105
1-37SECTION 105 – CONTROL OF THE WORK
105.01ROLE OF THE ENGINEER
acceptability of materials furnished, the manner of performance of the work, the rate of progress of the work, and compliance with the requirements of the Contract. The Engineer will decide all questions concerning interpretation of the Contract.
will determine the amount and quantity of the work performed and materials furnished that are to be paid for under the Contract. The Engineer will have the authority to enforce and make effective decisions and orders the Contractor fails to carry out promptly. In case of any dispute arising between the Contractor and the Engineer as to materials furnished or the manner of performing the work, the Engineer has the autho rity to reject the materials or to suspend the work until the dispute is decided by the Chief Engineer. The Engineer is not authorized to revoke, alter, enlarge, relax, or release any requirements of the Contract. The Engineer has the authority to suspend the work or withhold payment of all estimates due to the Contractor when necessary to secure proper compliance with the Contract.
the Engineer, the Engineer may, upon written notice, proceed to perform the work as deemed necessary. The cost of performing the work will be deducted from any monies due or which may become due the Contractor under the Contract.
binding the Agency in any way or releasing the Contractor from any obligations under the Contract.
105.02AUTHORITY AND DUTIES OF THE ENGINEER . As the direct representative of the Chief
Engineer, the Engineer on a project has immediate charge of the engineering details of the project and is responsible for the administration and satisfactory completion of the projects. The Engineer has the authority to reject defective material, to suspend any work that is being improperly performed, and to withhold payment until defective work has been corrected. The Engineer also has the authority to suspend work, or specific aspects of the work, if necessary to address a concern for safety of the workers or traveling public, or a serious environmental concern or violation. Notwithstanding any other provision of law, case law, regulation, or the Contract, no additional compensation shall be provided for any work suspensions of this sort.
105 1-38 105.03 AUTHORITY AND DUTIES OF INSPECTORS . Inspectors employed by the Agency are authorized to inspect all work done and materials furnished and to perform other duties as directed by the Engineer. Inspections can extend to all or any part of the work and to the preparation, fabrication, or manufacture of the materials u sed. An inspector is not authorized to alter or waive the provisions of the Contract, to issue instructions contrary to the Contract, or to act for the Contractor.
105.04CHIEF ENGINEER TO BE REFEREE
of the Contract. If the Contractor is aggrieved by the decision of the Chief Engineer, the Contractor may appeal the decision in writing to the Transportation Board via the Chief Engineer. Included with the notice of appeal shall be a complete outline of the nature and extent of the question or questions appealed together with any supporting documentation.
or the Contrac t, all appeals shall be made within 30 calendar days of the decision to which the Contractor is aggrieved, and not thereafter. 105.0 5 COMPONENTS OF THE CONTRACT . A complete description of the work requires both the Contract, which is furnished to the Contractor by the Agency, and the working drawings, which are submitted to the Agency by the Contractor or the Contractor’s suppliers. The Agency will make available the Contract in a digital format and t he Contractor shall keep the Contract available on t he project at all times.
105.06PLANS AND WORKING DRAWINGS
information to document the Contractor’s proposed actions to conform with Contract requirements. Drawings and procedures shall be submitted sufficiently in advance of the anticipated work to allow for reviews, comments, corrections, and if necessary, resubmittal. In the event that any condition requires a change to any previously approved or conforming working drawings, the Contractor is required to submit updated drawings prior to performing the work . Design calculations shall be included with the submittal of the working drawings for structural elements that have not been designed and detailed in the Contract, including temporary and permanent work. When a Contract item requires additional calculations to be submitted, the calculations shall be included with the submittal of the working drawings. Manufacturer’s engineering data for pref abricated materials, including that for falsework and forms, shall be submitted with each set of working drawings.
105
1-39All submittals shall be transmitted electronically to the Agency unless prior approval has been
granted by the Engineer. Submittals shall be flattened prior to transmitting so that information added to the submittal becomes an integral part of the document rather than separate information on top of the document. The do cument shall have a clean appearance so that any comments or stamps placed as part of the submission cannot be mistaken as review comments. Resubmittals shall be free from previous review comments and have a clean appearance so that any comments or stamps placed cannot be mistaken as a review comment. All resubmittals shall include a separate summary of review comments and responses, including an explanation of how each review comment was addressed in the resubmittal. Drawing and detail sheets shall be pro vided as an ISO standard Portable Document Format (PDF) file. The PDF document properties shall be set up with an appropriate page size and engineering or architectural scale. The page size and scale shall be of sufficient size to permit to -scale plotting of the document(s) on paper for review, use in construction , and shall include the following:
detailed in the Plans shall be submitted to the Agency for approval. Fabrication drawings are a type of working drawing that are submitted for approval. Working drawings submitted to detail work that has not been designed in the Plans shall be designed and detailed by a professional engineer and submitted to the Agency to be reviewed for conformance with the Contract. These working drawings shall ensure that the Contractor or Contractor’s suppliers have correctly interpreted the intent of the Contract. Construction drawings and design drawings are types of working drawings that are submitted to be reviewed for conformance.
105
1-40Exceptions to this guidance will be detailed by the specification for the individual pay item
No work shall begin on any item associated with a working drawing until all of the associated drawings have been approved, approved as noted, marked as conforming, or conforming with comments by the Agency. The Contractor or fabricator shall assume all risk for materials ordered or work performed prior to written notification by the Agency.
Contractor or fabricator of compliance with all specifications and code requirements. The Agency assumes no responsibility for errors and/or omissions in the drawings and procedures. Drawings and procedures identified as being approved as noted indicate that specific clarification or conditional changes have been identified and take precedence over submitted information. Withholding of approval by the reviewer for selected details or procedures shall not constitute a basis for delay of performance of a non -related item of work that has approval to proceed. After approval of the drawin gs and/or procedures, no changes shall be made without the written approval of the Agency.
conformance , the Agency will review the submittal for compliance with the requirem ents of the Contract. The Contractor shall submit the required drawings and/or procedures in advance of the proposed work . The Contractor is entirely responsible for the work associated with these submittals. The Agency will not be responsible for errors i n dimensions, incorrect erection procedures, or design requirements. If the drawings and/or procedures have misinterpreted the Plans or specifications, the submittal will be returned as non-conforming. The submittal shall not be marked as conforming or conforming with comments until all of the required information has been received and reviewed. After the drawings have been marked conforming or conforming with comments, no changes shall be made without the written approval of the Agency. The Contractor or fabricator shall assume all risk for materials ordered or work performed prior to the changes being marked as conforming by the Agency.
105 1-41 (c) Categories of Working Drawings .
with materials furnished by a fabricator or supplier. They shall consist of complete details developed from information in the Contract, and field measurements to define dimensions, sizes, procedures, and materials necessary to complete fabrication and installation or erection of the work specified. Once a complete submittal has been received for approval, the reviewer shall be allowed 28 calendar days for the initial review period and a 14 calendar day review period for each subsequent resubmittal unless stated otherwise in the specification requirements. The Contractor is entirely responsible for the work associated with these submittals. The Agency will not be responsible for errors in dimensions, incorrect erection procedures, design requirements, or successful completion of the work .
Agency. Prior to processing the final estimate , the Engineer shall verify that all as- builts have been received by the Agency.
optional details, procedures, and materials, the Contractor shall prepare and submit to be reviewed for conformance detailed drawings , calculations, and procedures of how the Contractor proposes to perform and control the work . Construction drawings , calculations, and procedures shall be stamped and signed by a professional engineer . The professional engineer is responsible for the design, performance of the designed element, and preparation of the construction drawings calculations, and procedures.
Once a complete submittal has been received, the reviewer shall be allowed 21 calendar
days for the initial review period and 14 calendar days for review of a submittal returned
as non-conforming unless stated otherwise in the specification requirements. The
Contractor is entirely responsible for the work associated with these submittals. The
Agency will not be responsible for errors in dimensions, incorrect erection procedures,
design requirements, or successful completion of the work.
project which has not been designed and detailed in the Plans, the Contractor shall prepare
and submit to be reviewed for conformance detailed design calculations, procedures, and
drawings for the item or element of work. Design drawings, calculations, and procedures
shall be stamped and signed by a professional engineer.
105
105.07CONFORMITY WITH PLANS AND ALLOWABLE DEVIATIONS
sections, dimensions, and material requirements, including tolerances, shown in the Contract. Any
deviation from the Contract required will be determined by the Engineer and authorized in writing.
finished product in which the materials are used do not conform to the Contract requirements, but
reasonably acceptable work has been produced, the Engineer will determine if the work will be
accepted and remain in place. If accepted, the Engineer will document the basis of acceptance,
which may require a Contract modification and price adjustment.
materials or the finished product in which the materials are used do not conform to the Contract
requirements, and the Engineer determines that the product is unsatisfactory, the Engineer will
direct the work or materials be removed, replaced, or otherwise corrected by the Contractor at the
Contractor’s expense.
105.08COOPERATION BY THE CONTRACTOR. The Contractor shall:
Engineer, including but not limited to all information used to prepare the bid proposal. Failure to
provide such documents may result in the waiver of any right to bring a claim for additional
compensation under Subsection 105.20.
English-speaking superintendent authorized to receive orders and to act for the Contractor. The
Contractor shall make every effort to provide continuity in the position of superintendent.
However, the Agency reserves the right to refuse or terminate the assignment of any superintendent
on the project; this shall not be grounds for a claim under Subsection 105.20.
of the work a competent and reliable English-speaking employee designated as the safety officer.
This person shall be authorized to receive orders and issue binding directions concerning safety to
all persons associated with the project who are employed by the Contractor, subcontractors, or
material suppliers. This individual shall be well versed in all applicable OSHA regulations, shall
be capable of implementing a plan to conform to these regulations, and shall have the authority to
stop operations on the project.
The safety officer shall maintain a complete copy of the safety plan(s) for the Contract, which shall
be available at all times during the prosecution of the work for inspection and/or copying by the
Engineer.
105
of the Contractor’s personnel who can be reached in an emergency. The Contractor shall alert
certain personnel to stand by and shall inform the Engineer of all arrangements therefore.
facilities and furnish the information, assistance, and samples required by the Engineer or inspector
to properly inspect and test materials and quality of work; and cooperate in setting and preserving
stakes, benchmarks, and other control points used in laying out the work.
105.09COOPERATION WITH UTILITIES
affected and endeavor to have all necessary adjustments of the public or private utility fixtures,
pipelines, and other appurtenances within or adjacent to the limits of construction made as soon as
practical.
water and gas meter boxes, water and gas valve boxes, light poles, cableways, signals, and all other
utility appurtenances within the limits of the proposed construction which are to be relocated or
adjusted are to be moved by the owners at their expense, unless otherwise provided in the Contract.
the time of bid submission, it has considered all of the permanent and temporary utility facilities
or appurtenances in their present and/or relocated positions as shown on the Plans and evident at
the site. Notwithstanding any other provision of law, case law, regulation, or the Contract, no
additional compensation will be allowed for any delays, inconvenience or damage sustained by
the Contractor due to any interference from utilities, utility companies, utility facilities,
appurtenances, or the operation of moving them.
of location of any utility facilities or appurtenances for convenience in performing the work, the
Contractor shall satisfy the Agency that the proposed relocation does not interfere with its own or
other Contractors’ operations or the requirements of the work and does not cause an obstruction
or a hazard to the traveling public. The Contractor shall be responsible for requesting such
relocation work of a utility and/or other affected parties. Such relocation work shall be done solely
at the Contractor’s expense.
105.10COOPERATION BETWEEN CONTRACTORS
additional work on or near the work covered by the Contract at any time.
105
project, each Contractor shall conduct its own work so as not to interfere with or hinder the
progress or completion of the work being performed by other Contractors. Contractors working on
the same project shall cooperate with each other as specified or ordered by the Engineer.
or otherwise, in connection with its own Contract and shall defend, indemnify, protect, and save
harmless the Agency from any and all damages or claims that may arise because of inconvenience,
delay, or loss experienced by the Contractor because of the presence and operations of other
Contractors working within the limits of the same project.
105.11CONSTRUCTION STAKES
will be responsible for setting sufficient points to establish the initial alignment and elevation of
the proposed work. The Contractor shall check the proposed grades; any mistakes or errors
identified shall immediately be brought to the attention of the Engineer, and adjustments will be
made by the Engineer.
the layout for the permanent centerline traffic markings, including passing zones, breaks for town
highways and side roads, and any other items required for the centerline markings. The Contractor
shall be responsible for the layout of all non-centerline markings.
and markings and shall replace any stakes or grades that are destroyed or disturbed. No claim shall
be brought and no additional compensation will be paid on account of any alleged inaccuracies in
the construction layout, including any additional layout that the Engineer may perform that is not
covered in this subsection, unless the Contractor notifies the Engineer of the inaccuracies in writing
at least 24 hours prior to commencement of the work.
replacement of the original set, which may be required for the construction operations, shall be
furnished, set, and properly referenced by qualified personnel employed by the Contractor.
or procedure of the next work contemplated. The Contractor shall inform the Engineer sufficiently
in advance of construction to permit the Engineer to take the necessary measurements for the
computation of quantities and to check the Contractor’s layout. The Contractor shall lay out in a
timely manner and maintain a sufficient number of grade stakes so the Engineer can monitor and
regulate all portions of the Contract work.
be included in the unit price bid for the Contract items involved.
105
105.12INSPECTION OF WORK
allowed access to all parts of the work at all times and shall be furnished by the Contractor all
information and assistance necessary to make a complete and detailed inspection. The Contractor
shall furnish such help as the Engineer desires and/or needs to ascertain whether or not the work
is performed in accordance with the requirements and the intent of the Contract.
Contractor shall remove or uncover portions of the finished work as the Engineer may direct. After
the examination, the Contractor shall restore the portion of the work to the standard required by
the Contract. If the work thus exposed or examined proves acceptable, the expenses of uncovering
or removing and replacing the parts removed shall be paid for as extra work as defined in
Subsection 109.06; but if the work exposed or examined is unacceptable, the expenses of
uncovering or removing and replacing the parts removed shall be borne by the Contractor.
done or materials used without supervision or inspection by the Engineer or an inspector.
Supervision/inspection includes project, mill, plant, or shop inspection of any work furnished
under the Contract.
portion of the cost of the work covered by the Contract, its respective representatives shall have
the right to inspect the work. Such inspection shall not make any entity a party to this Contract and
shall not interfere with the rights of either party hereunder.
105.13REMOVAL OF UNACCEPTABLE AND UNAUTHORIZED WORK
unacceptable unless otherwise determined to be acceptable under the provisions of Subsection
quality of work, use of defective materials, damage through carelessness, or any other cause found
to exist prior to the acceptance of the work, shall be removed immediately and replaced in an
acceptable manner.
105
provided by the Engineer. Work performed contrary to the instructions of the Engineer, beyond
the lines shown on the Plans, or without authority will be considered unauthorized and no payment
therefore will be made. Work so done may be ordered removed or replaced at the Contractor’s
expense.
with any order of the Engineer communicated under the provisions of this subsection, the Engineer
will have authority to require unacceptable work to be remedied or removed and replaced and to
require unauthorized work to be removed. In either case, the Engineer is authorized to deduct the
costs from any monies due or to become due to the Contractor.
renewals, or repairs which the Contractor has failed or refused to make shall be paid for out of any
monies due or which may become due the Contractor or may be charged against one or more
Contract bonds.
the work described in this subsection.
105.14SUNDAYS, HOLIDAYS, HOURLY RESTRICTIONS, AND NIGHT WORK
Contractor shall not perform construction operations on Sundays.
Contractor shall not work during the following holiday periods:
New Year’s Day January 1 st
Martin Luther King Jr. Day Third Monday in January
Presidents’ Day Third Monday in February
Town Meeting Day First Tuesday in March
Memorial Day Last Monday in May
Independence Day July 4 th
Bennington Battle Day August 16 th
Labor Day First Monday in September
Indigenous Peoples’ Day Second Monday in October
Veterans Day November 11 th
Thanksgiving Day Fourth Thursday in November
Day After Thanksgiving Day After Thanksgiving
Christmas Day December 25 th
105
If a holiday falls on a Sunday, the Monday immediately following it shall be considered the
holiday. If a holiday falls on a Saturday, the Friday immediately preceding it shall be considered
the holiday.
Designated holiday periods shall begin at 12:00 noon on the day before the weekend or holiday,
whichever applies, and shall end at 6:00 a.m. on the day after the holiday or the weekend, as
appropriate. The Engineer may require the Contractor to cease construction operations for the
entire day before if a holiday falls on a Tuesday, or for the entire day after if a holiday falls on a
Thursday.
required to work during certain hours or may limit the type of operations that may be performed
during certain hours.
If work is performed between 7:00 p.m. and 6:00 a.m., the Contractor shall take measures to
mitigate the noise caused by its construction operations. Wherever practicable, the Contractor
should sequence work such that noisy activities occur concurrently. Other potential noise reduction
mitigation measures are outlined in the FHWA Highway Construction Noise Handbook. In
addition, the Contract may specify a maximum decibel limit or other required noise restrictions.
The cost for mitigating noise will not be paid for separately but will be considered incidental to all
other Contract items. At a minimum, the Contractor shall use the following noise mitigation
techniques:
adjustable backup alarms where the volume can be adjusted down for the ambient noise
level.
as specified in Section 641.
emergency repairs, and proper protection of the work, including but not limited to the curing of
concrete and the repair and servicing of equipment.
The limitations in this subsection also shall not relieve the Contractor of any responsibility for the
work involved as set forth in Subsection 105.08, Subsection 107.17, or elsewhere in the Contract.
105
105.15CONVICT LABOR. No incarcerated convict labor shall be employed on the Contract
105.16LOAD RESTRICTIONS
activities shall comply with all legal load restrictions specified in 23 V.S.A. § 1392 in the hauling
of equipment or material on public roads, including that beyond the limits of the project. The
application for and possession of any hauling or related permit will not relieve the Contractor or
others involved in any project-related activities of any liability that may arise due to any damage
resulting from the use or moving of equipment, vehicles, or any other project-related activity.
following:
permitted on any structure as defined by the Engineer.
equipment loaded so as to cause damage to structures, the roadway, or to any other type of
active construction will not be permitted, regardless of the limits set forth in 23 V.S.A.
bituminous pavement or any structure during active construction will not be permitted.
all damage incurred to any public roadway as defined in 23 V.S.A. due to the use of any
equipment or vehicles related to project activities.
limits shall be within the legal load limit or the load limit imposed by a current overload permit
for the roadways and structures. Should any vehicle not meet these requirements, in addition to
the appropriate penalty under 23 V.S.A. § 1391a, the difference in weight between the legal load
limit and the gross vehicle weight shall be converted to the appropriate measurement quantity for
the item involved and treble this amount shall be deducted from the quantity of the item to be paid
the Contractor. The Contractor shall not deduct this amount from the payment to its trucking
subcontractors or suppliers.
to the Engineer prior to the commencement of hauling. Copies of permits provided after hauling
has begun will not be considered to be in effect for the project prior to the time that the Engineer
receives the copy.
105
vehicles carrying or delivering materials to be used on a project. A tare weight shall be the weight
of the unloaded vehicle with full fuel tank and water tank as applicable.
reduction, shall apply to the Contractor’s vehicles as well as all other vehicles used in conjunction
with the construction of this project, including the vehicles of subcontractors and suppliers.
105.17MAINTENANCE OF THE PROJECT DURING CONSTRUCTION
accepted. This maintenance shall constitute continuous and effective performance of the work day-
by-day with adequate equipment and forces so that the project is kept in satisfactory condition at
all times.
be included in the Contract unit prices for the various pay items, and the Contractor will not be
paid an additional amount for such work.
with the provisions of the Contract or for any other reason, the Contractor shall maintain the project
as provided herein and provide such ingress and egress for local residents as necessary during the
period of shutdown.
105.18FAILURE TO MAINTAIN THE PROJECT. Failure on the part of the Contractor to properly
maintain the work will result in the Engineer immediately notifying the Contractor to comply with the
required maintenance provisions. If, after receipt of such notice, the Contractor fails to remedy the
situation to the Engineer’s satisfaction, the Engineer will proceed with adequate forces and equipment to
maintain the project; the cost of this maintenance will be deducted from monies due or which may become
due the Contractor under the Contract.
105.19FINAL INSPECTION AND ACCEPTANCE
satisfactorily completed.
Engineer will review the work and issue a written order if the project has achieved substantial
completion. The written order will document the date on which the project achieved substantial
completion.
105
The Engineer will arrange a date for a final inspection of the work. As a result of the final
inspection a final punch list will be developed and provided to the superintendent.
When the punch list is completed and all work provided for and contemplated by the Contract is
found to be completed, the Contractor will be informed in writing that the project is complete and
accepted.
105.20CLAIMS FOR ADJUSTMENT
result in costs and/or delays that were not anticipated by the Contractor at the time of bid, the
Contractor shall provide the Engineer with notice of that fact immediately or as soon as reasonably
possible. It is critical that the Agency be aware of potential Claims at the earliest opportunity so
that it can carefully monitor the potential additional costs and potentially assist the Contractor in
taking steps to mitigate those additional costs. Thus, the Contractor shall promptly file a Notice of
Intent to File a Claim.
If the Contractor later decides to file a Claim for additional compensation under the Contract, that
Claim must provide certain key pieces of information to the Construction Engineer so that the
claim can be evaluated expeditiously. If necessary, the Construction Engineer will contact the
Contractor for additional information about the Claim and may request a meeting with the
Contractor. The Construction Engineer typically does not invite legal counsel to such meetings
unless the Contractor chooses to have its own legal representation at the meeting.
and conditions not clearly covered under the Contract, the Contractor shall provide written notice
(“Notice of Intent to File a Claim for Additional Compensation” or the “Notice”) to the Engineer
before incurring any costs or conducting any work that could in any way be included in any such
Claim for additional compensation under the Contract (the “Claim”). The Engineer’s written
acknowledgement of receipt of the Notice and the Contractor’s daily reporting under this
subsection, shall not be construed as an approval by the Agency of the merits of the Claim.
large print at the top of the document. The Notice shall specify the basis for the Claim, including
the nature of the Claim, the reason why the Contractor believes that the Agency is responsible for
payment of the Claim, and a description of the additional compensation, including reference to
each activity associated with the work and/or materials, including reference to any impacts to the
Contractor’s progress schedule, as defined in Subsection 108.03(a), or CPM schedule, as defined
in Section 633. If the Contractor fails to provide the Notice as specified herein, the Contractor
waives its right to bring the Claim under the Contract and the Agency may deny the Claim on this
basis alone.
105
project superintendent shall commence daily records for all labor hours, equipment hours (idle and
operating), and materials involved with the work or materials at issue in the Notice and submit
such records to the Engineer on a daily basis. (“Daily Records”). Such records shall separate the
work and/or materials subject to the Claim from the undisputed work, and include a written
analysis of how the work and/or materials at issue in the Notice impact(s) the critical path. If the
Contractor fails to provide such records to the Engineer as required herein, the Contractor waives
its right to bring the Claim, and the Agency may deny the Claim on this basis alone.
the following documentation in support of the claim (“Claim Documentation”). This
documentation shall be structured, formatted, and labeled as noted.
became aware of the actions or conditions giving rise to the Claim, all necessary dates,
locations, and work and material items at issue in the Claim, including copies of the Daily
Records. Pages shall be labeled page 1-1 through page 1-X.
through page 2-X.
Contractor believes have knowledge or information concerning the facts giving rise to the
Claim. Pages shall be labeled page 3-1 through page 3-X.
subcontractors, whom the Contractor believes have knowledge or information concerning
the facts giving rise to the Claim. Pages shall be labeled page 4-1 through page 4-X.
the Claim, and a description of why the Contractor believes those provisions support the
Claim. Pages shall be labeled page 5-1 through page 5-X.
support the Claim, and copies of the same. Pages shall be labeled page 6-1 through page
6-X.
are being requested in the Claim. Pages shall be labeled page 7-1 through page 7-X.
105
number of days being requested, supported with reference to how the facts underlying the
Claim affected the Contractor’s performance schedule, including how such facts affected
the critical path. Reference shall be made to the Contractor’s baseline CPM schedule and
any updates or revisions thereto, and a schedule analysis providing evidence of delays to
the critical path shall be provided. If no time extension is being requested in the Claim, a
statement to that effect shall be provided. Pages shall be labeled page 8-1 through page 8-
X.
of any and all costs being sought in the Claim, listed by category of work, including, but
not limited to, work items, labor and materials costs, and costs relating to delays associated
with performing the work. Such documentation shall include invoices for rented
equipment, the EquipmentWatch Rental Rate Blue Book analysis for owned equipment,
and subcontractor agreements. If no additional compensation is being requested in the
Claim, a statement to that effect shall be provided. Pages shall be labeled page 9-1 through
page 9-X.
following Claims Certification.
Under penalty of law for perjury or falsification, the undersigned, [insert
individual’s name, job title, and company name], certifies that this claim
for additional compensation for work on the Contract is a true and accurate
statement of the actual costs incurred (in the amount of [insert amount],
exclusive of interest) and is fully documented and supported under the
Contract between the parties.
The Claims Certification shall be signed, dated, and notarized and executed by a senior
officer of the Contractor with legal authority to bind the Contractor, or if the Contractor is
a sole proprietor, by the proprietor. The Claims Certification may be used in any
proceedings regarding false Claims under 31 U.S.C. § 3729 or 32 V.S.A. § 631. This page
shall be labeled page 10-1.
Claim will be made by the Construction Engineer.
Claim Documentation provided by the Contractor meets the requirements of Subsection
(e). If the Claim Documentation is not complete, structured, formatted, and labeled
as required, it will be deemed incomplete and the Contractor will be required to resubmit
it in its entirety.
105
The Construction Engineer will endeavor to make the Completeness Determination within
30 calendar days of receipt of the Claim. Where this 30 calendar day period is unfeasible,
the Construction Engineer will inform the Contractor as to the status of the Completeness
Determination, if necessary, on a quarterly basis. The review and analysis of the merits of
the Claim may be postponed pending the Completeness Determination. The Construction
Engineer will inform the Contractor, in writing, that the Completeness Determination has
been issued.
Determination, the Construction Engineer will begin a principled, merits-based analysis of
the Claim (“Initial Claim Judgment” or “ICJ”). The Construction Engineer may seek
additional documentation from the Contractor, including but not limited to a full set of the
Contractor’s original bid preparation package.
subcontractors and conduct other interviews or seek additional documents from
other entities, including the Agency. The Construction Engineer may also hold an
informal hearing with the Contractor to ask any follow-up and clarifying questions,
and to give the Contractor a full and fair opportunity to present the merits of the
Claim. The Construction Engineer will endeavor to keep the Contractor informed
as to the status of the Claim, if necessary, on a quarterly basis.
ICJ, allowing or denying the Claim, in whole or in part, within 180 calendar days
of the Completeness Determination. The ICJ shall include findings of fact and
conclusions of law with respect to the specific contractual provisions governing the
Claim.
the Chief Engineer. Notwithstanding any other provision of law, case law, regulation, or the
Contract, all appeals shall be made within 30 calendar days of the decision to which the Contractor
is aggrieved, and not thereafter.
documents or interviews will be necessary to decide the appeal. The Chief Engineer may
interview or re-interview employees of the Contractor and subcontractors and conduct
other interviews or seek additional documents from other entities, including the Agency.
The Chief Engineer may also hold an informal hearing with the Contractor to ask any
follow-up and clarifying questions, and to give the Contractor a full and fair opportunity to
present the merits of the Claim. The Chief Engineer will endeavor to keep the Contractor
informed as to the status of the Claim, if necessary, on a quarterly basis.
105
the Agency’s final determination on the merits of the Claim (“Final Claim Judgment” or
“FCJ”), as required under paragraph eight of Form CA-111B, “Dispute Resolution,
Exclusivity of Administrative Remedies,” within 180 calendar days of the date of the
appeal.
The FCJ may affirm the ICJ in whole or in part, or may allow or deny the Claim, in whole
or in part, on other grounds. The FCJ shall include findings of fact and conclusions of law
with respect to the specific contractual provisions governing the Claim.
review of the FCJ before the Transportation Board pursuant to Subsection 105.04. The
Transportation Board shall defer to the factual findings of the FCJ and review the legal
conclusions of the FCJ de novo.
the Contract, all Claims by the Contractor shall be submitted in writing within 90 calendar days
after the acceptance date of the Contract or within 90 calendar days of the Notice of Intent to File
a Claim, whichever occurs first, and not thereafter (the “Claim Filing Period”). Such Claims shall
meet the requirements set forth above, including, but not limited to, complete documentation
supporting the Claim. Any additional time granted by the Construction Engineer because the Claim
was incomplete or for the time to produce supplemental information shall not be the subject of any
demand for interest payments or for attorneys’ fees and/or other costs.
If the Contractor fails to file the Claim within the Claim Filing Period, the Contractor waives its
right to bring the Claim. If the disputed work continues to be performed beyond the Claim Filing
Period, the Contractor shall submit a written request to extend the Claim Filing Period prior to the
expiration of the Claim Filing Period. The Contractor shall submit such requests for extension of
the Claims Filing Period every 90 calendar days until the disputed work is completed. Once the
disputed work is complete, the Contractor must submit the complete Claim within the latest
approved Claim Filing Period, or 90 calendar days from the date the disputed work was completed,
whichever is first, and not thereafter.
105.21PAYROLLS
Contract. This requirement shall also apply to the work of any subcontractor having a subcontract
for any part of the work performed on the job. Any costs associated with this work will not be paid
for directly but will be considered incidental to the Contract pay items.
105
authorized representative to examine the Contractor’s orders for construction workers on file with
the local employment office of the Vermont Department of Labor.
$250,000, the Contractor shall implement a payroll process by which during every pay period the
Contractor shall submit a list all workers who were on the jobsite during the pay period, including
those employed by subcontractors and independent contractors, the work performed by those
workers on the jobsite, and a daily census of the jobsite.
This information, including confirmation that Contractors, subcontractors, and independent
contractors have the appropriate workers’ compensation coverage for all workers at the jobsite,
and similar information for the subcontractors regarding their subcontractors, shall also be
provided to the Vermont Department of Labor and to the Vermont Department of Financial
Regulation, upon request, and shall be available to the public.
105.22ENVIRONMENTAL REGULATION. The Contractor shall perform all project related operations
so as to give protection to the natural and cultural resources of the state.
The Contractor shall conduct the work in conformance with all regulations and permit conditions
applicable to the Contract. If the Contractor proposes to perform the work differently than the manner
provided in the Contract, the Contractor shall obtain approval from the appropriate regulating entities prior
to performing the work. The costs associated with obtaining and complying with permits required to
perform the work will not be paid for directly, but will be considered incidental to the Contract.
105.23EROSION PREVENTION AND SEDIMENT CONTROL
the Contractor shall submit a plan in writing for the prevention of erosion and control of
sedimentation and pollution on the project and on associated access roads, material waste and
borrow areas, and staging areas. The plan shall be submitted no later than the preconstruction
conference and a Notice to Proceed will not be issued until the plan has been found to be in
conformance.
measures shall be installed and maintained in conformance with the Contract. Unless otherwise
specified in the Contract, this work shall be performed as described in this section, Section 653,
and The Low Risk Site Handbook for Erosion Prevention and Sediment Control published by the
Vermont Agency of Natural Resources.
105
earth material exposed by construction activities and to direct the Contractor to provide immediate
permanent or temporary erosion prevention and sediment control measures to minimize adverse
effects on resources. This may include restricting the area of clearing and grubbing, excavation,
borrow, and embankment operations such that these activities are commensurate with the
Contractor’s capability to install erosion prevention and sediment control measures in accordance
with the erosion prevention and sediment control plan.
incorporate all temporary and permanent erosion prevention and sediment control measures into
the project at the earliest reasonable time. Temporary erosion prevention and sediment control
measures shall be used to prevent erosion and to correct conditions that develop during
construction prior to installation of permanent measures. As the earthwork proceeds, slopes shall
be graded to finish grade whenever practical, and all disturbed areas shall be stabilized by seeding
and mulching or other acceptable methods within 48 hours of disturbance.
resulting exposed surfaces are stabilized with temporary or permanent measures within 48 hours.
state, or local agencies, the more restrictive provisions shall apply as determined by the Engineer.
be stabilized. If permanent stabilization is not possible, exposed areas shall be shaped and then
covered with mulch or matting to intercept and divert runoff to locations where the least amount
of erosion will result. During a suspension of construction operations, the Contractor shall act
immediately to correct any deficiencies that develop with the erosion prevention and sediment
control measures and/or stabilized areas.
erosion prevention and sediment control measures shall be acceptably maintained until both the
permanent drainage facilities have been constructed and vegetation has been established
throughout the project.
105.24POLLUTION CONTROL
land and water of the state and shall comply with applicable statutes and regulations relating to the
prevention and remediation of pollution.
105
cutting, welding, or grinding operations, the Contractor shall include a description of any proposed
containment measures as part of their erosion prevention and sediment control plan, submitted in
accordance with Subsection 105.23(a). When the bridge activities listed above are in progress
where lead paint is known or suspected, the Contractor shall use containment devices to retain all
generated materials. The Contractor shall also consult with the Vermont Department of Health to
determine if a lead abatement permit is required. When required, the Contractor shall coordinate
with the Agency’s Hazardous Materials and Waste Coordinator to administer the permit request.
transportation regulations when cleaning, handling, moving, repainting, cutting, welding, sanding,
or grinding any coated or treated materials.
pollution associated with construction operations. The methods employed shall be acceptable to
the Engineer and compatible with the location of the work. The burning of tires or other
manufactured products is prohibited.
In accordance with 23 V.S.A. § 1110, equipment shall not be permitted to idle for more than 5
minutes in a 60 minute period.
chemical or petroleum odors or presence of non-native materials including, but not limited
to, solid waste, asphalt, or ash) be discovered during construction, the Contractor shall
immediately notify the Engineer. The Agency will work with the Contractor to notify
regulators as necessary and to develop a plan to manage the materials, waste, or both.
that any generated contaminated material or hazardous waste was characterized as
necessary and disposed of in conformance with all applicable regulations.
appropriate federal or state regulating authority, mechanized equipment shall not be operated in the
waters of the state.
bitumen, raw sewage, sediment, or other waste, shall not be discharged into or alongside wetlands,
waters of the state, or natural or constructed channels leading thereto. Any construction activity in
or adjacent to regulated waters shall comply with the Vermont Water Quality Standards.
105
105.25OPENING OFF-SITE ACTIVITY AREAS
accordance with all Contract permits and that the following requirements are met:
aesthetically or as it relates to drainage.
capability plan, whether site specific, local, or regional.
residences, and other facilities.
201.06. The Contractor shall remove, stockpile, and preserve topsoil, sod, and other
suitable material from the surface of the area prior to proceeding with other operations.
indicated in the conforming erosion prevention and sediment control plan, in place prior to
use of the area. At a minimum, the requirements of The Low Risk Site Handbook for
Erosion Prevention and Sediment Control published by the Vermont Agency of Natural
Resources shall be used as best management practices for OSA areas.
review of potential natural and cultural resource impacts. A list of these exemptions is part
of the Off-Site Activity Exemption Record form that is available on the Agency’s website.
To use an exempt OSA area, the Contractor shall complete this form and then submit it to
the Engineer.
Activity Submittal form that is available on the Agency’s website. The completed form
shall be submitted to the Environmental Section to review potential natural and cultural
resource impacts. A copy of this form shall also be submitted to the Engineer. Within 21
calendar days, the Environmental Section will provide an OSA review form indicating
conformance or non-conformance of the site, along with any specific conditions.
necessary federal, state, and local permits and clearances prior to using an area for an Agency
project. Any fees related to applications for such permits shall be the responsibility of the
Contractor.
105
105.26MAINTAINING OFF-SITE ACTIVITY AREAS
The Contractor shall keep in a condition acceptable to the Engineer the portions of an area where
a pit or pits have been opened and shall maintain all access roads with sufficient dust control and
proper drainage to prevent damage to adjacent properties. Area operations shall be restricted to
normal working hours except with the express written approval of the Engineer and shall be in
accordance with all permit conditions. All OSA areas shall comply with the environmental
regulations described in Subsection 105.22 and the pollution control described in Subsection
prevention and sediment control measures at OSA areas shall be consistent with the conforming
erosion prevention and sediment control plan for the specific area. The on-site plan coordinator
Contractor shall grade to no steeper than 1:3 (V:H) and seed and mulch disturbed fill areas prior
to shutting down for the season.
105.27CLOSING OFF-SITE ACTIVITY AREAS. With the exception of those areas which will remain
open for commercial use, the Contractor shall complete the following prior to the completion and
acceptance of the project:
condition, properly and thoroughly graded and drained.
disposed of.
be left steeper than 1:2 (V:H) for fill made up of stone or concrete. The tops of slopes and toes of
slopes shall be neatly rounded.
spread over the surface of the area. The complete area shall be seeded and mulched in accordance
with Section 651.
105
105.28PAYMENT FOR EROSION PREVENTION AND SEDIMENT CONTROL
maintenance and, where necessary, removal for those erosion prevention and sediment control
measures required by the Plans and/or the Engineer that are not items in the Contract will not be
paid for directly, but will be considered incidental to all other Contract items.
Environmental protection work in connection with erosion prevention and sediment control for the
opening, maintaining, and closing of OSA areas and pollution control measures will not be paid
for directly, but will be considered incidental to all other Contract items.
Costs for damage to OSA areas, to the owners thereof, or to adjacent property owners shall be the
responsibility of the Contractor.
prevention and sediment control work not attributable to the Contractor’s negligence, carelessness,
or failure to install permanent controls will be performed and paid for as specified in Subsection
(a), or as ordered by the Engineer
Temporary erosion prevention and sediment control measures required due to the Contractor’s
negligence, carelessness, or failure to install permanent controls as a part of the scheduled work or
as ordered by the Engineer shall be performed by the Contractor at the Contractor’s expense.
control erosion, pollution, or siltation, the Engineer may employ outside assistance or use state
forces to provide the necessary corrective measures. Such incurred direct costs, plus project
engineering costs, will be charged to the Contract and appropriate deductions made from any
money or monies due or to become due the Contractor.
105.29VALUE ENGINEERING
initiate, develop, and present to the Engineer for consideration cost reduction proposals involving
changes in the drawings, designs, specifications, or other requirements of the Contract. These
provisions do not apply unless the proposal submitted is specifically identified by the Contractor
as being presented for consideration as a VE proposal.
The change in cost proposals contemplated are those that would require a change order modifying
the Contract and would produce an overall savings to the public by providing items or methods
other than those specified in the Contract and/or reduce future maintenance costs without impairing
or compromising essential functions and characteristics such as service life, safety, durability,
reliability, economy of operation, ease of maintenance, and necessary standardized features.
105
A VE proposal shall contain proven features that have been used under similar conditions, and is
presented as such, and does not contain equivalent options already provided in the Contract.
The Agency will not be responsible for schedule delays that occur as a result of the Contractor’s
desire to pursue a VE proposal.
in three steps:
the amount of payment due to the Contractor and credit due to the Agency.
Contractor shall submit a written Conceptual Value Engineering Proposal (CVEP) to the
Engineer for consideration. The CVEP is not a formal and complete submittal based upon
detailed technical analysis, but instead relays a conceptual idea based upon the Contractor’s
knowledge and expertise. The CVEP shall include the following information based upon
the Contractor’s best knowledge and understanding:
includes the basic differences between the existing Contract and the proposed
change.
advantages and disadvantages of the CVEP including effects on the service life,
safety, durability, reliability, economy of operation, ease of maintenance, and any
other factors significantly altered by the CVEP.
necessary to address existing permits, new permits, or third-party agreements that
may be impacted or required in order to initiate the proposed change(s). In addition,
the Contractor shall describe its expectation of securing or modifying these
documents, who is responsible for securing them, and required timeframe(s).
105
another Agency project, the date, the project name and number, and the action taken
by the Agency shall be indicated.
concept(s) included in the CVEP that is known to the Contractor, including the
tester, the conditions, and the results.
(c). This amount shall not include the cost to prepare and submit the CVEP
develop and submit a Detailed Value Engineering Proposal (DVEP). This estimate
shall include a detailed estimate of both the engineering costs the Contractor will
incur in preparing the DVEP (the “Internal DVEP Costs”) and the cost the
Contractor will incur to obtain specialty engineering services that the Contractor
cannot perform and which are necessary to prepare the DVEP (the “External DVEP
Costs”) (collectively, the “DVEP Costs”). If the Contractor establishes, to the
satisfaction of the Construction Engineer, that it does not have the financial
resources to incur the DVEP Costs, the Agency may, in its sole discretion, decide
to advance the Contactor up to 50% of the DVEP Costs. In no event will the Agency
pay more than 50% of the DVEP Costs, nor will the DVEP Costs exceed 50% of
the Net Savings amount, as defined in Subsection 105.29(c)(3).
to submit a DVEP and the time-sensitivity of the savings identified. Such estimate
shall specify the date by which the Agency must approve the DVEP to obtain the
maximum cost reduction, and the latest date by which the Agency must approve
the DVEP for the Contractor to avoid significant impacts on the estimated Net
Savings or the Contractor’s schedule of work. If the Agency determines that the
time for response is insufficient for review, the Contractor will be promptly
notified. The Contractor shall identify the date by which if the DVEP is not
approved the VE will be withdrawn and the original work can commence without
delay to the project.
construction drawings in accordance with Subsection 105.06, showing the
proposed revisions relative to the original Contract features and requirements. VE
proposals that require engineering design, computations, or analysis shall be
prepared under the responsible charge of, and sealed and signed by, a professional
engineer. The plan, specification, and engineering changes should be progressed
far enough along to clearly show the design intent and be able to provide a quality
cost estimate.
105
shall be available to attend a meeting scheduled by the Agency for the purpose of
presenting and answering questions regarding the CVEP. The purpose of the
meeting is to discuss possible risks, design implications, and schedule impacts
associated with the VE proposal. If applicable, the Contractor shall be accompanied
by their engineer responsible for the plan and specification revisions associated
with the VE proposal.
and respond to the Contractor within 14 calendar days of receipt. The Agency may,
at its sole discretion:
(b)(2)k.1., the Contractor may submit a Detailed Value Engineering Proposal
(DVEP). DVEPs will be processed in the same manner as prescribed for any other
alterations of the Contract that require a change order and shall contain, as a minimum, the
following information:
and what is being proposed to improve upon the originally designed feature.
specifications, pay items, and unit prices) that must be changed and a
recommendation of how to make each change, including a description of the
advantages and disadvantages and where these items have been successfully used
on other projects before or tested elsewhere.
to be generated as defined in Subsection 105.29(c)(3), actual DVEP development
costs, and estimated savings and schedule impacts, including approval date(s)
required. If the Agency determines that the time for response is insufficient for
review, the Contractor will be promptly notified.
105
have on other costs to the Agency, including environmental effects, traffic impacts,
and preventive action or treatment costs.
construction drawings in accordance with Subsection 105.06, showing the
proposed revisions relative to the original Contract features and requirements. All
DVEPs that require engineering design, computations, or analysis shall be prepared
under the responsible charge of and signed and sealed by a professional engineer.
time for the completion of the Contract. An extension to the original Contract
completion date will generally not be approved.
to properly evaluate the DVEP. Where design changes are proposed, such
additional information may include results of field investigations and surveys,
design computations, specifications, and any field changes already incorporated
into the project. The Contractor shall promptly provide any such requested
information.
the Contractor’s cost analysis.
the local governing body must also provide approval. The Contractor shall present
their proposal to the local governing body and allow sufficient time to present the
proposal and receive comments.
and provide the Contractor with a written response within 30 calendar days of receipt of
all of the information it has determined was necessary to properly evaluate the DVEP. Such
a response will include a brief description of the Agency’s reason(s) for its decision. The
Agency, at its sole discretion, will either accept the DVEP, accept it with contingencies, or
reject it.
105
proposal submitted. The Contractor may withdraw in whole or in part any VE proposal not
accepted within the period specified in the proposal. The decision of the Agency as to the
acceptance or rejection of VE proposals will be final and will not be subject to the
provisions of Subsection 105.04 or Subsection 105.20.
the Contractor, will prompt the Agency to reject the DVEP before the execution of a change
order. Contingencies may include, but are not limited to, the necessary approvals of
permits, amendments, execution or amendments to third-party agreements, specific
deadlines for completion of submittals, or execution of permits, agreements, and/or
amendments thereof.
The Agency, in its sole discretion, will determine whether to reimburse the Contractor for
DVEP Costs, and if so, what percentage of those costs. In no event will the Agency pay
more than 50% of the DVEP Costs. These costs will not include the cost to prepare the
CVEP.
the Contractor wants to proceed, the necessary Contract modifications will be effected by
execution of a change order which will provide for equitable price adjustments giving the
Contractor and the Agency equal shares in the net savings. Unless and until a proposal is effected
by such Contract modification, the Contractor shall remain obligated to perform in accordance
with the terms of the existing Contract.
In addition to the requirements of Subsection 109.04 and Subsection 109.05, the DVEP will set
forth the credit due the Agency calculated as the difference between the cost of performing the
work, as originally specified, and the amount payable to the Contractor for the revised work. The
payment for this Contract modification will only include the following amounts:
prices.
provided in Subsection 105.29(b)(2)g., if any.
105
Agency, calculated as follows:
𝑁𝑆 = 𝐸𝐺𝑆 + 𝐶𝑆𝑃 − 𝐶𝑈𝐷𝐶 − 𝐴𝑉𝐸𝐶
where:
NS = Net Savings generated by the DVEP.
EGS = Estimated Gross Savings is an agreed upon difference between the cost of
performing the work as originally specified in the Contract and the cost of performing the
work as revised by the DVEP.
CSP = Cost Savings to the Public are those funds not expended by the public, including
but not limited to reduced maintenance costs and reduced road user costs. CSP shall not
include any cost savings attributable to a time period exceeding 10 years from the Contract
completion date.
CUDC = Contractor’s Unreimbursed Development Costs related to the preparation of the
DVEP, including costs of the Contractor’s design subconsultants and subcontractors, but
excluding all such costs already paid by the Agency under Subsection 105.29(b)(2)g.
AVEC = Agency’s VE Costs related to review, approval, and implementation of the DVEP
including design costs, field inspection, and the value of any Agency-provided property.
The change order effecting the necessary Contract modifications shall establish the Net Savings
agreed upon and shall provide for such adjustment in the Contract price as will divide the Net
Savings equally between the Contractor and the Agency. All reasonably incurred costs of
developing the cost reduction proposal and implementing the changes, including any increased
costs to the Agency resulting from its application, will be deducted from the total estimated
decrease in the Contractor’s costs of performance to arrive at the Net Savings.
DVEP, the Agency, on its own initiative or upon request by the Contractor, may review the actual
Net Savings realized by the DVEP. The Contractor will be afforded an opportunity to review and
comment on such a review.
If the actual Net Savings were greater than set forth in the change order, the increased savings will
be shared equally between the Agency and the Contractor. If the Net Savings were less than set
forth in the change order, the reduction in savings will be borne equally by the Agency and the
Contractor by a reduction of amounts otherwise due to the Contractor.
105
unrestricted right to use any approved DVEP, or any DVEP in which the Agency has
reimbursed the Contractor for any portion of the development costs, on other Agency
projects without notice, cost, or liability to the Contractor.
and submit all proposals initiated by the Contractor’s subcontractors.
otherwise before approval of a DVEP. The Contractor is responsible for all delays caused
by the VE proposal that were not negotiated in the change order.
accordance with the Contract.
the Agency for additional compensation or time resulting from the delayed review or
rejection of a DVEP, including but not limited to development costs, loss of anticipated
profits, and increased material or labor costs.
on its use or on disclosure of the information submitted shall be void, and the Agency shall
thereafter have the right to use, duplicate, and disclose in whole or in part any data
necessary to the use of the proposal on this project or other projects.
corresponding adjustment in the Contract completion time. No incentive pay will be
provided for early completion days resulting from time savings of any approved VE
proposals.
proposal decisions by the Agency are final and are not subject to the dispute resolution
provisions provided in this Contract or otherwise available in law.
105
order. If the Contractor elects to withdraw the DVEP in accordance with this provision, the
Contractor waives its right under Subsection 105.29(b)(2)g. for reimbursement of DVEP
costs, including any costs advanced to the Contractor. If such costs have been advanced,
the Contractor shall reimburse the Agency for those costs within 30 calendar days of
withdrawing its DVEP.
Agency for any design errors and/or omissions associated with the DVEP implementation.
106
1-69SECTION 106 – CONTROL OF MATERIAL
106.01SOURCE OF SUPPLY AND QUALITY REQUIREMENTS . The material used in the work shall
meet the requirements of the Agency’s Quality Assurance Program . The Agency ’s Quality Assurance Program , including the Materials Sampling Manual , has been developed to clearly articulate the processes for acceptance of materials in construction and maintenance. In order to expedite the inspection and testing of materials, the Contractor shall notify the Engineer of the proposed approved sources of materials at least 96 hours prior to delivery. Sources not previously approved by the Agency will require a minimum of four weeks’ advanced notification to complete the necessary inspection and testing of materials. At the option of the Engineer, materials may be approved at the source of supply before delivery is started. If it is found during acceptance that supplied materials from previously approved sources do not meet specifications, the Contractor shall take action to supply materials that meet specif ications.
106.02LOCAL MATERIAL SOURCES . The Contractor shall determine potential sources of material
and the amount of equipment and work required to produce material meeting the specifications. The Agency’s Geologist maintains a list of material sources that have previously produced materials meeting specifications. The ability to purchase from the owner(s) of the source(s) and the quality of the material are not guaranteed by the Agency. The Contractor acknowledges that it is not possible to ascertain from samples the limits of a deposit and th at variations in quality in a material source are normal and to be expected. Exploration for new material sources will be the responsibility of the Contractor. The Engineer may order procurement of material from any portion of a material source and may rej ect portions of the material sources as unacceptable. It shall be the responsibility of the Contractor to acquire the right to take materials from any source together with the right to use such property as required for whatever purpose, including plant sites, stockpiles, and haul roads. The Contractor shall pay all costs related thereto together with any costs resulting from exploring and developing these sources.
106.03SAMPLES AND TESTS . All materials will be inspected, sampled, tested , or accepted by the
Engineer as incorporated into the work . Under any applicable quality acceptance (QA) specifications, the Contractor shall perform all process quality control testing with the Engineer performing all quality acceptance testing. Any work in which untested and/or unaccepted materials are used without the approval or written permission of the Engineer shall be performed at the Contractor’s risk. Any work determined to be unacceptable and unauthorized will not be paid for. When modified AASH TO or ASTM test methods or Agency test methods are designated, the test method will be available from the Agency’s Materials Testing and Certification Section. Tests for compliance with specification requirements will be made by and at the expense of the A gency.
CONTROL OF THE WORK in other states
Get an email when 105 changes
Vermont revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.