B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
General Provisions (00100-00999)

631FIELD OFFICE

VT · 2024 Standard Specifications✓ Full text on BuildSpecBook pages 913–925 Save this section

Ask about Section 631

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

631

6-139SECTIO N 631 – FIELD OFFICE

631.0 1 DESCRIPTION . This work shall consist of furnishing, erecting, equipping, and maintaining field offices and testing equipment . The work shall include cleaning, supplying utilit y services, office furniture, equipment , and supplies as required for the exclusiv e use of the Agency engineering staff at locations approved by the Engineer . Upon completion of the project , the field offices, furniture, accessories, and equipment provided shall remain the property of the Contractor. The testing equipment and supplies shall be furnished for the use of the Agency during the term of the Contract and shall be subject to use by Agency personnel to conduct tests of any materials at any location as directed by the Engineer. Equipment furnished for testing of protective coatings will be used by the Engineer as required by the Contract. 631.0 2 FIELD OFFICES .

(a)General Requirements . Field offices shall be available solely to the representatives of the state and

the federal government throughout the duration of use and shall be removed when released by the Engineer . Field offices and equipment shall always be cleaned, disinfected, and maintained in working condition to the satisfaction of the Engineer, including adequate supplies. Field offices shall not be loca ted within any Operating Railroad right -of-way. All field offices shall meet the following requirements:

(1)Foundation . Field offices shall be constructed on a firm foundation that will remain

vibration free and that will not be adversely affected by frost action or water runoff.

(2)Design . Field offices shall be a commercial -type field office trailer of standard commercial

quality, or a building, in good condition as determined by the Engineer , with a minimum width of 10 feet . They shall have a minim um of two means of egress equipped with dead bolt locks and a minimum 4 foot × 4 foot deck with steps and railings in accordance with the VOSHA Safety and Health Regulations for Construction . The Contractor shall provide the Engineer with three sets of keys. The Contractor shall not access the field office without approval of the Engineer.

631

6-140Commercial -type field office trailers shall have a minimum of four side w indows, one front

window, and one rear window . Standard buildings shall have sufficient windows to the satisfaction of the Engineer . All windows shall be glassed and screened with provisions for opening and locking and shall be equipped with adjustable lou vered blinds. Field offices shall have a lighting system capable of providing a minimum of 50 foot - candles on all work surfaces and shall have a n exterior security light satisfactory to the Engineer .

(3)Electrical Service . Field offices shall be equipped with a 1 20 volt AC, 60 Hz, single -phase

electrical system with service entrance equipment suitable for power company attachment and with at least 12 properly positioned interior electrical duplex outlets . The materials and installation methods of all electrical wiring, connections, switches, and grounds shall conform to the provisions of the National Electrical Code and shall be in accordance with all state and local electrical ordinances. The Contractor shall be responsible for arr anging the connection of the electrical service to the field office .

(4)Communications Services . Field Offices shall have independent telephone and internet

services such that both can be used simultaneously without impacting functionality. The Contractor shall provide the Engineer with a list of all internet services available at the proposed field office location and the Engineer will select the service to be provided. In all cases, internet service shall have a minimum download speed of 4 Mbps and a min imum upload speed of 1 Mbps. The specified internet speeds shall be achieved without using compression algorithms. Jacks for connection to internet and telephone services shall be located at each end of the field office for both services. When telephone o r internet service is not practical, as determined by the Engineer, services may be omitted from the field office . The Contractor shall be responsible for establishing all connections for communications services and maintaining communications services thro ughout the duration the field office is in use.

(5)Heating and Cooling Systems . Field offices shall have heating and cooling systems capable

of maintaining a temperature of 68°F at all times . Field offices shall have thermostats capable of controlling and displaying the interior temperature.

631

6-141The heating and cooling systems shall be fitted with high efficiency particulate air (HEPA)

filters meeting the requirements of DOE -STD-3020 . New HEPA filters shall be installed upon initial erection of the field office. All HEPA filters shall be replaced with new filters every 12 months, or when airflow through the filter becomes restricted, or as recommended by the manufacturer, whichever is more frequent.

(6)Sanitary Facilities and Cleaning Supplies . Sanitary facilities consisting of a flush toilet,

chemical toilet, or other approved type, shall be furnished by the Contractor, with proper sewage disposal as is necessary to comply with the requirements and regu lations of the state and local Boards of Health and VOSHA. Sanitary facilities shall be cleaned and disinfected regularly, in accordance with current CDC guidance. The frequency of cleaning shall be as outlined in the CDC guidance, or as directed by the En gineer. The degree of cleanliness shall be approved by the Engineer. Sanitary facilities shall be provided with either hot, running, potable water, and soap, or an alcohol -based hand sanitizer containing at least 70% alcohol by volume, for use in washing h ands. A potable water system consisting of a sink with a faucet within the office, with a continuous supply of pressurized clean potable water, shall be supplied for the duration of the project. When clean potable water is not available, a commercial bottled drinking water system shall be installed in the field office complete with necessary disposable drinking cups (8 oz. size or larger) and cup dispenser. The system shall supply both hot and cold water. The system and the bottled water shall be furnished by a commercial water service on a regular basis agreeable to the Engineer for the duration of the Contract. The Contractor shall supply the field office with hand sanitizer to be used for washing hands, and with a disinfectant for use in disinfecting sur faces. The hand sanitizer shall be alcohol based and shall contain at least 70% alcohol by volume. The disinfectant shall be one of the products identified on EPA List N: Disinfectants for Coronavirus (COVID -19) and shall have a contact time of 5 minutes o r less, as specified on the list . If the disinfectant supplied is of the liquid or spray -on type, the Contractor shall also supply the field office with disposable paper towels for use in applying the disinfectant.

(7)Office Equipment . All field offices shall contain the following standard commercial -

quality office equipment , with substitutions allowed upon approval of the Engineer: 1 Standard office desk a minimum of 60 inches wide × 30 inches deep and with drawers, locks, and keys

631 6-142 1 Ergonomic offic e chair with adjustable lumbar support, adjustable height, and rolling casters 1 Secure, four -drawer, legal -size file cabinet, fire -resistant (rated to withstand a one -hour fire) with lock and two keys 1 Telephone with touch tone dial, compatible with the local telephone service available , and capable of receiving and storing messages 2 30-gallon trash cans with trash bags 1 Electric clock having a dial face at least 8 inches in diameter 1 First aid kit conforming to ANSI/ISEA Z308.1 1 5-pound dry chemical fire extinguisher, with a UL rating of 3A:40B:C or better, or as needed in accordance with OSHA requirements 1 Outdoor thermometer, weatherproof, easy to read, and having a minimum scale range of -40°F to 120°F in graduations of 2°F Field offices shall be provided with ventilation and gas connections as required. The Contractor shall furnish all labor and materials for winterizing field offices.

(b)Field Office, Engineer ’s. The field office shall be available for use 7 calendar days prior to any

work commencing, including erection of construction approach signing , until 30 calendar days after final inspection of the project , unless otherwise directed by the Engineer . In addition to Subsection 631.02(a) , the field office shall meet the following requirements:

(1)Size. The field office shall have a minimum floor space of 360 square feet.
(2)Office Equipment . The field office shall contain the following standard commercial quality

office equipment , with substitutions allowed upon ap proval of the Engineer: 1 Rain gauge 2 Standard office desks a minimum of 60 inches wide × 30 inches deep and with drawers, locks, and keys

631 6-143 2 Ergonomic office chairs with adjustable lumbar support, adjustable height, and rolling casters 1 Storage cabinet a minimum of 36 inches wi de × 24 inches de ep × 24 inches high 1 Storage locker or closet of sufficient size for secure storage of surveying equipment 1 Printer/scanne r/copier combination unit, color when deemed necessary by the Engineer, with a minimum tray capacity of 50 sheets and a minimum print speed of 10 sheets per minute. The combination unit shall be capable of handling 11 inch × 17 -inch sheets. The combination unit shall be compatible with Microsoft Windows 10 and later versions and shall have wired and wireless network capabilities. The printer/scanner/copier combination unit shall have a stand of sufficient size and strength to support the unit. Supplies for the printer/scanner/copier shall include 8 -1/2 inch × 11 -inch paper, 11 inch × 17 -inch paper, and ink or toner in black and color as applicable. 1 Microwave with a minimum capacity of 1 cubic foot 1 Refrigerator with a minimum capacity of 4 cubic feet All furnished equipment shall be maintained in good working order . Replacement equipment shall be provided within 48 hours for all equipment that is damaged, stolen, or becomes inoperative in any way. The Contractor shall provide training to the Engineer in the use of the furnished equipment .

(c)Field Office, Soils and Materials . The field office shall be available for use from the day the

Contractor commences any work requiring the testing of soils and materials until 30 calendar days after acceptance of the project , or upon release by the Engineer. In addition to Subsection 631.02(a) , the field office shall meet the following requirements:

(1)Size. The field office shall have a minimum floor space of 240 square feet.
(2)Office Equipment . The field office shall contain the following standard commercial quality

office equipment with substitutions allowed upon approval of the Engineer. 1 Bench top cabinet, approximately 36 inches high and 24 inches wide with a minimum bench area of 32 square feet and a minimum storage area of 32 square feet using a suitable combination of fully enclosed shelf space and drawers

631 6-144 1 Sink with gooseneck faucet located within the office, wi th a continuous supply of pressurized, clean, potable water for the duration of the project 2 Adjustable height drafting stools

(3)Testing Equipment and Supplies . At a minimum, t he field office shall contain the following

testing equipment and supplies , with substitutions allowed upon approval of the Engineer. 1 Balance scale with a 20-pound minimum capacity , accurate to 0.2 ounces 1 Scale with a 2-pound minimum capacity, accurate to 0.004 ounces

1 Double-burner electric hot plate with variable temperature controls

1 Electric motorized sieve shaker, with either rocking and tapping action or circular and

tapping action, with a capacity of at least six sieves, cover, and 8-inch diameter pan,

confined in a dust-retaining enclosure

1 Set of U.S. Standard Sieves, brass, 8-inch diameter, full height, woven wire, meeting

the requirements of ASTM E11. The required sieves are as follows:

1 4 inch (100.0 mm) 1 3-1/2 inch (90.0 mm)

1 3 inch (75.0 mm) 1 2-1/2 inch (63.0 mm)

1 2 inch (50.0 mm) 1 1-3/4 inch (43.0 mm)

1 1-1/2 inch (37.5 mm) 1 1 inch (25.0 mm)

1 3/4 inch (19.0 mm) 1 5/8 inch (16.0 mm)

1 1/2 inch (12.5 mm) 1 3/8 inch (9.50 mm)

2 No. 4 (4.75 mm) 2 No. 8 (2.36 mm)

2 No. 10 (2.00 mm) 2 No. 16 (1.18 mm)

2 No. 30 (0.600 mm) 2 No. 40 (0.425 mm)

2 No. 50 (0.300 mm) 2 No. 100 (0.150 mm)

4 No. 200 (0.075 mm) 3 8-inch sieve pans

3 8-inch sieve covers

631

(4)Additional Equipment. Additional equipment and supplies shall include the following

items:

2 Pairs of safety gloves, 14 inches in length and capable of withstanding temperatures up

to 1,110°F

1 Brush, brass (wire bristle)

1 Broom, standard floor type

1 Shovel, round-pointed with D-handle

1 Shovel, square-pointed with D-handle

2 Heavy canvas sheets, 4 feet long × 2-1/2 feet wide, for quartering samples

10 Aluminum moisture cans, 3-1/2 inches in diameter × 2 inches deep

2 Paint brushes, soft bristle, 2 inch

4 Table brushes, 2 inches × 8 inches

1 Mason’s trowel, pointed, 8 inch

4 Plastic dish pans, 14 inches long × 12 inches wide × 5 inches deep

8 Cake pans, 9 inches long × 9 inches wide × 2 inches deep

1 Grain scoop, 6 inch

1 Spatula with 10 inch × 1-1/8 inch blade

2 Mixing spoons, heavy duty plated steel, 12 inches long

4 Microwaveable pans a minimum of 8 inches long × 8 inches wide × 2 inches deep

1 Compaction mold, 4 inches in diameter and meeting the requirements of AASHTO T

99

1 Rammer, 5-1/2 pounds in weight and meeting the requirements of AASHTO T 99

631

1 Straightedge, steel and meeting the requirements of AASHTO T 99

1 Density apparatus consisting of a sand cone and baseplate and meeting the

requirements of AASHTO T 191

2 One-gallon mason jugs with standard “G” mason jar top threading with covers

1 Carrying box, cushioned, for the two one-gallon mason jugs

2 One-gallon metal cans with moisture-proof friction covers and handles (similar to paint

cans)

1 Two-pound rubber mallet with 10-inch handle

1 Storage box to of adequate size to contain the compaction testing equipment

A microwave oven with a minimum rating of 500 watts, a digital display of power level

and time, and a minimum of ten adjustable power levels. The microwave shall have a

minimum internal volume of approximately 0.7 cubic feet. The interior dimensions shall

be approximately 11 inches long × 11 inches wide with an acceptable height. The interior

dimensions shall be of adequate size to accept the microwaveable pans listed in this

subsection.

Standard Ottawa sand meeting the requirements of ASTM C778, Section 3.1 shall be

supplied in the amount of approximately 100 pounds of sand for every 50,000 cubic yards

of embankment.

When compaction testing in accordance with AASHTO T 180 is required, the Contractor

shall also supply one 10 pound rammer meeting the requirements of AASHTO T 180.

All the foregoing testing equipment shall be in good condition and shall be replaced or repaired by

the Contractor if, during the duration of the project, it becomes unsuitable for testing purposes. All

calibration records shall be available to the Engineer.

Equipment provided for concrete testing, bituminous testing, or grout testing, when such

equipment is also in the Contract, will not be considered common to the testing equipment for the

soils and materials field office and shall not be used as such.

631

631.03TESTING EQUIPMENT, CONCRETE. The following equipment shall be provided to perform

concrete field tests:

(a)General Concrete Testing Equipment.

1 Cylinder test set meeting the requirements of AASHTO R 100

1 Slump test set meeting the requirements of AASHTO T 119

1 Platform beam scale sensitive to 0.01 pounds with a minimum capacity of 100 pounds

1 Wheelbarrow, steel, contractor-grade

1 Shovel, square-pointed with D-handle

1 Pressure air meter meeting the requirements of AASHTO T 152 and all accessory items required

for use with the particular design of apparatus used. Accessory items shall include a flat,

rectangular, metal plate at least 1/4 inch thick, a glass or acrylic plate at least 1/2 inch thick, or

a wire reinforced glass plate at least 1/4 inch thick with a length and width at least 2 inches

greater than the diameter of the measuring bowl of the air meter with which it is to be used.

1 Concrete curing box of standard commercial quality and designed to maintain an internal water

temperature of 70°F ± 10°F and 100% humidity. One or more curing boxes shall be supplied

to meet specimen requirements for the project.

1 Straightedge, a minimum of 10 feet long

(b)Class LW Concrete Testing Equipment. For testing Class LW concrete, the following additional

testing equipment shall be provided:

1 Volumetric air meter meeting the requirements of AASHTO T 196, supplied with a wooden

carrying case, syringe, tamping rod, measuring vessel, and baffle

1 One-unit weight measure meeting the requirements of AASHTO T 121, supplied with a flat,

rectangular, metal plate at least 1/4 inch thick, a glass or acrylic plate at least 1/2 inch thick, or

a wire reinforced glass plate at least 1/4 inch thick with a length and width at least 2 inches

greater than the diameter of the measuring bowl of the air meter with which it is to be used

All of the foregoing testing equipment shall be in good condition and shall be replaced or repaired by the

Contractor if, during the duration of the project, it becomes unsuitable for testing purposes.

631

All equipment and supplies furnished by the Contractor shall be available prior to placing any concrete.

When the Contractor places concrete at more than one location simultaneously, the necessary testing

equipment shall be furnished at each location.

When concrete testing equipment is required by the Contract, it will not be considered common to the

equipment for gradation testing, compaction testing, or bituminous concrete testing and shall not be used

as such.

631.04TESTING EQUIPMENT, BITUMINOUS. The following equipment shall be provided:

1 Straightedge, a minimum of 16 feet long

1 Straightedge, 10 feet in length

1 Shovel, round-pointed with D-handle

1 Metal shovel, square-head, 5.5 inch minimum width, with long handle

1 Metal spatula, of an appropriate size to clean shovels

1 Thermometer, electronic hand-held with a digital display visible under all lighting conditions, a

temperature range of -60°F to 1,200°F in increments of 2°F, automatic zero adjustment, and low

battery indication, with instruction manual. The unit shall be completely self-contained and shall not

require any external probes or other attachments to perform the required functions.

1 Probe thermometer

1 Micrometer with a range of 0 to 1 inch with graduations of 0.1 mils

1 Building level with case. The level shall be a 48-inch electronic model, with bubble indicators, digital

readout with a range of 0° to 90° degrees in 0.1° increments, percent slope from 0% to 100% in 0.1%

increments, and pitch in inches of rise per foot of run. The level shall be capable of being recalibrated.

1 Mechanical measuring wheel with a minimum wheel circumference of 3 feet and a sealed counter

capable of measuring a minimum of 9,999 feet

1 Relative humidity pen

631

The Contractor shall provide a non-petroleum asphalt release agent for cleaning the bituminous testing

equipment.

The Contractor shall provide 7.5 inch × 7.5 inch × 7.5 inch sampling containers meeting the requirements

of AASHTO R 97. The number of containers provided shall be sufficient for the quantity of bituminous

concrete material installed and the sampling frequency identified in the Materials Sampling Manual.

Black duct tape and tar paper or asphalt-treated felt shall be supplied in adequate amounts for the Engineer

to perform necessary thickness and moisture testing.

All the foregoing testing equipment shall be in good condition and shall be replaced or repaired by the

Contractor if, during the duration of the project, it becomes unsuitable for testing purposes.

All equipment and supplies furnished by the Contractor shall be available prior to the placement of any

bituminous concrete or pavement markings.

When the Contractor places bituminous concrete or pavement markings at more than one location

simultaneously, the necessary testing equipment shall be furnished at each location.

When the equipment to be provided for bituminous concrete testing is required by the Contract, it will not

be considered common to equipment for gradation testing, compaction testing, or concrete testing and

shall not be used as such.

631.05TESTING EQUIPMENT, PROTECTIVE COATINGS. The following equipment shall be

provided:

1 Psychrometer kit with wet-bulb and dry-bulb thermometers for measuring dew point, meeting the

requirements of ASTM E337, Method B, with a range from 34°F to 110°F and an accuracy of ± 1°F.

As a minimum the psychometer kit shall include matching thermometers with conversion charts and

a thermometer for measuring the surface temperature of a steel object.

1 Thickness probe, electronic dry film, meeting the requirements of ASTM D7091. The probe shall be

capable of measuring a range of 0 mils to 60 mils with an accuracy of ± 2%.

1 Adhesion testing kit meeting the requirements of ASTM D3359, Method A. At a minimum, the

adhesion testing kit shall include a cutting tool, a cutting guide, tape, rubber eraser, and an illuminated

magnifier.

631

1 Surface profile kit meeting the requirements of ASTM D4417, Method C. The surface profile kit shall

include coarse and extra coarse tapes as specified in ASTM D4417, Section 6.3 with a minimum of one

roll (100 pieces) of tape for each range, plus extras as required.

All the foregoing testing equipment shall be in good condition and shall be replaced or repaired by the

Contractor if, during the duration of the project, it becomes unsuitable for testing purposes.

The equipment furnished shall have been calibrated within one year or shall have appropriate means of

being calibrated in the field.

631.06TESTING EQUIPMENT, GROUT. For testing mortar, flowable fill, and other combinations of

sand and cement, the following additional testing equipment shall be provided:

1 Trowel having a steel blade 4 inches to 6 inches in length, with straight edges

1 Tamper meeting the requirements of AASHTO T 106

Specimen molds meeting the requirements of AASHTO T 106. The number of molds shall be sufficient to

perform both the acceptance testing required for the Contract item and any necessary control of work

testing. Each specimen mold shall be capable of producing 3 individual cubes.

All of the foregoing testing equipment shall be in good condition and shall be replaced or repaired by the

Contractor if, during the duration of the project, it becomes unsuitable for testing purposes.

All equipment and supplies furnished by the Contractor shall be available prior to placing any grout.

When the Contractor places grout at more than one location simultaneously, the necessary testing

equipment shall be furnished at each location.

When the equipment to be provided for grout testing is required by the Contract, it will not be considered

common to the equipment for gradation testing, compaction testing, concrete testing, or bituminous

concrete testing and shall not be used as such.

631.07METHOD OF MEASUREMENT. The quantity of each type of Field Office or Testing

Equipment to be measured for payment will be on a lump sum basis for each type specified and used on

the project.

The quantity of Field Office Communications (N.A.B.I.) to be measured for payment will be to the nearest

hundredth of a dollar for all communication services supplied. The Agency will include in the proposal a

quantity of dollars for all communication services required. However, the Contractor will be reimbursed

the actual costs of providing the communication services as evidenced by the paid bills submitted to the

Engineer.

631

631.08BASIS OF PAYMENT. The accepted quantity of Field Office or Testing Equipment of the type

specified will be paid for at the Contract lump sum price. Payment will be full compensation for

performing the work and furnishing all materials, labor, tools, equipment, and incidentals necessary to

provide, construct, install, maintain, and remove the type of field office or testing equipment specified,

including the installation, removal, and connection of communications lines and waste removal.

Replacement of equipment that becomes unsuitable and providing supplies that become exhausted will

not be paid for directly but will be considered incidental to the Contract item they are furnished under.

Partial payments for this work will be made as follows:

(a)The first payment of 25% will be made after each specified office or equipment unit has been

installed on the project in full working order.

(b)The second payment of 25% will be made when 33% of the anticipated construction time has

elapsed.

(c)The third payment of 25% will be made when 67% of the anticipated construction time has elapsed.
(d)The final payment of 25% will be paid upon completion and acceptance of the project.

The quantity of Field Office Communications (N.A.B.I.) to be paid will be the total dollar value of all

communications bills, paid by the Contractor, for providing all telephone and internet services supplied

to the field offices. Payment for this work will be made upon receipt of each paid communications bill

submitted to the Engineer. The total will be limited to the total of paid communications bills submitted to

the Engineer.

The cost of furnishing separate telephone lines, including installation and removal, will not be paid for

directly, but will be considered incidental to the appropriate Field Office item. The monthly service

charges will be paid under Field Office Communications (N.A.B.I.).

Payment will be made under:

Pay Item Pay Unit

631.1000 Field Office, Engineer’s ............................................................................Lump Sum

631.1100 Field Office, Soils and Materials ..............................................................Lump Sum

631.1600 Testing Equipment, Concrete....................................................................Lump Sum

631.1700 Testing Equipment, Bituminous ...............................................................Lump Sum

631.1800 Testing Equipment, Protective Coatings...................................................Lump Sum

631.1900 Testing Equipment, Grout .........................................................................Lump Sum

631.2600 Field Office Communications (N.A.B.I.) .................................................Dollar

632

6-152SECTIO N 632 – RAILROA D FLAGGERS

632.0 1 DESCRIPTION . This work shall consist of maintaining Operating Railroad traffic and coordinating with the Agency and the Operating Railroad for inspection and review of the Contractor’s work in conjunction with construction operations. A railroad flagger shall be requested any time construction operations will be within 25 feet of the nearest rail or within the Operating Railroad right -of- way, whichever is furthest. 632.0 2 GENERA L REQUIREMENTS . A railroad flagger shall be a person who is furnished, employed, and qualified by the Operating Railroad . When, as stipulated in the Contract , or in the opinion of the Engineer and the Operating Railroad, the construction work would cause hazard to the safe operation of trains and other facilities in the Operating Railroad right -of-way, including signal and communic ation lines, the Operating Railroad will furnish the necessary qualified employees to protect their trains and other facilities. The Contractor shall provide advanced notice to the Operating Railroad prior to the commencement of any work , or any portion of the work , over or adjacent to the Operating Railroad right -of-way, so that necessary arrangements can be made by the Operating Railroad to protect Operating Railroad traffic. Railroad flaggers shall be required whenever the Contractor is performing work over, under, or adjacent to the Operating Railroad tracks or right -of-way, such as excavation, sheeting, shoring, erection or removal of forms , or handling material . Railroad flaggers sha ll also be required whenever equipment is used which , by swinging over or by failure , could foul the track, or when any other type of work is being performed that, in the opinion of the Engineer or the Operating Railroad, requires such service. The Contrac tor shall be required to plan, coordinate, and organize the work effort in a way that shall absolutely minimize the use and number of Operating Railroad protective personnel required . The Agency and the Operating Railroad will review and approve all Contra ctor work schedules prior to the commencement of work and prior to the assignment of protective personnel . Misuse of these protective services by the Contractor due to inadequate work procedures will not be allowed and shall be sufficient cause for the Age ncy to require the Contractor to bear all inappropriate costs. Operating Railroad train crews necessary for the operation of Contractor -scheduled work trains or Contractor -owned or leased locomotive equipment shall not be paid by the Agency under this section , as all such costs will be considered incidental to the Contractor’s work and therefore shall be entirely borne by the Contractor.

Get an email when 631 changes

Vermont revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Vermont Standard Specifications for Construction, 2024 Edition. Pages 913–925 of 1,380. View official source ↗

Ask about this section

Scoped to Vermont 2018 Standard Specifications for Construction, Section 631 — FIELD OFFICE. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.