5-327 SECTIO N 543 – CONTRACTOR -FABRICATE D PRECAS T CONCRET E STRUCTURE
543.0 1 DESCRIPTION . This work shall consist of manufacturing, transporting, handling, and erecting
precast concrete structure components fabricated by the Contractor at a location other than a PCI or NPCA certified precast concrete facility.
543.0 2 MATERIALS . Materials sh all meet the material requirements specified in Subsection 501.02 ,
Subsection 507.02 , and Subsection 540.02 . Concrete shall meet the material requirements specified in Subsection 540.05 .
543.0 3 GENERA L FABRICATIO N REQUIREMENTS . Unless noted otherwise her ein, Contractor -
fabricated precast concrete (CFPC) shall meet the requirements of Section 501 , Section 507 , and Section 540.
543.0 4 SUBMITTALS . As soon as practical after award of the Contract, all required information shall
be prepared and submitted. Fa brication drawings and erection plans shall be submitted as separate submittals. If the Contractor proposes a different configuration than what is provided in the Plan s then a complete copy of the structural design calculations for the CFPC shall be submitted accompanying the construction draw ings in accordance with Subsection 105.06 . The design calculations shall substantiate that the proposed precast concrete satisfie s the design parameters of the Contract. The applicable design code will be the AASHTO LRFD Bridge Design Specifications unless indicated otherwise in the Contract . Fabrication drawings for the precast concrete shall be submitted in accordance with Subsect ion 105.06 . In addition to the requirements for fabrication draw ings in Subsection 105.06 , the following shall also be included:
543.05 INSPECTION . Materials furnished and the work performed herein shall be inspected by the
Agency. The Agenc y will test all concrete incorporated into the work in accordance with Section 501 . The inspector shall have the authority to reject any material or work that does not meet the requirements of the specifications. Advance notification of at least 14 calendar days shall be provided by the Contractor to the Engineer and the Structural Concrete Engineer c oncerning the proposed intention to commence work. A minimum notification of 5 working day s shall be provided by the Contractor to the Engineer and the Structural Concrete Engineer to confirm the fabrication start date.
543.0 6 Fabrication .
543.0 7 HANDLING , STORAGE , AND SHIPPING . Each CFPC structure shall be handled, stored, and
shipped in such a manner as to minimize chipping, cracks, fractures, discoloration, and excessive bending stresses. A unit damaged by handling, storage, or shipping shall be replaced at the Contractor’s expense. A CFPC structure shall not be installed until the respective unit has been inspected. This inspection shall verify that the pieces are free from defects, and that all specification requirements, including but not limited to those for compressive strength and tolerance requirements, have been achieved. In addition, a CFPC structure will not be considered for shipment until the completion of the cure period a nd the required strength has been attained as demonstrated by field cured cylinder breaks. 5-330 Field cured test cylinders for production site handling and shipping strength verification purposes shall be tested either at the Agency’s Materials Testing and Certification Section Central Laboratory or at an independent laborat ory approved by the Engine er. An Agency representative shall witness all tests. If an independent laborat ory is proposed to be used to test the field cured cylinders, the Contractor shall submit documentation providing verification for the following:
543.0 8 INSTALLATIO N METHODS , EQUIPMENT , AND ERECTION . Cranes, lifting devices, and
other equipment for CFPC structure erection shall be of adequate design and capacity to safely erect, align, and secure all members and components in their final positions without damage. The Contractor is solely responsible for the methods and equipment employed for the erec tion of the CFPC structure components. Construction drawings for CFPC structure component erection shall be submitted in accordance with Subsection 105.06 . The erection plan shall include the necessary computations to indicate the magnitude of stress in th e units during erection and to demonstrate that all of the erection equipment has adequate capacity for the work to be performed, and provisions for all stages of construction, including temporary stoppages. Post tensioning shall comply with Subsection 540 .12. Submittal of the erection plan is for documentation purposes only and shall in no way be construed as approval of the proposed method of erection. The Contractor shall follow the erection plan as submitted.
543.0 9 GROUT . Grout shall be placed in accordance with the requirements of Subsection 540.11 .
543.1 0 METHO D OF MEASUREMENT . The quantity of Contractor -Fabricated Precast Concrete
Structure of the type and size specified to be measured for payment will be on a lump su m basis in the complete and accepted work . The lump sum will include all of the CFPC structure components for each location specified in the Contract. 5-331 543.1 1 BASIS OF PAYMENT . The accepted quantity of Contractor -Fabricated Precast Concrete Structure of the type and size specified will be paid for at the Contract lump sum price. Payment will be full compensation for designing, detailing, fabricating, repairing, transporting, handling, and erecting the materials specified, for furnishing and implementing the erection plan, and for furnishing all labor, tools, equipment, and incidentals necessary to complete the work. Any grouting work, such as fairing out unevenness between adjacent precast concrete structure components and filling leveling screw holes, sh ear keys, transverse anchor recesses, and dowel holes, will be considered incidental to the work for Contractor -Fabricated Precast Concrete Structure. Payment will be made under: Pay Item Pay Unit
543.10 00 Contractor -Fabricated Precast Concrete Structure ................................ ....Lump Sum
5-332 SECTIO N 544 – PREFABRICATE D BRIDG E UNIT SUPERSTRUCTURE
544.0 1 DESCRIPTION . This work shall consist of manufacturing, transporting, and erecting concrete
and steel composite Prefabricated Bridge Units (PBUs) as shown on the Plan s. The work under this section shall be performed in accordance with these provisions, the Plan s, and Section 501, Section 506 , Section 507 , and Section 508 .
544.0 2 MATERIALS . Materials shall meet the material requirements specified in Subsection 501.02 ,
Subsection 506.02 , Subsection 507.02 , and Subsection 508.02 .
544.0 3 GENERA L FABRICATIO N REQUIREMENTS . The structural steel furnished under this section
shall be fabricated in a p lant meeting the requirements of Subsection 506.03 . After fabrication, the structural steel shall be transported to a location approved by the Agency where the steel will be shop galvanized , metallized , or painted, or where the remainder of the composite superstructure unit will be fabricated. The fabricator or Contractor constructing the reinforced concrete portion of the PBUs shall have demonstrated experience in forming, casting, curing, and finishing performance -based concrete superstructure decks in accordance with Section 501 .
544.0 4 SUBMITTALS . As soon as practical after award of the Contract, all required information shall
be prepared and submitted. Fabrication drawings and erection plans shall be su bmitted as separate submittals. Fabrication drawings for the PBUs shall be submitted in accordance with Subsection 105.06 . In addition to the requirements for fabrication draw ings in Subsection 105.06 , the following shall be included: