6-202 SECTIO N 651 – TURF ESTABLISHMENT 651.0 1 DESCRIPTION . This work shall consist of the preparation of an area and the application of topsoil, grubbing material, sod, seed, soil amendments, and mulch. 651.0 2 MATERIALS . Materials shall meet the requirements of the following subsections: Topsoil ................................ ................................ ................................ ....................... 755.02 Sod ................................ ................................ ................................ ............................. 755.03 Seed ................................ ................................ ................................ ............................ 755.04 Compost ................................ ................................ ................................ ..................... 755.05 Fertilizer ................................ ................................ ................................ ..................... 755.06 Agricultural Limestone ................................ ................................ .............................. 755.08 Liquid Lime ................................ ................................ ................................ ............... 755.09 Hay Mulch ................................ ................................ ................................ ................. 755.10(a) Fiber Mulch ................................ ................................ ................................ ................ 755.10(d) Hydraulic Matrix ................................ ................................ ................................ ........ 755.10(e) Tackifier ................................ ................................ ................................ ..................... 755.10(f) Straw Mulch ................................ ................................ ................................ ............... 755.10(g) Rolled Erosion Control Product, Type I ................................ ................................ ....755.1 1(a) Rolled Erosion Control Product, Type II ................................ ................................ ...755.11(b) Stakes for holding sod shall be rounded or square wooden stakes at least 8 inches long and have a cross - sectional area of approximately one square inch. Stakes of other materials or designs may be used when authorized by the Engineer. Grubbing material for use on stone fill along streams shall consist of grubbed or stripped earth material containing roots of native stream bank vegetation. Grubbing material for use on slopes shall consist of grubbed or stripped earth material containing roots (not necessarily from native stream bank vegetation) which will promote the growth of vegetation. Grubbing material from outside of the project limits shall not contain any invasive plant material found on the state or federal noxious weed lists on file with the Vermont Agency of Agriculture, Food, and Markets. 651.0 3 GENERAL REQUIREMENTS . Turf establishment shall occur during the time periods specified in the Plans, unless otherwise authorized under appl icable permits or directed by the Engineer. All seeded areas shall be inspected by the Engineer for turf establishment within 14 calendar days of application. Areas not showing signs of sufficient growth shall be reestablished at the Contractor’s expense. 6-203 651.0 4 PREPARATIO N OF AREA . Preparation of areas for turf establishment shall not take place when the area is frozen, excessively wet, or otherwise in a condition detrimental to the work, as determined by the Engineer. Areas receiving topsoil or sod shal l have an allowance made for the depth of topsoil or thickness of sod if not accounted for on the Plans. Surfaces shall be prepared with all breaks in grade well -rounded, to the satisfaction of the Engineer. All stones, lumps, roots, or other objectionable materials shall be removed .
755.02 and shall also be soil tested in accordance with Subsection 755.02 . Native material shall be
reworked as necessary to meet the requirements of Subsection 755.02 and any amendments needed, as determined by soil testing, shall be added at the determined rat es.
704.06 .
653.0 3 EPSC PLAN . The Contractor shall be responsible for the development of an EPSC plan and shall become a co -permittee with the Agency on project s with associated permits.