B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
General Provisions (00100-00999)

664RAILROAD SIGNALS

VT · 2024 Standard Specifications✓ Full text on BuildSpecBook pages 1049–1082 Save this section

Ask about Section 664

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

664

6-275SECTION 664 – RAILROAD SIGNALS

664.01DESCRIPTION . This work includes designing, furnishing and installing new railroad -highway

active warning systems with new metered power services, traffic preemption interconnection where indicated on the Plans, and testing of equipment, material, hardware, and all nece ssary appurtenances specified or required to provide a safe and operating automatic highway crossing warning systems

(AHCWS)as specified in this section and as indicated on the Plans.

664.02MATERIALS . Materials shall meet the requirements of the followi ng subsections:

Sand Borrow and Cushion ................................ ................................ ......................... 703.03 Dense Graded Crushed Stone for Subbase ................................ ................................ 704.06 Electrical Conduit ................................ ................................ ................................ ......752.0 6 Automatic Highway Crossing Warning System (AHCWS) ................................ ......781.03

664.03SUBMITTALS

(a)Pre-Installation Submittals . The following information shall be prepared and submitted for review

and approval by the Engineer . Submittals shall meet the requirements of Subsection 105.0 6.

(1)Catalog Cut Sheets . Catalog cut sheets and descriptive literature for all material as specified

herein.

(2)Working Drawings . Working drawings, including, but not limited to, the following:
a.Fabrication drawings for the assembly of automatic highway crossing warning

layout, including detailed bills of material. Fabrication drawings shall include detailed drawings of signal masts, cantilever gates, shelters and cases, and their respective foundations.

b.Design calculations in accordance with the AREMA C&S Manual for signal masts,

cantilever gates, and their respective foundations.

c.Detai led installation drawings for each layout indicating the location and sizes of

the new wiring.

d.Drawings showing the proposed size and equipment layout of the housing,

including rack, lighting, convenience outlet arrangement, and exhaust fan mounting and location.

664 6-276 e. Drawings showing the location, size, and mounting arrangement of the manual control box.

f.Drawings showing the manual control panel face plate configuration, including

types of buttons, plugs, levers, terminals, and lights that have been proposed to be furnished.

g.Drawings of the grounding arrangement.
h.Drawings of the battery trays and racks.
i.Drawings of the sizes and types of internal wire that the Contractor proposes to

furnish and install.

j.Design drawings showing the control of the specified equipment for each newly

circuited location. Design drawings will be used to generate the as -built drawings. As-built drawings shall meet the requirements specified in Subsection

( b)(2)

k.Drawings of each instrument and entrance rack showing the arrangement and

description of the mounted equipment and their proposed method of inter - and intra-rack wiring.

(3)Test Documentation . Documentation that all required factory tests of s ystems, subsystems,

assemblies, subassemblies, and components supplied under the Contract have been performed. All test records shall be submitted to the Engineer before the equipment is delivered to the site.

(4)Training Classes . Outline of training clas ses to be given by the Contractor to familiarize

railroad maintenance personnel with the initial setup, troubleshooting, and maintenance procedures for any Style C, motion sensor system, or crossing predictor system furnished under the Contract.

(5)Manuals. Six installation and maintenance manuals for each type of AHCWS equipment.
(6)Vital Signal Cable Pre -Qualification .
a.General Requirements . All cable manufacturers supplying cable for the Contract

shall be pre -qualified by the Engineer. The Contractor shall provide all the data required for the Engineer’s evaluation and shall make the arrangements for any required demonstrations and tests.

664 6-277 b. Qualifications . Qualifications shall be based on the following criteria:

1.Past Performance and Experience . The cable manufacturers must

demonstrate previous successful experience in supplying cable to the railway industry for use as vital signal control cables. A list of such installations shall be provided for each cable manufacturer to be considered.

2.Quality Assurance Program . The manufacturer of cables in accordance with

the requirements of this specification shall be in compliance with a quality assurance program that meets the intent of ASQ/ANSI/ISO 9001 . Prime concern must be focused on the necessa ry formal assurance requirements to ensure that cable failure cannot be attributed to actions or lack of actions by the manufacturer.

3.Technical Data . The Contractor shall provide full technical data which

demonstrates compliance with the requirements of this specification for each specified cable type the Contractor intends to supply.

4.Warranty . The manufacturer shall certify compliance with the following

warranty prior to selection:

i.The manufacturer warrants that the design, material, and

workmansh ip incorporated in each item of cable shall be of the highest grade and consistent with the established and generally accepted standards for aerial and underground cable for vital railroad signal, communication, and power circuits; and that each such item and every part and component thereof shall comply with this specification. ii. The manufacturer agrees that this warranty shall commence with the acceptance of each item of the cable, whether the defect is patent or latent, and shall continue for a period of two years after initial satisfactory operation of the item or four years after acceptance of the item, whichever is shorter.

664 6-278 iii. The warranty covering any length of cable that shall be replaced by the manufacturer under the above conditions shall be reinstated for a period of two years, effective as of the day when said replacement is effected. If the failure is found to be of major importance and affects any other item of cable, the reinstatement of the warranty shall then be extended to cover the item so affected as well, and shall start as of the date of such replacement. The warranty reinstatement provided herein shall apply only to the first replacement or repair of any such item and, in the case of failure of major importance, to the first ext ension of the said warranty to said affected items. iv. The foregoing warranties are exclusive and in lieu of all other warranties, written, oral, implied, or statutory (except as to title and freedom from lien). In no event shall the manufacturer be liabl e by reason of breach of warranty for special or consequential damages.

(7)Vital Signal Cable Quality Assurance .
a.The Contractor shall submit the following to the Engineer for approval prior to

shipment of the cable:

1.List of the cable manufacturer’s railway signal installations.
2.Each cable manufacturer’s quality assurance program.
3.Full technical data for each type of cable which the cable manufacturer

intends to supply.

b.The Contractor shall submit two certified copies of the following to the Engineer

for approval:

1.Cable test reports for all factory tests.
2.Test reports of cable tests conducted in the field in accordance with the

approved testing procedures.

3.Certification that each cable supplied complies with the requi rements of

these specifications.

664 6-279 4. Information to be supplied by certified cable test reports shall include the following:

i.Report number.

ii. Date and location of test. iii. Description of test and test conditions. iv. Complete cable or wire description.

v.Lot, batch, or reel identification number.

vi. Quantitative test results. vii. Summary of test results. viii. Information on the components of the cable tested, to include batch numbers and physical and electrical properties.

(b)Post-Installation Submittals . Upon acceptance of the AHCWS , the following information shall be

prepared and submitted for review and approval by the Engineer . Submittals shall meet the requirements of Subsection 105.0 6.

(1)Documentation that all required specified field tests have been performed and that the

installed system and equipment has successfully passed the test. All test records shall be submitted to the Engineer upon acceptance of the AHCWS.

(2)As-built drawings meeting the following requiremen ts:
a.Drawings shall be provided to the Contractor which are representative only of the

general principles and concepts upon which the Contractor shall base the design and location of the proposed system and equipment.

b.Five copies bound in a protective covering of the as -built drawings for the work

shall be provided by the Contractor to the Engineer no more than 10 calendar days after the work is complete and in -service. The Contractor shall furnish to the Engineer a copy of the as -built drawings in Mic roStation DGN and PDF format.

664 6-280 c. Working drawings shall be in accordance with the industry standards for AHCWS circuit design and detail design. Approval of the working drawings shall be at the discretion of the Engineer. The drawings shall conform to t he following:

1.Use of AREMA standard symbols and nomenclature.
2.Conformance with specifications.
3.Logical grouping and arrangement of subject matter.
4.Drawings shall not be crowded or cluttered but shall be arranged for easy

reading for troubleshooting and maintenance .

5.Complete, well described circuits shall be shown on each drawing insofar

as possible. A minimum of circuit continuations shall be used . When continuations are used, they shall be clear and specific and shall include the identity of the continuation sheet. Circuitry shall be presented on the drawing with a minimum of crossed or offset lines.

6.The arrangement of circuitry shall be in suc h a manner that no more than

two wires shall be shown connected to a single terminal or contact pin. A uniform method of 0.10 inch right or left 45° angle, as drawn in the MicroStation DGN file, shall be used to indicate the actual location of double wire connections. Wires shall be shown at the actual point of termination.

7.Circuits shall not be drawn as schematics but shall be drawn to reflect the

actual wiring of the circuits.

8.Circuit drawings shall provide sufficient information by means of contact

and terminal numbering to easily enable the tracing and testing of such circuits.

9.A minimum distance of 0.40 inches shall be maintained between lines

representing circuit wiring. Lettering or printing shall be at least 0.10 inches high. All spacing sha ll be in multiples of tenths of inches.

10.Circuits shall be arranged to geographically match the track layout.

664 6-281 11. Relay nomenclature shall appear at the top of the contact and at the top of the coil.

12.Local circuits sh all be drawn with relay coils, timers, motors, or other

operated devices shown near the right or left border of the drawing wherever practical. Where there is a choice, the right border shall be favored. Contacts in circuits shall be laid out in geographical succession insofar as possible and practical.

13.Relay contacts shall line up with the controlling coil and other contacts of

the same relay insofar as practicable. Different relay contacts and coils shall not line up. Stick contacts shall line up under the coil of controlling relay.

14.A cover sheet with the name of the crossing, mile post, and DOT number

shall be included.

15.An index sheet listing the sheets included in the working drawings shall be

included. .

16.Track and cable plan showing the proposed crossing layout and cables to

field appurtenances shall be included.

d.As-built drawings shall include fabrication drawings as specified in Subsection
e.The Contractor shall submit with the as-built drawings a detailed bill of materials.

This list shall include the part number of all materials used on the project.

664.04DELIVERY, STORAGE, AND HANDLING

(a)All equipment shipped within AHCWS shelters shall be properly fastened and braced to prevent

damage during transit. Any equipment damaged during transit shall be replaced at no additional

cost to the Agency.

(b)Batteries shall be shipped wet, filled to the correct level, and in a fully charged state. Each battery

shall be equipped with transit plugs or rubber stoppers to prevent spillage of the electrolyte.

Batteries shall be shipped separately from the housings in which they are to be used.

(c)Vital relays shall be shipped separately from the wired racks in which they are to be used. They

shall be packaged individually, each in a sturdy corrugated cardboard carton with the drawing

number of the relay printed on the outside of the carton. Relays shall be stored in a protected area

until tested and installed.

664

(d)All cable shall be shipped on reels and adequately protected from damage in shipment, including

the hazard of reels moving obliquely against each other, by heavy wrapping or wood lagging. The

manufacturer shall also be responsible for any change in the shape of the cable occurring in normal

transit which results in an increase in the maximum diameter beyond that specified. The external

protective wrapping on reels shall be secured by at least two steel bands to ensure damage-free

shipment.

(e)Each length of cable shall be wound on a separate reel. Reels shall be substantial to withstand

handling and shall be so designed that the inner end of the cable will be secured and accessible but

protected from injury. If the inner end of the cable projects through the flange of the reel, the inner

end shall be protected by a suitable cover of metal having rounded ends and sides and securely

fastened in place to protect the cable end. Both ends of cable on reel will be secured in place, to

prevent their becoming loose in transit or handling of reel. The diameter of the reel drum shall be

at least 14 times the cable diameter to prevent damage to the cable during reelings. The arbor hole

shall admit a spindle 2-1/2 inches in diameter without binding. The reels shall be designated and

constructed as non-returnable when drum size and cable weight and volume permit. The maximum

width of the reel shall not exceed 48 inches unless otherwise specified.

(f)After passing factory tests, cable shall be effectively sealed against the entrance of moisture. Both

ends of each length of cable shall be protected by wrappings of rubber tape and plastic tape, an

effective boot taped or sealed into place, or other suitable means approved by the Engineer. The

use of friction tape, other than as external mechanical protection over an adequate rubber or plastic

tape, will not be accepted. The cable end protection shall be adequate to protect the cable in

shipment and prolonged external storage in the weather if not immediately employed without

regard to the position of the reel while so stored.

(g)Cable shall be closely and tightly wound, in a uniform manner, in each layer on reels. An arrow

shall be painted on one head of each reel pointing the opposite direction from the outer end of the

cable with the words “roll this way” employing letters not less than 3/4-inch high and an arrow not

less than 6 inches in length and 1/2 inch in width.

(h)LED units shall be packaged separately from flashing light units in which they are to be used.

664.05DESIGN CRITERIA

(a)Fail Safe Design Criteria.
(1)Vital circuits shall be designed on fail-safe design principles, which is to say that broken

wires, damaged or dirty contacts, a relay failing to respond when energized, or a loss of

power supply energy shall not result in unsafe conditions.

664

(2)Component or system failures which are not self-detecting shall not cause unsafe

conditions. Even if added to other failures, any number of simultaneous component or

system failures attributable to the same cause or related causes shall not cause unsafe

conditions. Any component or wire becoming grounded or any combination of such

grounds shall not cause unsafe conditions.

(3)The articles or units submitted by the Contractor must be in production and must have had

a previous, satisfactory in-service performance record of at least two years on Class I or

Class II railroads. The manufacturer shall provide proof of performance statements upon

request. Articles or units that do not meet this requirement shall be made available for type

acceptance testing.

(4)Type acceptance testing shall be conducted by the Contractor. The Engineer and the

Operating Railroad shall be notified prior to testing.

(5)All vital circuits shall be double-break, except within a signal instrument house or case,

after the entering or leaving circuits are double-broke.

(6)All vital repeater relay circuits shall be designed on the cascade principle. The paralleling

of vital repeater relays will not be permitted.

(7)Repeater relay contacts shall be assigned so that safety will not be compromised by the

failure of any repeater relay to energize.

(8)Highway crossing warning start circuits shall provide initiation of the warning equipment

from both sides of the crossing and shall also include separate island circuits with 5 seconds

minimum loss-of-shunt.

(9)AHCWS total warning times and approach circuit distance calculations shall be provided

on the crossing track plan. Total warning time shall be calculated as follows:

𝑇 𝑇𝑊 = 𝑇 𝑀𝑊 + 𝑇 𝐵 + 𝑇 𝐸𝑅 + 𝑇 𝐶 + 𝑇 𝑃

where:

TTW = Total warning time (seconds)

TMW = Minimum warning time (seconds)

TB = Buffer time (seconds)

664

TER = Equipment response time (seconds)

TC = Clearance time (seconds)

TP = Preemption time (seconds)

The value of each variable shall be determined as follows:

a.The minimum warning time shall be the FRA minimum time of 20 seconds.
b.The buffer time shall be 10 seconds for crossings equipped only with flashing light

signals and 15 seconds for crossings equipped with automatic flashing lights and

gates.

c.Equipment response time shall be provided per the manufacturer’s

recommendation.

d.Clearance time shall be provided for locations with multiple track crossings,

skewed angle crossings, or wide travel surfaces. Clearance times for wide crossings

are shown on the Plans and shall be verified and submitted to the Engineer for

approval prior to completion of the design.

e.Preemption time shall be added for advanced traffic preemption.
(10)Vital relays shall be included for the gate control relay (GCR), emergency control stick

relay (ECSR), preemption relay (PER) and other vital circuits included in the Contractor’s

design.

a.The GCR shall be controlled by an output from a vital logic gate delay unit, used

to control the gates.

b.The PER shall be driven by an output of the motion sensor unit. The PER relay

shall be equipped with heavy duty contacts and shall be a four-wire double break

circuit to the traffic controller in advance of the start of the flasher signals.

c.The ECSR will be used to disable the crossing and will include the emergency

cutout switch and control of a red LED, indicating that the crossing is out-of-

service.

d.The LED shall be located on the side of the shelter.

664

(b)Control Circuits.
(1)Control circuits shall be in accordance with the AREMA C&S Manual recommended

practices where such practices do not conflict with these specifications.

(2)Where means are provided for cutting out the warning devices during intervals when trains

make regular operating stops or perform switching operations on approach circuits, the

following requirements shall be met:

a.Controls shall be designed to ensure that warning devices are operating before the

train enters the crossing.

b.Automatic control of the warning devices actuated by approaching trains other than

the train that has stopped or is performing switch operations shall take precedence

over any cut-out features.

c.Hand throw switches equipped with circuit controllers shall not cause the warning

devices to operate without trains within the approach circuits when the switch is

reversed.

(3)Warning devices shall operate until the rear of the train clears the crossing for trains

operating in either direction.

(c)Modular Design.
(1)Modular design shall be used throughout the system. Electrical and mechanical

components shall be organized in plug-in assemblies or modules whenever practical and

shall be shelf-mounted, unless noted otherwise.

(2)Components mounted on printed circuit (PC) cards and weighing more than one-half ounce

or with a displacement of more than 1/2 cubic inch shall have a mechanical attachment to

the card which is separate from any electrical connection.

(3)The Contractor shall organize the printed circuit wiring so that wires serving the same

function shall be connected to the same terminal of PC cards. PC cards containing the same

circuitry shall be interchangeable between subsystems.

(4)The design and construction of PC cards of the same subsystem shall be the same. Cards

of different subsystems shall be of the same design and construction wherever practicable.

664

(5)Adjustable components for electronic equipment shall be avoided wherever possible by the

use of appropriate circuitry, stable components, and high-tolerance circuits. Adjustable

components, where used, shall have locking devices or shall be self-locking to prevent

inadvertent operation or drift. Whenever practical, two or more points of adjustment which

are required during the same tune-up operation shall be located within 12 inches of each

other and in such a way that they can be operated by one person. Interacting adjustments

will not be acceptable. The replacement of a component or PC card with a spare shall not

require compensating adjustments to other components or modules.

(6)Test points shall be provided for checking essential voltages and wave forms and for

injecting test signals. Test points shall permit detection of defective PC boards and

equipment modules without the disconnection of wires. All test points shall be readily

accessible when the equipment is in the normal operating position and shall be clearly

labeled. Test points shall be capable of accepting probes and connectors used with standard

test equipment such as voltmeters and oscilloscopes.

(7)When built-in indicators or meters are associated with adjustments, the adjustment point

shall be sufficiently close to the associated indicator so that the adjustments may be

manipulated and the indicator observed simultaneously by one person. Built-in indicators

or meters shall be provided when frequent observation or adjustments are necessary or

when portable test equipment will not provide the necessary information or accuracy.

(d)Environment.
(1)All equipment housed in signal equipment housings or cases shall function in accordance

with these specifications and within an operating temperature range of -40°F to +158°F at

a relative humidity of 5% to 95% non-condensing, per AREMA C&S Manual, Part 11.5.1

for Class C environment requirements.

(2)Signal equipment installed outside of the signal housing shall be designed to operate

satisfactorily in all weather conditions such as rain, snow, temperature, and humidity

variations. This shall be determined by the climatic conditions from data published by

NOAA for the Vermont area. In addition, the recommendations of the AREMA C&S

Manual, Part 11.5.1, shall be followed to minimize condensation and frost buildup.

(3)The electrical environment that the signal equipment will be exposed to shall be determined

by the Contractor. Design, construction, and field application of the signal system shall

prevent interference by the site environment from affecting the signal system operation.

Possible sources of interference include, but are not limited to, 60 Hz AC electricity,

rotating machinery, poor ballast conditions, and lightning.

664

(e)Quality Assurance.
(1)The design and workmanship of the apparatus will comply in every respect with the

requirements of 49 C.F.R. Part 236.

(2)Unless otherwise specified herein, all items furnished or installed shall be in accordance

with the applicable standards, practices, and recommendations of the Agency, Operating

Railroad, AREMA, NEMA, and the Institute of Electrical and Electronic Engineers, and

the requirements of 49 C.F.R. Part 234 and 49 C.F.R. Part 236.

(5)All apparatuses, including the signal junction boxes and all other miscellaneous

components that form a complete system, shall be furnished completely factory wired and

tested.

(6)The Contractor shall verify the testing and inspection of the equipment prior to shipment

in accordance with the approved factory test as specified in Subsection 664.07(b) and

inspection as specified in Subsection 664.07(a)(3).

(7)All miscellaneous components and products shall be new, free of manufacturing defects,

and clearly and permanently labeled with value or type identification.

(8)All electrical components shall be rated to operate at power, voltage, current, and

temperature levels exceeding by 20% those which the components will be subject to in

service, unless otherwise specified herein.

(9)The AHCWS shall be designed to meet the requirements of the MUTCD.
(f)AHCWS Materials.
(1)The Contractor shall ensure proper integration of components into a complete highway

crossing signal layout. In the event the Contractor’s proposed equipment does not fit the

vital design specified, it will be the Contractor’s responsibility to modify the design and

submit an alternate design for approval.

(2)Highway crossing warning equipment shall meet the requirements established by AREMA

C&S Manual, Part 3.3.1 and AREMA C&S Manual, Part 3.1.15, except where such

instructions and requisites conflict with this specification.

(3)The active warning system configurations shall be as shown on the Plans.

664

664.06INSTALLATION OF AHCWS

(a)General Requirements. All work shall be accomplished in a manner that will protect the crossing

throughout the prosecution of work and ensure the safety of workers, pedestrians, and vehicular

traffic.

(b)Excavation and Backfill.
(1)Excavation of Pavements. Excavation of pavements for the installation of signal conduit

shall be performed in accordance with Subsection 203.07. Cuts in the pavement shall be

made with a concrete saw to a minimum depth of 2 inches along the neat lines of the area

to be removed.

(2)Excavation for Conduit and Buried Cable. Trenches necessary for placing conduit and

buried cable shall be excavated in accordance with Section 204. The bottom of conduit

trench shall be graded to a pitch of not less than 3 inches per 100 feet.

(3)Excavation for Signal Foundations. Excavation for signal foundations shall be performed

in accordance with Section 204.

(4)Backfill. Backfill shall be placed and compacted as specified in Subsection 204.05.
(5)Buried Cable. All buried cable shall be marked with 6-inch wide yellow plastic marking

tape as specified in Subsection 781.03(j)(31). The tape shall be placed in the backfill 12

inches below finished grade.

(c)Installation.
(1)General Requirements.
a.AHCWS equipment shall be installed in accordance with the approved working

drawings.

b.AHCWS equipment shall be mounted in such a manner as to provide for easy

access to test points, indicators, and adjustments.

c.Track termination diodes and shunts shall be installed in accordance with the

manufacturer’s standard and at locations shown on the approved working drawings.

664

d.Electrical work and materials shall be subject to inspection and approval of the state

or municipal electrical inspector, as applicable.

e.All work shall meet the requirements of the National Electrical Code and the

National Electrical Safety Code.

(2)Foundations and Cribbing.
a.At all locations where precast or cast-in-place concrete foundations are installed, a

crushed stone base as specified in Subsection 704.06 shall be placed and compacted

on the accepted subgrade to a total depth of not less than 4 inches after compaction.

b.When placing foundations, the Contractor shall exercise care to ensure that anchor

bolts are not bent or the threads damaged. All anchor bolt threads, washers, and

nuts shall be protected by applying friction tape until such time as the unit to be

supported is installed. Anchor bolts requiring leveling nuts shall be of sufficient

length and size for the load application and have the necessary concrete coverage

to ensure that it does not push out under compression or pull out under tension.

c.Foundations and pads shall be installed level and plumb.
d.Finishing of foundations exposed to view shall be in accordance with Subsection

541.14

e.After backfilling foundations, the Contractor shall ensure that the foundation is

plumb and level. The top of foundation shall be at the same elevation as the crown

of the roadway and no more than 4 inches above the final top of grade.

f.Cribbing shall be installed as shown on the Plans. Each tier of timber cribbing shall

be drift bolted to the one upon which it rests with 3/4-inch galvanized drift bolts of

sufficient length to extend through two tiers and not less than 4 inches into the third

tier. Concrete or steel cribbing shall be installed in accordance with the

manufacturer’s instructions.

g.The filling of the interior of the crib shall closely follow the erection of the

successive tiers and at no time shall the cribbing be laid up higher than 3 feet above

the backfilled portion.

h.The cribbing shall be installed so as to have a minimum perimeter walkway around

the case or signal of 6 feet.

664

(3)Flashing Light Signal Installation.
a.The flashing light signal mast shall be securely fastened within the split base in a

manner such as the distance between the split halves of the base shall be equal. The

heads of the bolts in the base assembly shall be squared with each other and facing

oncoming highway traffic.

b.The base shall be securely fastened to the concrete foundation with the hardware

provided for that purpose. The mast shall be plumb when the base assembly is

fastened to the foundation. Shims, spacers, or other filler devices shall not be used

to level and plumb flashing light signal equipment.

c.A hole shall be factory-drilled in the mast for the bottom cross-arm. The center line

of the hole shall be located so that, when the cross-arm with light unit is attached

thereto, the lowest part of the light assembly shall be between 7-1/2 feet and 9-1/2

feet above the crown of the roadway. Holes for additional cross-arms, when

required, shall be located and drilled in the field after the bottom cross-arm has been

secured to the mast. The centerline of the additional light units shall be 23 inches

above the centerline of the lower light unit.

d.Electronic bells shall be installed on the top of the mast of the flashing light unit as

shown on the Plans. If a bell is not specified, then a pinnacle shall be provided.

e.Underground cables shall be installed in the split base junction box. The cables

shall be pot headed, tagged, and terminated. No. 10 AWG wire shall be run to the

cross-arm junction box in a manner as specified in the AREMA C&S Manual, Part

10.4.1.

1.Wiring for the flashing light units and the bell shall be 37 strand, No. 10

AWG.

2.Where additional light units are used, wiring for these units shall be run

from the corresponding terminals in the next lowest cross-arm junction box.

3.Wiring for bells shall go directly from the bottom cross-arm junction box to

the bell.

4.Terminations for flasher unit and bell wiring shall be solderless

compression type terminals as specified in Subsection 781.03(j)(13).

664

f.With AC power off and standby battery in a fully charged condition, the lamp

voltage shall be adjusted to 9.5 volts for LED lights (measured at the lamp) by

varying the resistor for the flasher unit.

g.The front lights of the flashing light unit shall be focused to provide maximum

visibility for oncoming highway traffic. The back lights of the flashing light unit

shall be focused to provide close up visibility for oncoming highway traffic from

the opposite direction.

(4)Cantilever-Gate Combination Installation.
a.The base of the cantilever shall be securely fastened to the concrete foundation with

the hardware provided for that purpose. The mast shall be plumb when the base

assembly is fastened to the foundation. Shims, spacers, or other filler devices shall

not be used to level and plumb cantilever layouts. Leveling nuts shall be installed

prior to installation of the signal.

b.The railroad crossing sign and ENS sign for the cantilever arm shall be securely

fastened with the hardware provided for that purpose as per the manufacturer’s

recommendation.

c.Installation of the cantilever shall provide a minimum clearance of 17-1/2 feet

above the roadway.

d.Gate mechanisms and gate arms shall be installed per the manufacturer’s

instructions. The Contractor shall install light units, gate arm deflectors, high wind

gate arm supports, off set conversions brackets and all equipment required for a

complete assembly.

(5)Automatic Highway Crossing Warning Gate Installation.
a.The gate arm tip light shall be steadily illuminated and the other gate arm lights

shall flash in unison with the mast or cantilever mounted lights.

b.Sidewalk gate tip lights shall be steadily illuminated.
c.Gate lights shall be adjustable for installations not perpendicular to the tracks.

664

d.Gate arm counterweights shall be adjusted in accordance with the manufacturer’s

standards for the length of gate arm specified.

e.Ground mount gate masts shall be securely fastened within the junction box base

in a manner such that the distance between the split halves of the base shall be equal

when tightened.

f.The base shall be securely fastened to the concrete foundation with the hardware

provided for that purpose.

g.The mast shall be plumb when the base assembly is fastened to the foundation.

Shims, spacers, or other fillers shall not be used to level and plumb highway

crossing warning gates.

h.Gate operating mechanism, including counterweight arms, shall be securely

fastened to the mast with the hardware provided for that purpose.

i.The mechanism shall be located on the pole in a position that shall allow for the

gate arms, when in the down position, to be not more than 4-1/2 feet, nor less than

3-1/2 feet, above the crown of the roadway.

j.Underground cables shall be installed in the split base junction box. The cables

shall be pot headed, tagged, and terminated.

(6)Cable Installation.
a.General Requirements.
1.The installation of wire and cable shall conform to AREMA C&S Manual,

Part 10.4.1, except as modified herein.

2.Prior to the installation of underground cables, a sand bed, using material in

accordance with Subsection 703.03, shall be compacted to a depth of not

less than 3 inches on the accepted subgrade. Following the installation of

the cables, sand backfill shall be placed and compacted with hand tools

around and over the cables in 4-inch to 6-inch layers, to a uniform depth not

less than 8 inches without damage to the cables.

3.The Contractor shall provide sufficient slack in cable conductors at all

terminating posts to enable three re-terminations of the conductor due to

broken eyelets without re-servicing or re-pot heading the cable.

664

4.Cables shall not be bent to a radius less than 10 times the diameter of the

cable during installation, or as finally installed.

5.All cable runs shall be continuous without splices between cable

terminating locations.

6.Tags to identify cables shall be of plastic material. Tags shall be lettered to

correspond with the cable destination and the number of conductors in the

cable. The type of tag to be used shall be as specified in Subsection

781.03(j)(14)

7.All cables shall be terminated in conductor order. Individual cable

conductors shall be identified at each cable termination with plastic tags as

specified herein. All spare conductors in each cable shall be terminated and

identified.

8.All cable entrance openings in equipment enclosures and junction boxes

shall be sealed with a pliable sealing compound after the cable is in place.

Sealing compound shall be used to seal the area around cable where the

cable emerges from the end of a conduit, pipe, or duct bank. All spare

conduits shall be sealed or plugged in accordance with AREMA C&S

Manual, Part 15.2.15.

9.A suitable lubricating medium, non-injurious to the cable insulation, shall

be used when pulling cables into conduit or pipe.

10.Wherever multiple conductor cables are terminated, the outer sheath of the

cable shall be carefully removed to the point of cable entrance. At the end

of the cable sheath or covering, two layers of plastic electrical tape shall be

applied.

11.When paralleling the tracks, cable shall be buried at a minimum depth of 30

inches below finished earth or ballast. Cable shall be laid loosely in the

trench with a sand bed and backfill as specified. When passing under tracks,

cable that is not protected in conduit shall be buried a minimum depth of 48

inches below the top of tie.

12.Upon request, and only under extreme circumstances and because of

installation hardship, the Engineer may allow installation of a to a depth of

less than 30 inches. The cable shall be protected in a manner as approved

by the Engineer.

664

13.Whenever any signal cable is to pass under pavement or a roadway, if

existing conduit is not provided, the cable shall be installed in a 4-inch

galvanized steel conduit, as specified in Subsection 752.06, and the conduit

shall extend 20 feet beyond the edges of the pavement.

14.Where cable leaves the ground at locations other than buildings or in

foundations, it shall be protected by a bootleg or other covering extending

above the ground line. The top of such protective coverings shall be filled

with a sealing compound in accordance with AREMA C&S Manual, Part

15.2.15.

15.The Contractor shall install polyethylene cable marking tape at a depth of

approximately 12 inches below final grade while backfilling each cable

trench. This tape shall be as specified in Subsection 664.06(b)(5).

16.The pot heading of buried cabled shall be applied whenever cable is

terminated in signal equipment and such termination is within 2 feet of the

grade level. This neoprene end seal pot head shall be installed in accordance

with the manufacturer’s instructions.

(7)Rail and Turnout Bonding Installation.
a.Non-Insulated Joint Bars. All non-insulated joint bars in the crossing circuited

territory shall be bonded with one bond installed on the field side of the joint bars.

b.Turnouts. All turnouts within the crossing approach shall be furnished with fouling

wires and switch heel bonds. Track switch, frog fouling bonds, and track circuit

connections shall plug-type rail web bonds.

c.Exothermically Welded Rail Head.
1.The surfaces of the rails where the bond is to be applied shall be ground

clean with a reinforced grinding wheel, of a type recommended by the

bonding material manufacturer. Vitrified grinding wheels shall not be used.

After grinding, the surface shall be cleaned with an approved non-toxic

solvent to remove all traces of grease and dirt. After the surface has been

ground and cleaned, it shall be heated to drive out any moisture. The bond

wire shall then be welded to the rail in a manner to ensure a thorough

mechanical and electrical connection.

664

2.The Contractor shall ensure that each bond connection is thoroughly welded

to the rail. The Engineer reserves the right to require a test of each weld.

3.The Contractor shall demonstrate that the bonding is in accordance with the

requirements of this section and as specified in AREMA C&S Manual, Part

8.1.20, AREMA C&S Manual, Part 8.1.30, and AREMA C&S Manual, Part

8.6.40.

d.Plug-Type Rail Web Track Circuit Connections.
1.Track circuit connectors shall be furnished and installed in accordance with

AREMA C&S Manual, Part 8.1.20 and AREMA C&S Manual, Part 8.1.25

for Type 2 plugs. The opposite end of the connectors shall have a 7-inch

length of turned bond strand with a compression sleeve installed for

connection to bond strand wires.

2.Rail shall be drilled in accordance with AREMA C&S Manual, Part 8.6.25.

Rail shall be drilled with an approved 3/8-inch bonding drill bit and drill

normally used for this purpose to permit the application of the bond to the

rail web.

3.No hole shall be drilled through the rail brand. Holes shall be drilled within

± 3/16 inch of the neutral axis of the rail. All holes shall be clean and

deburred. Bond wires shall be installed on the same day as the hole is

drilled. In the event that bond wires cannot be installed on the same day, the

bond hole shall be protected against the elements with a suitable plug.

4.Plugs shall be driven with a hammer approximately three pounds in weight,

and when in-place shall be tight to provide the best possible contact

throughout the web of the rail.

5.Track circuit connectors shall be furnished and installed with insulated bond

strand cable. The bond strand shall have a nominal diameter of 0.200 inch

and be jacketed with 3/32-inch rubber compound. The bond strand shall be

connected to the solid No. 6 AWG insulated twisted track wire with

compression sleeves and taped and insulated to prevent corrosion. The

connection between track wire and bond strand shall be housed in rubber

water hosing to prevent damage from ballast and frost in the ground.

664

6.The underground cable shall be stripped back a sufficient distance for the

exposed conductor to be fully inserted into the compression sleeve. The

sleeve shall then be compressed with the type of compression tool designed

for that purpose. The sleeve shall then be covered with two layers of vinyl

plastic electrical tape.

7.A 24-inch piece of hose, as specified in Subsection 781.03(j)(17)b.1., shall

be located beneath the rail base and sealed with sealing compound in

accordance with the AREMA C&S Manual, Part 15.2.15.

8.Any track circuit connection installed by the Contractor that is found to be

defective prior to acceptance shall be removed and a new track circuit

connection installed at no additional cost to the Agency.

9.Care shall be taken to avoid excessive slack in the bond conductor to prevent

vandalism. A connector sleeve shall be used on the base of the rail.

e.Plug-Type Rail Web Turnout Bonding.
1.Turnout bonding connectors shall be furnished and installed in accordance

with AREMA C&S Manual, Part 8.1.20 and AREMA C&S Manual, Part

8.1.25 for Type 2 plugs.

2.Rail shall be drilled in accordance with AREMA C&S Manual, Part 8.6.25.

Rail shall be drilled with an approved 3/8-inch bonding drill bit and drill

normally used for this purpose to permit the application of the bond to the

rail web.

3.No hole shall be drilled through the rail brand. Holes shall be drilled within

± 3/16 inch of the neutral axis of the rail. All holes shall be clean and

deburred. Bond wires shall be installed on the same day as the hole is

drilled. If bond wires cannot be installed on the same day, the bond hole

shall be protected against the elements with a suitable plug.

4.Plugs shall be driven with a hammer approximately three pounds in weight,

and when in-place shall be tight to provide the best possible contact

throughout the web of the rail.

664

5.Fouling bond wires for all turnouts within the crossing approach shall be

installed as close as practicable to the transposition joints. The holes for

bond wires shall be located 2-1/2 inches apart and centered above a tie bay.

6.The fouling wires shall be installed so as to allow for the plug end of the

one wire to be placed on the outside of the far rail and the other end of the

inside of the opposite far rail. The second wire installation shall be the

reverse of the first wire.

7.Fouling wire shall be stapled to separate ties, 1-1/2 inches below the top of

tie, opposite each other in the same tie bay. The fouling wires shall be

installed to avoid touching the tie plates. Fouling wires shall be left exposed

to allow visual inspection.

8.Any bond, weld, or connection installed by the Contractor that is found to

be defective prior to acceptance shall be removed and a new bond installed

at no additional cost to the Agency.

f.Existing Bonding. If existing rail bonding is in place on the approach circuits, then

the Contractor shall inspect and verify that all such bonding, including track

switches, is in accordance with these specifications. If additional rail bonding, or

rail bonding corrections, is required then the Contractor shall correct any such

deficient existing rail bonding at no cost to the Agency in accordance with these

specifications, or as directed by the Engineer. Final determination of bonding

requirements shall be approved by the Engineer and Railroad.

(8)Installation of AHCWS Shelters and Cases.
a.Each AHCWS shelter shall be mounted level and plumb using the foundation

leveling system provided as part of the shelter.

b.Cable entrance pipes shall be installed through the cable knockout holes provided

in the floor of the house behind the terminal boards.

c.The AHCWS shelter or case shall be grounded as specified in Subsection

(g)(9) and Subsection 781.03(j)(22)

d.Cables shall enter shelters by entrance knockouts and fittings and entrance pipes

provided. Cables shall be dressed, pot headed, tagged, and terminated as specified

in Subsection 664.06(c)(6).

664

e.Relays shall be installed on the relay plug-boards corresponding to the relay

nomenclature and securely fastened in place with the hardware provided.

f.Batteries shall be installed on battery trays. Battery posts shall be coated with

approved grease and battery connectors shall be securely fastened to the battery

posts.

g.Manual control boxes shall be mounted and wired in accordance with the approved

working drawings.

h.Grade crossing predicator, motion sensor, or similar solid-state equipment, as

shown on the approved working drawings, shall be shelf mounted with rubber

matting under the units.

i.AHCWS shelters and cases, if of sheet steel construction, shall be painted as

specified in Subsection 781.03(g)(12).

(9)Metered Power Service Grounding. Power service equipment grounding shall be installed

in accordance with the National Electrical Code and the power company’s requirements.

(10)Signs. Two signs shall be mounted to the AHCWS masts, one on each side of the crossing

on the right-hand side of the driver approaching the crossing. One sign shall be mounted

on the signal house or case. All signs shall be mounted in a manner approved by the

Engineer. The signs shall conform to the applicable Standard Drawings.

(11)Retirement and Disposal of Existing Equipment. All retired existing AHCWS equipment

or passive crossing warning devices shall be removed by the Contractor and transported to

a site designated by the Engineer.

(12)Protective Service Costs. Following the date of in-service operation, all railroad flagging

and related crossing protection expense, during periods that the warning system fails to

operate as specified in this section, shall be borne by the Contractor at no additional cost

to the Agency until the system is accepted by the Agency.

664.07TESTING OF AHCWS

(a)Quality Assurance Testing Procedures.
(1)All test procedures and inspection procedures shall be subject to the approval of the

Engineer and shall comply with all FRA rules and regulations.

664

(2)Test equipment of the proper type, capacity, range, and accuracy shall be supplied by the

Contractor to perform the required tests and inspections. This equipment shall be in good

working order and properly calibrated at the time the tests or inspections are conducted.

(3)Each component and unit of the AHCWS shall have an inspection performed at its point

of manufacture, and evidence of this inspection and acceptability shall be indicated on the

item where practicable.

(5)All approved system and subsystem tests to demonstrate that the installation meets these

specifications and design requirements shall be completed prior to any operational testing

of systems or subsystems.

(6)No more than 3 days prior to placing in service, the Contractor shall adjust all rectifiers

and DC power supplies for maximum output for a period of 24 hours. Following this

operation, the Contractor shall adjust the output in excess of the load requirements in

accordance with the battery manufacturer’s recommendations.

(7)The Engineer and the Operating Railroad will have the right to witness any or all field tests

conducted. The Engineer and the Operating Railroad shall be notified in writing at least 48

hours prior to each field test. No part of the AHCWS shall be placed in service without an

authorized representative of the Agency and the Operating Railroad being present and

witnessing the in-service tests, unless otherwise agreed by the Engineer.

(8)The work shall include all tests required to ensure the proper and safe operation of all

systems and subsystems and to prove the adequacy and acceptability of the total installation

specified herein. The tests to be performed shall cause each system and subsystem to be

sequenced through its required operations, including the imposition of simulated

conditions to prove that the installation complies with all specified fail-safe requirements.

(9)In the event that the system does not meet the requirements of this section, all deficiencies

shall be corrected and retested to prove compliance, at no additional cost to the Agency.

(b)Factory Test Procedures.
(1)Confirmation shall be provided by the Contractor that all required factory tests of systems,

subsystems, assemblies, subassemblies, and components supplied under this Contract have

been performed. These tests shall verify design and name-plate ratings and adequate and

proper performance.

664

(2)All vital systems, subsystems, and equipment shall be inspected and tested.
(3)Non-vital components, those not related to fail-safe circuits, may be tested on a sampling

basis. An approved number of randomly selected components or units from the

manufacturing process shall be tested to ensure the adequacy and acceptability of all

components and units produced.

(4)When test results are not recorded on a test-data plate affixed to the equipment or unit,

certified test reports shall be furnished for each item at the time of delivery in a form and

format suitable for regular office file record keeping.

(c)Factory Tests and Instructions.
(1)Vital Relay Tests. All DC vital relays shall be factory tested and inspected in accordance

with the AREMA C&S Manual, Part 6.4.1.

(2)Wired AHCWS Shelters and Cases.
a.Operational and Wiring Verification Test. Each AHCWS shelter and case shall be

wired complete at the point of assembly, with all equipment installed. An

operational and wiring verification test shall be made in accordance with the

approved design drawings. Functions external to the housing shall be simulated

where required.

b.Energy Distribution Tests. Energy distribution tests shall include, but not be limited

to, the following:

1.All fuses shall be removed and circuit breakers placed in the open position.
2.All over-current devices shall be of the sizes shown on the approved design

drawings.

3.All energy distribution shall be checked using a resistance test instrument

to verify agreement with the approved design drawings.

4.All wire gauges shall be verified as matching that called for on the approved

design drawings. All incorrect wire sizes shall be replaced with the proper

size wire.

5.Each energy bus shall be tested to all other energy buses to ensure that no

crosses exist.

664

6.During energy distribution breakdown, a wire count on each terminal, relay

contact, etc. shall be taken to ensure that only the number of wires called

for on the approved design drawings are present at each terminal, relay

contact, etc. Any discrepancies found shall be corrected and excess wires,

if found, shall be removed.

7.Tags shall be verified for proper nomenclature and terminal location.
8.All power supplies shall be checked for correct setting and quantities.
c.Wiring Verification Test. All circuitry shall be checked for accuracy against the

approved design drawings. Tests may be done with energy on or off and shall verify

the following:

1.Point to point wiring.
2.During wire verification test, a wire count on each terminal, relay contact,

etc. shall be taken to ensure that only the number of wires called for on the

approved design drawings is present at each terminal, relay contact, etc.

Any discrepancies found shall be corrected.

3.Tags and nomenclature where applicable.
4.That all components, relays, resistors, etc. are the same as called for on the

approved circuit drawings and are located in the proper positions.

d.Vital Circuit Tests.
1.Tests shall be conducted with energy on during simulation testing.
2.All vital circuits shall be tested to ensure that the opening of each contact in

a control circuit cuts off the control current under the conditions shown on

the approved design drawings following through all multiple circuits and

cut arounds. When a circuit is broken by a relay contact twice or when it is

broken by some other relay contact, whose coil circuit is opened by opening

the relay, the wires in the circuit shall be disconnected in addition to opening

the relay.

3.Adjustments and corrections of defects in the housing wiring shall be made

as necessary to obtain proper operation.

4.All design changes found necessary to obtain proper operation shall be

submitted to the Engineer for approval.

664

e.Other Factory Tests. Factory tests and inspections of other components, products,

and subsystems shall be as specified elsewhere in this section.

(d)Field Test Procedures.
(1)The field tests performed shall cause each installed system and subsystem to be sequenced

through its required operations, including the imposition of simulated conditions, to

demonstrate that the installation complies with all specified fail-safe design requirements

and operational functions.

(2)The quality of the installation shall be demonstrated by field tests for continuity, insulation

resistance, resistance of ground connections, circuit breakdown, visual inspection, and any

other tests required by this section. These tests shall be performed prior to any operational

testing of systems or subsystems.

(3)The Contractor’s test procedures shall consist of pre-printed data sheets or inspection

sheets for each test. When completed by the field test personnel and checked for accuracy

and completeness, the sheet shall be submitted as the test report.

(4)When tests require specific meter or test instrument readings, the pre-printed data sheet

shall show the allowable range of values for each part of the test. The test report shall also

contain a check-off system for each action and a blank space adjacent to the expected value

in which to record the test readings.

(5)The test report shall also contain a final description sheet on which the Contractor shall

record discrepancies found and action taken. This document shall be furnished to the

Engineer.

(6)All test reports shall be dated and signed by the responsible employee of the Contractor or

subcontractor on the day the test is performed. Space shall also be provided for the

signature of those witnessing the test, including the Engineer and Operating Railroad

inspector.

(7)The report shall show the specific test instruments used on each test, with the instruments

identified by name, type, serial number, and calibration due date.

(8)Should an error be discovered during field testing due to field wiring and connections that

do not agree with the approved design drawings, the Contractor may correct such errors

without prior approval of the Engineer. The Contractor shall not, however, make any

changes which affect the safety of operation of the approved circuits as designed without

prior written approval of the Engineer.

664

(9)The Engineer will make all final determinations as to whether only a part, or the whole test,

shall be rerun when any specific field test does not meet the requirements specified for the

test.

(10)Any changes made after completion of the test procedure shall be retested in accordance

with the applicable test procedure.

(e)Field Tests and Inspection.
(1)General Field Tests. General field tests shall include, but not be limited to, the following:
a.Ground verification test.
b.Power racks – energy distribution system and failure alarm checks.
c.Breakdown test of all vital circuitry.
d.Wiring verification of all non-vital circuitry.
e.Vital function tests.
f.Operating tests.
g.All applicable tests prescribed by AREMA C&S Manual, Part 2.4.1, where the

AREMA inspections and tests do not conflict with the requirements of these

specifications.

(2)Specific Field Tests.
a.Ground Resistance Testing.
1.Testing. The Contractor shall perform testing of all signal locations using a

ground resistance direct-reading single test meter using the alternating

current fall-of-potential method and two reference electrodes.

2.Test Procedure.
i.The ground electrode to be tested and the two reference electrodes

shall be oriented in a straight line spaced a minimum of 50 feet apart.

ii. The two reference electrodes shall be driven 5 feet deep.

664

iii. The maximum resistance value goal of the main ground for wayside

outdoor locations shall be within a range of 1 ohm to 5 ohms. If it is

found that the resistance value of the main ground exceeds this

range, the Contractor shall install additional ground rods, up to a

maximum of 4. Additional ground rods shall be spaced no less than

10 feet apart. If, after additional ground rods are installed, excessive

resistance readings persist, the Contractor shall notify the Engineer.

iv. The Contractor may propose an alternate method to the fall-of-

potential method for approval by the Engineer in consultation with

the Operating Railroad. Any such alternate method shall be

supported by documentation that validates that the resultant

measurement readings are analogous.

b.Insulation Resistance Tests. The procedure for testing insulation resistance shall

include tests to verify the following:

1.All wire and cable installed for vital circuits along the right-of-way and wire

and cable entering or leaving wayside instrument housings shall be tested

after installation to ensure that insulation of wires and cable and connected

equipment meet the specified resistance value. A direct reading instrument,

having a 0-megohm to 200-megohm-scale range and a self-contained DC

power supply rated 500 volts minimum to 1,000 volts maximum, shall be

used to measure the insulation resistance. Resistance between conductors

and ground shall not be less than that specified in 49 C.F.R. § 234.267.

2.The insulation resistance of each conductor to ground and between each

conductor and all other conductors in each multi-conductor cable shall be

tested. Power sources, made grounds, and connections to the rails shall be

disconnected from the circuits during testing.

3.The point used as ground shall be the most convenient ground available.
4.Insulation resistance test values shall be recorded on approved insulation

resistance record forms and turned over to the Engineer upon their

acceptance of this test requirement.

664

c.Vital Relays.
1.All DC vital relays shall be tested for pick-up and drop-away values. These

values shall be in accordance with field requirement values stated in the

AREMA C&S Manual, Part 6.4.1, Table 641-1.

2.These measured values shall be recorded on the approved relay record forms

and turned over to the Engineer upon their acceptance of this test

requirement.

3.These tests shall be performed after the housing has been set.
d.Energy Distribution.
1.Energy-Off Tests. With all power to AHCWS instrument shelters or case

off, the following checks and tests shall be performed. These tests shall

include but not be limited to:

i.Verifying that circuit breaker size compares to that of the approved

design drawings.

ii. All energy distributions shall be checked using a resistance test

instrument to verify agreement with the approved fabrication

drawings.

iii. Wire gauges shall be compared with those called for on the approved

circuit drawings. All discrepancies in wire sizes shall be replaced

with the proper size wire.

iv. Terminal board tags shall be verified for proper nomenclature and

terminal location.

v.Each energy bus shall be tested to all other energy buses to ensure

that no crosses exist.

2.Energy-On Tests. Upon completion of the energy-off tests, the following

checks and tests shall be performed. These tests shall include, but not be

limited to, the following:

i.Inserting circuit breakers for power supply feeds and verifying

proper size according to the approved circuit drawings.

664

ii. Turning on energy feeds and testing operation of power transfer for

proper operation.

iii. Measuring and recording each AC voltage input.

iv. Measuring and recording each power supply or charger output

voltage.

v.Verifying that the proper voltage is present at all distribution points.

vi. Checking circuit power failure alarms, and all other alarms that

indicate to Central Control.

vii. Checking battery water level and specific gravity of all cells.

3.Circuit Continuity Tests. All wire and cable installed by the Contractor shall

be tested to verify the continuity of each conductor and that each conductor

is connected to the proper terminal as shown on the approved drawings.

Where parallel circuits exist, each parallel path shall be tested

independently to verify the continuity of each path.

4.Circuit Wiring Verification. All vital and non-vital circuit wiring shall be

checked for accuracy against the approved design drawings. Tests may be

performed with energy on or off and shall verify, but not be limited to, the

following:

i.Point to point wiring.

ii. A wiring count of all field installed wires shall be conducted for each

terminal, relay contact, etc. to ensure that only the number of wires

called for on the approved designed drawings is present at each

terminal, relay contact, etc. Any discrepancies found shall be

corrected.

iii. Tags and nomenclature where applicable.

iv. That all components, relays, resistors, etc. are the same as called for

on the approved circuit drawings and are located in the proper

positions.

664

5.Breakdown of Control Circuits.
i.All vital relay circuits shall be tested in their entirety for the correct

operation of and response to each contact on each circuit element,

such as relays and contactors. Where parallel paths exist, the tests

shall validate each path, and circuits shall be opened when required

to ensure the proper tests.

ii. Each circuit shall be tested by simulating all operating conditions to

verify that the circuit operates in accordance with these

specifications and approved submittals.

6.Power Tests. The following power tests shall be performed and recorded:
i.The voltage of the main power feeders shall be measured and

recorded.

ii. A check of all circuit breakers shall be performed for correct size

and type.

iii. All power supplies, battery chargers, and batteries shall be checked

for correct setting and quantities.

iv. Bus-to-bus checks shall be made to determine that no shorts,

crosses, or grounds exist.

7.AHCWS Operational Tests.
i.A test train shall be used to verify that any AHCWS motion sensor

or predictor equipment installed under this Contract has the

specified warning time at each highway grade crossing.

ii. Tests of the AHCWS shall be performed in both directions at

various speeds to the satisfaction of the Engineer.

iii. As an alternative to test train operation, the Contractor may propose

a field train simulation test procedure for the approval of the

Engineer. Any such alternate procedure proposed shall be

accompanied by verification documentation of such field tests

performed by the Contractor for similar AHCWS installation

projects.

664

664.08TRAINING FOR SYSTEMS. The Contractor shall provide a qualified field engineer to instruct

maintenance personnel on recommended initial setup, troubleshooting, and maintenance procedures for

predictor, motion sensor, or Style C systems. This training course shall be conducted on the Operating

Railroad’s property and will be limited to two 8-hour days of instruction. The Contractor shall submit a

request for the Agency to arrange the training 14 calendar days in advance of the proposed date.

664.09METHOD OF MEASUREMENT. The quantity of Railroad-Highway Crossing Active Warning

System to be measured for payment will be on a lump sum basis for each system installed in the complete

and accepted work.

664.10BASIS OF PAYMENT. The accepted quantity of Railroad-Highway Crossing Active Warning

System at the location specified will be paid at the Contract lump sum price. Payment will be full

compensation for designing, furnishing, transporting, handling, placing, and testing and placing in service

the materials and equipment specified, including all new equipment, as-built signal circuits for placement

in the shelter, insulated joints, and traffic pre-emption interconnection; concrete, backfill, permanent

number signs, excavation, trench excavation, trench pavement replacement, and removal of existing signal

lights; resurfacing or other restoration work; and for furnishing all labor, tools, equipment, and incidentals

necessary to complete the work.

Payment will be made under:

Pay Item Pay Unit

00 Railroad-Highway Crossing Active Warning System ..............................Lump Sum

665

6-309SECTION 665 – RAILROAD TURNOUT CONSTRUCTION

665.01DESCRIPTION . This work shall consist of providing new welded railroad turnouts, including a

complete timber switch tie set; connecting the turnout to the existing track, including realignment of existing track, installation of new rail, welds, and compromise welds, as required; raising, aligning, and surfacing turnouts and crossovers; and the removal of turnouts and crossovers.

665.02MATERIALS . Materials shall meet the r equirements of the following subsections:

Aggregate for Railroad Ballast ................................ ................................ .................. 704.03 Switch Ties ................................ ................................ ................................ ................. 709.04(d) Tie Plugging Material ................................ ................................ ................................ 709.04(e) New Rail ................................ ................................ ................................ .................... 715.0 6(a) Railroad Turnouts ................................ ................................ ................................ ......715.07 Other Track Material (OTM) ................................ ................................ ..................... 715.0 8 New turnouts shall be of the rail section and weights shown on the Plans. Ballast shall be of the type shown on the Plans.

665.03SUBMITTALS . The following information shall be prepared and submitted for review and

approval by the Engineer . Submittals shall meet the requirements of Subse ction 105.0 6.

(a)Fabrication drawings shall be submitted in accordance with the requirements of Subsection 105.06 .

All details, dimensions, quantities, parts, specifications, and sections necessary to fabricate and assemble the turnout shall be included i n the submittal.

(b)A complete schedule of the materials proposed for installation and the source of the material.

Information to be provided on the rail shall include rail weight, rail section, drilling pattern, typical rail length, date rolled, and the name of the mill where the rail was rolled.

(c)Sub-assembly component and bolt certificates of origination.
(d)Source for ballast and gradation analysis of a sample from the ballast source.
(e)Manufacturer’s certificate of compliance for all materials that are incorporated into the work.
(f)Manufacturer’s cut sheet of lubricant or graphite for application to switch plates following the

cleaning of the plates.

Get an email when 664 changes

Vermont revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Vermont Standard Specifications for Construction, 2024 Edition. Pages 1049–1082 of 1,380. View official source ↗

Ask about this section

Scoped to Vermont 2018 Standard Specifications for Construction, Section 664 — RAILROAD SIGNALS. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.