B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
General Provisions (00100-00999)

541STRUCTURAL CONCRETE

VT · 2024 Standard Specifications✓ Full text on BuildSpecBook pages 681–729 Save this section

Ask about Section 541

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

541

5-267SECTION 541 – STRUCTURAL CONCRETE

541.01DESCRIPTION . This work shall consist of furnishing and placing Portland cement concrete for

structures and incidental construction. The Portland cement concrete may consist of a homogeneous mixture of Portland cement, fine aggregate, coarse aggregate, water, admixtures, and pozzolans, proportioned and mixed according to these specifications.

541.02MATERIALS . Materials shall meet the requirements of the following subsections:

Portland Cement ................................ ................................ ................................ ......... 701.02 Portland -Pozzolan Cement ................................ ................................ ......................... 701.04 Portland -Limestone Cement ................................ ................................ ...................... 701.05 Portland Blast -Furnace Slag Cement ................................ ................................ ......... 701.06 Ternary Blended Cement ................................ ................................ ........................... 701.07 Fine Aggregate for Concrete ................................ ................................ ...................... 704.01 Coarse Aggrega te for Concrete ................................ ................................ .................. 704.02 Lightweight Coarse Aggregate for Concrete ................................ ............................. 704.14 Lightweight Fine Aggregate for Concrete ................................ ................................ .704.19 Mortar, Type I ................................ ................................ ................................ ............ 707.01 (b) Mortar, Type IV ................................ ................................ ................................ ......... 707.0 1(e) Preformed Joint Filler, Cork, and Asphalt -Treated Felt ................................ ............ 707.0 6 Polyvinyl Chloride (PVC) Waterstop ................................ ................................ ........ 707.08 Concrete Bonding Systems ................................ ................................ ........................ 707.1 4 Steel for Corrugated Metal Forms ................................ ................................ ............. 715.03 Epoxy Bonding Systems ................................ ................................ ............................ 719.01 Concrete Curing Materials ................................ ................................ ......................... 725.01 Air-Entraining Admixtures ................................ ................................ ........................ 725.02(b) Retarding Admixtures ................................ ................................ ................................ 725.02(c) Water -Reducing Admixtures ................................ ................................ ..................... 725.02(e) Water -Reducing and Retarding Admixtures ................................ .............................. 725.02(f) Water -Reducing, High Range Admixtures ................................ ................................ 725.02(g) Water -Reducing, High Range, and Retarding Admixtures ................................ .......725.02(h) Accelerating Admixtures ................................ ................................ ........................... 725.02(i) Water -Reducing and Accele rating Admixtures ................................ ......................... 725.02(j) Specific Performance Admixtures ................................ ................................ ............. 725.02(k) Anti-Washout Admixtures ................................ ................................ ......................... 725.02(l) Pozzolans ................................ ................................ ................................ ................... 725.03(a) Silica Fume ................................ ................................ ................................ ................ 725.03(b) Ground Granulated Blast -Furnace Slag (GGBFS) ................................ .................... 725.03(c)

541

5-268Polystyrene Insulation Board ................................ ................................ ..................... 735.01

Blanket Insulati on Material ................................ ................................ ........................ 735.02 Pipe Insulation ................................ ................................ ................................ ........... 740.06 Water ................................ ................................ ................................ .......................... 745.01 Concrete Repair Materials ................................ ................................ ......................... 780.01 Normal weight coarse aggregate for superstructures shall be conditioned so that the total moisture percentage shall be the absorption percentage plus, at a minimum, 0.25% free moisture for the aggregate.

541.03CLASSIFICATION AND PROPORTIONING . Concrete shall meet the requirements specified in

Table 541.03A and shall be used as shown on the Plans. TABLE 541.03A – STRUCTURAL CONCRETE CLASSES AND PROPERTIES Concrete Type 1 Min. Cementitious Material (lbs/CY) 2 Max. W/CM Ratio Slump/Spread Range (in.) 3 Air Content Coarse Aggregate Gradation Table 56-Day Compressive Strength (psi) 4 Class HPAA 705 5 0.40 -- 7.0% ± 1.5% Table 704.02B 4,000 Class HPA 611 5 0.44 -- 7.0% ± 1.5% Table 704.02C 4,000 Class HPB 564 5 0.49 -- 7.0% ± 1.5% Table 704.02D 3,500 Class AA 705 6 0.40 -- 7.0% ± 1.5% Table 704.02B 4,000 Class A 660 6 0.44 -- 7.0% ± 1.5% Table 704.02C 4,000 Class B 611 6 0.49 -- 7.0% ± 1.5% Table 704.02C , Table 704.02D 3,500 Class C 564 6 0.49 -- 5.5% ± 1.5% Table 704.02C , Table 704.02D 3,000 Class D 470 6 0.58 -- 4.5% ± 1.5% Table 704.02C , Table 704.02D 2,500 Class SCC 7 TBD 8 0.44 TBD 9 7.0% ± 1.5% -- 4,000 Class LW 660 5 0.44 -- 7.0% ± 1.5% [Note 10] 4,000 Flowable Fill TBD 11 TBD 12 TBD 13 10% (min.) Table 704.01A 1,500 (max.) 14 Flowable Fill, Excavatable TBD 11 TBD 12 TBD 13 10% (min.) Table 704.01A 125 (max.) 14 1 HP = High Performance SCC = Self -Consolidating Concrete LW = Lightweight 2 If optimized gradation is used, the minimum cementitious material may be reduced as specified herein.

541 5-269 3 The mix shall not exhibit segregation at the slump/spread used at placement. If the Engineer suspects there is segregation, the Engineer will require a slump/spread test be performed by the Contractor to visually observe the characteristics of the mix. If, in the opinion of the Engineer, the mix does exhibit segregation, the load will be rejected and subsequent loads shall be tested for a minimum of three loads or until the problem is corrected. If the Contractor needs a concrete with a slump/spread greater than 8 inches, the Contractor shall propose to the Engineer to use an SCC mix, which shall be submitted to the Engineer for review and acceptance. 4 The concrete may be accepted if the design compressive strength from standard cured cylinders has been obtained at 28 days. Any 56 day acceptance cylinders shall be tested regardless of the results of earlier tests. 5 See Table 541.03B , Table 541.03C , Table 541.03D , Table 541.03E , Table 541.03F , and Table 541.03G for required cementitious materials. 6 A minimum 20% fly ash or 25% GGBFS replacement of total cement content is required . 7 The Contractor shall determine the surface resistivity in accordance with Subsection 541.03(b)(1) . 8 A minimum 20% fly ash or 25% GGBFS replacement of total cement content is required. Silica fume may be used as an additional replacement in conjunction with fly ash or GGBFS. 9 The Contractor shall determine the spread limits in accordance with Subsection 541.03(b)(2) . The spread shall be maintained within the determined spread limits for the placement. The mix shall not exhibit segregation. If the mix does exhibit segregation or exceeds the upper spread limit, the load shall be rejected . and subsequent loa ds shall be tested by the Contractor until the mix meets the allowable limits. The Engineer may perform a J -ring test at the time of placement if blocking is a concern. 10 Gradation for Class LW concrete shall meet the requirements of Subsection 704.14 . 11 A mineral admixture shall be used to replace a portion of the cement. The Contractor shall determine the replacement rate of cement. 12 The minimum amount of water shall be used to produce the desirable flow for the intended use without showing segregation. 13 The slump/spread (flowability) shall be such that material can completely fill the voids or area as needed without segregation. 14 A minimum of three cylinders per test age are required to constitute a test. If the average strength at 56 days exceeds 115% of the maximum strength, then payment for item 541.4500 or item 541.4600 will be 85% of the Contract bid price. TABLE 541.03B – REQUIRED CEMENTITIOUS MATERIALS, OPTION 1 Concrete Class Portland Cement or Portland -Limestone Cement (lbs/CY) Fly Ash (lbs/CY) Silica Fume Admixture (lbs/CY) Total Cementitious Materials (lbs/CY) HPAA 524 141 40 705 HPA 449 122 40 611 HPB 412 113 40 565 LW 528 132 0 660

541

5-270TABLE 541.03C – REQUIRED CEMENTITIOUS MATERIALS, OPTION 2

Concrete Class Portland Cement or Portland -Limestone Cement (lbs/CY) GGBFS (lbs/CY) Silica Fume Admixture (lbs/CY) Total Cementitious Materials (lbs/CY) HPAA 489 176 40 705 HPA 418 153 40 611 HPB 384 141 40 565 LW 495 165 0 660 TABLE 541.03D – REQUIRED CEMENTITIOUS MATERIALS, OPTION 3 Concrete Class Portland -Pozzolan Cement (5.0% to 9.0% Silica Fume)(lbs/CY) Fly Ash (lbs/CY) Total Cementitious Materials (lbs/CY) HPAA 564 141 705 HPA 489 122 611 HPB 452 113 565 TABLE 541.03E – REQUIRED CEMENTITIOUS MATERIALS, OPTION 4 Concrete Class Portland -Pozzolan Cement (5.0% to 9.0% Silica Fume)(lbs/CY) GGBFS (lbs/CY) Total Cementitious Materials (lbs/CY) HPAA 529 176 705 HPA 458 153 611 HPB 424 141 565 TABLE 541.03F – REQUIRED CEMENTITIOUS MATERIALS, OPTION 5 Concrete Class Ternary Blended Cement (5.0% to 9.0% Silica Fume, min. 20% GGBFS)(lbs/CY) Total Cementitious Materials (lbs/CY) HPAA 705 705 HPA 611 611 HPB 565 565 LW 660 660

541

5-271TABLE 541.03G – REQUIRED CEMENTITIOUS MATERIALS, OPTION 6

Concrete Class Portland Blast Furnace Slag Cement (Min 25.0% GGBFS)(lbs/CY) Silica Fume Admixture (lbs/CY) Total Cementitious Materials (lbs/CY) HPAA 665 40 705 HPA 571 40 611 HPB 525 40 565 LW 620 40 660 Unless otherwise specified in the Contract, Class B concrete shall be used. The Contractor, following mix design criteria and procedures outlined by the Agency, shall submit the mix design, required data, and test results to the Structural Concrete Engineer for review and acceptance. For initial submittals, a minimum of 14 calendar days shall be allowed for evaluation of the submitted mix design, test results and required data. No production of concrete for the proj ect shall commence until the Structural Concrete Engineer has reviewed and accepted the concrete mix design.

(a)Mix Design Information . The mix design shall contain the following information:
(1)Class of concrete.
(2)Type of mix, conventional or self-consolidating concrete (SCC).
(3)Saturated surface dry or dry weights (specify which).
(4)Aggregate types, sources, specific gravities, and absorption values.
(5)56 day design compressive strength, psi.
(6)Cementitious content and the amount of each, pounds per cubic yard.
(7)Air content and range, percent.
(8)56 day surface resistivity value.
(9)Determined spread lower limit and upper limit for SCC.

541

(10)Maximum water/cementitious materials (W/CM) ratio.
(11)Volumetric quantities of each material in the mix design.
(12)Design unit weight of the mix.
(13)Chemical admixture types, brand names, and dosages.
(b)Mix Qualification Tests. The following mix qualification tests shall be performed for Class SCC

concrete:

(1)The surface resistivity of the test mix shall be measured at 56 days based on the

requirements of AASHTO T 358. Results shall be categorized as Low, Very Low, or

Negligible in accordance with AASHTO T 358, Table 1. The surface resistivity may be

accepted prior to 56 days if the results meet these requirements. The 56 day test results

shall be completed and submitted regardless of the results of earlier tests.

(2)The Contractor shall determine the lower and upper spread limit. ASTM C1621 testing shall

be performed at the proposed upper and lower spread limits. Each spread limit shall not

exceed the blocking assessment “Minimal to Noticeable Blocking”. The slump cone shall

be filled in accordance with ASTM C1621, Procedure B. At both the upper and lower limits,

the visual stability index (VSI) shall not be greater than 1.

(c)Density of Class LW Concrete. The maximum unit density of Class LW concrete shall be 125

pounds per cubic foot when plastic.

At a minimum, an air entraining admixture shall be used. Other admixtures may be used in conjunction

with an air entraining admixture. The use of an accelerating or water-reducing and accelerating admixture

to alter the setting characteristics of concrete mixtures shall be permitted only with the approval of the

Engineer.

The use of chlorides or admixtures containing chlorides is prohibited. All admixtures will be considered

incidental to the work and included in the Contract unit price of the concrete.

The concrete materials shall be proportioned using the absolute volumes method in accordance with the

requirements for each class as specified in Table 541.03A. The volumetric proportioning method such as

that outlined in ACI 211.1, or other approved volumetric proportioning methods, shall be employed in the

mix design.

541

The Contractor may use industry methods to develop gradations not specified in Section 704 that are better

optimized to satisfy the required concrete characteristics. If the Contractor is using a combined gradation,

they shall provide the method or methods of how they will monitor gradation, the limits of the gradation

ranges, and the frequency of monitoring. The Contractor may also at the same time reduce the cementitious

content per cubic yard for the intended class of concrete if a trial batch is performed to demonstrate that

the minimum 56-day compressive strength is met, and the maximum W/CM ratio is not exceeded to obtain

a workable mix using an air content within the specified range. The trial batch shall be a minimum of 3

cubic yards. Workable mix shall be defined as a cohesive mix which, when tested for slump in accordance

with AASHTO T119, does not segregate or shear after removing the slump cone. Slump testing shall be

conducted at 3 inches and 7 inches and performed on an individual batch for each slump along with testing

the 56-day compressive strength in accordance with AASHTO T 22.

Production activities shall be conducted so that no intentional deviations are made from the reviewed and

accepted mix design. If test results indicate a failure to obtain the 56-day compressive strength as specified

in Table 541.03A based on tests conducted in accordance with AASHTO T 22, changes to the mix design

shall be made with no extra payment. Changes may include, but are not limited to, using additional cement,

changing the source of cement or aggregates, using a water reducer or other additives, or, if necessary,

obtaining concrete from another supplier.

After the materials to be furnished by the Contractor have been approved, no proposed change in the

source, proportions, or characteristics of the materials shall be made without the review and acceptance

of the Engineer. No new materials shall be used until such materials and their proportions have been

reviewed and accepted by the Engineer. In no case shall concrete from more than one mix design be

permitted to be used during the same pour without prior written approval of the Engineer.

The Engineer may order concrete production and delivery suspended and a new mix design or altered mix

design submitted if components or final product material characteristics are determined to be out of

tolerance, unsatisfactory, or if proposed changes in the source, proportions, or characteristics of the

materials are proposed. No production of concrete for the project shall resume until the Engineer has

reviewed and accepted the new or altered mix design. For evaluation, new mix design submittals shall be

considered as initial mix design submittals.

The various classes of concrete shall have an air content by volume as specified. The entrained air may be

obtained using an approved admixture.

For Class AA, Class A, Class B, Class C, and Class D concrete, the Contractor, at their option or as

required by the Structural Concrete Engineer, may substitute fly ash or ground granulated blast-furnace

slag (GGBFS), Grade 100 or Grade 120, for Portland cement.

541

The minimum substitution rate for fly ash shall be 20.0% of the required Portland cement for concrete.

The fly ash shall be substituted at a ratio of 1 pound of fly ash for 1 pound of Portland cement. The

minimum substitution rate for GGBFS shall be 25.0% of the required Portland cement for concrete. The

GGBFS shall be substituted at a ratio of 1 pound of GGBFS for 1 pound of Portland cement. A substitution

of fly ash and GGBFS will not be permitted in the same concrete mixture.

When any mineral admixture is incorporated into a standard class of concrete, necessary adjustments to

the mix design shall be made by the Contractor and reviewed and accepted by the Structural Concrete

Engineer. Proportioning of the concrete mixtures containing mineral admixture shall be by the absolute

volumes method in accordance with the requirements for each class as specified in Table 541.03A, except

that the listed W/CM ratio shall be based on total cementitious material (Portland cement and mineral

admixture).

When using concrete with mineral admixtures, the setting time may be retarded in cool weather. The

Engineer, after consultation with the Structural Concrete Engineer, may require that the curing period, as

designated in Table 541.15A, be extended.

541.04BATCHING. Measuring and batching of materials shall be performed at an approved batch plant

Batch plants shall have an inspection completed prior to the first concrete placement on an Agency project

if it has been more than 12 calendar months since the last inspection. Requests for inspection and required

documentation shall be received by the Agency’s Materials Testing and Certification Section a minimum

of 21 calendar days prior to the date of the requested inspection.

All deficiencies shall be corrected and verified a minimum of 5 calendar days prior to the first concrete

placement for any Agency project. The batch plant shall meet the requirements of AASHTO M 157, except

as modified in these specifications, and shall always be maintained in good repair. The batch plant shall

be subject to periodic inspections by authorized representatives of the Agency. The batch plant shall have

approved methods of storing, measuring, and dispensing approved admixtures.

All concrete batch plants offered for Agency approval shall be equipped for semi-automatic batching and

proportioning of all cementitious material, aggregates, water, and for the automatic insertion of

admixtures. The plants shall be equipped to automatically and accurately record and report batch weights.

Proper facilities shall be provided for the Engineer to inspect ingredients and processes used in the

batching and delivery of the concrete. The Contractor shall, without charge, afford the Engineer all

reasonable facilities for securing samples to determine whether the concrete is being furnished in

accordance with these specifications. In the batch room area, the producer shall provide the inspector with

a 24 inch × 18 inch horizontal working surface, at a sufficient working height with a seat and an adequate

view of the batching controls, display, and power supply.

541

The Contractor shall give the Engineer 24-hours’ notice of their intent to place concrete. Failure to give

notice which causes postponement of placing operations will not be a reason for determining an extension

of Contract time per the requirements of Subsection 108.11.

(a)Batch Weight Tickets. Batch weight tickets shall include the following information:
(1)Approved mix design identification number
(2)Weight of all aggregates
(3)Weight of cementitious material
(4)Quantity of admixtures by type
(5)Quantity of water batched
(6)Aggregate moistures
(7)Total water to cementitious ratio

Materials on the batch weight ticket shall be identified by type. All batch weight ticket information

shall be provided in English units. All materials added to the concrete batch shall be added to the

batch weight ticket prior to delivery.

(b)Semiautomatic Batch Plants. When actuated by a starting mechanism, the semiautomatic batch

controller shall start the weighing operation of the materials and stop the flow automatically when

the designated weight has been reached. It shall be interlocked to ensure that the discharge

mechanism cannot be opened until the weight is within the tolerance specified in Subsection

Water and admixtures may be batched in a weigh batcher or by volume in a volumetric device.

When actuated, volumetric controls shall start the measuring operation and stop the flow

automatically when the designated volume has been reached.

(c)Testing Laboratory. The Contractor shall provide a weatherproof building or room at the plant site

for the use of Agency personnel as a testing laboratory. The Contractor shall attain and maintain a

qualified laboratory status in accordance with the current edition of the Agency’s Qualified

Laboratory Program. Failure to comply with this program may result in suspension of material

production for Agency projects.

541

The testing laboratory shall have a minimum gross internal area of 150 square feet with a layout

providing a minimum internal width of 7 feet, in which to house and use the equipment specified.

Should the Contractor elect to provide additional equipment relevant to testing of Portland cement

concrete and materials, the gross inside floor area of the laboratory shall be increased in proportion

to the area required to house and operate the additional equipment. If the additional equipment is

to be operated on a bench, the length of bench sections shall also be proportionally increased.

Adequate ventilation, lighting, heating, and any necessary electrical or gas connections shall be

provided. Proper sanitary toilet facilities with a lavatory shall be available for use by Agency

personnel at the plant site. Dedicated private telephone and internet services shall be provided to

the laboratory in accordance with Subsection 631.02(a)(4), except that selection of the service by

the Engineer is not required.

The laboratory shall be equipped with the following items and equipment:

1 Standard office desk, with lockable drawers or a separate lockable two-drawer file cabinet and

chair

1 Agency Qualified Laboratory Binder with producer equipment calibration data

1 Set of bench sections at least 2 feet wide providing a minimum of 28 square feet of working

area with under-counter shelving

1 Standard laboratory stool

1 Electronic calculator with eight-digit capacity

1 Standard laboratory sink and faucet provided with an adequate supply of water meeting the

requirements of Subsection 745.01. The sink shall drain to the outside of the laboratory.

1 Bench brush

1 Floor brush

1 Motorized 8-inch sieve shaker with an adjustable timer. The shaker’s operation shall be

conducted by means of lateral and vertical motion of the sieve accompanied by jarring action

with the following 8-inch diameter sieves: 3/8 inch (9.50 mm), No. 4 (4.75 mm), No. 8 (2.36

mm), No. 16 (1.18 mm), No. 30 (0.600 mm), No. 50 (0.300 mm), No. 100 (0.150 mm), plus

pan and cover.

541

1 Mechanical aggregate shaker with an adjustable timer, a 1 cubic foot capacity, together with

the following screens: 1-3/4 inch (43.0 mm), 1-1/2 inch (37.5 mm), 1 inch (25.0 mm), 3/4 inch

(19.0 mm), 1/2 inch (12.5 mm), 3/8 inch (9.50 mm), 1/4 inch (6.30 mm), No. 4 (4.75 mm), No.

8 (2.36 mm), No. 16 (1.18 mm), and pan. The aggregate shaker may be placed in a separate

enclosed area, or be shielded for dust and sound control. When the aggregate shaker is placed

in a separate enclosed area, there shall be a minimum of 5 feet of clear space measured from

the front frame of the aggregate shaker outward, as well as a bench section measuring

approximately 36 inches high, 24 inches deep, and 50 inches long located adjacent to the

aggregate shaker. The area shall be well lit and ventilated.

1 Square pointed shovel

5 Five gallon plastic buckets, with handles

1 Electronic balance with a minimum capacity of 50 pounds and accurate to 0.0002 pounds. If

separate fine and coarse aggregate scales are to be used, the fine aggregate scale shall meet the

requirements of AASHTO M 231, Table 2, Class G2, with a minimum capacity of 1.75 pounds

and readable to 0.0002 pounds. The coarse aggregate scale shall meet the requirements of

AASHTO M 231, Table 2, Class G5, with a minimum capacity of 50 pounds and readable to

0.002 pounds.

1 Set of standard masses (weights) to use for verifying the accuracy of the electronic balance

2 Double-burner hot plates with variable temperature controls

3 Metal pans with a nominal size of 9 inches × 9 inches × 2 inches

5 Metal pans with a nominal size of 9 inches × 13 inches × 2 inches

1 Sample splitter with a 2-1/2 inch chute

1 10-inch blunted trowel

1 4 foot × 4 foot minimum heavy canvas for quartering samples

1 Brass wire-bristle brush

1 Pair of heat-resistant gloves (500°F, short-contact)

2 1-1/2 inch soft bristle paint brushes

Acceptable substitutes for these items and equipment may be made with the approval of the

Structural Concrete Engineer.

541

Batching operations shall not begin until the testing laboratory has been approved as being in

compliance with these specifications and all equipment and equipment calibration requirements of

the Agency’s Quality Assurance Program and Qualified Laboratory Program documents.

Removal of any equipment, except upon written request and with the written approval of the

Structural Concrete Engineer, will revoke any prior approvals or qualifications and require the

termination of batching operations.

The building or room designated as a testing laboratory shall be maintained in a clean condition

by the producer and kept free of all articles not necessary for the testing of materials. Cleaning

supplies shall be furnished by the Contractor.

(d)Bins and Scales. The batch plant shall include bins, weighing hoppers, and scales with adequate

separate compartments for fine aggregate and for each required separate size of coarse aggregate.

If cement is used in bulk, a bin, hopper, and scale for cement shall be included. Each compartment

shall be designed to discharge efficiently and freely into the weighing hopper or hoppers. Means

of control shall be provided so that when required, the material may be added slowly in minute

quantities and shut off with precision.

Hoppers shall be constructed to eliminate accumulations of tare materials and to discharge fully

without jarring the scales. Partitions between compartments shall be configured to prevent spilling

under any working condition. All batch plant structures shall be properly leveled and maintained

in that condition within the tolerance required by the design of the weighing mechanism.

The scales for determining the mass (weight) of aggregate, water and cementitious material shall

be comprised of a suitable system of levers or load cells. The levers or load cells shall determine

the mass (weight) consistently within 0.5% under operating conditions, with loads indicated either

by means of a beam with balance indicator, a full-reading dial, or a digital read-out or display.

Adequate means for checking the accuracy of the scales shall be provided by the Contractor either

using 50 pound weights or by other methods approved by the Structural Concrete Engineer.

Weights shall be certified annually by the Weights and Measures Section of the Vermont Agency

of Agriculture, Food, and Markets. All exposed fulcrums, clevises, and similar working parts of

scales shall be kept clean.

When beam-type scales are used, provision shall be made for indicating to the operator that the

required load in the weighing hopper is being approached. Poises shall be designed to be locked

in any position to prevent unauthorized change of position. All measuring and weighing indicating

devices shall be in full view of the operator while charging the hopper and the operator shall have

convenient access to all controls.

541

The scales shall be serviced and their accuracy verified annually by a hopper-scale service person

licensed by the Weights and Measures Section. For Vermont plants, an inspector representing the

Weights and Measures Section shall witness all testing conducted by the service person and will

attach a seal to each hopper scale, provided it meets the current specifications, tolerances, and

regulations adopted by the Weights and Measures Section. Standard test weights used to determine

the accuracy of hopper scales shall be certified yearly by the Weights and Measures Section in

accordance with their established standards.

The ready-mixed concrete producer shall hire a licensed hopper-scale service person for annual

checking and service of scales. In addition, Vermont producers shall schedule an inspection with

the Weights and Measures Section between February 16 th and April 30 th of each year, inclusive.

After April 30 th , Vermont plants without current seals affixed to the hopper scales will not be

permitted to supply concrete to Agency projects, unless otherwise directed by the Engineer or until

the seals are affixed.

Out-of-state concrete producers shall observe all annual hopper scale weighing and seal

requirements of their respective states.

(e)Production Tolerances for Batching. For weighed ingredients, the accuracy of batching is

determined by a comparison between the desired weight and the actual scale reading. For

volumetric measurement of water and admixtures, accuracy is determined by checking the quantity

either by weight on a scale or by volume in a calibrated container.

Admixture-dispensing systems shall, at a minimum, be annually calibrated by an admixture

distributor representative. The admixture distributor representative shall check at least two

volumes, with a check done at approximately 15% of the minimum and at 15% of the maximum

manufacturer’s recommended dosage range, or other targets as approved by the Structural

Concrete Engineer.

Batching shall be conducted to accurately measure the desired quantities of materials within the

tolerances specified in Table 541.04A.

541

TABLE 541.04A – CONCRETE PRODUCTION TOLERANCES FOR BATCHING

Material

Production Tolerance

Class HPAA, HPA,

HPB, AA, A, B, C, D,

SCC, or LW Concrete

Flowable Fill and

Flowable Fill,

Excavatable

Cement ± 1% ± 5%

Water ± 1% --

Aggregates ± 2% --

Chemical admixtures ± 3% --

Mineral admixtures + 10%, - 1% + 25 lbs or 10% , -1%

The positive tolerance will be the greater of the two based on the target batch

quantity for mineral admixture.

(f)Storage and Proportioning of Materials.
(1)Portland Cement. Either sacked or bulk cement may be used. No fraction of a sack of

cement shall be used in a batch of concrete unless the cement is weighed.

All bulk cement shall be weighed on an approved weighing device. The bulk cement-

weighing hopper shall be properly sealed and vented to preclude dusting during operation.

Facilities shall be provided for the sampling of cement at the batch plant, either from the

storage silo or from the weighing hopper. The sampling device shall provide a sample that

represents the true nature of the material being used. This device shall be a permanent

installation located to allow for safe and easy access.

(2)Water. Water may be measured either by volume or by weight. When measurement is by

meter, the water meter shall be so located that the measurements will not be affected by

variable pressures and temperatures in the water supply line.

Measuring tanks shall be equipped with an outside tap and valve to provide for checking

the setting, unless other means are provided for readily and accurately determining the

amount of water in the tanks.

All water metering methods shall be verified and calibrated on an annual basis or at any

time there is a question of accuracy. All water added to the concrete at any point shall be

through an approved metering method.

541

(3)Aggregates. Aggregate stockpiles shall be formed on hard, well-drained areas that prevent

contamination from underlying material and accumulation of excessive moisture.

Aggregates from different sources or of different gradations shall not be stockpiled

together. Only rubber-tired equipment shall be permitted to operate on aggregate

stockpiles.

Stockpiles shall be constructed as follows:

a.If the stockpile is to be made using mechanical equipment (front end loader, clam

bucket, rock ladder, radial stacker, or other approved equipment), the stockpile shall

be made in such a manner that segregation is kept to a minimum.

b.If the stockpile is to be made by dumping from trucks in multiple layers, each layer

shall be approximately 4 feet in depth. Each layer shall be completely in place

before commencing the next layer. Care shall be taken that successive layers do not

cone down over the previous layer.

c.No equipment shall be used to haul aggregate over the stockpiled material except

to deposit the material for the layer being placed. It shall be the responsibility of

the Contractor to ensure that the aggregate is kept free from deleterious material or

degradation.

Stockpiles shall be maintained in such a manner that twice the anticipated aggregate

requirement for any Agency project placements will be on hand and available for

sampling and testing at least 48 hours before mixing operations for the placements

are scheduled to begin. The Engineer may modify this requirement when special

aggregates are required.

Aggregates shall be handled from stockpiles or other sources to the batch plant in

such a manner as to secure a uniform grading of the material. Aggregates that have

become segregated or mixed with earth or foreign material shall not be used. All

aggregates, except lightweight coarse aggregate, produced or handled by hydraulic

methods, and washed aggregates, shall be stockpiled or binned for draining at least

12 hours before being batched. In case the aggregates have a high or non-uniform

moisture content, a storage or stockpile period longer than 12 hours may be required

by the Engineer.

541

Stockpiles being watered per the specifications or allowed through producer QC

procedures shall be watered for a sufficient time to ensure consistent moisture

throughout the stockpile. Aggregate stockpiles being watered shall be loaded in the

bin within 1 hour of being batched.

The Contractor shall conduct moisture content tests within 1.5 hours of the

anticipated concrete batching time. If there is a visual difference in aggregate

moisture appearance, aggregate moisture content will be tested again and new

moisture test results shall be obtained and used as soon as possible. Material that

has been stored in a storage bin for more than 10 hours shall be retested for moisture

content. A minimum of one cubic yard of aggregate will be removed from the

bottom of the storage bin and discarded. A minimum of one cubic yard of aggregate

will then be removed and a moisture content sample taken.

Plants that employ moisture probes shall have them calibrated and verified a

minimum of 24 hours prior to batching or as directed by the Structural Concrete

Engineer. The procedure for checking the meter will be to run aggregate over the

probe and then collect a portion of the aggregate on which to perform a moisture

content test. If the difference between the meter and the tested moisture content is

greater than 0.5%, then the meter shall be calibrated.

d.Lightweight coarse aggregate stockpiles shall be presoaked for a minimum period

of time to ensure that the aggregate is completely saturated surface dry or greater

immediately prior to use as indicated by moisture testing. Soaking shall be

accomplished by continuous sprinkling or other suitable means that will provide a

uniform moisture content throughout the stockpile. The stockpile shall be allowed

to drain for 12 hours to 15 hours immediately prior to use.

(4)Admixtures. The Contractor shall follow an approved procedure for adding the necessary

amounts of admixtures to each batch. Admixtures shall be dispensed in such a manner that

will ensure uniform distribution of the material throughout the batch within the required

mixing period. Except as specified herein, all admixtures shall be added to the batch at the

plant, unless otherwise authorized by the Structural Concrete Engineer.

Chemical admixture containers, metering equipment, and scales shall be calibrated

annually by a qualified admixture distributor representative. Admixture calibration and

verification shall be done at 15% of the high, at approximately the middle, and at 15% of

the low recommended ranges for the admixture being dispensed by the system. The

calibration and verification shall be done in the presence of an Agency representative when

requested by the Agency.

541

All dispensers shall include visual inspection aids such as graduated transparent cylinders.

A separate dispenser shall be provided for each liquid admixture. If the dispensing system

does not provide visual inspection aids, then periodic verification tests shall be done at a

frequency satisfactory to the Structural Concrete Engineer. Calibration and verification

records shall be kept at the production facility for a minimum of one year. The producer

shall perform the calibration and verification of the metering systems when requested.

Storage and dispensing systems for liquid admixtures shall be equipped to allow thorough

circulation and agitation of all liquid in the system. This shall be required prior to the first

batching of concrete for Agency projects in any calendar year and periodically thereafter

at intervals not to exceed 60 calendar days for the duration of the period the plant is

supplying concrete for Agency projects.

If the plant has received a delivery of at least 25% of the volume of the storage container,

this will be considered as a method of circulation or agitation. If the circulation method is

used, the admixture shall be circulated until a complete exchange of admixture is achieved.

If an agitation method is used, the method shall be subject to approval by the Structural

Concrete Engineer. If an admixture does not need agitation, then the admixture

manufacturer shall submit a written statement annually indicating that agitation is not

required.

Storage and dispensing systems for liquid admixtures shall be maintained within the

manufacturer’s stated temperature and environmental conditions.

It shall be the responsibility of the Contractor to use the quantity of Agency-approved

admixtures needed to obtain concrete meeting the requirements of the Contract. All

admixtures shall be approved by the Structural Concrete Engineer prior to incorporation

into the mix.

a.Air-entraining admixtures shall be used as required to obtain the specified air

content.

b.The dosages of water-reducing, retarding, and water-reducing and retarding

admixtures, accelerators and specialty admixtures shall be in the recommended

range as stated by the manufacturer, unless otherwise approved by the

manufacturer.

(5)Fly Ash or GGBFS. Fly ash or GGBFS shall be stored at the batch plant in separate storage

or holding bins or other approved holding containers and shall be protected from rain and

moisture.

541

541.05MIXING AND DELIVERY

(a)General Requirements. Concrete may be mixed at the site of construction, at a central point, or

wholly or in part in transit mixers. The production of concrete shall meet the requirements of

AASHTO M 157 with the following additional requirements:

(1)All concrete shall reach its final position in the forms no more than 1.5 hours after the

cement has been added to the water. When an approved admixture to slow or temporarily

halt the hydration process of the cement is used, this time limit will be extended to 2 hours,

provided the mix has adequate workability. Prior to discharge, the Contractor shall perform

concrete temperature testing on every load of concrete which will be deposited after the

1.5 hour time limit, as defined above, to verify the concrete temperature is within the limits

specified in Subsection 541.07.

A time limit greater than 2 hours may be approved if the request is made a minimum of 3

working days prior to the placement and all quality control test results are within

specification immediately prior to placement. The request to extend the time limit beyond

2 hours shall include the requested time limit and required admixture dosages. Acceptance

testing will be performed by the Engineer, concrete will not be accepted on the basis of

quality control tests performed by the Contractor.

Concrete shall not have water added once discharging has begun. Admixtures may be

adjusted as required by the producer before discharge has begun. Admixtures to slow or

temporarily halt the hydration process of the cement shall only be added at the production

facility.

If, in the opinion of the Engineer, any concrete appears to have visually changed from

previously placed concrete, the Contractor shall perform quality control tests to confirm

the concrete conforms to the specifications.

(2)To obtain the required concrete characteristics, a representative from the concrete producer

shall be present on the project to determine the final admixture dosage and water addition

for each load of concrete. The dosage shall be applied by means of a dispenser, or by other

means of accurately measuring volume as approved by the Engineer. The Contractor shall

provide QC concrete testing personnel, with current ACI Concrete Field Testing

Technician Grade I Certification, to confirm the concrete is within specifications for the

required work.

541

(3)Addition of water or admixtures at the project site shall be communicated to field

inspection personnel. If additional mixing water, admixtures, or other additions are

required, a minimum of 30 revolutions of the mixer drum at mixing speed shall be required

before discharge of any concrete. If water is added in excess of the specified maximum

W/CM ratio, the concrete shall not be used.

(4)The Engineer may require the Contractor to perform uniformity tests on a transit mixer or

agitator, in accordance with AASHTO M 157 and reported except as modified below. Two

samples shall be taken. The first sample shall be taken after 15% of the load volume has

been discharged, and the second prior to 85% of the load volume being discharged.

Slump and air content tests shall be performed on each sample. The maximum difference

in air content between the two samples shall be 1%. For concretes with a specified slump

of 4 inches or less, the maximum difference between the two samples shall be 1 inch. For

concretes with a specified slump greater than 4 inches, the maximum difference shall be 1-

1/2 inches. If both conditions are not met, then the Contractor will be required to either

modify the mixing procedure or batching sequence, or that transit mixer or agitator will not

be allowed to deliver concrete to the project. The Contractor will be required to perform

uniformity tests to confirm the changes have satisfactory results.

(5)Each load of concrete delivered to the job site shall be accompanied by a batch weight

ticket meeting the requirements of Subsection 541.04(a).

(6)The Contractor shall provide direct communication service from the site of the work to the

batch plant that shall be available to the Engineer at all times during concrete operations.

The cost of this service will be considered incidental to the work.

(7)All concrete shall be discharged into the forms before 300 revolutions of the drum or

blades, not including initial mixing revolutions. The total allowed number of revolutions

may be increased as directed by the Engineer.

Mortar shall be mixed in an approved mixer at the site of placement or in transit mixers when

approved by the Engineer. The Engineer will withdraw approval for use of transit mixers, if

necessary, to ensure a quality product or if the rate of delivery cannot be coordinated with finishing

requirements.

(b)Stationary Mixers. When a stationary mixer is used for the complete mixing of the concrete, the

mixing time for mixers that have a capacity of 10 cubic yards or less shall be not less than 90

seconds. For mixers that have a capacity of more than 10 cubic yards, the mixing time shall be

determined by the concrete producer.

541

The time is valid provided that mixer efficiency tests prove the concrete is satisfactory for

uniformity and strength. The plant shall be equipped with a timing device that will not permit the

batch to be discharged before the predetermined mixing time has elapsed. Vehicles used in hauling

shall comply with the requirements of Subsection 541.05(c).

(c)Transit Mixers. Transit mixers and agitators shall be subject to periodic inspections by an

authorized representative of the Agency. Such equipment shall bear a currently dated inspection

sticker supplied by the Agency indicating that the transit mixer or agitator conforms to the

Agency’s requirements.

For the purpose of this specification, the term agitator shall be interpreted to mean a vehicle with

a drum that is not used to perform the initial mixing of the concrete but is used to transport the

concrete and mix the concrete prior to discharge.

Transit mixers shall be equipped with a water-measuring tank with a visible sight gauge for use

when the water for the batch is supplied from the transit mixer tank. The gauge shall be clean and

legibly graduated. Measuring tanks shall be provided with outside drain valves or other means to

check their calibration. These should be easily opened for checking at any time.

Electrically actuated revolution counters shall be required on all transit mixers except on mixers

charged at central mix plants and used as agitator trucks only.

All mechanical details of the mixer or agitator such as water measuring and discharge apparatus,

condition of the blades, speed of rotation of the drum, general mechanical condition of the unit

and clearance of the drum shall be checked before a further attempt to use the unit will be

permitted.

Mixers and agitators shall be kept free from accumulation of hardened concrete or mortar. The

mixing blades shall be rebuilt or replaced when any part or section is worn 3/4 of an inch or more

below the original height of the manufacturer’s design. A copy of the manufacturer’s design,

showing the dimensions and arrangements of blades shall be available to the Engineer at the plant

at all times.

Concrete containing silica fume shall be mixed in accordance with the appropriate situation:

(1)When silica fume is added to the batch by bags or in bulk from a silo, each batch of concrete

shall be mixed for not less than 125 revolutions of the drum or blades at the rate of rotation

designated by the manufacturer of the equipment as the mixing speed. The mixing and

agitating speeds shall be found on the metal plate on the mixer.

541

(2)When silica fume is blended with cement or a combination of cement and mineral

admixture at the cement plant prior to being delivered to the concrete plant, each batch of

concrete shall be mixed for not less than 70 nor more than 100 revolutions of the drum or

blades at the rate of rotation designated by the manufacturer of the equipment as the mixing

speed. The mixing and agitating speeds shall be found on the metal plate on the mixer. If

inconsistent test results are obtained, or the batch of concrete appears not to be completely

mixed, the mixing revolutions shall be extended as necessary.

When a transit mixer or agitator is used for transporting concrete, mixing during transport shall be

continuous and at two to six rotations per minute or as designated by the manufacturer of the

equipment as agitating speed. Failure to do so will be cause for rejection of the concrete.

Transit mixers and agitators assigned to a project shall not be used for other purposes until the

desired work is completed at the site, and shall arrive at the project within the cycle that anticipated

placement conditions dictate. The interval between loads shall be controlled such that concrete in

place shall not become partially hardened prior to placing succeeding batches. The plant capacity

and transportation facilities shall be sufficient to ensure continuous delivery at the rate required.

Before discharging concrete from a transit mixer that has been operating at agitating speed, the

drum or blades shall be rotated approximately one minute at mixing speed. The same procedure

shall apply to agitators.

Upon discharge of the concrete from the drum, a sufficient amount of water shall be charged into

the drum to properly cleanse the drum. This water shall not be used as a part of the next succeeding

batch but shall be discharged from the drum prior to the charging of the drum with the concrete

ingredients. The drum shall be completely emptied before receiving materials for the succeeding

batch. Re-tempering of concrete or mortar that has partially hardened, by remixing with or without

additional materials, shall not be permitted.

541.06QUALITY CONTROL. The Contractor shall provide assistance, equipment, materials, and

curing for field sampling and testing as required by the Engineer. All costs shall be included in the Contract

unit prices under Section 631. The Engineer shall perform all acceptance sampling and testing in

accordance with the Agency’s Quality Assurance Program. The Contractor shall perform all on-site

quality control (QC) sampling and testing. The person performing the QC sampling and testing shall have,

as a minimum, current ACI Concrete Field Testing Technician Grade I Certification.

541

(a)Sampling. Sampling for tests shall be taken in accordance with the requirements of AASHTO R 60

or other procedures approved by the Agency. Sampling will be done at the point of placement or

as close to it as practical.

(1)Changes. Any time that there is a change in admixture dosage outside of the allowable

tolerances, whether modified at the batch plant or at the site, additional QC sampling and

testing shall be performed on the modified load prior to incorporating the concrete into the

work.

(2)Beginning of Load Sampling. Beginning of load sampling is sampling for QC testing

purposes that is taken before 15% of the load has been discharged. Beginning of load

sampling shall be performed as required by the Engineer, or as needed to ensure that the

concrete meets the Contract requirements at the point of placement. The QC personnel

shall monitor the placement operation and adjust the mix accordingly to ensure that the

material being incorporated into the work meets Contract requirements.

(b)Slump Tests. Slump tests shall be made in accordance with AASHTO T 119.
(c)Spread Tests. Spread tests for Class SCC concrete shall be performed in accordance with ASTM

C1611, Procedure B. The concrete inside the cone shall not be tamped.

(d)Visual Stability Index (VSI) Tests. VSI tests for Class SCC concrete shall be performed in

accordance with ASTM C1611, Appendix X.1 and shall be performed on each completed spread

test.

(e)Air Content Tests. Air content tests shall be made in accordance with the pressure method specified

in AASHTO T 152.

For Class SCC concrete, the specimens shall be fabricated in accordance with ASTM C1758.

A volumetric air meter shall be used for determining the air content of Class LW concrete in

accordance with AASHTO T 196.

(f)Compressive Strength Tests.
(1)General Requirements. The number of compressive strength tests performed for acceptance

will be as specified in the Materials Sampling Manual. The Engineer may order additional

tests as deemed necessary.

541

Compressive test cylinders shall be made in accordance with the requirements of AASHTO

R 100 and tested for compressive strength in accordance with the requirements of AASHTO

T 22.

For Class SCC concrete, the specimens shall be fabricated in accordance with ASTM

C1758.

(2)Categories of Testing.
a.Acceptance Testing. Acceptance testing uses specimens to determine the

compliance with requirements for the project. All test cylinders used for quality

acceptance testing shall be stored in an approved curing box until they are shipped

to the Agency’s Materials Testing and Certification Section Central Laboratory.

b.Job Control Testing. Job control testing uses specimens to determine whether

adequate curing procedures are being followed and for early form removal or early

loading of structure. All job control specimens shall be stored on the structure and

shall receive the same curing and protection from the elements as the concrete that

they represent up until 24 hours before anticipated testing of specimens.

c.Specimen Curing Requirements. Specimen curing requirements shall be as stated

in the specifications or as directed by the Engineer. If not specifically stated, the

curing shall be as specified in Table 541.06A.

TABLE 541.06A – CONCRETE SPECIMEN CURING REQUIREMENTS

Testing Category Number of Specimens Curing Location

Acceptance See the Materials

Sampling Manual Curing box

Job control 2 per test On structure

(g)Concrete Temperature. Concrete temperature tests shall be conducted in accordance with the

requirements of ASTM C1064.

541.07WEATHER AND TEMPERATURE LIMITATIONS. The temperature of the concrete just prior

to placement in the forms shall not be less than 50°F nor more than 85°F. Aggregates and water shall be

heated or cooled as necessary to produce concrete within these temperature limits.

Placement and curing procedures shall be approved by the Engineer prior to actual placement.

541

(a)Hot Weather Concrete. Placement of concrete during hot weather may be limited by the Engineer

based on an assessment of temperature, humidity, wind velocity, and sun radiation conditions. No

concrete shall be placed when the ambient air temperature is, or is expected to be, above 90°F.

(b)Cold Weather Concrete.
(1)General Requirements. Cold weather concrete will be any concrete placed or cured when

the ambient air temperature is expected to be below freezing at any point or below 40°F

for a continuous 8-hour period. No concrete shall be placed when the ambient air

temperature is lower than 10°F except by written permission of the Engineer. A cold

weather concrete plan shall be submitted to the Engineer for their review and acceptance

before any cold weather concrete is placed.

When placing cold weather concrete, the Contractor shall have adequate equipment for

heating and protecting the materials and freshly placed concrete meeting the approval of

the Engineer. This equipment shall be on the job and ready to deploy prior to the

commencement of concrete placing operations.

No concrete shall be placed in any superstructure or thin section under cold weather

conditions.

(2)Heating of Materials. The heating equipment deployed for cold weather concrete

placement shall be capable of heating the materials uniformly. Aggregates shall not be

heated to a temperature exceeding 150°F. If water is heated to a temperature exceeding

140°F, the water shall be mixed with the aggregate before the cementitious material is

added.

The materials shall be heated in such a manner, for such a period of time, and in such

quantity, as to produce concrete having a uniform temperature within the specified

temperature range at the time of placement. Materials containing frost or frozen lumps shall

not be used.

Stockpiled aggregates may be heated using dry heat or steam. Aggregates shall not be

heated directly by gas or oil flame, or on sheet metal over a fire. When aggregates are

heated in bins, steam-coil or water-coil heating, or other methods that will not be

detrimental to the aggregates, may be used.

(3)Antifreeze Compounds. Salts, chemicals, or other foreign materials shall not be used in the

mix to lower the freezing point of the concrete.

541

(4)Preparation of Forms. Before placing concrete, any ice, snow, or frost shall be completely

removed from the forms.

Concrete shall not be placed on any surface or in any forms that are frozen, have surface

temperatures below 32°F, or that contain frozen materials. The frozen surface or forms

shall be completely thawed the day before the placement of the concrete and shall be kept

continuously thawed until the concrete is poured. The temperature difference between

forms or substrate and the plastic concrete shall not exceed 40°F.

(5)Housing. The Contractor shall furnish sufficient canvas with a supporting framework or

other suitable type of housing to fully enclose and protect the structure when placing and

curing cold weather concrete. The sidewalls and roofing of the protective housing shall be

completely built before the placing of any concrete.

The protective housing shall be constructed independently of the forms and bracing and

with adequate space to allow for form removal and the initial finishing of the concrete as

required during the heating period. Joists shall be located to suitably support the housing

roof with no sagging. The protective enclosure shall be heated to the proper temperature

before placing any concrete.

When the temperature readings taken on or in the concrete indicate the temperature of the

concrete may fall below 50°F, the Contractor shall, without exposing the concrete,

immediately build the necessary enclosures around the area involved and supply heat to

ensure curing conditions as specified in Subsection 541.15. The enclosure shall be removed

when directed by the Engineer.

(6)Heating the Enclosure. The enclosure shall be heated in such a manner that the temperature

of the concrete and the enclosed air shall be kept above 50°F, and not more than 40°F above

the internal concrete temperature, for the designated curing period. During this time, the

concrete shall be kept continuously wet to provide proper curing. The internal concrete

temperature shall not exceed 160°F. After the curing period, the temperature shall be

gradually lowered to that of the surrounding atmosphere, taking at least 48 hours for the

transition but at no time exceeding a 1°F change per hour.

When dry heat is used, a means of maintaining atmospheric moisture shall be supplied.

The Contractor shall also maintain adequate fire protection and shall provide personnel to

keep the heating units in continuous operation. When concrete placement operations are in

locations where water levels may fluctuate, the supports for heating equipment shall be

built so that the heating equipment can be raised and steam lines shall be placed above the

probable high water level.

541

The enclosure shall be well-ventilated to avoid accumulation of carbon dioxide and carbon

monoxide.

When using a hydronic heating system with heat-transfer fluid that circulates through a

series of hoses, the heat-transfer hoses shall be laid on top of the vapor barrier, usually

plastic sheeting, then covered with approved insulating materials or by other approved

methods for retaining heat.

(7)Temperature Records. The Contractor shall provide an automatic temperature recorder to

continuously record concrete curing temperatures and ambient air temperatures for the

entire curing period. Recording thermometers shall be capable of measuring and recording

temperatures within the range of 0°F to 200°F with maximum graduations of 5°F.

Temperature sensors shall be carefully placed within the curing enclosure or in the concrete

to ensure that temperatures are measured at typical locations. Concrete temperature sensors

shall be embedded between 2 inches and 3 inches into the concrete or as directed by the

Engineer. The recorder’s accuracy shall be certified once every 12 months, with the

certificate displayed with each recorder. The Engineer may make random checks of each

recorder.

On each recorder chart or file, the Contractor shall indicate the location of the

representative concrete, the placement date, and start and finish times of the temperature

record. At the completion of the curing period, the recorder charts shall be submitted to the

Engineer.

A thermometer shall be provided that is capable of displaying the current ambient

temperature with a maximum gradation of 1°F. The inspector will use the thermometer to

take periodic temperature measurements of the enclosure at varying locations.

The Contractor shall provide a hand-held infrared thermometer capable of taking no-

contact measurements that is accurate within plus or minus 2% of the reading. The

thermometer’s accuracy shall be certified once every 12 months, with the certificate

provided with each thermometer.

When the Contractor places concrete at more than one location within the specified curing

period or if the Engineer determines that monitoring of a single pour is necessary in

multiple locations, additional monitoring and recording equipment shall be furnished to

provide temperature records at each location.

541

541.08FORMS. The Contractor shall be responsible for, and shall make good, any injury arising from

inadequate forms. The Engineer shall be provided the opportunity to inspect all forms prior to concrete

placement.

Unless the Plans specifically allow for the use of stay-in-place forms, such forms shall not be used in the

construction of any superstructure or bridge deck. Stay-in-place forms will only be allowed as approved

by the Engineer.

(a)Falsework. In general, falsework that cannot be founded upon a solid footing shall be supported

by falsework piling. The Engineer may require the Contractor to employ screw jacks or hardwood

wedges to correct any deflections or settlement, however slight, occurring in the falsework.

(b)Construction. Forms shall be mortar-tight and sufficiently rigid to prevent distortion due to the

pressure of the concrete and other loads incidental to the construction operations, including

vibration. Forms shall be constructed and maintained to prevent the opening of joints due to

shrinkage of the lumber. Sealers and caulking as approved by the Engineer shall be used where

forms abut structural steel members, such as top flanges of beams and girders.

To ensure their easy removal, forms shall be filleted and chamfered at all sharp corners, unless

otherwise shown on the Plans or directed by the Engineer, and shall be given a bevel or draft in

the case of all projections, such as girders and copings.

Falsework and forms for slabs, beams, and girders shall be constructed to provide the camber

shown on the Plans or ordered by the Engineer.

Falsework and forms for Class SCC concrete construction shall be designed with consideration

given to concrete placement rates, mix temperature, additives, and placement procedures that

affect hydrostatic pressure of the concrete. Forms shall be water-tight and sufficiently rigid to

prevent distortion due to the pressure of the concrete and other loads incidental to the construction

operations, including vibration.

(c)Form Lumber. All face form lumber for exposed surfaces shall be concrete form exterior grade

plywood, not less than five ply and with a minimum thickness of 3/4 inch. In computing stud

spacing, plywood shall be considered 1-inch lumber, provided that the grain of three of the plies

runs perpendicular to the studs.

Form lumber for unexposed surfaces may be dressed tongue-and-groove, dressed shiplap, or

square-edge surfaced four sides of uniform width and thickness, with a minimum thickness, after

finishing, of 3/4 inch.

541

All form lumber shall be sound and free from loose or rotten knots, knotholes, checks, splits, or

wanes showing on the surface that will be in contact with the concrete. Used face form lumber,

having defects or patches which may produce work inferior to that resulting from new material,

shall not be used.

Other form materials may be used with the permission of the Engineer.

(d)Form Ties. Metal ties or anchorages within the forms shall be constructed to permit their removal

to a depth of at least 1 inch from the face without injury to the concrete. Wire ties shall be used

only in locations where they will not extend through surfaces exposed in the finished work and

then only when authorized by the Engineer.

Unless otherwise specified, cavities shall be filled with a product that meets the requirements of

Subsection 780.01. The manufacturer’s recommendations shall be followed for surface

preparation, mixing, application, and curing.

(e)Surface Treatment. All forms shall be treated with commercial form oil prior to placing

reinforcement and wood forms shall be saturated with water immediately before placing the

concrete. Any material that will adhere to or discolor the concrete shall not be used.

(f)Metal Forms. The specifications for wood forms regarding design, mortar-tightness, filleted and

chamfered corners, beveled projections, bracing, alignment, removal, reuse, and oiling also apply

to metal forms. The metal used for forms shall be of such thickness that the forms will remain true

to shape throughout the concrete placement operations.

All bolt and rivet heads shall be countersunk. Clamps, pins, or other connecting devices shall be

designed to hold the forms rigidly together and to allow removal without injury to the concrete.

Metal forms that do not present a smooth surface or do not line up properly shall not be used. Care

shall be exercised to keep metal forms free from rust, grease, or other foreign matter.

(g)Removal of Forms.
(1)Deck Superstructure. The forms, or their supports, for any portion of a structure shall not

be removed before the end of the cure period for the deck specified in Table 541.15A.

Forms under beams or floor slabs may be removed upon approval of the Engineer after the

concrete attains 85% of the minimum compressive strength as specified in Table 541.03A,

but not prior to the end of the cure period specified in Table 541.15A.

541

(2)Substructure. The forms, or their supports, for any portion of a substructure shall not be

removed before the end of the cure period specified in Table 541.15A unless otherwise

approved by the Engineer. Removal of forms prior to the end of the cure period will only

be allowed if a vertical surface curing plan has been approved by the Engineer. Forms

under arches, pier caps, or other special design conditions may be removed upon approval

of the Engineer after the concrete attains 85% of the minimum compressive strength as

specified in Table 541.03A, but not prior to the end of the cure period specified in Table

541.15A

Methods of form removal likely to cause overstressing of the concrete shall not be used.

Forms and their supports shall not be removed without approval of the Engineer. Supports

shall be removed in such a manner as to permit the concrete to uniformly and gradually

take up the stresses due to its own dead load.

(h)Stay-In-Place Corrugated Metal Forms (SIPCMF) for Superstructure Deck Slabs.
(1)General Requirements. When SIPCMF are allowed, their use for superstructure deck slab

construction shall be subject to the following requirements:

a.Fascia overhangs shall be formed with removable forms that leave the resulting

concrete with a flat-surfaced finish.

b.Bays that are constructed in stages such that a longitudinal joint is required shall be

made with removable forms.

c.Form flutes (or valleys) shall be filled with closed cell foam, or approved equal, to

maintain the deck thicknesses shown on the plans.

(2)Design Requirements. The following requirements shall govern the design of SIPCMF:
a.The design span shall be the clear span of the form plus 2 inches, measured parallel

to the form flute (also referred to as the form valley).

b.The design load shall be the sum of the weight of forms, bar reinforcement, plastic

concrete, and 55 pounds per square foot for construction loads.

c.The unit working stress shall not exceed 75% of the specified minimum yield

strength of the material.

541

d.The dead load deflection shall not exceed 1/180 times the form span length or 1/2

inch, whichever is less.

e.Physical design properties shall be computed with the requirements of the AISI

North American Specification for the Design of Cold-Formed Steel Structural

Members.

(3)Construction Requirements. The following construction requirements shall apply to the use

of SIPCMF:

a.Construction Drawings. The Contractor shall submit construction drawings for

SIPCMF in accordance with the requirements of Subsection 105.06. These

drawings shall contain the following information as a minimum:

1.The name of the SIPCMF supplier.
2.A layout showing the compression and tension region of each beam or

girder.

3.The method of SIPCMF attachment for the compression and tension

regions.

4.The geometric properties of each type of panel being used.
5.The number, location, and type of panels being used within each girder bay.
6.Panel laps, considering the direction of concrete pours.
7.The specifications for the material used to fill the flutes.
8.Any other material data, erection information, or miscellaneous notes that

may be required.

b.Handling and Installation. Care and protection shall be given the metal form sheets,

supports, and accessory items during handling, shipping, and storage. During

loading, hoisting, and unloading operations, extra precautions and care shall be

taken to prevent damage to ends, corners, and edges of form sheets, supports, and

accessory items.

541

If the form units and accessories are to be stored prior to installation, they shall not

be placed in contact with the ground and shall be adequately covered or protected

to keep them dry.

Form supports shall be placed in direct contact with the flange of the beam, girder,

stringer, or floor beam. All attachments shall be made by permissible welds, bolts,

clips, or other approved means. The welding of form supports to steel not

considered weldable or to portions of flanges subject to tensile stresses shall not be

permitted. Welds and welding shall be in accordance with the requirements of

Subsection 506.10, with the exception that a 1/8-inch fillet weld will be permitted.

Form sheets shall not be permitted to rest directly on the flanges. They shall be

securely fastened to form supports by self-tapping screws and shall have a

minimum bearing length of 1 inch at each end. Transverse construction joints shall

be located at the bottom of a valley. A 1/4 inch diameter weep hole shall be drilled

at the lower end of each flute or valley.

Screed and pouring runway supports shall not be located directly on the form

sheets, form supports, or reinforcing steel. No loose sheets or miscellaneous

hardware shall be left on the structural slab at the end of the working day.

The corrugated metal sheets shall be fabricated for the placement sequence used,

with the joints between sections of sheets overlapped or securely fastened to

eliminate differential deflections. Any exposed form metal where galvanizing has

been damaged shall be cleaned and repaired to the satisfaction of the Engineer.

(4)Inspection Procedures. The following three-step inspection procedure will be used to check

the soundness of the concrete deck against the SIPCMF.

a.Step 1. Not less than two days after completion of a concrete structural slab pour,

but prior to the next slab pour, one panel of the SIPCMF shall be removed from the

most recently completed pour of each span, at a location selected by the Engineer,

to provide visual evidence that the concrete mix or the construction procedures are

obtaining the desired results.

If the concrete mix or the construction procedures are varied significantly within a

pour, such as a change in the extent of vibration or change in the workability of the

mix, another section of forming shall be removed to verify that the new procedures

are yielding desirable results.

541

b.Step 2. After the concrete has attained 85% of the specified design strength, the

Engineer will spot-check the underside areas of the steel forms by sounding with a

suitable weight hammer. If honeycomb or voided areas are detected, the SIPCMF

at that location shall be removed for a visual inspection.

c.Step 3. A minimum of 2% of the total SIPCMF area shall be removed for visual

inspection of the concrete surface. The amount of sounding and form removal may

be moderated, at the Engineer’s discretion, after a substantial amount of the slab

has been constructed and inspected, if the Contractor’s methods of construction and

results of the inspections as outlined above indicate that sound concrete is being

obtained throughout the slab.

If, after removing a section of form, the concrete is found to be defective, additional

panels shall be removed as directed by the Engineer. All defective concrete shall

be repaired to match the adjacent concrete in section and color to the satisfaction of

the Engineer.

The Contractor shall provide all facilities required for the safe, suitable, and

convenient means of access to the forms for the Engineer’s inspection procedures.

The form sections shall be removed by a metal saw or air-carbon-arc gouging with

minimum damage to the concrete. Cuts shall only be sufficiently deep to sever the

form. Any other method of removal shall be submitted to the Engineer for approval.

Cuts parallel to the corrugations in the forms shall be located on the sloping surface

midway between a crest and valley. Cuts parallel to the supporting beams or girders

shall be made through the supporting angles taking care not to damage the structural

steel beams or girders.

The Contractor will not be required to replace the forms which have been removed.

541.09PLACING CONCRETE

(a)Workforce. The Contractor shall always have sufficient skilled personnel during the concreting

operations to properly place, consolidate, and finish the concrete. If, in the opinion of the Engineer,

the Contractor does not have sufficient skilled personnel to handle the concrete properly, the

Engineer may postpone the start of the concreting operations until the Contractor has remedied

this situation.

541

(b)Pre-Placement Meeting. For deck pours, or as required by the Engineer, a pre-placement meeting

shall be scheduled by the Contractor to take place at least 7 calendar days before concrete

placement. Attendees at the pre-placement meeting shall include, but not be limited to, the

Contractor’s project superintendent, the Engineer, the Structural Concrete Engineer, and the

concrete producer.

The Contractor shall provide a placement plan that addresses, but is not limited to, the following

topics:

(1)Time of concrete placement and amount
(2)Batch plant testing
(3)Delivery of concrete
(4)Method of concrete placement on the deck
(5)Consolidation and finishing of concrete
(6)QC testing of the plastic concrete
(7)Protection of the concrete from evaporation
(8)Curing of the concrete
(9)How to avoid long delays for balance loads
(10)Screed, work bridge, and rail set-up
(11)Dry run schedule
(12)Contingency plans for long delays, break downs, weather events and other potential

problems

(13)Crew size and responsibilities
(14)Available equipment
(15)Project layout including locations for all pumps, cranes, testing, cleanouts, staging, etc.

541

(c)Placement Limitations. All concrete shall be placed in daylight, unless otherwise authorized in

writing by the Engineer. Authorization to place concrete at any other time shall not be given unless

an adequate lighting system is provided prior to beginning the concrete placement operations.

Concrete shall not be placed under adverse environmental conditions that the Engineer determines

will interfere with acceptable placement or finishing operations.

Concrete shall not be placed until the depth and character of the foundation, the apparent adequacy

of the forms and falsework, and the placing of the reinforcing steel have been approved by the

Engineer. The interior of the forms shall be clean of all debris before concrete is placed.

The Contractor shall submit to the Engineer a schedule of batching, delivery, and placement prior

to the beginning of the concreting operations. The Contractor shall comply with the requirements

of Subsection 541.05.

For deck pours, the Contractor shall submit the required retarder schedule to the Engineer a

minimum of 3 working days in advance of the placement. The retarder schedule shall demonstrate

how the Contractor will ensure that concrete will remain plastic until the deck is fully placed. The

retarder schedule shall include considerations for the maximum time between batching and

discharge, duration of the pour, weather, possible delays, and any other factors that may impact

the time to initial set.

Equipment and tools necessary for handling materials and performing all parts of the work shall

meet the approval of the Engineer as to design, capacity, and mechanical condition and shall be on

the site before the work is started. Any equipment, in the judgment of the Engineer, that proves

inadequate to obtain results prescribed shall be improved or new equipment substituted or added.

The Engineer may suspend the pour or reject the pour if the Contractor deviates from the accepted

pour plan which will also include unacceptable delivery rates. The Contractor will not be allowed

compensation due to the pour being suspended or rejected due to the Contractor deviating from

the accepted pour plan or uncontrolled delivery rates.

For simple spans, concrete shall be deposited by beginning at the lower end of the span and

working toward the upper end. For continuous spans, where required by design considerations, the

concrete placing sequence shall be as shown on the Plans.

Concrete shall not be deposited in the forms more than 4 feet from its final position.

The dropping of unconfined concrete more than 5 feet will not be permitted.

541

Concrete shall not be deposited in running water.

The rate of placing the concrete shall be so regulated that no excessive stresses are placed on the

forms. Concrete in all decks shall be placed in one continuous operation, unless otherwise

specified.

Concrete shall be placed in continuous horizontal layers, the thickness of which shall not exceed

18 inches, unless otherwise directed by the Engineer. Each succeeding layer shall be placed before

the underlying layer has taken initial set and shall be consolidated in a manner that will eliminate

any line of separation between the layers. When it is necessary, due to any emergency, to place

less than a complete horizontal layer at one operation, such layer shall terminate in a vertical

bulkhead.

After the concrete has taken its initial set, care shall be exercised to avoid jarring the forms or

straining the ends of projecting reinforcing bars.

Flowable fill shall be applied to voids and other locations as specified in the Contract and as

directed by the Engineer. Flowable fill shall be able to completely fill the existing voids.

If voids are discovered, the Engineer may direct the Contractor to submit a plan for filling the

remaining voids. This work, including preparing and submitting the plan and filling any remaining

voids, will be at the Contractor’s expense.

(d)Placement of Overlays. For a period of at least 24 hours before the placement of overlay material,

the prepared surface shall be flooded with water. After removal of all free water, the overlay

material shall be deposited on the damp surface and manipulated to coat the horizontal and vertical

surfaces to be covered. The rate of progress shall be controlled to prevent the drying of previously

deposited materials.

(e)Use of Chutes. Chutes, troughs, and pipes used in placing concrete shall be arranged to avoid

segregation of the materials and the displacement of the reinforcement and shall be approved by

the Engineer. Aluminum chutes, troughs, or pipes will not be permitted.

All chutes, troughs, and pipes shall be kept clean and free of hardened concrete by thoroughly

flushing with water after each run. Open troughs or chutes shall be either made of metal or be

metal-lined and shall extend as nearly as possible to the point of deposit. When the discharge must

be intermittent, a hopper or other device for regulating the discharge shall be provided.

Dropping of unconfined concrete more than 5 feet or depositing a large quantity at any point and

running or working it along the forms will not be permitted.

541

(f)Use of Vibrators. Unless otherwise specified, the concrete shall be consolidated with mechanical

vibrators, of an approved type and design, operating within the concrete. When required, vibrating

may be supplemented by hand-spading with suitable tools to ensure proper and adequate

consolidation.

Vibrators shall be manipulated to work the concrete thoroughly around the reinforcement and

imbedded fixtures and into corners and angles of the forms to produce surfaces free of

imperfections. Vibrators shall not be used to cause concrete to flow or run into position in lieu of

placing. The vibration at any point shall be of sufficient duration to accomplish consolidation but

shall not be prolonged to the point where segregation occurs.

Vibrators shall have non-metallic or rubber-coated heads. Vibrating machines shall at no time be

left running unattended in the concrete.

When it is necessary due to an emergency to discontinue the placing of a monolithic section, the

use of vibrators shall cease. Vibrators shall not again be used until a sufficient depth of fresh

concrete is placed to prevent any possibility of the effect of vibration on the concrete already in

place and in no case shall this depth be less than 2 feet.

The number of vibrators used shall be ample to consolidate the incoming concrete immediately

after it is deposited in the form. The Contractor shall have at least one spare vibrator in serviceable

condition at the site of the structure in which more than 25 cubic yards of concrete are to be placed.

The vibrators shall be capable of transmitting vibration to the concrete at frequencies of not less

than 4,500 impulses per minute under load. The vibration shall be of sufficient intensity and

duration to cause plasticity, settlement, and complete consolidation of the concrete without causing

segregation. The vibrator shall visibly affect a mass of concrete of 2-inch slump over a radius of

at least 18 inches.

Unless otherwise specified, Class SCC concrete shall not be consolidated with mechanical

vibrators. If the Engineer requests the use of a vibrator, it shall be of an approved type and design,

operating within the concrete. To avoid segregation of the concrete, it shall be used as little as

possible.

(g)Blasting Operations. All blasting operations within 200 feet of any concrete work shall be

completed prior to the placement of the concrete. Regardless of the above limitation on blasting

operations, the Contractor shall be responsible for any damage resulting from blasting operations.

541

541.10DEPOSITING CONCRETE UNDER WATER

(a)General Requirements. Concrete shall not be deposited under water except as specified by the

Contract or upon approval of the Engineer. Class SCC concrete shall be used for all underwater

concrete, unless otherwise approved by the Engineer. An anti-washout admixture shall be added

to the mix design for all underwater concrete. Underwater concrete with an anti-washout admixture

shall have a minimum air content of 3%. The anti-washout admixture may cause a delay in set

times.

(b)Placement. When placing concrete underwater, the Contractor shall use a tremie or an alternate

method of conveyance, approved by the Engineer, which minimizes the mixing of fresh concrete

and water. A tremie shall have a hopper at the top that empties into a watertight tube at least 10

inches in diameter.

The discharge end of the tube on the tremie shall include a device to seal out water while the tube

is first filled with concrete. An inflatable ball will not be permitted. The device shall keep its shape

and float without danger of deflation.

The placement shall be continuous to the elevations shown on the Plans and the resulting concrete

shall be monolithic and homogeneous.

Concrete shall not be deposited in water that has a temperature of 35°F or less. When the water

temperature is between 35°F and 40°F, the mixing water, the aggregates, or both shall be heated

as specified in Subsection 541.07(b).

A tremie shall be constructed of heavy-gauge steel pipe and consist of watertight joints between

the tremie sections with a diameter of not less than 10 inches. The tremie hopper shall have a

capacity of at least 1/2 cubic yard. When a batch is dumped into the hopper, the flow of the concrete

shall be induced by slightly raising the discharge tube, always keeping it in the concrete.

Tubes shall be kept continuously submerged in concrete during discharge. The depth that the tube

is submerged in concrete and the height of the concrete in the tube shall be sufficient to prevent

water from entering the tube. The Contractor shall continuously monitor the difference in elevation

between the top of the concrete and the end of the discharge tube.

Horizontal movement of discharge tubes through the concrete will not be allowed.

541

For minor quantities, at the sole discretion of the Engineer, a direct pumping method may be

approved. If a direct pumping method is to be implemented, the pipe discharging the concrete shall

consist of heavy-gauge steel sections. The Contractor shall demonstrate the ability to pump the

concrete without the pump line surging or otherwise moving in the water as concrete is being

pumped.

Cylinders cured as field cure shall be cured at the same temperature as the water covering the

concrete.

541.11PUMPING. Where concrete is conveyed and placed by mechanically-applied pressure, the

equipment shall be suitable in kind and adequate in capacity for the work. The pump shall be capable of

pumping concrete within the specified slump limits. The use of aluminum pipe as a conveyance for the

concrete will not be permitted.

The operation of the pump shall be such that a continuous stream of concrete without air pockets is

produced. When pumping is completed, the concrete remaining in the pipeline, if it is to be used, shall be

ejected in such a manner that there will be no contamination of the concrete or separation of the

ingredients. The equipment shall be arranged so that no resulting vibrations may damage freshly placed

concrete.

The pumping of Class LW concrete will not be permitted.

541.12CONSTRUCTION JOINTS

(a)Construction Joint Locations. Joints shall be formed at the location shown on the Plans. Any

variation or new location of joints shall require written permission of the Engineer. Feather edges

at construction joints will not be permitted. Joints shall be formed with inset formwork so that each

layer of concrete will have a thickness of not less than 6 inches.

(b)Joining Fresh Concrete to Previously Set Concrete. When joining fresh concrete to concrete that

has hardened, the surface of the set concrete shall be roughened in such a manner that will not

leave loosened particles or damaged concrete at the surface and shall be thoroughly cleaned of all

laitance, loose, and foreign material. Immediately prior to the placing of the new concrete, the

surface shall be saturated with water.

When shown on the Plans or ordered by the Engineer, the surface shall be thoroughly coated with

a very thin coating of mortar, neat cement grout, or epoxy bonding system and all forms drawn

tight against the face of the concrete. This coating shall not be allowed to dry out before being

covered with fresh concrete.

541

(c)Filled Construction Joints. Filled construction joints shall contain a pre-formed cork joint filler or

other pre-formed joint filler that may be shown in the Contract. Joint filler shall be cut to fit exactly

and shall completely fill the space that is shown on the Plans. Where a pour grade or caulking

grade filler is indicated to be used in the joints, that portion of the joint to be filled shall be formed

with a separate material (other than the pre-formed joint filler) that can easily be removed prior to

placement of the above indicated filler.

(d)Water Stops. Approved water stops shall be placed at locations shown on the Plans. They shall

form continuous watertight joints.

(e)Bond Breakers. Bond breakers shall be asphalt-treated felt or pipe insulation, as shown on the

Plans.

541.13EXPANSION JOINTS. All expansion joints shall be constructed according to details shown on

the Plans.

(a)Filled Compression and Expansion Joints. Filled compression and expansion joints shall be made

with a pre-formed self-expanding cork joint filler or other pre-formed joint filler that may be shown

in the Contract. Joint filler shall be cut to fit exactly and shall completely fill the space that is

shown on the Plans. Where a pour grade or caulking grade filler is indicated to be used in the joint,

that portion of the joint to be filled shall be formed with a separate material (other than the

expansion joint filler) that can easily be removed prior to placement of the above indicated filler.

(b)Special Types of Expansion Joints. Special types of expansion joints may be used when shown on

the Plans or ordered by the Engineer.

541.14CONCRETE FINISHING

(a)Formed Concrete. Unless otherwise specified, all concrete surfaces shall be given a dressed finish.

Other finish classes may be shown on the Plans for designated surfaces.

(1)Dressed Finish. All fins and irregular projections shall be removed from all surfaces except

from those that are not to be exposed. On all surfaces, the cavities produced by form ties

and all other holes, honeycomb spots, broken corners or edges, and other minor defects

shall be thoroughly cleaned, saturated with water, and carefully pointed and trued with a

product that meets the requirements of Subsection 780.01. The manufacturer’s

recommendations shall be followed for surface preparation, mixing, application, and

curing.

541

All construction and expansion joints in the completed work shall be left carefully tooled

and free of all mortar and concrete. The joint shall be left exposed to its full length with

clean and true edges.

Areas that contain minor defects shall be repaired to the satisfaction of the Engineer. Minor

defects are defined as the intermittent presence of holes, honeycombing, chips, or spalls,

which are 6 inches or less in the longest dimension, and that do not penetrate deeper than

1 inch into the concrete. Surface voids or bugholes that are less than 1/4 inch in diameter

and less than 1/8 inch deep need not be repaired.

Major defects are anything beyond the scope of minor as described above. The Contractor

shall submit a corrective action proposal to the Engineer for all major defects.

(2)Aesthetic Finish. In addition to the requirements for a dressed finish, the following work

shall be performed when an aesthetic finish is specified.

On all exposed surfaces, the cavities produced by form ties and all other holes, honeycomb

spots, broken corners or edges, and other minor defects shall be thoroughly cleaned,

saturated with water, and carefully pointed and trued with a mortar composed of the same

cement and fine aggregate and mixed in the same proportions used in the concrete being

finished, unless otherwise directed by the Engineer. Mortar used in pointing shall be not

more than 1 hour old. The mortar patches shall be cured for a minimum of 72 hours in

accordance with Subsection 541.15.

(b)Float Finish. This finish for horizontal surfaces shall be achieved by placing an excess of material

in the form and removing or striking off the excess with a template, forcing the coarse aggregate

below the mortar surface. Creation of concave surfaces shall be avoided. After the concrete has

been struck off, the surface shall be smoothed with a magnesium float.

Immediately after float finishing, the surface shall be given a broom finish, burlap drag finish, or

left smooth as determined by the Engineer.

(c)Bridge Seats. Surfaces of bridge seats under bearing devices shall be level. The entire bridge seat

surface shall be smoothed with a magnesium float.

(d)Finishing Bridge Decks and Overlays.
(1)General Requirements. The Contractor shall follow the procedures and details for placing

the deck in accordance with the pre-placement meeting. The procedure shall provide for

adequate labor, equipment, and material supply to complete placement of concrete on the

entire deck, or specified portion thereof.

541

If, during the placement, unforeseen circumstances delay the progression of the pour to a

point where the concrete begins to lose plasticity, the Contractor shall be prepared to place

a bulkhead, as directed by the Engineer.

If at any time the screed machine does not advance in a 15-minute period due to delayed

concrete delivery, mechanical breakdown, or other problem, the Contractor shall

immediately cover concrete that is under the screed machine past the leading edge of the

concrete with wet burlap. Just before concrete placement is to begin, the burlap shall be

removed, the screed machine will be moved back, fresh concrete will be added to the area

that was directly under the screed to the leading edge, and the area will be vibrated again.

The screed machine may then be advanced forward to continue the placement.

Approval of their methods and equipment does not relieve the Contractor of full

responsibility for obtaining the required surface finish.

Prior to texturing, the finished concrete surface shall be examined by the Contractor.

Surface irregularities greater than 1/8 inch in 10 feet in either the longitudinal or the

transverse direction shall be corrected in a manner acceptable to the Engineer. When a

bituminous concrete surface is to be placed on a bridge deck, the deviation shall not be

greater than 1/4 inch. When a sheet membrane is being applied, sharp ridges shall not be

allowed. Thin mortar or laitance, which may have accumulated ahead of the finishing

machine screed, shall be removed from the work site. These materials shall not be used to

fill depressions.

If the bridge deck concrete does not meet the above smoothness requirements, the

Contractor shall remove high spots up to 1/2-inch high by means of grinding. Any other

corrections shall be made only with the written approval of the Engineer. The use of bush

hammers will not be allowed. No concrete shall be removed that will result in a concrete

slab thickness less than that shown on the Plans.

Any deck that cannot be corrected by a method satisfactory to the Engineer shall be

removed and replaced at the Contractor’s expense.

Sidewalks shall receive their final finish with a fine bristled broom.

(2)Turf Drag. When specified on the Plans, the surface shall be given a suitable texture with

an artificial turf drag made of molded polyethylene or other material or method that will

provide an acceptable finish. The selection of turf drag or other method should be capable

of producing a surface texture with a horizontal peak-to-peak distance ranging from 0.02

inch to less than or equal to 0.25 inch and having a peak-to-peak amplitude of 0.005 inch

to 0.8 inch. A turf drag material or other acceptable method that will minimize tearing and

rolling of coarse aggregate from the surface shall be used.

541

The Contractor shall apply the finish texture in a transverse direction using hand methods.

Other directions may be allowed with the approval of the Engineer. All texturing shall be

performed from a work bridge immediately following the finishing operations and prior to

curing operations. A second work bridge will be required for curing purposes unless a

method using a single work bridge has been approved by the Engineer.

One pass of the turf drag over the finished area is desired. The drag shall leave a seamless

strip between passes. The finish texture resulting from the drag shall stop within 15 inches

of the curb face, rail anchor bolts, or edge of deck. Any buildup of concrete at the beginning

or end of the pass shall be hand troweled to provide an even transition.

The drag shall produce a transverse, skid-resistant micro-texture acceptable to the

Engineer, but shall not tear the surface. If the drag is not producing an acceptable micro-

texture, the Contractor shall adjust the means and methods until an acceptable micro-

texture is achieved.

The Contractor shall check the drag material before the deck pour and from time-to-time

during finishing for tears, worn surface, or hardened concrete. The Contractor shall clean

or replace the drag as often as necessary to maintain a well-defined micro-texture.

The turf drag or other acceptable methods shall not be applied when the surface is so wet

or plastic that the ridges formed flow back into the valleys when the drag has passed, nor

shall dragging be delayed until the concrete is so hard that sharp ridges cannot be formed

by the drag. Fogging or similar methods shall be deployed to ensure that the surface does

not dry prematurely.

If the 10-minute maximum, as specified in Subsection 541.15(c), for applying the wet cure

cannot be met, then fogging of the area shall be performed in a manner that keeps the

relative humidity above the evaporation rate of the concrete surface, but not so excessive

that water begins to collect on the surface prior to texturing or other surface manipulating

procedures.

(3)Finishing Machine Rail Supports. Finishing machine rail supports shall be of substantial

construction and accurately set so that the finished deck surface will conform to the profile

and transverse sections shown in the Plans. Finishing machine rail supports shall be placed

and adjusted to properly provide for the deflection of forms, falsework, and structural

supporting members which will occur during the placement of the concrete.

541

The finishing machine rail supports shall be spaced at a maximum of 2 feet on center and

of sufficient design as to secure the rail to prevent it from falling off the support. The screed

rails shall be configured to allow the screed machine and work bridges to be fully functional

over the entire deck area.

Sufficient screed rails shall be provided so that all rails necessary for any one continuous

pour may be preset and graded before the start of concreting operations. The removal of

screed rails and exposed chairs shall be accomplished without walking in the fresh concrete

and while the concrete is still plastic.

The Contractor shall furnish a work bridge or bridges of an approved type, capable of

spanning the entire width of the deck without deflection to the concrete slab surface.

(4)Finishing. After the concrete has been placed, it shall be struck off by a finishing machine

and the operation shall be repeated as necessary to produce a uniformly consolidated,

dense, smooth surface. The final passage of the finishing machine shall result in a uniform

surface at the required grade and slope over its entire area.

Finishing machines shall be kept in true adjustment. Machines shall not be used until the

proper adjustments have been made and the adjustments have been checked and approved

by the Engineer.

Sufficient time shall be provided prior to beginning concreting operations for the finishing

machine to be operated over the full length of the bridge deck segment to be placed. This

test run shall be made with the screed adjusted to its finishing position. While operating

the finishing machine in this test, the screed rails shall be checked for deflection and proper

adjustment, the cover on slab reinforcement shall be measured, and the controlling

dimensions of slab reinforcement and forms shall be checked.

After the concrete is placed, it shall be struck off by one of the following methods:

a.A self-propelled concrete finishing machine may be deployed, supported on

suitable rails, and equipped with adjustable strike-off and finishing roller screeds

capable of producing the required finish surface for the full width of the bridge from

face-to-face of curbs.

b.An approved mechanical vibrating screed, capable of exerting a force of at least 12

pounds per linear foot and generating at least 6,500 vibrations per minute when

checked by a vibration reed-type tester, may be deployed. The vibrating screed shall

provide a uniform finish throughout its entire length and shall be properly adjusted

so as not to drive the aggregate more than 1/4 inch below the surface.

541

The concrete finishing machine, or screed, shall be oriented perpendicular to centerline of

the bridge. Screed supports shall extend beyond the end of the deck as needed to ensure

that the finishing machine can operate over the full length of the bridge deck segment to

be placed. The finishing machine or screed shall not be operated on a skew unless the

Contractor is able to demonstrate by calculation that the design deck thickness and cross

slopes can be maintained throughout the full length of the segment placed.

In areas that are inaccessible to finishing machines, an approved manual vibratory-

equipped power screed with an approved grade-control method may be used with approval

from the Engineer. Smoothness shall be checked as specified in Subsection 541.14(d)(1)

to ensure a smooth ride and seamless transition to the finishing machine’s finished area. If

manual vibratory-equipped power screeds are used, then initial vibration of the concrete

for consolidation in those areas shall be of the minimal duration possible to avoid over-

vibration and loss of air entraining of the surface concrete in these areas.

Hand finishing will be allowed only in areas inaccessible to finishing machines or manually

driven vibratory-equipped power screeds. Hand screeds or bull floats shall be magnesium

and at least 10 inches in width. Care shall be taken not to overwork the concrete surface

during any finishing operation. Smoothness shall be checked as specified in Subsection

(d)(1) to ensure a smooth ride and seamless transition to the finishing machine’s

finished area.

CURING CONCRETE

(a)General Requirements. Water for use in curing concrete shall conform to the requirements of

Subsection 745.01. The effective cure time shall be only the time that the concrete has been

maintained in a wet condition with the concrete surface temperature above 50°F. If the concrete is

not maintained in a wet condition or the concrete surface temperature drops below 50°F, it shall

not be counted as effective cure time. The cure period will be extended 4 hours for every 1 hour

the concrete is below 50°F, beginning when the concrete temperature is raised to or exceeds the

minimum curing temperature.

Regardless of the curing medium specified, the entire surface of the newly placed concrete shall

be kept damp. This shall be achieved by applying water with a nozzle that atomizes the flow so

that a mist and not a spray is formed. The moisture shall not be applied under pressure directly

upon the concrete and shall not be allowed to accumulate in a quantity sufficient to cause a flow

or washing of the surface.

The atomized flow shall be applied continuously until the surfaces can be covered by the specified

curing mediums. For bridge barriers, curbs, and sidewalks the curing method shall be applied

within 15 minutes of the completion of the finishing process.

541

Concrete components shall be cured for the times specified in Table 541.15A.

TABLE 541.15A – CURING TIMES FOR CONCRETE COMPONENTS

Type of

Construction Curing Methods Effective Cure

Time (Days)

Substructure Subsection 541.15(b)(1), (2),

(3), (5), (7), and (8)

Superstructure Subsection 541.15(b)(2) and (8) 7

Retaining walls Subsection 541.15(b)(1), (2),

(5), (6), and (8)

Headwalls Subsection 541.15(b)(1), (2),

(5), (6), and (8)

Sidewalks, curbs,

and gutters

Subsection 541.15(b)(1), (2),

(3), (5), (6), (7), and (8)

There shall be no activity on the superstructure during the cure period.

(b)Curing Methods. All exposed surfaces of newly placed concrete shall be cured by one of the

following specified methods:

(1)Water Curing. Curing with water shall be performed by continuously sprinkling or flooding

all exposed surfaces with water for the entire required curing period.

(2)Burlap Curing. The entire exposed surface of the concrete shall be covered with two layers

of approved burlap that has been pre-soaked with water. The burlap shall then be covered

with a lapped layer of white polyethylene sheeting. Once the concrete superstructure has

hardened sufficiently, a stream of water, applied with a soaker hose or similar device, shall

be run continuously under the polyethylene sheeting until the cure period is complete.

(3)Sand Cover. The entire exposed surface of the concrete shall be covered with at least 3

inches of approved sand that shall be kept wet for the entire curing period.

(4)White Polyethylene Sheeting. The entire exposed surface of the concrete shall be covered

with a blanket of white polyethylene sheeting, maintained and fastened to provide a nearly

airtight condition in contact with the surface where possible. If, in the opinion of the

Engineer, this cover is not adequately provided or maintained to ensure the proper

conditions for the concrete cure, then the white polyethylene sheeting cure shall be

terminated and another method substituted.

541

(5)White Burlap-Polyethylene Sheeting. The entire exposed surface of the concrete shall be

covered with a blanket of white burlap-polyethylene sheeting. The burlap shall be

thoroughly dampened prior to placing and shall be placed next to the concrete. All joints

shall be lapped a minimum of 18 inches. The burlap shall be kept damp throughout the

curing period.

(6)Membrane-Forming Curing Compounds. White-pigmented or fugitive-dye membrane-

forming curing compounds may be used for curing concrete in minor drainage structures.

All other uses of curing compounds shall be approved in writing by the Engineer. Only

membrane-forming curing compounds approved by the Agency’s Materials Testing and

Certification Section shall be used.

When membrane curing is used, the exposed concrete shall be thoroughly sealed

immediately after the free water has left the surface. The concrete inside the forms shall be

sealed immediately after the forms are removed and necessary finishing has been done.

The solution shall be applied in one or two separate applications. If the solution is applied

in two increments, the second application shall follow the first application within 30

minutes. Satisfactory equipment shall be provided, together with means to properly control

and ensure the direct application of the curing solution to the concrete surface to result in

a uniform coverage of the surface area at the rate of 1 gallon of solution for every 150

square feet.

If rain falls on the newly coated concrete before the film has dried sufficiently to resist

damage, or if the film is damaged in any other manner, a new coat of the solution shall be

applied to the affected portions equal in curing value to that specified above.

Should the surface be subject to continuous injury or the use of curing compound results

in a streaked or blotchy appearance, the method shall be stopped and water curing applied.

(7)White Polyethylene Sheeting with Sand Cover. This method may be used only when

approved by the Engineer and shall conform to the requirements of Subsection

(b)(4). The airtight condition shall be obtained by the addition of a uniform sand

cover with a minimum depth of 2 inches.

(8)Pre-Dampened Cotton Mats. The entire exposed surface of the concrete shall be covered

with a blanket of cotton mats that has been pre-dampened with water. The mats shall be

maintained in a damp condition until the curing period is complete.

If, in the opinion of the Engineer, the Contractor’s curing procedure is not producing an adequate

cure, the Engineer may direct a change in the cure method at no additional cost to the Agency.

541

(c)Bridge Decks. For bridge decks, the curing method shall promptly follow the screed machine,

within a maximum lag time of 10 minutes and without interruption. If this lag time cannot be met,

then fogging of the area shall be performed in a manner that keeps the relative humidity above the

evaporation rate of the concrete surface, but not so excessive that water begins to collect on the

surface prior to texturing or other surface manipulating procedures.

541.16LOADING OF CONCRETE. After the concrete has been placed and the finishing operations

concluded, it shall not be walked on or disturbed in any manner, including removal of forms, for a

minimum period of 18 hours. If retarder is used as an admixture, this minimum period may be extended

as directed by the Engineer.

(a)Substructure. No backfill material shall be placed against a newly completed structure unless the

concrete cure is maintained in accordance with Table 541.15A, and until the field cured test

cylinders have attained 85% of the compressive strength specified in Table 541.03A. However,

the Contractor may erect forms for subsequent concrete placement on footings after 18 hours have

elapsed from the time that the footing placement was completed, provided the concrete has

sufficient strength to allow it to be worked on without damage, and proper cure is maintained.

Static loads, such as forms, reinforcing steel, or other materials necessary for construction, may be

placed on any concrete after it has been in place 72 hours, or a compressive strength of 1,800 psi

has been obtained, provided proper curing is maintained. Superimposed loads from subsequent

concrete pours will not be allowed on any substructure unit or section in place until the field cured

test cylinders have attained 85% of the compressive strength specified in Table 541.03A, and

provided curing of the supporting section is maintained in accordance with Table 541.15A.

(b)Superstructure. Static loads, such as forms, granite curbing, cast-in-place concrete curb, and other

materials necessary for deck construction, shall not be placed on deck concrete until the effective

cure time specified in Table 541.15A is complete and the field-cured test cylinders for this concrete

have attained 85% of the compressive strength specified in Table 541.03A.

The Contractor shall keep bridge floors free of all motor vehicles, transit mixers, and heavy

construction equipment until the curing period is satisfactorily completed, the field-cured test

cylinders for the bridge floor concrete have attained the compressive strength specified in Table

A, and the field-cured test cylinders for the curb concrete or bridge rail concrete, as

applicable, have attained 85% of the compressive strength specified in Table 541.03A.

(c)Vertical Joints. Concrete shall not be placed against a vertical construction joint until the

previously placed concrete has been in place a minimum of 72 hours.

541

541.17METHOD OF MEASUREMENT. The quantity of Concrete, Class HPAA, HPA, HPB, AA, A,

B, C, D, SCC, LW; Mortar, Type I; Mortar, Type IV; Flowable Fill; and Flowable Fill, Excavatable to be

measured for payment will be the number of cubic yards specified in the complete and accepted work, as

determined by the prismoidal method using dimensions shown on the Plans or as directed by the Engineer.

The quantity of concrete shall exclude the volume of steel or other stay-in-place forms and form filling

materials. No deductions will be made for the volume of concrete displaced by steel reinforcement,

structural steel, expansion joint material, scuppers, weep holes, conduits, tops of piles, scoring, chamfers

or corners, inset panels of 1-1/2 inches or less in depth, or any pipe less than 8 inches in diameter.

541.18BASIS OF PAYMENT. The accepted quantity of Concrete, Class HPAA, HPA, HPB, AA, A, B,

C, D, SCC, LW; Mortar, Type I; Mortar, Type IV; Flowable Fill; and Flowable Fill, Excavatable, will be

paid for at the Contract unit price per cubic yard. Payment will be full compensation for performing the

work specified, including designing the mix, and satisfactory finishing and curing. Payment will also be

full compensation for furnishing all forms, materials, including joint filler and bond breaker, labor, tools,

admixtures, and equipment, including automatic temperature recording units, trial batches, and incidentals

necessary to complete the work.

The cost of heating materials and protecting the concrete against cold weather, and any additional cost for

cement, will not be paid for separately but will be considered incidental to the Contract unit prices for the

applicable concrete pay items.

The cost of furnishing testing facilities and supplies at the batch plant and the setting of inserts,

benchmarks, and bridge plaques furnished by the Agency will not be paid for separately but will be

considered incidental to the Contract unit prices for the applicable concrete item.

Costs for all materials, labor and incidentals for steel or other stay-in-place forms and form filling

materials will not be paid for separately, but will be considered incidental to the Contract unit prices for

the applicable concrete item.

541

Payment will be made under:

Pay Item Pay Unit

00 Concrete, Class HPAA..............................................................................Cubic Yard

00 Concrete, Class HPA ................................................................................Cubic Yard

00 Concrete, Class HPB .................................................................................Cubic Yard

541.2000 Concrete, Class AA ...................................................................................Cubic Yard

541.2100 Concrete, Class A......................................................................................Cubic Yard

541.2200 Concrete, Class B ......................................................................................Cubic Yard

541.2300 Concrete, Class C ......................................................................................Cubic Yard

541.2400 Concrete, Class D......................................................................................Cubic Yard

541.2800 Concrete, Class SCC .................................................................................Cubic Yard

541.2900 Concrete, Class LW ..................................................................................Cubic Yard

541.4500 Flowable Fill .............................................................................................Cubic Yard

541.4600 Flowable Fill, Excavatable........................................................................Cubic Yard

541.5100 Mortar, Type I ...........................................................................................Cubic Yard

541.5400 Mortar, Type IV ........................................................................................Cubic Yard

542

5-316SECTION 542 – HIGH PERFORMANCE CONCRETE, RAPID SET

542.01DESCRIPTION . This work shall consist of designing, furnishing, and placing a high early

strength, high performance, Portland cement concrete for structures and incidental construction . The Portland cement concre te may consist of a homogeneous mixture of cement, fine aggregate, coarse aggregate, water, admixtures, and pozzolans, proportioned and mixed according to these specifications.

542.02MATERIALS . Materials shall meet the material requirements specified in Subsection 501.02 and

the following subsections: High Early -Strength Portland Cement ................................ ................................ ........ 701.0 3

542.03CLASSIFICATION AND PROPORTIONING . Concrete shall meet the requirements specified in

Table 542.03A and shall be used as shown on the Plans. TABLE 542.03A – HIGH PERFORMANCE CONCRETE, RAPID SET PROPERTIES Min. 28 -Day Compressive Strength (psi) Max. W/CM Ratio 1 Max. VSI 2 Slump Limit Spread Limit Air Content Limits Max. Free Shrinkage Max. 56 -Day Surface Resistivity 3 5,000 TBD 1 N/A 4 TBD 5 7.0% ± 1.5% 0.040% Low 1 The maximum W/CM ratio shall be determined by the Contractor as established by mix qualification testing. During production, the W/CM ratio shall be less than or equal to the W/CM ratio from the approved qualification mix. See Subsection 542.03(b) . The W/CM ratio shall be rounded to two decimal places in accordance with ASTM E29 . 2 For SCC mixes, visual stabi lity index (VSI) as determined in accordance with ASTM C1611 . 3 The Contractor shall determine the surface resistivity in accordance with Subsection 542.03( b)(3). 4 The mix shall not exhibit segregation. If the mix does exhibit segregation, the load shall be rejected . If the spread is equal to or exceeds 20 inches, the mix shall be classified as SCC mix. 5 For SCC mixes, the Contractor shall determine the spread target and limits in accordance with Subsection 542.03(b)( 4). The spread shall be maintai ned within the determined spread limits for the placement. The mix shall not exhibit segregation. If the mix does exhibit segregation or exceeds the upper spread limit, the load shall be rejected . and subsequent loads shall be tested by the Contractor until the mix meets the allowable limits. The Engineer may perform a J -ring test at the time of placement if blocking is a concern.

Get an email when 541 changes

Vermont revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Vermont Standard Specifications for Construction, 2024 Edition. Pages 681–729 of 1,380. View official source ↗

Ask about this section

Scoped to Vermont 2018 Standard Specifications for Construction, Section 541 — STRUCTURAL CONCRETE. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.