506
5-85SECTIO N 506 – STRUCTURA L STEEL
506.0 1 DESCRIPTION . This work shall consist of furnishing, erecting, and , when specified, coating fabricated metal structures and structural components.
506.02MATERIALS . Materials shall meet the requirements of the following subsections:
Mortar, Type IV ................................ ................................ ................................ ......... 707.0 1(e) Powder Coating Systems ................................ ................................ ........................... 708.02 Structural Steel Coating Systems ................................ ................................ ............... 708.0 3 Grease Rustproofing Compound ................................ ................................ ................ 708.0 4 Structural Steel ................................ ................................ ................................ ........... 714.02 High -Strength Low -Alloy Structural Steel ................................ ................................ 714.03 Carbon Steel Bolts, Nuts , and Washers ................................ ................................ .....714.04 High -Strength Structural Bolts and Assemblies, 120 ksi ................................ ........... 714.05 High -Strength Structural Bolts and Assemblies, 150 ksi ................................ ........... 714.06 Anchor Bolts for Bearing Devices ................................ ................................ ............. 714.08 Welded Stud Shear Connectors ................................ ................................ ................. 714.10 Steel Tubing ................................ ................................ ................................ ............... 714.11 Direct Tension Indicators ................................ ................................ ........................... 714.12 Tension Control Assemblies ................................ ................................ ...................... 714.13 Galvanizing ................................ ................................ ................................ ................ 726.0 6 Metalizing ................................ ................................ ................................ .................. 726.0 7 Unless otherwise specified in the Contract, all steel shall be high -strength low -alloy structural steel conforming to the requirements of AASHTO M 270, Grade 345W (Grade 50W). All materials shall conform to the prescribed AASHTO or ASTM specifications and no substitutions will be allowed. 506.0 3 GENERA L FABRICATIO N REQUIREMENTS . Except as modified below, fabrication shall be performed in accordance with the applicable AASHTO design code, ANSI/AASHTO/AWS D1.5 (hereinafter designated as AWS D1.5 ), and interim specifications in effect on the date of Contract advertisement . Unless otherwise indicated in the Contract, the applicable AASHTO design code shall be the AASHTO LRFD Bridge Design Specifications .
506
5-86Structural steel furnished under this section shall be fabricated in a plant having an AISC Certified Bridge
Fabricator – Advanced (ABR), or Intermediate (IBR) certification, and in a plant listed as a Category 1 fabricator on the Agency’s Pre-Qualified Fabricator List prior to Contract execution. Structural steel components such as bridge rail, bridge joints, bridge bearings, overhead sign structures , and compone nts for the repair of superstructures consisting of only cutting and drilling (no welding) which are fabricated under this section may be fabricated in a plant that does not have an ABR or IBR certification, provided that the fabrication plant has either a n AISC Certified Bridge Fabricator – Simple (SBR) certification or an AISC Bridge Component QMS certification, and is listed as a Category 2 fabricator on the Agency’s Pre-Qualified Fabricator List prior to Contract execution. Minor steel components, including, but not limited to, downspouts, scuppers, and pedestrian hand railings may be fabricated in a plant that does not have an AISC certification, provided that the fabrication plant is approved in writing by the Structural St eel Fabrication Engineer prior to Contract execution. All plants without certification shall have an organization, operation, and equipment capable of producing a product equal to a certified plant. These plants will be reviewed on a case -by-case basis. Structural steel that is to be painted or metalized under this section shall be coated in a plant having an AISC Sophisticated Paint Endorsement – Enclosed or SSPC -QP 3 – Enclosed Shop certification and which is listed as a Category 3 fabricator for the appl icable coating on the Agency’s Pre-Qualified Fabricator List prior to Contract execution. Structural steel that is to be galvanized or powder coated under this section shall also be coated in a plant listed as a Category 3 fabricator for the applicable coa ting on the Agency’s Pre-Qualified Fabricator List prior to Contract execution. The Agency’s Pre-Qualified Fabricator List can be found on the Agency ’s website. It is the responsibility of the fabricator to verify that they are on the list prior to bidding on work. It shall be known that being included on the list does not waive any certification requirements that are required for performing the intended work. Any fabricator who has been pre-qualified but does not perform any work for the Agency for a period of 5 years will be automatically removed from the list without notice. It is the fabricator’s responsibility to re -apply if they desire to be included on the list again . When certified fabrication or coating plants are required, the plant shall maintain certified status throughout the duration of the work under the Contract. The Agency reserves the right for the Structural Steel Fabrication Engineer to give written notification to any fabricator (regardless of certification level or status) restricting the types of items that they are approved to fabricate, up to and including restricting all structural steel fabrication for the Agency. Causes for such restrictions shall include concerns of quality, production, accountability, or any other cause that is deemed justifiable by the Agency.
506
5-87The fabricator shall demonstrate full capability for fabricating materials meeting the requirements of the
Contract. Failure to meet Contract requireme nts will result in rejection of the material being fabricated and the termination of the ability to fabricate material for the Agency . Prior to performing any work under this section, the fabricator shall have received approval for all fabrication drawings , welding procedures , and any special Contract requirements and have notified the Agency’s Structural Steel Fabrication Engineer in writing at least 10 working days in advance of fabrication. The Contractor shall bear full responsibility and costs for all materials ordered, raw materials stockpiled, or for work performed prior to approval of the fabrication drawings or written authorization from the State Bridge Engineer. Except as noted in this subsection, all work shall be performed by the fabricator indi cated on the approved fabrication drawings, unless otherwise authorized in writing by the Structural Steel Fabrication Engineer. For coatings, if the fabricator intends to use a subcontractor, it shall be clearly outlined on the fabrication drawings to be submitted for review. At a minimum, the provided information shall include the subcontractor’s name and address; the name, phone number , and e -mail address of the quality control contact; and an acknowledgement of the Agency quality assurance inspection requirements which apply to the subcontractor. If the fabricator wishes to request the use of a subcontractor for material processing (e.g. cutting, drilling, bending, rolling, punc hing, machining, etc.), they shall include this information on the shop drawings that are submitted for review or they shall submit a set of the previously approved shop drawings to the Agency for review, with the requested changes and required information clearly marked and indicated (e.g. by making all additional notes red). At a minimum, the submittal shall include the subcontractor’s name and address; the name, phone numbers and e -mail address of the quality control contact; an acknowledgement of the Agency quality assurance inspection requirements which apply to the subcontractor; and clear information on the extent and limits of work to be performed by the subcontractor. Requests will be evaluated on a case -by-case basis and may be rejected by the Agen cy for any reason. Use of a subcontractor does not relieve the fabricator of any responsibilities or quality control requirements specified by the Contract. All steel fabrication plants shall satisfy the following minimum requirements:
publications:
A5.29, AWS C2.18, AWS C2.23, AWS D1.1, AWS D1.2, AWS D1.3, AWS D1.4, and AWS D1.5
506 5-88 (2) AASHTO Standard Specifications for Transportation Materials and Methods of Sampling and Testing, Part I and Part II
In addition to the above, access to the latest editions of any applicable ASTM standards is required.
burning, heating, welding, etc.), as well during as any operations that may affect the quality of the coating system.
inspection, testing and quality matters shall be qualified and certified in accordance with the provisions of AWS QC 1 .
506 5-89 b. Coating Inspectors . The fabricator’s coatings quality control manager shall possess a minimum classification as a NACE Coating Inspector Level 2 – Certified, SSPC Bridge Coatings Inspector (BCI) Level 2, or SSPC Protective Coatings Inspector
classification as a NA CE Coating Inspector Level 1 – Certified, SSPC Bridge Coatings Inspector (BCI) Level 1, or SSPC Protective Coatings Inspector (PCI) Level 1.
the approved welding procedures, including tacking, in accordance with the requirements of AWS D1.5 for all structural bridge items and AWS D1.1 for items not covered in AWS D1.5.
approved by the Structural Steel Fabrication Engineer . To meet minimum requirements, a plant shall have the following facilities:
at least 500 amps
of Subsection 506.14
506
components requiring continuous welds over 2 feet in length shall also have the following
equipment:
applicable
components
be separate from the quality control facilities and shall include the following items:
506
The Structural Steel Fabrication Engineer reserves the right to reject inadequate office
facilities and require suitable alternatives.
or quality assurance, the fabricator shall have available the necessary nondestructive testing
equipment for material or weld inspection (such as magnetic particle, radiograph, ultrasonic, or
dye penetrant) or employ an outside inspection firm to fulfill the necessary nondestructive test
requirements of the code. Nondestructive tests shall be performed in accordance with the
applicable code in effect on the date of Contract advertisement.
506.04DRAWINGS AND PROCEDURES
fabrication drawings in accordance with the requirements of Subsection 105.06. Drawings, details,
and welding procedures shall be submitted as a complete package for each structure.
The Agency will review fabrication drawings, details, and procedures for their compliance with
the Contract. The Agency will refer to the requirements of AASHTO/NSBA G1.1, Section 4 and
use them as the basis for the review of structural steel fabrication drawings.
The Agency assumes no responsibility for dimensions and other information calculated by the
fabricator. The fabricator is responsible for the fit of all components. If errors occur that cause
problems during erection, the Contractor is responsible for making acceptable corrections.
The Agency is responsible for all principal dimensions and material properties contained in the
Contract. The fabricator and Contractor are responsible for bringing to the Agency’s attention any
errors or discrepancies they discover.
506
The fabricator is responsible for dimensioning members and ordering material to compensate for
weld shrinkage, distortion, elastic deformation, sweep, slope, machining, waste from cutting, and
other incidentals that are affected by the fabrication process.
shall be developed by the fabricator.
The fabrication drawings shall provide a material list on each sheet for tabulating the number of
pieces, piece marks, description, dimensions, type of material, and weight of each piece. When the
Contract item pay unit is on a per pound basis, the weight of each piece shall be extended and
summarized for each sheet as specified in Subsection 506.22. Weight extensions (extended
weights) shall be submitted to the Agency upon completion of fabrication.
All welds shown on the fabrication drawings shall identify, by symbol, the applicable procedures
and appropriate nondestructive testing requirements. A separate symbol shall be used to identify
each approved welding procedure.
provisions of the applicable AWS, ANSI, and AASHTO code revisions and submitted in
accordance with the following:
along with each procedure. Heat input values during welding shall be shown for each
procedure (except for SMAW procedures). All weld procedure sheets shall identify the
project name, number, structure, and procedure qualification record or fillet weld
soundness test.
presented in a format similar to example forms as shown in AWS D1.5 and AWS D1.1 as
applicable.
D1.1 as applicable) unless otherwise approved by the Structural Steel Fabrication Engineer.
box including provision for the date of revision, symbol of revision number, revision made by, and
description of each revision. As changes or revisions are made to previously approved sheets, the
appropriate information shall be recorded, a revision number symbol placed adjacent to the
appropriate detail, and the sheet resubmitted for approval. It is the fabricator’s responsibility to
transfer all as noted corrections to the originals.
Revisions of welding procedures shall also be resubmitted as they occur.
506
and any other procedures that are required to be submitted for approval, and are being used in
production, shall bear an Agency approved or approved as noted stamp.
506.05QUALITY ACCEPTANCE. Quality acceptance is inspection of fabrication by the Agency or the
Agency’s representative (quality assurance inspector), to verify compliance with these specifications.
Acceptance of materials, test results, or completed fabricated items by the quality assurance inspector or
Structural Steel Fabrication Engineer does not relieve the fabricator of any responsibility to meet Contract
requirements and specifications. The Contractor shall refer to the Agency’s Quality Assurance Manual
for Metal Fabrication for more information.
reports, and test results; the performance of tests specified; the evaluation of reports and tests; the
approval, disapproval, or rejection of materials, processes, quality of work, reports, and test results;
or other work specified or directed by the Engineer.
perform all the duties assigned and delegated to the Engineer in Section 105 as they pertain to the
Contract except for measuring quantities of materials and payment thereof. The inspector will
witness, interpret, and accept or reject all testing.
Inspection of the work will conform to the requirements of the applicable AWS, ANSI, and
AASHTO codes and specifications referenced in the Contract.
safety equipment. They may make use of any tools the fabricator is required to make available,
however, the fabricator is responsible for verifying that the equipment is properly calibrated and
in working order.
506.06QUALITY CONTROL
matters necessary for producing a product that conforms to the requirements of the Contract. The
fabricator is responsible for quality control.
The fabricator is responsible for performing all nondestructive tests required by the Contract and
any nondestructive tests necessary to determine the extent of metallurgical defects discovered in
the base metal.
506
scheduled nondestructive testing so that all tests can be witnessed by an Agency quality assurance
inspector. Nondestructive tests shall be performed in accordance with the requirements of AWS
D1.5.
Personnel performing and interpreting nondestructive tests (radiographic (RT), magnetic particle
(MT), ultrasonic (UT), and dye penetrant (PT)) shall be NDT certified for Level II qualification in
accordance with ASNT SNT-TC-1A.
However, ultrasonic testing may be used by the fabricator to determine the extent of
discontinuities, laminations, and inclusions discovered in any weld or base metal.
of overhead traffic sign structures, mast arms, and strain poles shall be in accordance with the
AASHTO Standard Specifications for Structural Supports for Highway Signs, Luminaires, and
Traffic Signals as well as the following:
original lot shall be examined using MT. If any welds in the second 10% require a welded
repair, all welds in that production lot shall be tested using MT.
all remaining PJP welds in that production lot shall be tested using MT.
For the purposes of this subsection, a production lot shall be defined as a day’s production on any
given project.
506.07MATERIAL IDENTIFICATION
clearly identified at all times during the fabrication of the product. If fabrication operations could
obliterate the identity, the fabricator may use a low stress die stamp placed in an area not exposed
on the finished structure. The die stamp character size shall be a minimum of 1/8 inch and a
maximum of 1/4 inch. Nonmetallic materials shall be identified to the satisfaction of the Engineer.
506
When requested, the Contractor shall furnish an affidavit certifying that throughout the fabrication
operation identification of the steel has been maintained in accordance with this specification.
When a steel stamp identification is used at a tension joint transition, the impression shall be placed
on the thicker of the members.
506.08BASE METAL REQUIREMENTS. When backing bars, extension bars, and runoff plates are part
of a welding process, the material used shall be of the same chemistry as the base metal.
Discontinuities, laminations, inclusions, or other anomalies discovered in the base metal during the
manufacturing process shall be individually evaluated. The Agency may require nondestructive testing to
determine the extent of the defect. Repair procedures or replacement will be approved on an individual
case basis.
Rolled beams shall be ordered from the mill without camber, unless pre-approved in writing by the State
Bridge Engineer.
Main members are defined as compression members, tension members, and members subject to reversals of
stress, including stringers, girders, cover plates, rigid frames, floor beams, gusset plates, and curved girder
cross frames. Other members may be indicated in the Contract as main members.
Material for main members shall be ordered and prepared so that the direction of rolling is parallel to the
stress in the member, in accordance with the requirements of AASHTO LRFD Bridge Construction
Specifications, Section 11.4.3.1. Charpy V-notch (CVN) testing shall be performed as required in
Subsection 714.01.
Members identified as fracture critical shall be subject to additional base metal requirements as specified
in Subsection 506.11.
506.09PREPARATION OF BASE METAL. Material flame cuts by any thermal cutting process shall be
made with an approved mechanically-guided torch.
The fabricator shall use preheating, post-heating, or control of the cutting process to ensure that flame-cut
edges of main members of structural steel are not flame-hardened. Flame-cut edges that will not be
included in a permanent weld shall have a Rockwell hardness value not greater than C30.
When pieces are to be bent during fabrication, bending shall be performed in accordance with the
requirements of AWS D1.5 and the applicable design code as defined in Subsection 506.03.
506
Cold bending of main members will not be permitted without written approval of the Agency. This
approval may limit the radius of curvature and require nondestructive testing to verify that no internal
distress or separation has occurred. Expenses incurred in performing any such nondestructive test
examination shall be the responsibility of the fabricator.
506.10WELDING
shall conform to the requirements of the AWS D1.5. For welding items other than those covered in
AWS D1.5, the Contractor shall adhere to AWS D1.1, AWS D1.2, AWS D1.3, or AWS D1.4 as
applicable.
Welding will not be permitted without approved welding procedures and fabrication drawings
meeting the requirements of Subsection 506.04.
Welding and inspection of shear connectors shall conform to the requirements of Section 508.
Stitch welds are not permitted, however, the skip-and-fill technique may be used when applicable
to prevent distortion.
Prior to performing any corrective weld repairs to base metal, the fabricator shall do the following:
Engineer in writing. Corrective procedures for radiographed butt welds may be included in
the welding procedure.
an approved welding procedure may be authorized by the Agency’s quality assurance
inspector.
The fabricator will be permitted a maximum of two repairs on any given welded joint.
Should nondestructive test inspection indicate weld rejection after two repairs, the Agency
may reject the entire weld and require its removal.
D1.5, Section 1 shall be deemed prequalified. Submerged arc welding (SAW), flux core arc
welding (FCAW), and gas metal arc welding (GMAW) shall be subject to qualification testing as
described in AWS D1.5 prior to approval. Other processes may be approved, on a project-by-
project basis, provided procedure qualification results meet the specified acceptance criteria.
506
Submerged arc welding (SAW) shall be used for all principal welds, as follows:
and attaching connection or stiffener plates to girder webs.
restricts the use of the automatic process.
The manual shielded metal arc welding process shall be limited to attaching connection plates to
rolled beams, welding bearing assemblies, repairs, tack welding, joints under 24 inches in length,
minor attachments, and other applications where the use of an automatic process is impractical.
When prior authorization has been granted, the GMAW and FCAW processes will be limited to
indoor shop welding of bridge rail, expansion joints, cross frames, bearing devices, scuppers, sign
fixtures, light fixtures, and low-stressed members or components. Gas metal arc welding-short
circuit arc (GMAW-S) will not be permitted.
Any gas shielded process subject to wind velocities in excess of 5 mph shall be protected using
draft barriers.
operators, and tackers qualified in accordance with the requirements of AWS D1.5. Requalification
may be required in accordance with the requirements of AWS D1.5. The requirements of AWS D1.1
shall be adhered to for welding of items not covered in AWS D1.5.
Groove welds shall be started and terminated with extension bars or runoff plates.
Fillet welds shall be performed in the flat or horizontal position unless restricted by member size
or physical position.
are on the Agency’s Pre-Qualified Welder List.
The requirements for field welding are contained in the Agency’s Field Welding Manual and shall
be adhered to. This manual may be obtained from the Agency’s website.
Welding performed in the field is subject to all of the requirements of Subsection 506.10. The
SMAW process is the only process approved for field welding.
506
All welds used to attach miscellaneous construction fixtures to any portion of the bridge structure
shall be approved in writing by the Engineer. Welding to tension members or tension components
of members will not be allowed.
Welding of miscellaneous construction fixtures such as form supports, screed supports, and
reinforcing steel chairs to any portion of the bridge structure will not be permitted without
approved drawings and welding procedures. Any increase in material thickness made necessary
by reduced allowable stresses resulting from such welding shall be at the Contractor’s expense.
Approval for any welding requiring an increase in material thickness shall be obtained before the
affected structural steel is fabricated.
Shear connectors shall be installed in accordance with the requirements of Section 508.
qualified in accordance with the requirements of AWS D1.5.
Welding and testing of samples shall be witnessed by the Agency, or the Agency’s quality
assurance inspector, or an authorized representative of a testing agency that is AWS
certified in accordance with the provisions of AWS QC 1.
AWS D1.5. The requirements of AWS D1.1 shall be adhered to for items not covered in
AWS D1.5.
506.11FRACTURE CRITICAL MEMBERS. The Agency will identify in the Contract the members or
member components that are categorized as fracture critical.
Material for members or member components identified as fracture critical shall be furnished and
fabricated in conformance with the requirements of AWS D1.5 for fracture critical components.
Welding performed on fracture critical members or components, and testing, shall be witnessed by an
Agency representative. Qualification acceptance for any welding procedure shall be based on the results
of mechanical tests and chemical analysis of deposited weld metal. Procedure requirements and basis of
acceptance shall meet the requirements in AWS D1.5 for fracture critical components.
506
506.12ASSEMBLY
drawings.
cutting the flange plates to the required curvature. Each plate shall be flame cut simultaneously on
both edges to reduce unbalanced shrinkage stresses. The flange plate lengths between shop splices
shall not be less than 20 feet. Web plates shall be aligned to the center of the flange plates.
If the final curvature is not as specified after the flanges have been welded to the web, the girder
shall be corrected by application of heat in accordance with an approved procedure.
measured only after the member has cooled. The member shall be supported in a manner that will
ensure accurate measurements for sweep and camber. The web shall be in a vertical position for
measuring curvature and in a horizontal position for measuring camber.
Heating shall be performed in such a manner that the temperature of the steel does not exceed
1,150°F. Any member heated to a temperature of more than 1,200°F shall be rejected.
Artificial cooling will not be permitted until a member has cooled to 600°F. Under no conditions
will water be permitted for cooling. Dry air may be used subject to the approval of the quality
assurance inspector.
to a minimum 1/16-inch radius by grinding.
provisions of Subsection 506.18.
may require different tolerances of fit. Terms used to define the fit of connections are as follows:
0.02 inch with a permissible variation of 1/16 inch for the remaining 50% of projected area.
0.01 inch with a permissible variation of 1/32 inch for the remaining projected area.
contact.
506
maximum allowable gap of 1/16 inch.
written approval by the Agency. Procedures will be required describing in detail the distortion to
be corrected and all procedures for heating, cooling, verifying final dimensions, and nondestructive
tests.
506.13TOLERANCES. Rolled steel plates, shapes, and bars shall be supplied to the permissible
tolerances specified in ASTM A6. The camber and sweep of fabricated rolled members shall be subject to
the same dimensional tolerances specified for welded members in AWS D1.5.
The metal bearing surface of any masonry bearing plate shall be flat, with a maximum permissible
variation of 0.04 inch from a plane determined by any three of its corners.
The fabricator is responsible for straightening to specification tolerances any weldments that may have
been distorted through stress relieving during the galvanizing process.
506.14SURFACE PREPARATION. All materials shall be blast-cleaned to the specified grade as defined
by the SSPC Painting Manual and supplemented by reference to SSPC-VIS 1. Further preparation shall
conform to the following:
This work may be performed either before or after fabrication. The final surface appearance after
fabrication shall be clean and free from any contaminants or blemishes so as to allow the metal to
weather uniformly.
and prepared in accordance with the appropriate Contract specifications.
506.15MARKING, STORING, AND SHIPPING
identification mark on the approved fabrication drawings.
Identification marks may be painted on members that will receive field coats of paint.
Identification marks on unpainted steel shall be impressed into the member with a low-stress stamp
in a non-stressed or low-stressed area of the member. The fabricator shall identify to the Contractor
the procedure used for marking material.
506
suitable supports. It shall be kept clean, properly drained, and protected from unwanted corrosion.
Free circulation of air shall be provided around all surfaces.
Girders and beams shall be stored in the upright position, supported at their ends or points of
bearing. Long members (e.g. columns and chords) shall be supported at sufficient points to prevent
damage from deflection.
Special care shall be taken for unpainted steel to ensure that it can weather uniformly.
In addition to the requirements specified above, material or raw material stockpile storage shall be
subject to any other storage criteria deemed necessary by the Engineer in accordance with the
requirements of Subsection 106.09.
shape prohibits shipment in the upright position, the fabricator shall submit a proposed method
and details of shipment to the Agency for approval.
The fabricator shall not ship any material, either to the project or to another manufacturer or
subcontractor, without the Agency’s approval. The Agency’s quality assurance inspector will place
a seal of approval on all material (or on the bill of lading) that has been accepted for shipment and
will accept the loading, positioning, and anchorage of all material being shipped. If the quality
assurance inspector is not available, the Structural Steel Fabrication Engineer shall be contacted
for approval to ship.
506.16FIELD HANDLING AND STORING. The Contractor is responsible for providing equipment
that is adequate to safely lift and place, without damage, all material furnished. Permanent distortion
caused by handling or storage will be cause for rejection.
The edges of nicks or bumps caused by handling shall be carefully ground to a 1/16-inch radius.
The storage requirements in Subsection 506.15 shall be applicable for all materials stored in the field.
506.17ERECTION
erection shall be of adequate design and capacity to safely erect, align, and secure all members and
components in their final positions without damage. The Contractor is solely responsible for the
methods and equipment employed for the erection of the structural steel. However, the Contractor
shall lift and erect curved girders so that the web of the girder is maintained vertical within a 10°
vertical tolerance.
506
The Contractor shall submit construction drawings in accordance with the requirements of
Subsection 105.06 for the methods and sequence of structural steel erection, the temporary bracing,
and the equipment to be used for the erection. The Agency will use the requirements specified in
AASHTO/NSBA S10.1, Appendix B and AASHTO/NSBA S10.1, Appendix C, as the basis for review
of erection plans.
The erection plan shall include the necessary computations to indicate the magnitude of stress in
the segments during erection and to demonstrate that all of the erection equipment has adequate
capacity for the work to be performed. The erection plan shall contain provisions for all stages of
construction, including offloading, temporary storage conditions, and temporary stoppages.
The Contractor shall include additional information in the erection plan for curved girders as
indicated in AASHTO LRFD Bridge Construction Specifications, Section 11.8.2.
The structural steel may be used for support of equipment prior to placement of the deck only with
the written permission of the Engineer. The proposed use of structural steel for support of
equipment shall be detailed in the erection plan.
Submittal of the erection plan is for documentation purposes only and shall in no way be construed
as approval of the proposed method of erection. Unless otherwise directed by the Engineer, the
Contractor shall follow the erection plan as submitted.
drawings, following match marks when provided. Material shall be carefully handled so
that no members or pieces will be bent, broken, or damaged. Hammering that will injure
or deform members will not be permitted. Bearing surfaces and contact surfaces shall be
clean.
Only light drifting will be permitted. Any member subjected to drifting that results in
distortion of the member or elongation of the holes will be rejected. Cylindrical erection
pins, the same size as the hole, shall be used at least in the extreme corners of all main
member connections.
506
Main members shall be match marked by the fabricator and should fit together easily.
Main members shall not be reamed larger than the hole size indicated on the approved
fabrication drawings without written authorization from the Project Manager. Secondary
members may be subjected to limited field reaming with the written approval of the
Engineer. Assembled parts that have been approved for field drilling or reaming shall be
disassembled to remove any burrs, shavings, oils, or lubricants.
Pins used for hinged connections and bearings shall be inserted with care and aligned so
the members take full and even bearing. Nuts shall be adequately tightened and locked in
position either by upsetting the threads or tack welding the nut to the bolt.
the Engineer. The Engineer shall approve any corrective action prior to it occurring.
506.18BOLTING AND CONNECTIONS
requirements of Subsection 714.05 unless otherwise specified. Bolts and nuts shall be furnished
by the same supplier. Bolts, nuts, and washers shall be packaged and shipped so they are kept dry.
When not in transit, bolts, nuts, and washers shall be stored indoors under dry, ventilated
conditions.
All bolts and nuts shall be adequately and uniformly lubricated. Bolts and nuts not properly
lubricated shall be cleaned and re-lubricated prior to installation in accordance with applicable
specifications.
Bolt holes are specified as 1/16 inch larger in diameter than the bolt. Bolt holes shall be fabricated
to the requirements of the AASHTO LRFD Bridge Construction Specifications, Section 11.4.8,
except that holes shall not be punched full-size unless otherwise permitted in the Contract or
approved by the Structural Steel Fabrication Engineer.
gaskets or other interposed compressible material. All joint contact surfaces and areas adjacent to
bolt holes shall be free of scale, burrs, dirt, and other foreign material that may prevent solid seating
of the parts.
506
Unless otherwise specified in the Contract, faying surfaces of bolted connections shall have a Class
B slip coefficient value of not less than 0.50 as specified by AASHTO.
Splices and field connections of main members shall have all holes filled with high-strength bolts
or cylindrical drift pins, with bolts snug-tightened before external support systems are removed.
Cylindrical drift pins shall be used in the extreme corners of all main member connections to ensure
alignment and shall remain until all bolts in the connection have been fully tightened.
element. Hardened steel washers shall be used under both the head and the nut when bolts are used
for the following connections:
shall not be allowed unless approved in writing by the Engineer)
Where an outer face of the bolted parts has a slope of 1:20 (V:H) or steeper with respect to a plane
normal to the bolt axis, a smooth beveled washer shall be used to compensate for the lack of
parallelism.
Bolts installed with the stem oriented vertically shall have the heads up. Bolts installed with the
stem oriented horizontally shall have the head towards the weather unless clearance restrictions
dictate otherwise.
Normally the nut will be the turned element. However, if the position of bolt entering or wrench
operation clearances prohibit this procedure, the bolt may be the turned element.
Tightening of a bolt group shall progress systematically from the most rigid part of the joint to its
free edges.
Previously tightened bolts shall be re-tightened until all bolts in the connection are tightened to the
minimum required tension.
506
Recalibration of the tightening wrench may be required any time there appears to be a significant
change in the bolt tightening conditions.
All bolts in a connection shall first be brought to a snug tight condition. Snug tight is defined as
initial tension sufficient to bring all the plies of the connection into firm contact while the drift
pins remain in the connection. Snugging shall progress systematically, beginning at the most rigid
part of the connection and progressing to the free edges until the connection is fully compacted.
All high-strength bolts shall be tightened to the specified tension as soon after installation as
feasibly possible. Under no circumstances shall bolts be left untightened for more than 5 days after
installation unless specific requirements to do so are indicated in the Contract or directed by the
Engineer. Bolts left in place beyond five days without specific requirements in the Contract or as
directed by the Engineer shall be removed and replaced with new bolts at the Contractor’s expense.
Bolts shall be tightened to develop a tension not less than 5% more than the minimum bolt tension
specified in Table 506.18A. Unless otherwise indicated on the Plans, ASTM F3125 Grade A325
hex head bolts shall be used.
Engineer using one of the following methods:
control bolt with a spline end and a suitable nut and washer. This method shall be employed
when installing button-headed or dome-headed high-strength bolts. This method shall only
be used when required by the Contract.
All bolts shall be tightened by the application of torque to the nut and counter-torque to the
spline end of the bolt using an approved spline drive installation tool. A random sample of
not less than three tension control assemblies of each diameter, length, grade, and type to
be used in the work shall be checked a minimum of once each working day in a device
capable of indicating bolt tension.
The test shall be performed to verify that the spline twist-off develops a tension at least 5%
greater than the minimum bolt tension specified in Table 506.18A. Additional verification
of the tension control assemblies shall be performed as directed by the Engineer. Separate
checks will be required for each diameter fastener with hardened washers placed under the
nut or bolt head as they will be used in the structure. Variations in the number or location
of washers will require separate checks.
506
washers capable of indicating that a specified minimum bolt tension has been attained.
DTIs installed with high strength bolts to indicate bolt tension shall be subjected to field
verification testing prior to installation and the installation requirements specified in this
subsection.
DTIs installed with high-strength bolts to indicate bolt tension shall be placed under the
head of the bolt with the protrusions facing the head of the bolt, and the nut shall be turned,
with a hardened washer underneath it, to tension the fastener. Additional hardened washers
shall be provided if required by the DTI manufacturer for their specific product. If for
reasons of wrench operations clearance it is necessary to place the DTI under the turned
element, the DTI shall be oriented so that the protrusions face outward from the work, and
a hardened washer shall be placed between the DTI and the turned element. Placement of
the DTI under the turned element will only be allowed when approved by the Engineer.
The bolt, DTI, hardened washer, and nut assembly used in the verification testing device
and installed in the work shall be such that at least three and preferably not more than five
threads are in the grip. The grip is defined as the distance between the bearing face of the
nut and the bolt head.
The Contractor shall supply 5-mil tapered feeler gauges, a calibrated bolt tension-
measuring device and equipment necessary to perform field verification testing and
inspection of tensioned bolts. The feeler gauges, fasteners, and impact and manual
wrenches shall be the same as that to be used in the work.
The Contractor shall obtain the services of a qualified technical advisor employed by the
DTI manufacturer to make at least one site visit to assist the Contractor and to ensure the
proper installation and use of DTIs. This requirement may be waived by the Engineer if
the Contractor can demonstrate to the Agency’s satisfaction successful use of DTIs on
previous projects for the Agency.
Verification testing shall be performed in a calibrated bolt tension measuring device, such
as a Skidmore-Wilhelm Calibrator, with a special flat insert (supplied by the Contractor)
replacing the normal bolt head-holding insert. The special insert allows the DTI to be
located on the flat front face of the tension measuring device for ease of observation and
improved access for measuring the DTI gap during testing. The Contractor shall supply
hardened steel spacers as needed for testing longer bolts in the bolt tension measuring
device. Stacked washers will not be permitted as a substitute for hardened steel spacers.
506
The purpose of verification testing is to validate the DTI assembly’s ability to indicate
installation tension above the minimum. The verification tension specified in Table
A is 5% higher than the minimum required installation tension in Table 506.18A
The increase provides confidence that the installation tension can be achieved for the lot.
Three verification tests are required to be performed on random samples of each
combination of fastener rotational-capacity lot, DTI lot and DTI position (under the nut or
bolt head) used on the project. All three tests must pass for the DTI and assembly
combination to be approved. Testing shall be performed at the project site by the Contractor
and witnessed by the Engineer.
When testing for the normal DTI position, the nut shall be turned from the rear of the
tension measuring device, with the bolt head against the DTI restrained from turning with
another wrench. When testing with the DTI under the turned element, the turned element
shall be placed on the flat front face of the tension measuring device and the unturned
element will be in the rear held by another wrench.
A for the grade and size of fastener. If an impact wrench is used,
tension to a load two-thirds below the required load and use a manual
wrench to attain the required tension.
spaces between the protrusions. When using galvanized or epoxy coated
DTIs under the turned element, there shall be at least one entry of the feeler
gauge.
The DTI lot will be rejected if the number of entries is less than the value
in column 2 of Table 506.18B. If coated DTIs are used under the turned
element, the DTI lot will be rejected if there are no entries.
the range in column 3 of Table 506.18B.
506
verification tension load in Table 506.18A. If the actual pretension
developed in the fastener is less than the verification tension load specified
in Table 506.18A, the causes shall be determined and resolved before the
fasteners are used in the work. Cleaning, lubrication, and retesting new
fasteners is permitted for this step provided that all fastener assemblies are
treated in the same manner.
If the bolts are too short to be tested in the tension measuring device, the verification
test for the DTI shall be conducted on longer bolts supplied by the Contractor. The
longer bolts shall be new, meet the requirements of Subsection 714.05, and be of
the same type as the DTI being tested. Three verification tests are required as
specified above.
Bolts and DTIs used in verification tests shall be marked and shall not be reused in
the work.
TABLE 506.18A – BOLT TENSION VALUES FOR ASTM F3125 BOLTS
Nominal Bolt
Diameter (in.)
Minimum Bolt Tension (kips) Verification Tension (kips)
Grade A325 Grade A490 Grade A325 Grade A490
1/2 12 15 13 16
5/8 19 24 20 25
3/4 28 35 29 37
7/8 39 49 41 51
1 51 64 54 67
1-1/8 64 80 67 84
1-1/4 81 102 85 107
1-3/8 97 121 102 127
1-1/2 118 148 124 155
Equal to 70% of the specified minimum tensile strength of bolts.
Verification tension is 1.05 times the minimum bolt tension.
506
follows:
condition. Snugging shall progress systematically beginning at the most
rigid part of the connection and progressing to the free edges until the
connection is fully compacted. At the snug-tight condition all of the DTIs
shall be inspected with the feeler gauge to verify that they meet the number
listed in column 2 of Table 506.18B.
If the number of entries is less than the values specified in Table 506.18B,
the fastener shall be removed and another DTI installed, followed by re-
snugging of the fastener. This is required because a fastener’s tension may
have relaxed during the snugging of adjacent fasteners. A compressed DTI
does not rebound if the fastener tension is reduced. If a DTI which has fewer
entries were left in place, it would give a false indication of bolt tension.
point that the number of entries for a 5-mil feeler gauge meets the number
listed in column 3 of Table 506.18B. Tightening shall progress
systematically beginning at the most rigid part of the connection and
progressing to the free edges. Drift pins shall be removed during this
process, with the exception that drift pins in the extreme corners of main
member connections shall remain in place until all other bolts are fully
tensioned. Several cycles may be required.
The Contractor shall use the minimum amount of force necessary to achieve
the number of entries listed in column 3 of Table 506.18B. If DTIs are
consistently being tensioned to a point where there are zero entries of the
feeler gauge, the amount of force applied to the bolt shall be reduced.
506
TABLE 506.18B – NUMBER OF DTI ENTRIES FOR ASTM F3125 BOLTS
Number of
Spaces Between
DTI Protrusions
Verification -
Required Number
of DTI Entries 1, 2
Installation -
Required Number
of DTI Entries 1, 3
4 2 – 4 0 – 1
5 3 – 5 0 – 2
6 3 – 6 0 – 2
7 4 – 7 0 – 3
8 4 – 8 0 – 3
9 5 – 9 0 – 4
An entry occurs when a 5-mil tapered feeler gauge fits into
the space between DTI protrusions and touches the bolt
shank.
For coated DTIs under the turned element, at least one
entry is required.
For coated DTIs under the turned element, 0 – 1 entries are
required.
observed to determine if the tightening procedure is working properly and the correct tension has
been achieved
The Contractor shall provide a tension measuring device, such as a Skidmore-Wilhelm Calibrator,
which has been calibrated within the last year and is accompanied by a certificate verifying its date
of calibration.
Before the installation of fasteners in the work, the Engineer shall check the marking, surface
condition, and storage of bolts, nuts, and washers and the faying (contact) surfaces of joints for
compliance with the Contract requirements.
Bolt tension for fasteners with DTIs shall be verified using 5-mil tapered feeler gauges provided
and operated by the Contractor.
506
All bolts installed using DTIs shall be inspected after snug tightening and again after full
tensioning, with 100% of the bolts inspected visually and 10% of the bolts in any connection (but
not less than two) inspected by feeler gauge. If the installation of inspected bolts is accepted, then
the connection shall be accepted as properly tensioned.
If any bolt in a connection does not pass inspection, then all (100%) of the bolts in that connection
shall be inspected with the feeler gauge. Any bolt which does not pass inspection as described
herein shall be further tensioned if required.
If the Engineer suspects that the Contractor is using an excessive amount of force on fasteners with
DTIs, the Engineer may require a sample of no less than three fasteners to be removed from the
work in one or more locations for further inspection. All costs for further inspection, including
replacement fasteners, shall be at no additional cost to the Agency. Further inspection shall be
performed as follows for each sample of fasteners:
full length of the threads, excluding thread runout. If this is successful for all fasteners, the
fasteners represented by the sample will be accepted and new fastener assemblies and DTIs
shall be installed in the work where the sample fasteners were removed. If the nut cannot
be turned down the full length of the threads by hand on all fasteners, proceed to Step 2.
tensioned to the verification tension load in Table 506.18A. The bolt tension measuring
device shall be supplied with short bolt plates and bushings as needed for testing shorter
bolts and hardened steel spacers as needed for testing longer bolts. Stacked washers will
not be permitted as a substitute for hardened steel spacers, with the exception that
additional flat washers may be used in combination with hardened steel spacers if necessary
to achieve the appropriate grip length. The complete fastener assembly that was removed
from the work, excluding the DTI, shall be installed in the calibrated bolt tension measuring
device with a grip length equal to or greater than the grip length when installed in the work.
If this is successful for all fasteners, the fasteners represented by the sample will be
accepted and new fastener assemblies and DTIs shall be installed in the work where the
sample fasteners were removed. If all fasteners cannot be tensioned to the verification
tension load in Table 506.18A, the Contractor shall replace all fasteners in the work
represented by the sample as determined by the Engineer.
506
Bolts installed using tension control assemblies shall be visually inspected for consistent twist-off
and thread stick-out.
Undamaged fasteners may only be reinstalled with the approval of the Engineer. Galvanized bolts,
ASTM F3125 Grade A490 bolts, tension control assemblies, and DTIs shall not be reinstalled.
An additional required inspection step is to check the bolt thread stick-out on the nut side after
installation to the final specified gap to look for inconsistency of pattern. Any stick-outs greater
than the other bolts shall be investigated and discarded (e.g. if necking down of the bolt has
occurred or the wrong length bolt was used). The end of the properly installed bolt shall be at least
flush with the nut.
The Engineer shall be provided with safe access in accordance with the requirements of Section
105 to conduct all inspection deemed necessary during and after the installation of the bolts. If the
Engineer determines that the access provided is unsafe, work will be ordered to halt until such time
that the access is made safe. Any delays incurred by the unsafe access will not be cause for a
monetary, material, or delay claim.
506.19RIVET REMOVAL. When the Plans specify existing rivets to be removed, they shall be removed
without damaging the base metal. The rivets identified for removal shall have the rivet head ground flush
with the base metal and the shaft drilled for removal. If necessary, the rivet head on the opposite side shall
be removed in the same manner. The use of pneumatic rivet breakers and punching of rivet shanks will
not be allowed, unless approved in writing by the Engineer. Flame cutting, performed by a certified welder
on the Agency’s Pre-Qualified Welder List, will be allowed if approved by the Engineer. Each worker
performing rivet removal work shall successfully demonstrate the process on scrap metal to the
satisfaction of the Engineer prior to each worker performing any rivet removal work on the bridge. If it is
necessary to pierce the shaft of rivets with a torch, the outer surface of the rivet shank shall remain intact
during this process.
Absolutely no gouging or other damage to the structural steel will be permitted on any member that will
remain in service after the rivet is removed. If the rivet removal process causes any damage to structural
steel, the damaged member shall be repaired or replaced in a manner satisfactory to the Engineer at the
Contractor’s expense. If any gouging or other damage to structural steel occurs, the rivet removal work
shall stop immediately, and the Engineer shall be notified. At the discretion of the Engineer, the Contractor
may be required to obtain the services of a professional engineer to assess the structural capacity of the
damaged member prior to restoring traffic. All costs associated with assessing damage caused by this
removal process will be at the Contractor’s expense.
506
Where rivets are specified to be replaced, they shall be replaced with high-strength bolts meeting the
requirements of Subsection 506.18 unless otherwise specified in the Contract. Rivets shall be replaced
one at a time, unless otherwise specified in the Plans or approved by the Project Manager. Use of
temporary bolts to replace a rivet will only be allowed with written approval from the Engineer, and
provided that temporary bolts meet the requirements of Subsection 506.18.
506.20STRAIGHTENING BENT MATERIAL. Damaged, bent, or misaligned structural steel may only
be straightened or corrected by procedures approved by the Agency. The method of repair proposed by
the Contractor shall be submitted as construction drawings for approval in accordance with the
requirements of Subsection 105.06. No corrective work shall be performed without Agency approval.
Heating limitations and procedures shall conform to the requirements of Subsection 506.12.
Members or parts to be heat straightened shall be free of stress from external forces other than those
necessary and used in conjunction with the application of heat. Following straightening, the surface of the
metal shall be free of any evidence of distortion or fracture. Required nondestructive tests shall be
performed by NDT Level II or NDT Level III personnel at the Contractor’s expense.
506.21FIELD CLEANING. When assembly of the fabricated structural components is complete, any
rust, scale, dirt, grease, or other foreign material shall be removed from the metal components. The cost
of such necessary cleaning will not be paid for directly but will be considered incidental to the Section
items in the Contract.
506.22STEEL SURFACES AND COATINGS. All welding and anticipated hot work shall be completed
prior to applying any coatings on a given item unless approved in writing by the Structural Steel
Fabrication Engineer.
surfaces of unpainted steel during storage, erection, and construction of the deck.
due to oxide formation on the steel.
beams and bottom surface of their lower flanges shall be cleaned of all foreign material to
a uniform appearance. The Engineer may require the exposed surfaces to be blast cleaned
to meet SSPC-SP 10. The use of acids for cleaning is prohibited.
726.06and the following:
506
furnished to the quality assurance inspector (or the Structural Steel Fabrication Engineer,
if there is no quality assurance inspector assigned to the project) prior to shipment from the
galvanizer’s plant. Certifications shall include a report of all test results and measurements.
approved otherwise by the Engineer. Products containing aluminum shall not be used.
treated with chromate conversion coatings.
seal coated in accordance with Subsection 726.07.
accordance with the requirements of this subsection.
grade powder meeting the requirements of Subsection 708.02.
105.06for construction drawings, which includes the following information. The
submittals shall be made sufficiently in advance of coating work to allow for review,
resubmittals, and approval.
methods of surface preparation and types of equipment to be used. The plan shall
identify the solvents proposed for solvent cleaning.
blast cleaning.
product manufacturer’s recommendations for coating thickness, curing, and
product data sheets for each and every coating product.
temperature, the thickness of each coat to be applied, and the curing time and
temperature for each coat, and shall be in accordance with the manufacturer’s
recommendations.
506
inspections. The personnel performing any QC tests shall be trained in coatings inspection
and the use of the testing instruments. Documentation of training shall be provided upon
request. Reports for all quality control testing and observations shall be completed and
provided to the QA inspector on a daily basis unless otherwise authorized by the Structural
Steel Fabrication Engineer.
Fabricator QC inspections shall include, but are not limited to, the following:
etc.).
numbers.
with the manufacturer’s recommendations. At a minimum, the steel surface shall be
prepared by SSPC-SP 1 followed by SSPC-SP 7.
When powder coating is to be applied over galvanizing, the galvanized surface shall be
prepared by SSPC-SP 1, followed by SSPC-SP 16, and in accordance with ASTM D7803.
Surface grinding in accordance with SSPC-SP 11 and ASTM D7803 will be permitted in
areas where SSPC-SP 16 is not achievable or practical.
2 mils for galvanized steel shall be produced. If the profile requirements of the coating
manufacturer are more restrictive, the fabricator shall advise the Structural Steel
Fabrication Engineer and comply with the more restrictive requirements.
The surface profile produced by the fabricator’s surface preparation procedures shall be
determined by replica tape and spring micrometer and in accordance with SSPC-PA 17.
Areas having unacceptable measurements shall be further tested to determine the limits of
the deficient area. The replica tape shall be attached to the daily report.
506
When unacceptable profiles are produced, work shall be suspended. The fabricator shall
make the necessary adjustments to ensure that the correct surface profile is achieved on all
surfaces. The fabricator shall not resume work until the new profile is verified by the QA
observations and they confirm that the profile is acceptable.
but shall be applied within 8 hours of the completion of blast cleaning.
with SSPC-PA 2 and shall be within the manufacturer’s recommended thickness range. The
minimum total DFT of the powder coating shall not be less than 5.0 mils.
in accordance with the requirements of this subsection.
of Subsection 708.03.
Shop applied systems may have isolated areas where the coatings were damaged during
shipping or erection and will have areas around faying surfaces that may need field applied
primer, intermediate, and top coatings. Thus, any coating system that is used in the shop
shall be acceptable for the field conditions that are expected to be encountered.
When the plans specify paint to be applied over galvanizing, a galvanized coating applied
in accordance with Subsection 506.22(b) shall be used in place of the prime coat of the
three coat system. The first coat of paint applied over the galvanizing (intermediate coat)
shall be recommended for application over galvanizing by the manufacturer. Any and all
galvanizing repair products used prior to painting shall be compatible with the intermediate
coat.
for construction drawings, which includes the following information. The
submittals shall be made sufficiently in advance of coating work to allow for review,
resubmittals, and approval.
shall include the specified methods of surface preparation and types of equipment
to be used for removal of rust, mill scale, or foreign matter.
506
The plan shall identify the solvents proposed for solvent cleaning, together with the
solvent safety data sheets (SDS). If any detergents, additives, or inhibitors are
incorporated into the water used for any coating work operations, the plan shall
include the names of the materials and their SDS.
The plan shall also include the methods of coating application, including any
required stripe coats, and all equipment to be used.
The plan shall also identify all applicable QC/QA hold points. Specific inspection
items throughout these specifications are designated as hold points. These hold
points are for the QA inspector to perform inspections. QA inspections will be
performed only after a proper QC inspection by the fabricator. Permission to
proceed beyond a hold point without a QA inspection will be granted solely at the
discretion of the Structural Steel Fabrication Engineer, and only on a case-by-case
basis. If re-work is necessary, as determined by a QA inspection, it shall be
accomplished and a new hold point for the re-work shall be observed as defined
above.
blast cleaning and their SDS. For expendable abrasives, the Contractor shall
provide certification from the abrasive supplier that the abrasive meets the
requirements of SSPC-AB 1. For steel grit abrasives, the certification shall indicate
that the abrasive meets the requirements of SSPC-AB 3.
product manufacturer’s application and thinning instructions, SDS, and product
data sheets for each and every coating, thinner, sealer, and grease rustproofing
compound. Specific attention shall be drawn to storage temperatures and the
temperatures of the material, surface, and ambient air at the time of application.
Recommended minimum ambient weather conditions during curing shall also be
included A letter or written instructions from the coating manufacturer shall be
provided indicating the length of time that each coat must be protected from cold
or inclement weather (e.g. exposure to rain) during the drying/curing period.
506
When the Agency accepts the submittals, the fabricator will receive written
notification. The fabricator shall not construe Agency acceptance of the submittals
to imply approval of any particular method or sequence for conducting the work,
or for addressing health and safety concerns. Acceptance of the submittals does not
relieve the fabricator from the responsibility to conduct the work according to the
requirements of federal, state, or local regulations, this specification, or to
adequately protect the health and safety of all workers involved in the project and
any members of the public who may be affected by the project. The fabricator
remains solely responsible for the adequacy and completeness of the programs and
work practices, and adherence to them.
inspections. The personnel performing any QC tests shall be trained in coatings inspection
and the use of the testing instruments. Documentation of training shall be provided upon
request. Painters shall perform wet film thickness measurements, with the quality control
inspector conducting random spot checks of the wet film. Reports for all quality control
testing and observations shall be completed and provided to the QA inspector on a daily
basis.
cleaning, etc.).
sweat-in time, and wet/dry film thickness).
spray, pinholes, shadow-through, skips, misses, etc.).
product batch numbers.
506
perform QC inspections:
and relative humidity, together with all necessary tables or psychrometric
charts.
3 SSPC-VIS 1 and SSPC-VIS 3, as applicable.
a width between 1 and 3 inches.
painting, and inspection activities.
work.
The instruments shall be calibrated within 12 months of the date of project usage or
according to the equipment manufacturer’s recommendations and the fabricator’s QC
Program if they require a shorter duration.
any or all phases of the work. The presence or activity of QA inspector observations in no
way relieves the fabricator of the responsibility to provide all necessary daily QC
inspections and to comply with all requirements of this specification.
The Structural Steel Fabrication Engineer has the right to reject any work that was
performed without adequate provision for QA observations.
506
where natural light is inadequate, to allow proper cleaning, inspection, and painting.
Illumination for inspection shall be at least 30 foot-candles.
include gauges capable of accurately measuring fluid and air pressures and shall have
valves capable of regulating the flow of air, water, or paint as recommended by the
equipment manufacturer. The equipment shall be maintained in proper working order.
Hand tools, power tools, abrasive blast cleaning equipment, brushes, rollers, and spray
equipment shall be of suitable size and capacity to perform the work required. All power
tools shall be equipped with vacuums and high efficiency particulate air (HEPA) filtration.
Appropriate filters, traps, and dryers shall be provided for the compressed air used for
abrasive blast cleaning and conventional spray application. Paint pots shall be equipped
with air operated continuous agitation devices unless prohibited by the coating
manufacturer. The air discharge from power tools and air motors shall be directed away
from steel surfaces. If this is not possible a filtering device shall be appropriately placed.
and other contaminants. The fabricator shall control operations to ensure that dust, dirt, or
moisture does not come in contact with surfaces cleaned or painted that day. The following
ambient conditions shall be met:
during final surface preparation operations.
above dew point, and the maximum relative humidity shall be less than or equal to
85% during the application and cure/dry time of each coat of the paint system. If
the manufacturer’s published literature is more restrictive it shall be followed for
specific temperature, dew point, and humidity conditions during the application
cure/dry of each coat. The cure/dry time shall be measured as the time following
application when the ambient conditions are within the ranges above.
506
The fabricator shall monitor and document temperature, dew point, and relative
humidity at the beginning of each work day and every 4 hours during surface
preparation and coating application, in the specific areas where the work is being
performed. The frequency of monitoring shall increase if weather conditions are
changing. If the weather conditions are forecast to be borderline relative to the
limits established by the manufacturer, monitoring shall continue at a minimum of
4 hour intervals throughout the curing/drying period. The Structural Steel
Fabrication Engineer has the right to reject any work that was performed under
unfavorable weather conditions. Rejected work shall be removed, re-cleaned, and
repainted at the fabricator’s expense.
blowing down the surfaces, and painting with conventional spray, the fabricator shall verify
that the compressed air is free of moisture and oil contamination in accordance with the
requirements of ASTM D4285. The tests shall be conducted at least one time each shift for
each compressor system in operation. If air contamination is evident, the fabricator shall
change filters, clean traps, add moisture separators or filters, or make other adjustments as
necessary to achieve clean, dry air. The fabricator shall also examine the work performed
since the last acceptable test for evidence of defects or contamination caused by the
compressed air. Affected work shall be repaired at the fabricator’s expense.
abrasive blast cleaning to meet the requirements of SSPC-SP 10.
When the Plans specify paint to be applied over galvanizing, the galvanized surface
shall be prepared prior to applying the intermediate coat. The galvanized surface
shall be prepared by SSPC-SP 1 followed by SSPC-SP 16, and in accordance with
ASTM D 6386. Surface grinding in accordance with SSPC-SP 11 and ASTM D6386
will be permitted in areas where SSPC-SP 16 is not achievable or practical.
abrasives (other than silica sand), or recyclable steel grit abrasives. Expendable
abrasives shall be used one time and disposed of. The fabricator shall verify that
recycled abrasives are free of oil contamination by conducting oil content tests in
accordance with SSPC-AB 2 on a daily basis.
506
that the abrasive will produce a uniform surface profile of 1.5 mils to 3.5 mils for
bare steel and 1 mil to 2 mils for galvanized steel. If the profile requirements of the
coating manufacturer are more restrictive, the fabricator shall advise the Structural
Steel Fabrication Engineer and comply with the more restrictive requirements. For
recycled abrasives, an appropriate operating mix shall be maintained in order to
control the profile within these limits.
The surface profile produced by the fabricator’s surface preparation procedures
shall be determined by replica tape and spring micrometer and in accordance with
SSPC-PA 17. Areas having unacceptable measurements shall be further tested to
determine the limits of the deficient area. The replica tape shall be attached to the
daily report.
When unacceptable profiles are produced, work shall be suspended. The fabricator
shall make the necessary adjustments to ensure that the correct surface profile is
achieved on all surfaces. The fabricator shall not resume work until the new profile
is verified by the QA observations and they confirm that the profile is acceptable.
degrees of cleaning immediately prior to painting and shall be painted before
rusting appears on the surface. If rust appears or bare steel remains unpainted for
more than 8 hours, the affected area shall be prepared again at the expense of the
fabricator.
All surface preparation cleaning residue on steel surfaces shall be removed prior to
painting.
The quality of surface preparation and cleaning of surface dust and debris shall be
accepted by the QA inspector prior to painting. The Structural Steel Fabrication
Engineer has the right to reject any work that was performed without adequate
provision for QA observations to accept the degree of cleaning. Rejected coating
work shall be removed and replaced at the fabricator’s expense.
according to these specifications and as specified in the paint manufacturer’s written
instructions and product data sheets for the paint system used. In the event of a conflict
between these specifications and the coating manufacturer’s instructions and data sheets,
the fabricator shall advise the Structural Steel Fabrication Engineer and comply with the
most restrictive requirements.
506
published instructions, including handling, minimum and maximum temperatures,
and warming as required prior to mixing. All coatings shall be supplied in sealed
containers bearing the manufacturer’s name, product designation, batch number,
and mixing/thinning instructions. Leaking containers shall not be used. The paint
shall be stored in a secure fireproof location.
Mixing shall be performed according to the manufacturer’s instructions. Thinning
shall be performed using thinner provided by the manufacturer, and only to the
extent allowed by the manufacturer’s written instructions. In no case shall thinning
be permitted that would cause the coating to exceed the local volatile organic
compound emission restrictions. For multiple component paints, only complete kits
shall be mixed and used. Partial mixing is not allowed.
The ingredients in the containers of paint shall be thoroughly mixed by mechanical
power mixers according to the manufacturer’s instructions, in the original
containers before use or mixing with other containers of paint. The paint shall be
mixed in a manner that will break up all lumps, completely disperse pigment, and
result in a uniform composition. Paint shall be carefully examined after mixing for
uniformity and to verify that no unmixed pigment remains on the bottom of the
container.
Excessive skinning or partial hardening due to improper or prolonged storage will
be cause for rejection of the paint, even though it may have been previously
inspected and accepted. Manufacturer recommended induction/sweat-in times and
temperature of mixed coatings shall be observed.
Multiple component coatings shall be discarded after the expiration of the pot life.
Single component paint shall not remain in spray pots, paint buckets, etc. overnight
and shall be stored in a covered container and remixed before use.
coat of paint shall be applied as a continuous film of uniform thickness free of
defects including, but not limited to, runs, sags, overspray, dry spray, pinholes,
voids, skips, misses, and shadow-through. Defects such as runs and sags shall be
brushed out immediately during application.
506
Unless prohibited by the coating manufacturer’s written instructions, paint may be
applied by spray methods, rollers, or brushes. If applied with conventional or airless
spray methods, paint shall be applied in a uniform layer with overlapping at the
edges of the spray pattern.
The painters shall monitor the wet film thickness of each coat during application.
The wet film thickness shall be calculated based on the specified dry film thickness
using the solids by volume of the material and the amount of thinner added.
When brushes or rollers are used to apply the coating, additional applications may
be required to achieve the specified thickness per layer.
considered dry for re-coating according to the re-coat time/temperature/humidity
criteria provided in the manufacturer’s instructions, and when an additional coat
can be applied without the development of film irregularities such as lifting,
wrinkling, or loss of adhesion of the under coat.
an additional stripe coat to edges, crevices, welds, and similar surface irregularities
for the prime coat and intermediate coat. The stripe coat shall be applied by brush
or roller, as per the manufacturer’s recommendations, such that the coating is
thoroughly worked into or on the irregular surfaces. The stripe coat shall extend
onto the surrounding steel a minimum of 1 inch in all directions. The purpose of
the stripe coat is to build additional thickness and to ensure complete coverage of
these areas.
The stripe coat shall not be applied as part of the application of the full coat. The
stripe coat shall be applied and dried separately according to the manufacturer’s
recommended drying times. Also, the color of the stripe coat shall contrast with the
colors used for the full coats immediately preceding and succeeding the stripe coat.
applied as follows:
Once the full prime coat has dried, the prime stripe coat shall be applied.
stripe coat shall be applied and allowed to dry, followed by the full
intermediate coat.
506
be applied.
measured in accordance with SSPC-PA 2. If the manufacturer’s upper or lower thickness
limit is more restrictive, it shall be followed instead.
and 5.0 mils dry film thickness.
mils and 6.0 mils dry film thickness.
dry film thickness. The top coat color shall be according to Contract.
under certain conditions. Amine blush often appears as a yellowish milky or blotchy
residue on the coating surface and is a deterrent to the adhesion of subsequently applied
coating layers. If amine blush is detected, the Contractor shall provide the Engineer with
written procedures from the coating manufacturer for complete removal prior to the
application of additional coating layers.
newly installed coating system, at no cost to the Agency. If the damage extends to the
substrate, the damaged areas shall be prepared to meet SSPC-SP 3.
The surrounding coating at each repair location shall be feathered for a minimum distance
of 1-1/2 inches to achieve a smooth transition between the prepared areas and the existing
coating.
If the bare steel is exposed, all coats shall be applied to the prepared area. If only the
intermediate and finish coats are damaged, the intermediate and finish coats shall be
applied. If only the finish coat is damaged, the finish coat shall be applied.
All hold points and specifications are applicable to the repair of damaged areas and areas
concealed by containment.
506
Contractor may request that the Engineer waive the requirements for NACE certification
and SSPC-QP 1 certification for the necessary field painting of the bolted connection areas.
Requests will be reviewed on a case-by-case basis and will only be considered on projects
with limited amounts of required field painting such as diaphragm and cross frame
connections. If the Engineer grants the request, all other requirements for certifications,
inspections, quality control, supplying inspection equipment, hold points, etc. will remain
in effect.
Contract requires installation of bolts that are to be painted. This work shall occur after bolt
tensioning has been completed. All exposed oils, lubricants, and wax on the bolts, nuts,
washers, and surrounding surfaces to be painted shall be completely removed by solvent
cleaning. This also includes any foreign material that has come out of the DTIs during the
tensioning process. Light hand wire brushing or scrubbing with bristle brushes is allowed.
Use of power tools is not allowed.
For galvanized hardware, the Contractor shall remove the colored lubricant from the nuts.
The galvanizer may be able to provide information to the Contractor on the most effective
solvent cleaner to remove the colored lubricant (common examples include methyl-ethyl-
ketone (MEK), foaming glass cleaners containing ammonia, and foaming alkaline-type
household cleaners). It is not necessary to remove 100% of the dye, and it is acceptable for
some staining to remain after cleaning. A white cloth wipe test with no color transfer can
be used to confirm that all lubricant and non-absorbed dye has been removed, leaving only
the residual stain on the surface. The final cleanliness shall be acceptable to the Engineer.
shall be performed in accordance with Subsection 708.04.
Grease rustproofing compound shall be uniformly applied in a single coat by brush or spray at an
approximate rate of 20 square feet per gallon to the steel as specified. This shall occur after all
concrete form work has been removed, and after the final coat of paint, including repairs, has fully
cured. A fully cured condition has occurred when a thumbnail driven into the coating surface does
not leave an impression and when a thumb firmly pushed against the surface and twisted does not
disturb the coating.
Surfaces adjacent to areas being grease coated shall be protected against over-spray. Non-metallic
and stainless steel surfaces shall not be coated.
506
506.23METHOD OF MEASUREMENT
item, to be measured for payment will be the number of pounds used in the complete and accepted
work. The weight of the material to be measured for payment under this item will be computed
based on the approved fabrication drawings, as follows:
specified in Table 506.23A.
TABLE 506.23A – MATERIAL DENSITIES
Material Density (lbs/ft )
Aluminum, Alloy 173
Bronze, Cast 536
Copper, Alloy 536
Copper, Sheet 558
Iron, Cast 445
Iron, Wrought 487
Lead, Sheet 707
Steel – Rolled, Cast, Copper
Bearing, Silicon, Nickel, or Stainless 490
For any material not listed in Table 506.23A, the material will be paid for by actual weight
as measured on a certified scale.
foot as shown on the Plans or, if not shown on the Plans, by the weights shown in the AISC
Steel Construction Manual.
The weight of rolled shapes will be based on the overall net length shown on the approved
fabrication drawings, with no allowance for milling, finishing, or overrun, and with no
deduction for cuts, clips, copes, or open holes.
fabrication drawings, with no allowance for milling, finishing, tolerance, or overrun, and
with no deductions for copes, clips, and open holes. The weights of beveled plates or curved
surface plates will be based on the finished maximum thickness shown on the approved
fabrication drawings.
506
For gusset plates, scupper components, slotted plates, and similar minor fixtures the net
finished dimensions will be the minimum rectangular dimensions from which the parts are
cut, except when it is practical to cut the parts in multiples from pieces of larger dimensions,
in which case the weight will be based on the dimensions of the larger pieces, making
necessary allowance for the material lost in cutting.
The net finished dimensions of flange plates will be the nominal width and the finished
length measured along the centerline of the flange without deduction for width transitions,
bevels, or chamfers.
The net finished dimensions of the webs of all girders and of the webs of rigid frame legs
will be the actual area of the web as detailed on the approved fabrication drawings.
will be made for the weight of weld metal used.
incorporated into the structure and temporary erection bolts, nuts, and washers shall be
incidental to the Structural Steel item and no measurement will be made for weight of the
bolts, nuts, direct tension indicators, and washers.
item, to be measured for payment will be on a lump sum basis in the complete and accepted work.
number of existing rivets replaced with high strength bolts in the complete and accepted work.
Rivets measured for replacement will be made in only the locations specified in the Contract and
in any other locations identified for replacement by the Engineer. Unless otherwise specified in
the Contract, rivet removal and installation of new fasteners associated with structural steel repairs
will not be measured for payment as Rivet Replacement.
506.24BASIS OF PAYMENT. The accepted quantity of Structural Steel will be paid for at the Contract
unit price per pound or at the Contract lump sum price for the items specified in the Contract. Payment
will be full compensation for furnishing, detailing, handling, transporting, and placing the materials
specified, including nondestructive testing of welds; for preparing the surface of new steel to be painted,
galvanized, metalized, or to remain unpainted; for necessary field cleaning; and for painting, metalizing,
sealing, galvanizing, or grease coating of surfaces, unless otherwise paid for. Payment will also be full
compensation for furnishing and implementing the erection plan, nondestructive testing, quality control
activities, and for furnishing all labor, tools, equipment, and incidentals necessary to complete the work.
506
The Engineer may authorize partial payments in the following manner:
approved for fabrication.
completed and accepted in accordance with the approved fabrication drawings, stored in a location
and manner accepted by the Structural Steel Fabrication Engineer, and all applicable material
certifications have been approved.
falsework removed, and painting of connections and touch-up completed where required.
of all work under this section, including extended weights being received and checked.
The accepted quantity of Rivet Replacement will be paid for at the Contract unit price for each. Payment
will be full compensation for performing the work specified and for furnishing all labor, tools, equipment,
and incidentals necessary to complete the work.
Payment will be made under:
Pay Item Pay Unit
506.5000 Structural Steel, Rolled Beam ...................................................................Pound
506.5500 Structural Steel, Plate Girder ....................................................................Pound
506.5600 Structural Steel, Curved Plate Girder........................................................Pound
506.5700 Structural Steel, Truss ...............................................................................Pound
506.6000 Structural Steel ..........................................................................................Pound
506.7500 Structural Steel ..........................................................................................Lump Sum
506.8500 Rivet Replacement ....................................................................................Each
507
5-130SECTIO N 507 – REINFORCIN G STEEL
507.0 1 DESCRIPTION . This work shall consist of furnishing and placing bar reinforcement of the level specified, dowels, wire, welded wire reinforcement (WWR), and mechanical bar connectors. Levels and associated types of reinforcing steel are specified as follows:
coated reinforcing steel.
continuously -galvanized , low -carbon chromium, and hot-dipped galvanized reinforcing steel.
reinforcing steel. The location, level, and when specified, type of reinforcing shall be as indicated on the Plans. Reinforcing supplied shall meet the requirements of the level specified or any higher level. Only one type of reinforcing steel shall be used for each level for the Contract work, unless permitted in writing by the Engineer. 507.0 2 MATERIALS . Materials shall meet the requirements of the following subsections: Mortar, Type IV ................................ ................................ ................................ ......... 707.0 1(e) Bar Reinforcement ................................ ................................ ................................ .....713.01 Mechanical Splices for Bar Reinforcement ................................ ............................... 713.02 Welded Wire Reinforcement ................................ ................................ ..................... 713.0 3 507.0 3 FABRICATIO N AND SHIPMENT . Bar reinforcement shall be deformed bar cold bent to the shapes required. Bar reinforcement shall be fabricated, bundled, tagged, marked, and shipped in accordance with the CRSI Manual of Standard Practice . The fabricator shall maintain records that will provide traceability of identifying heat numbe rs for all material being fabricated for Agency projects or Contract orders referencing materials covered under this section . 507.0 4 PROTECTIO N OF MATERIAL . Reinforcing steel shall be protected from damage at all times by storing it on blocking, racks, or platforms. When multiple levels of reinforcing steel are used on a project, they shall be stored separately, including during transport in order that there is no direct contact between the bars. When placed in the work, the reinforcing steel shall be free from dirt, detrimental scale, paint, oil, previously placed concrete, or other foreign substances.
STRUCTURAL STEEL in other states
Get an email when 506 changes
Vermont revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.