105.1 Authority and Duties of Commission in Contract Administration. The Commission is subject to comply with and to have the power and authority provided in, among others, the following laws in execution of the Commission’s authority over all state transportation programs and facilities:
105.10 Inspection of Work. All material and each part or detail of the work will be subject to inspection by the
engineer. The engineer shall be allowed unlimited access to all parts of the work and shall be furnished with such information and assistance by the contractor as is required to make a complete and detailed inspection.
105.10.1 If requested by the engineer, the contractor, at any time before acceptance of the work, shall remove or
uncover such portions of the finished work as may be directed. After examination, the contractor shall restore said portions of the work to the standards required by the contract documents. If the work thus exposed or examined proves acceptable, the uncovering, the removing, recovering or making good the parts removed will be paid for in accordance with Sec 109. If the work so exposed or examined proves unacceptable, the uncovering, removing, recovering or making good the parts removed shall be at the contractor’s expense.
105.10.2 Any work done or material used without inspection by an authorized Commission representative may
be ordered removed and replaced at the contractor’s expense.
105.10.3 If any unit of government or political subdivision pays all or a portion of the cost of the work covered
by the contract, the unit’s respective representatives shall have the right to inspect the work.
105.10.4 When any work is being done on, over or under railroad right of way or adjustments are being made to
any public or privately-owned utility facility, the respective representatives shall have the right to inspect the work.
105.10.5 Inspections authorized in Secs 105.10.3 and 105.10.4 will not make any of these agencies a party to the
contract or affect the rights of the parties to the contract.
105.10.6 Adequate provisions for lighting, meeting the prior approval from the engineer, shall be provided by
the contractor to permit satisfactory construction and inspection of all work done and material produced.
105.10.7 Final Inspection. Upon presumptive completion of the entire project, the engineer will make an
inspection. If all construction contemplated by the contract has been completed to the engineer’s satisfaction, that inspection will constitute the final inspection. The engineer will make the acceptance for maintenance upon completion of the final inspection. The engineer will notify the contractor in writing of acceptance for maintenance as of the date of the final inspection, with the exception of items covered by item specific performance bonds. Final acceptance will take place within a maximum of 30 days of receipt of final documentation from the contractor.
105.10.7 1 Following the final inspection, the contractor, subcontractors and suppliers will be relieved of any
new or additional liability to third parties for personal injury, death or property damages which may be alleged to result from the design or construction of the work, unless additional work on the right of way will be required by the engineer.
105.10.7 2 Nothing in Sec 105.10.7 shall be deemed to excuse the contractor of liability or responsibility for any
personal injury, death or property damages which may have occurred prior to the final inspection of the work.
105.11 Unauthorized and Defective Work.
105.11.1 All changes in the work or departures from the plans, except those due to reclassification of excavation
material, will be considered unauthorized and at the contractor’s expense unless, before proceeding with the work, the contractor has a copy of an order record signed by the engineer, or a change order signed by all parties whose signatures are provided for, except the federal engineer. These forms will contain complete detailed instructions regarding the proposed changes. Any departure from the instructions contained in such a written order will be considered unauthorized.
105.11.2 The engineer may order unauthorized work removed and replaced at the contractor’s expense.
105.11.3 All construction and materials that have been rejected or declared unsatisfactory shall be remedied or
removed and replaced in an acceptable manner by the contractor at the contractor’s expense. Upon failure of the contractor to remedy or remove and properly dispose of rejected material or work, or to replace them immediately after receiving written notice from the engineer, the engineer may employ labor to rectify the work, and the cost of rectification will be deducted from any payment due or which may become due the contractor.
105.12 Load Restrictions.
105.12.1 The contractor’s movement of equipment and vehicles over bridges and pavements within the limits of
the project will be subject to the load limit regulations for highways as prescribed by state statutes in effect when the movement occurs, and the contractor shall acquire special permits from the Commission prior to the movement of any such equipment or vehicles with a gross weight in excess of the load limits permitted by statute. All costs of obtaining special permits shall be at the contractor’s expense, unless the special permit will be required by a restriction first imposed after the contractor has submitted the bid on the project. Outside of project limits, width, length, height and weight limitations as prescribed by state statutes shall be adhered to by the contractor during the movement of equipment and vehicles over any part of the state highway system, to include project exceptions, and the contractor shall not move or operate any such equipment or vehicles that exceed any statutory limitation without special permits from the Commission. All costs of obtaining special permits shall be at the contractor’s expense. Material receipts issued by the engineer will not indicate compliance with any weight restriction regulations. All permits required for movement over highways other than those that are state owned or maintained shall be obtained by the contractor from the respective authority at the contractor’s expense.
105.12.1 1 Special permits will not be required for the movement of construction equipment over any part of a
bridge or pavement that is constructed or rehabilitated in the contract.
105.12.1 2 All movement will be subject to the same conditions and regulations established by the Commission
for movements under special permits with the following additional requirements:
105.12.1 3 Movement of equipment over bridges or pavement not constructed under the contract, but located
within the limits of the contract, will be subject to all requirements of this section, and a special permit will be required.
105.12.2 Track or crawler-type equipment having a gross weight of 40,000 pounds or less, evenly distributed
over the treads, may be moved over bridges not posted for lesser loads or over rigid-type pavements without special permits. Such equipment having a gross weight in excess of 40,000 pounds shall have a special permit before moving. Crawler-type equipment having a gross weight in excess of 75,000 pounds will not be permitted on bridges or rigid type pavements unless authorized by the engineer.
105.12.3 Track or crawler-type equipment that is subject to unequal distribution of weight, such as cranes and
paving mixers and which have a gross weight in excess of 18,000 pounds but less than 40,000 pounds , may be operated upon bridges not posted for lesser loads and rigid type pavements, provided special precautions satisfactory to the engineer are taken to distribute the weight evenly over the treads. Such equipment in excess of 40,000 pounds will require a special permit from the Commission.
105.12.4 The contractor shall not move or operate any type of equipment of such weight or so loaded that the
equipment will cause damage to highway facilities either being constructed or in existence. Equipment and vehicles with steel lugs will not be permitted to operate directly on bridges or pavements at any time.
105.12.5 When it is required that material from roadway or borrow excavation be hauled across existing
pavement, the contractor may move the material across the pavement with equipment that results in overweight loading, provided the following requirements are met at the contractor’s expense:
105.12.6 The contractor shall not store or stockpile any materials on a bridge without approval from the
engineer.
105.12.7 Nothing contained herein or in any special permit will relieve the contractor of liability for any damage
caused to highway facilities from the movement or operation of equipment and vehicles over the highway system.
105.13 Maintenance of the Work. The contractor shall maintain the work during construction until the work is
accepted. This maintenance shall be prosecuted such that the roadway or structures are kept in satisfactory condition at all times.
105.13.1 In the case of a contract for placing a course upon a course or subgrade previously constructed, the
contractor shall maintain the previous course or subgrade during all construction operations.
105.13.2 No direct payment will be made for maintenance of the work before the work is accepted.
105.14 Failure to Maintain Roadway or Structure. If the contractor’s performance at any time fails to comply
with the provisions of Sec 105.13, the engineer will notify the contractor of such non-compliance. If notice is provided verbally, notice will be promptly confirmed in writing. If the contractor fails to remedy unsatisfactory maintenance within 24 hours after receipt of such notice, the engineer may immediately proceed to maintain the project, and the entire cost of this maintenance will be deducted from monies due or to become due the contractor.
105.15 Acceptance.
105.15.1 Partial Acceptance. The contractor may request that the engineer inspect the following completed
sections of work for acceptance at any time during the prosecution of the project:
105.15.1 1 If the contract contains seasonal items, such as sodding, painting or such items as might delay the
final completion of the project, a partial acceptance of the completed portion may be made prior to completion of the entire project. If the engineer finds upon inspection that the completed work is in acceptable condition, the contractor will be notified in writing and after such notice has been given, the contractor will be relieved of the duty of maintaining and protecting that work to the extent provided in the notice.
105.15.1 2 Nothing in the contract shall be construed to relieve the contractor of full responsibility for making
good any non-latent defect in work or material found on any section of work prior to final acceptance of the entire project, to alter in any manner the method of payment prescribed in the contract or to constitute a waiver of any claim the Commission might have against the contractor on the entire project.
105.15.2 Final Acceptance. Upon receipt by the engineer of all project documentation required by the contract
and verification by the engineer that all material incorporated into the work has been properly inspected, the engineer will make the final acceptance upon completion of the final inspection and acceptance for maintenance in accordance with Sec 105.10.7.
105.15.2 1 When required by the contract, project documentation shall consist of the following: Contractor’s
Affidavit Regarding Settlement of Claims (Form C-242), Final Change Order, DBE Participation List and Final Verification, Affidavit – Compliance with the Prevailing Wage Law.
105.15.2 2 Final acceptance will not excuse the contractor’s liability or responsibility to the Commission for any
latent defects in the work or material incorporated into the work, or for claims relating to any work or material incorporated into the work.
105.16 Controversies and Claims for Adjustment.
105.16.1 The contractor shall follow the requirements of Sec 104.4 for written notification of differing site
conditions or significant changes in the character of work and Sec 108.15 for suspensions of work directed by the engineer. If, after receiving a written reply from the engineer the contractor considers additional compensation is due, the contractor shall file a written notice of claim for additional compensation within 60 days after completing the work in question. The procedure for filing a claim shall be as described in Secs
105.16.6 through 105.16.8.2.
105.16.2 If the contractor considers additional compensation may be due for work or material not clearly
covered in the contract or not ordered in writing by the engineer as change in the work, the contractor shall notify the engineer in writing of the intention to make a claim before beginning the work in question. If notification is not given and the engineer is not afforded proper facilities by the contractor to provide necessary inspection and for keeping strict account of actual costs, the contractor agrees to waive any claims for additional compensation. Notice by the contractor and the fact that the engineer has kept account of the costs shall not be construed as substantiating the validity of the claim. The contractor shall file a written notice of claim for additional compensation within 60 days after completing the work in question. The procedure for filing the claim shall be as described in Secs 105.16.6 through 105.16.8.2.
105.16.3 Claims for additional time or compensation under Sec 104 shall be filed within 60 days after
completing the work in question. Claims for additional time or compensation in accordance with Sec 108 shall be filed within 60 days after receipt of the engineer’s determination. The procedures for filing and the disposition of the claim or controversy shall be in accordance with Secs 105.16.3 through 105.16.9.
105.16.4 If the contractor has any claim against the Commission arising out of the provisions of the contract or
the performance or non-performance thereunder, and is not within the scope of Sec 105.16.1 through 105.16.3, the claim shall be filed within the earlier of:
105.16.5 If the Commission has a claim against the contractor that in any way arises out of the provisions of the
contract or the performance or non-performance thereunder, the claim will be filed within 90 days after the date of final inspection under Sec 105.10.7, except for claims of a differing site condition or defects in work or material under Sec 105.15.2.2.
105.16.6 If the claim is against the Commission, the written claim shall be personally delivered or sent by
certified mail to the Office of the Secretary of the Commission in Jefferson City, Missouri. If the claim is against the contractor, the written claim will be personally delivered or sent by certified mail to the contractor at the address shown under the signature on the contract. If the claim is against an assignee, the written claim will be personally delivered or sent by certified mail to the assignee at the address shown on the accepted notice of assignment.
105.16.6 1 This provision shall not extend the claim filing time limits of the contractor or the Commission in the
case of a differing site condition or a suspension of the work under Sec 108.
105.16.6 2 This provision will not limit the Commission’s claim filing time for defects in work or material not
discovered within 90 days after the date of final inspection under Sec 105.10.7 or other claim rights not discovered within 60 days of filing of any claim by the contractor, or as to any work covered by a separate or continuing performance bond specified to survive project final acceptance.
105.16.7 Claim submittals on the contractor’s part shall be in sufficient detail, as specified in this section, to
enable the engineer to determine the basis for additional time or compensation. The following minimum information shall accompany each claim submitted:
105.16.8 Required Certification of Claims. The claim submittal shall include the contractor’s written
certification, under oath, attesting to the following:
105.16.8 1 The person signing the claim and affidavit under oath shall be the owner if the contractor is a sole
proprietorship, shall be a general partner if the contractor is a partnership, shall be an authorized agent if the contractor is a limited liability company or joint venture, or shall be an authorized officer or member of the board if the contractor is a corporation.
105.16.8 2 No claim shall be deemed filed under the contract by a contractor until:
105.16.9 Duty to Supply Records and Information Regarding a Claim or Controversy. The Commission is
subject to a legal duty to pay no additional sum to a contractor after a contract has been entered into and performed in whole or part, or any claim under any agreement or contract made without express authority of law. The Commission is under the further legal duty to pay only those claims that are supported, which have a basis in the terms of the contract and applicable state law as fairly construed and which are in accordance with prevailing principles of public contract law. The Commission is obligated by law to set forth both the contractual basis and the cost data, supported by audit, of actual costs incurred by the contractor to substantiate any amount paid.
105.16.9 1 Record Retention. From and after the date the contractor determines a cause has occurred for a
possible contract adjustment, and notwithstanding any policy the contractor may have regarding record retention, the contractor shall retain all files, records and data, in whatever form, that relate to the contractor’s bid and performance of the contract relevant to the possible contract adjustment.
105.16.9 2 Duty to Supply Information. During the review of the claim, the contractor and the contractor’s
subcontractors and suppliers shall cooperate with MoDOT and shall provide, if requested, access to the documents that contain the below information, to the extent requested by MoDOT and MoDOT’s attorneys or consultants. Request for some, but not all, of the following information will not preclude MoDOT’s right to request the same or additional information at another time:
105.16.9 3 Confidentiality of Records. The contractor and, if applicable, the contractor’s subcontractors and
suppliers, shall deliver to MoDOT and MoDOT’s attorneys or consultants, all information and documents requested, notwithstanding any claim of confidentiality or proprietary interest in the records. MoDOT and MoDOT’s attorneys and consultants will affirmatively act to protect the records and information from disclosure beyond those persons having a need to know the information for the purpose of making a decision regarding the claim, or for law enforcement purposes. The contractor shall identify and segregate any documents or information that the contractor considers particularly sensitive.
105.16.10 On any claim for additional compensation for work on the project, whether claimed under the
contract, for a differing site condition, as a change in the work, for breach of the contract, for a positive representation by which the contract was induced or otherwise, the following items shall never be allowable or claimed directly or indirectly:
105.16.11 Any claim, controversy or item of any claim or controversy not included in the writings required to be
filed in Sec 105.16, or any claim included but not clearly defined and specifically set out, itemized and supported, or any notice or claim not filed within the time and in the manner provided in Sec 105.16, shall be forever waived, and shall neither constitute the basis of nor be included in any legal action, counterclaim, defense, set-off, arbitration or other alternative dispute resolution procedure mutually agreed upon between the parties.
105.16.11 1 The omission of any claim or of the detail required to be in a claim in accordance with Sec 105.16.7
will not be subject to cure by making the claim or supplying the details in any later court or alternative dispute resolution proceeding.
105.16.11 2 MoDOT has established a written procedure for handling contractor claims and controversies that
provides the process for resolution of all claims and the engineer’s final decision. The completion of that process and the engineer’s final decision will be a condition precedent to any legal action, counterclaim, defense, set-off or arbitration concerning the matters claimed. Any claim or controversy, or any portion thereof that has not been presented for handling in accordance with MoDOT’s contractor claims and controversies procedure will not be subject to resolution in an alternate dispute resolution process.
105.16.12 MoDOT’s review of a claim pursuant to Sec 105.16 will be in addition to the right or duty of MoDOT
or the Commission to conduct audits or other reviews of a claim or contractor’s books of account or operations otherwise provided by federal or state laws or the rules of civil procedure.
105.17 Venue. Any action concerning any matter, thing or dispute arising out of or relating to the terms,
performance, non-performance or otherwise of the agreement, shall be filed in the Circuit Court of Cole County, Missouri. The parties agree that the contract is entered into at Jefferson City, Missouri, and substantial elements of the contract’s performance will take place or be delivered at Jefferson City, Missouri, by reason of which the contractor consents to venue of any action by or against the contractor in Cole County, Missouri. The contractor shall cause this provision to be incorporated in all of the contractor’s agreements with, and to be binding upon, all subcontractors in the performance of this agreement.
105.18 Arbitration.
105.18.1 Purpose. By adoption of 226.096 RSMo (L. 2003, HB 668), certain controversies or claims to which
the Missouri Department of Transportation is a party that arises out of or relates to a contract awarded pursuant to subdivision (9) of subsection 1 of 226.130 (RSMo) subject to certain limits and preconditions are subject to, “be settled (sic) by arbitration administered by the American Arbitration Association under its Construction Industry Arbitration Rules, except as provided, in 226.096”. Under the provisions of Chap. 435 RSMo arbitration is the subject of agreement between the parties to a contract. This section provides for incorporation of the, American Arbitration Association’s, Construction Industry Arbitration Rules and Mediation Procedures (AAA Rules), amended and effective on the date arbitration is demanded and for their modification and revisions as permitted by the AAA Rules and Chap. 435 RSMo.
105.18.2 Incorporation. The AAA Rules are incorporated as part of the contract except as amended or
excluded. The AAA Rules are further expressly amended or excluded as provided herein and as provided directly or indirectly by 226.096 RSMo (L. 2003, HB 668) and Chap. 435 RSMo.
105.18.3 Regular Track Procedures. The AAA Construction Industry Arbitration Rules, Regular Track
Procedures, October 1, 2009 are amended as follows:
105.18.3 1 R-1. Agreement of Parties and Designation of Applicable AAA Rules. Not revised.
105.18.3 2 R-2. AAA and Delegation of Duties. Not revised.
105.18.3 3 R-3. National Panel of Construction Neutrals. Shall be replaced with the following:
In cooperation with the National Construction Dispute Resolution Committee the AAA shall establish and maintain a National Roster of Construction Arbitrators (“National Roster”) and shall appoint arbitrators as provided first by the provisions of Missouri law, including 7 CSR 10-26, and then as provided in these rules. The term “arbitrator” in these rules refers to the arbitration panel, constituted for a particular case, whether composed of one or more arbitrators, or to an individual arbitrator, as the context requires.
105.18.3 4 R-4. Filing Requirements Under an Arbitration Agreement in a Contract. Not revised.
105.18.3 5 R-5. Filing Requirements under a Submission Agreement. Not revised.
105.18.3 6 R-6. Changes of Claim or Counterclaim. Shall be replaced with the following:
The contract between the parties provides for a Notice of Controversy or a Claim for adjustment to the contract prior to any demand for arbitration. Arbitration demands, issues, nature or amount of relief sought, shall not differ or be additional to that in the Notice of Controversy or Claim for contract adjustment provided for in the contract. There may not be a revision of the issues, nature of relief sought or increase in relief during or by way of any presentation of evidence during the arbitration. No award may be upon different issues or basis of relief or provide relief different in nature or greater in amount than contained in the Notice of Controversy or Claim given under the contract and stated in the demand for arbitration. No new or different controversy, claim or counterclaim may be submitted to the arbitrator except with the consent of both parties and the arbitrator and any consent must be clearly expressed, written and signed by the parties. There will be no amendments by implication.
105.18.3 7 R-7. Consolidation or Joinder. Shall be replaced with the following:
If Commission expressly agrees in writing with regard to multiple disputes arising under a particular contract, multiple demands may be consolidated so long as the relief sought in total does not exceed $409,123 in the principal relief sought, as adjusted on an annual basis effective January first of each year in accordance with the Implicit Price Deflator for Personal Consumption Expenditures as calculated pursuant to subsection 5 of section 537.610, RSMo. See http://insurance.mo.gov/industry/sovimmunity.php. Demands to which Commission is not a party in direct privity of contract will never be joined. The issue of consolidation of claims and joinder of parties will not be arbitrable. Nothing in this section shall prohibit more than one demand for arbitration pursuant to the same contract, provided that each demand for arbitration arises from a separate claim based upon facts supporting a separate right of relief, filed with the Department and accepted by the department under the Missouri Department of Transportation’s “Contractor Claims and Controversies Procedures”. Neither shall a prime contractor be prohibited from filing a demand for arbitration arising from work, which was subcontracted provided that; (a) the claim was initially accepted by the department under “Contractor Claims and Controversies Procedures.” and (b) would provide a right to contract adjustment separate from any claimed or which could be claimed by the prime contractor for its sole benefit. However, subcontractors shall have no right to file a demand for arbitration with the Commission.
105.18.3 8 R-8. Interpretation and Application of Rules.
105.18.3 9 R-9. Jurisdiction. Not revised.
105.18.3 10 R-10. Mediation. Not revised.
105.18.3 11 R-11. Administrative Conference. Not revised.
105.18.3 12 R-12. Fixing of Locale. Not revised.
105.18.3 13 R-13. Date, Time and Place of Hearing. Not revised.
105.18.3 14 R-14. Arbitrators Appointment from National Construction Panel. Delete paragraphs (a), (b),
(c), (d) and (e) and replace with the following: Arbitrators will be selected and appointed in accordance with 7 CSR 10-26.
105.18.3 15 R-15. Direct Appointment by a Party. Not revised.
105.18.3 16 R-16. Appointment by a Chairperson by Party-Appointed Arbitrators or Parties. Not revised.
105.18.3 17 R-17. Nationality of Arbitrator in International Arbitration. Not revised.
105.18.3 18 R-18. Number of Arbitrators. Not revised.
105.18.3 19 R-19. Disclosure. Not revised.
105.18.3 20 R-20. Disqualification of Arbitrator. Not revised.
105.18.3 21 R-21. Communication with Arbitrator and the AAA. Not revised.
105.18.3 22 R-22. Vacancies. Not revised.
105.18.3 23 R-23. Preliminary Management Hearing. Not revised.
105.18.3 24 R-24. Exchange of Information. Not revised.
105.18.3 25 R-25. Attendance at Hearings. Not revised.
105.18.3 26 R-26. Representation. Not revised.
105.18.3 27 R-27. Oaths. Not revised.
105.18.3 28 R-28. Stenographic Record. Not revised.
105.18.3 29 R-29. Interpreters. Not revised.
105.18.3 30 R-30. Postponements of Hearings. Not revised.
105.18.3 31 R-31. Arbitration in the Absence of a Party or Representative. Not revised.
105.18.3 32 R-32. Conduct of Proceedings. Not revised.
105.18.3 33 R-33. Evidence. Not revised.
105.18.3 34 R-34. Evidence by Affidavit and Posthearing Filing of Documents or Other Evidence. Not
revised.
105.18.3 35 R-35. Inspection or Investigation. Not revised.
105.18.3 36 R-36. Interim Measures. Not revised.
105.18.3 37 R-37. Closing of Hearing. Not revised.
105.18.3 38 R-38. Reopening of Hearing. Not revised.
105.18.3 39 R-39. Waiver of Rules. Not revised.
105.18.3 40 R-40. Extensions of Time. Not revised.
105.18.3 41 R-41. Serving of Notice. Paragraphs (a) and (b) shall be replaced with the following:
(a)Any papers, notices, or process necessary or proper for the initiation or continuation of an arbitration under these rules; for any court action in connection therewith, or for the entry of judgment on any award made under these rules, may be served on a party by mail addressed to the party or its representative at the last known address with return receipt or by personal service, in or outside the state where the arbitration is to be held, provided that reasonable opportunity to be heard with regard thereto has been granted to the party. (b)The AAA, the arbitrator and the parties may also use overnight delivery with return receipt or electronic facsimile transmission (fax) to give the notices required by these rules. Facsimile transmission must require an acknowledgment that an entire legible transmission was received. Where all parties and the arbitrator agree, notices may be transmitted by electronic mail (email), or other methods of communication.
105.18.3 42 R-42. Majority Decision. Not revised.
105.18.3 43 R-43. Time of Award. Not revised.
105.18.3 44 R-44. Form of Award. Paragraph (b) shall be replaced with the following:
105.18.3 45 R-45. Scope of Award. Not revised.
105.18.3 46 R-46. Award upon Settlement. Not revised.
105.18.3 47 R-47. Delivery of Award to Parties. Not revised.
105.18.3 48 R-48. Modification of Award. Not revised.
105.18.3 49 R-49. Release of Documents. Not revised.
105.18.3 50 R-50. Withdrawal of Claims or Counterclaims.
105.18.3 51 R-51. Applications to Court and Exclusion of Liability. Paragraph (c) shall be replaced with the
following:
105.18.3 52 R-52. Administrative Fees. Not revised.
105.18.3 53 R-53. Expenses. Not revised.
105.18.3 54 R-54. Neutral Arbitrator’s Compensation. Not revised.
105.18.3 55 R-55. Deposits. Not revised.
105.18.3 56 R-56. Remedies for Nonpayment. Not revised.
105.18.4 Fast Track Procedures. The AAA Construction Industry Arbitration Rules, Fast Track Procedures,
October 1, 2009 are amended as follows:
105.18.4 1 F-1. Fast Track Applicability. Not revised.
105.18.4 2 F-2. Answers and Counterclaims. Not revised.
105.18.4 3 F-3. Limitation on Extensions. Not revised.
105.18.4 4 F-4. Changes of Claim or Counterclaim - Shall be replaced with the following:
The contract between the parties provides for a Notice of Controversy or a Claim for adjustment to the contract prior to any demand for arbitration. Arbitration demands, issues, nature or amount of relief sought, shall not differ or be additional to that in the Notice of Controversy or Claim for contract adjustment provided for in the contract. There may not be a revision of the issues, nature of relief sought or increase in relief during or by way of any presentation of evidence during the arbitration. No award may be upon different issues or basis of relief or provide relief different in nature or greater in amount than contained in the Notice of Controversy or Claim given under the contract and stated in the demand for arbitration. No new or different controversy, claim or counterclaim may be submitted to the arbitrator except with the consent of both parties and the arbitrator and any consent must be clearly expressed, written and signed by the parties. There will be no amendments by implication.
105.18.4 5 F-5. Appointment and Qualification of Arbitrator. Shall be replaced with the following:
The provisions of 7 CSR 10-26 and the procedures for regular track arbitrator selection, apply to fast track procedure arbitrations.
105.18.4 6 F-6. Serving of Notice for Hearing – Shall be replaced with the following:
105.18.4 7 F-7. Preliminary Telephone Management Hearing. Not revised.
105.18.4 8 F-8. Exchange of Information. Not revised.
105.18.4 9 F-9. Discovery. Not revised.
105.18.4 10 F-10. Date, Time, and Place of Hearing. Not revised.
105.18.4 11 F-11. The Hearing. Not revised.
105.18.4 12 F-12. Time Standards. Not revised.
105.18.4 13 F-13. Time of Award. Not revised.
105.18.4 14 F-14. Neutral Arbitrator’s Compensation. Not revised.
105.18.5 Form of Award – Shall be added as follows:
The arbitrator shall provide a concise, written breakdown of the basis of the award and a written explanation and justification for the awarded amount.
105.19 Electronic Signatures. The contractor may utilize a verifiable electronic signature to sign contract
documents. The electronic signature shall be verified by a recognized independent third party or the Construction and Materials Divisions.