative Remedies. If the Contractor ’s claim in any administrative proceeding or in the Court of Claims seeks relief greater t han the amount sought at a prior level, or if the claim is based on facts or issues that differ from those presented at a prior level, the Contractor has failed to exhaust its administrative remedies. If the Contractor fails to exhaust its administrative r emedies, the claim must be returned by the Department to the preceding level for a new review and decision. The Department in its sole discretion will determine whether the Contractor has exhausted its administrative remedy at any level. The Department ’s decision is final and binding and not subject to further review or consideration. Nothing in this paragraph precludes the Contractor from withdrawing any portion of its claim or reducing the amount sought at any time. The Contractor ’s written acceptance of an administrative proceeding panel ’s decision on claim item(s) constitutes a settlement of the claim item(s) and bars the Contractor from pursuing further legal remedies against the Department on the settled claim item(s). 104.11. Work Zone Safety an d Mobility
A.General Traffic Control. The Contractor must not close roads, bridges, or sections of roads and bridges to traffic unless required by the contract or directed by the Engineer .
B.Contractor Operations. The Contractor must develop and provide an Internal Traffic Control Plan (ITCP) for the project in accordance with the Work Zone Safety and Mobility Manual unless otherwise directed by the Engineer. The ITCP must outline the Contractor ’s haul routes, w ork area access points, and the maintenance of the temporary traffic control devices. The Contractor must ensure that the ITCP minimizes conflicts between construction vehicles and motorists and maintains overall safety and mobility within the work zone.
1.Limitations for Construction Equipment On or Crossi ng Pavements and Structures. The Engineer will consider allowing the Contractor to use construction equipment on pavements and structures within project limits after the Contractor performs the following:
a.Saws transverse expansion joints and places temporary or permanent seals; MDOT Standard Specifications for Construction Section 104
1-50 b. Makes relief cuts for transverse contraction and longitudinal joints;
c.Places applicable temporary or permanent seals in transverse contraction joints that have been sawed full width;
d.Completes the transverse post tensioning of a brid ge span; and
e.Ensures that the concrete has gained sufficient strength for the placement of the intended load. Construction equipment traveling on pavements must not have tire loads greater than 850 pounds per inch of nominal tire width. The Contractor must not use equipment that will damage the surface without protective devices, such as planks or timbers. The Contractor cannot use an earth cushion on a bridge structure. Permission to use construction equipment on pavements and structures will neither constitute a waiver of applicable provisions of subsection 107.11 nor waive the Contractor ’s legal responsibility to observe weight restrictions on highway sections that the Department has approved for traffic in accordance with subsection 107.21. The Department defines overweight vehicles as having maximum gross axle loadings greater than the limits specified in accordance with Michigan l aw. The Department defines legal load limits, as the term is used in this section, as loads carried by vehicles with axle loading in accordance with Michigan l aw. The Contractor must determine concrete strength as specified for applicable work progress specimens in Division 10 .
2.Construction Equipment Crossing Structures that Have Not Attained 100 % of Design Strength. The Engineer will consider requests to cross concrete bridges, grade separations, and box and slab culverts based on the gross vehicle load and the concrete strength as specified in Table 104-1. The Contractor must ensure that the maximum axle loading is no greater than the loadings permitted under the Michigan Vehicle Code (MCL 257.1 et seq. ) for the axle spacing indicated therein. MDOT Standard Specifications for Construction Section 104 1-51 Table 104- 1: Loads Permitted to Cross Structures as Concrete Gains Strength Minimum Design Compressive Strength Maximum Total Gross Vehicle Weight or Maximum Allowable Number of Axles(a) 60% 30,000 lb 67% 37,500 lb 75% 5 axles 80% No limit on axle number
a.The Department will evaluate crawler -mounted equipment on an individual basis.
3.Construction Equipment Crossing Structures that Have Attained 100% of Design Strength. If the Contractor requests permission to cross structures within the project limits with veh icles that weigh more than the legal load limit, the Engineer will make a design analysis of the structure and the proposed loading based on established criteria. If the Engineer approves, the Contractor may cross structures with vehicles that weigh more t han the legal load limit subject to the follow ing:
a.General Requirements. The Contractor must grade and maintain structure approaches flush with the bridge deck at least 50 feet from each end of the structure. The Contractor must place a temporary concrete or structural timber header on the pavement seat at each end of the structure. The Contractor must use a ¼ -inch wood divider, two thicknesses of heavy building paper, or 6 mil polyethylene to separate a temporary concrete header from the pavement seat. The Contractor must remove and dispose of the temporary header and divider board at the time of paving. The Contractor must ensure that equipment comes to a complete stop before crossing a structure. The Contractor must allow only one loaded vehicle on the structure at a time. The Contractor must ensure that equipment does not travel on the structure at speeds greater than 5 miles per hour unless otherwise required by the contract.
b.Specific Requirements. The Department will state the following specific conditions in the authorization: MDOT Standard Specifications for Construction Section 104 1-52 Material to be used to cover and protect joints from infiltration and damage; Axle weights loaded and unloaded; Spacing of axles; Spacing of wheels on each axle; Tire size; and Estimated number of vehic le crossings to be made.
c.Damage to the Structure. The Contractor must inspect the structure with the Engineer before and after hauling to determine whether damage has occurred. The Engineer will determine what constitutes damage and the repairs to be made. The Contractor must repair damage to the structure, including joints, resulting from hauling operations at no additional cost to the Department.
d.Violation of Requirements. If the Contractor violates any of these requirements or any conditions specified by the Department, the Engineer will immediately revoke the authorized permission. The Contractor must not consider the authorization to haul across a structure or the withdrawal of authorization to haul across a structure as the basis for compensation, a revision to the contract unit price for any item , or entitlement to an extension of time.
4.Overloads Not Exceeding Legal Limits by 50% On or Crossing Pavements. The Department will consider loads on concrete pavements, other than temporary concrete pavements, that do not exceed legal limits by 50% in accordance with Table 104-2. Table 104- 2: Required Concrete Pavement Strength Before Crossing New and Existing Pavements within Project Limits Flexural Strength All Concrete Grades ( psi) Maximum Load Type Allowed 450 Slip-form pavers and finishing equipment 550 Load within legal limits 600 Loads up to 25 % over legal limits (for batch -hauling and shoulder operations only) 650 Occasional loads up to 50 % over legal limits (to complete construction activities) The Engineer may allow occasional loads that exceed the legal limit by not more than 50 % on HMA pavements after rolling is complete MDOT Standard Specifications for Construction Section 104
1-53 and the mat has cooled to ambient temperatures. The Contractor must
protect pavement, including edges, to prevent damage to the pavement. If the Contractor ’s hauling operations cause damage, the Contractor must repair the damage at no additional cost to the Department.
5.Overloads Exceeding Legal Limits by 50% On or Cross ing Pavements. The Engineer may allow loads that exceed the legal load limit by 50 % or more to cross existing concrete pavements at designated locations under the following conditions:
a.The Contractor places transverse joint saw cuts in the pavement and uses painted lines to define the crossing area (approximately 50 feet wide);
b.The Contractor maintains traffic on the pavement during hauling and reconstruction, as approved by the Engineer; and
c.After completing hauling with overloads, the Contractor must remo ve the pavement between the two saw cuts and replace the pavement with new pavement of the same type and design as the original pavement. If traveling across existing or new HMA pavements with loads that exceed the legal load limit by 50% or more, the Contractor must remove and replace the crossing area to the required surface tolerances, as directed by the Engineer. If the Contractor crosses existing pavements while hauling material from sources other than Department -designated sources, the Contractor must perform repair and restoration work as consideration for permission to haul with overloaded wheels or axles at no additional cost to the Department. If the Contractor crosses existing pavements while hauling material from a Department -designated borrow area, the Department will pay for the removal and replacement of pavement, if directed by the Engineer, at the contract unit price for required items of work. 104.12. Approval for the Use of the Right -of-Way The proposed right -of-way use must be directly related to the operations of the project under contract. The Contractor may use Department -owned right-of-way to perform the w ork if prior written approval is given by the Engineer. Additional restrictions regarding the use of right -of-way may exist in the contract. The use of right -of-way in wetlands and floodplains or the crossing of water courses by construction equipment is prohibited. MDOT Standard Specifications for Construction Section 104
1-54 To use Department right -of-way, the Contractor must submit to the Engineer a
written request including a Right -of-Way Use Plan. The Contractor must include the following in the plan:
A.Site location and layout ;
D.Any access through right -of-way fencing or boundaries;
E.Identification of materials and method of storage as applicable ;
F.Soil erosion and sedimentation control plan;
G.Site restoration requirements ;
H.Drainage and environmental protection plan ;
I.Acquisition of necessary permits ; and
J.Commitment to follow all local laws and ordinances. The Engineer may direct the Cont ractor to include additional information in the plan. The Department will review the written request and provide a written response to the request indicating approval, approval with conditions or modifications, or denial with reason.
Source: Michigan Standard Specifications for Construction, 2020 Edition. Pages 49–66 of 1,146.