108.1 Subletting of Contract. 108.1.1 The contractor shall not sublet, sell, transfer, assign or otherwise dispose of the contract or contracts or any portion thereof, or of any right, title, or interest therein, without written consent of the engineer. Requests for permission to sublet, assign or otherwise dispose of any portion of the contract shall be in writing and accompanied by evidence that the organization that will perform the work is particularly experienced and equipped for such work. In case such consent is given, the contractor will be permitted to sublet a portion thereof, but the contractor's organization shall perform work amounting to no less than 30 percent of the original contract price. Certification or classification of a contractor by type of work performed or consent to a subcontract shall not constitute the Commission's endorsement of the qualifications of the subcontractor or that the particular subcontractor’s work will constitute compliance with any other provisions of the contract. 108.1.2 The value of the work sublet will be the amount designated in the contractual agreement between the contractor and the subcontractor. The subcontractor shall perform the work described in the subcontract agreement. No subcontracts, or transfer of contract, will in any case release the contractor's liability under the contract and bonds. Consent to a subcontract will not create a direct contractual relationship between the subcontractor and the Commission. 108.1.3 The contractor shall submit to the engineer an electronic copy of all executed subcontract agreements, including any revisions. 108.1.4 A contractor, at the discretion of the engineer, may make a substitution for a subcontract that was disclosed with the bid in accordance with Sec 102.7 or may add a subcontract that would have required disclosure in accordance with Sec 102.7. The contractor shall submit the name of the new subcontractor, the category of work, the dollar value of each subcontract and the reason for the substitution or addition in writing to the engineer for consideration. 108.2 Notice to Proceed. The notice to proceed will stipulate the date the contractor is expected to begin work. The Commission will issue the notice to proceed by stipulating the date on the notice of award sent to all successful bidders. Prior to the stipulated date, the contractor shall execute the contract, file the prescribed bonds, and furnish to the Commission satisfactory evidence of having complied with insurance requirements. 108.3 Prosecution of Work. The contractor will be expected to start work on the date stipulated by the notice to proceed when completion of the work is specified to be completed by working days, calendar days, or calendar date. For contracts that include both a calendar day limit and a completion date, the contractor holds discretion to start on any date from the notice to proceed through the date that allows use of the full amount of calendar days prior to the stipulated completion date. If all contract requirements have been met in accordance with Sec 108.2 the contractor may start work before the date stipulated by the notice to proceed, upon review and approval by the engineer. 108.3.1 The contractor shall continuously and diligently prosecute the work in such order and manner as will ensure the completion of the work within the specified time, and the contractor shall be fully responsible for the prosecution and coordination of all work being performed under the contract. 108.3.2 The work in progress shall receive the personal attention either of the contractor or of a competent and reliable representative of the contractor who shall have full and final authority to act for the contractor. If authority is delegated to a representative of the contractor, the contractor shall notify the engineer in writing, stating the name of the person authorized to act as the contractor’s representative, and stating the name or names of persons authorized to sign the various documents such as change orders, force account statements, labor payrolls and any other documents that may be required during the progress of the work. If progress at any time is not adequate to meet the contractor's schedule and the contract completion time, the contractor shall take all steps necessary to complete the work in the time and manner specified in the contract. 108.3.3 Prior to beginning any work on contracts involving a joint venture, the joint venturers shall appoint and maintain a single representative having full and final authority to act for the joint venture. The engineer shall be notified in writing of the name of this representative and of any replacements. 108.4 Progress Schedules. The contractor shall submit a progress schedule to the engineer for review prior to or at the pre-construction conference. The progress schedule shall be used to establish construction operations and to monitor the progress of the work, although the engineer's determination of the then major operation or controlling item of work will always prevail. The progress schedule shall be in the form specified in Sec 108.4.1, unless the contract contains different requirements. The progress schedule shall be based on the number of working days, calendar days or other increments as set forth in the contract that the contractor expects to require in completing the project, recognizing the capabilities of labor, equipment, arrangements for material, mobilization, shop drawing preparation and approvals, and other relevant items. If an electronic computer software program is used to generate the schedule, the initial and any revised schedules shall be accompanied by a disk containing the schedule files in the native format of the software program used to create the schedule. The disk shall be labeled with the contract ID, route, county, date of revision, and the name of the software program used. The contractor will not be required to provide any copies of the software program. 108.4.1 Form and Contents of Progress Schedule. The progress schedule shall contain an activities schedule bar chart and may, at the contractor's option, include a written narrative that breaks down into detail the time in working days, calendar days or completion date involved in performing all construction activities for the duration of the project, and which is in a suitable scale as to indicate the percentage of work scheduled for completion at any time. The schedule shall indicate all interdependencies between activities. The progress schedule shall also clearly outline the intended maintenance of traffic, work phasing provided by the contract and such other information, as required by the contract. 108.4.2 Preparation of Initial Schedule. The contractor shall complete development of a progress schedule and present a copy to the engineer prior to or at the pre-construction conference. 108.4.2.1 The construction time, as indicated by the progress schedule, for the entire project or any milestone, shall not exceed the specified contract time. If any milestone date or contract completion date is exceeded in the schedule, time estimates on the progress schedule shall be revised. The controlling activity shall be clearly shown for each day of the schedule. A controlling activity will be defined as that part of a progress-controlling item or items that must be performed before the next progress-controlling item of work can be started. Following a review of the progress schedule by the engineer, the engineer and contractor will meet for a joint review, correction and adjustment of the schedule, if necessary. 108.4.2.2 If necessary, this process will be repeated. However, the schedule shall be finalized by the contractor within seven days after request for correction and adjustment to the schedule. 108.4.3 Cost and Intent of Progress Schedules. The review by the engineer of any progress schedule will not constitute a determination that the schedule is reasonable, that following the schedule will result in timely completion, or that deviation will result in a delayed completion. The progress schedule, and any updates provided, is not a part of the contract. If the schedule reflects a completion date different than that specified in the contract, that does not void the completion date or working days specified in the contract. If any schedule reflects a completion time earlier than that specified in the contract, the contractor specifically understands that no claim for additional contract time or compensation will lie against the Commission if the work is not completed by the earlier time shown on the schedule. It will be the contractor's responsibility to determine the most feasible order of work consistent with the requirements of the contract. 108.4.3.1 No direct payment will be made for furnishing progress schedules or revisions. 108.4.3.2 If the contractor fails to comply with the requirement to supply an initial or any revised progress schedule, the engineer may withhold progress payments until a schedule has been submitted and reviewed. 108.4.4 Revised Progress Schedules. The contractor shall provide a revised progress schedule, which will then become the current progress schedule:
108.10 Default of Contract. After notice and an opportunity to remedy, the engineer may declare the contractor
in default, if the contractor:
108.10.1 The engineer will give notice in writing to the contractor and surety of the condition described in Sec
108.10, and advise the contractor and surety of the actions required for remedy. If the contractor does not proceed to remedy the condition within ten days of receipt of this notice, the engineer may declare the contractor in default. The declaration of default will be made in writing to the contractor and the surety.
108.10.2 If within ten days after receipt of the declaration of default, the surety does not proceed to assume the
contract for completion under the direction of the engineer, the Commission has full power and authority, without impairing the obligation of the contract or the bond:
108.10.3 Liability for Costs. The contractor and surety shall be liable for all costs and expenses incurred in
completing the work, and for all liquidated damages in conformity with the contract. The contractor and surety are obligated to comply with all change orders and directives of the engineer to the same extent, and for the same compensation, if any, as the contractor would have been in the absence of default. In case the sum of such liquidated damages and the expense so incurred is less than the sum that would have been payable under the contract if the work had been completed by the contractor, the contractor or surety will be entitled to receive the difference. If the sum of such expense and such liquidated damages exceeds the sum that would have been payable under the contract, the contractor and surety will be liable and shall pay the amount of such excess. This provision will apply regardless of whether the surety or the Commission completes the contract work. The contractor and surety will solely be liable for the costs and expenses of a completing contractor, laborers and suppliers with which either has contracted.
108.10.4 If it is determined after termination of the contractor's right to proceed that the contractor was not in
default, the rights and obligations of the parties will be the same as if the termination had been issued for the convenience of the Commission under Sec 108.11. Sums to which a contractor may be entitled as a result of the contract termination will be limited to amounts determined under Sec 108.11.
108.10.5 Sureties' Continued Acceptability. A surety failing to proceed within ten days after the written
declaration of default by the engineer under Sec 108.10 may be required to show cause to the Commission why the surety should continue to be accepted for future bonds.
108.11 Termination of Contract for Convenience of the Commission. The Commission may terminate the
entire contract, or any portion thereof, if the engineer determines that a termination is in the Commission's best interest. The engineer will deliver to the contractor and surety a notice of termination specifying the extent of termination and the effective date. A termination of the contract for convenience may be directed at any time after the Commission has made a determination to award a contract. The bidding documents may provide for a termination of the contract for convenience under this section upon the occurrence or nonoccurrence of a specified event after bid opening.
108.11.1 Submittals and Procedures. After receipt of a notice of termination, the contractor shall immediately
proceed with the following obligations:
108.11.2 Settlement Provisions. When the Commission orders termination of all or a part of the contract
effective on a certain date, completed items of work as of that date will be paid for at the contract unit price. Payment for partially completed work will be made either at agreed prices or under the provisions below. When items are eliminated in their entirety by such termination, the contractor will be paid for actual work done and actual costs incurred before notification, including mobilization of equipment or material.
108.11.2 1 Additional Costs. Within 60 days of the effective termination date, the contractor shall submit any
request for additional damages or costs not covered in Sec 108.11 or elsewhere in the contract. Such a request may include only such cost items as: mobilization, overhead expenses proven to be attributable to the project or the part terminated and not paid for under work not terminated, subcontractor costs not otherwise paid for, actual idle equipment and idle labor cost only for any time the work is stopped in advance of the termination date, guaranteed payments for private land usage as part of the original contract, and any other actual cost for which the contractor feels reimbursement should be made.
108.11.2 1.1 Anticipated profits, including anticipated earnings on usage of owned equipment, and impact, delay
or other direct or indirect costs resulting from this termination that are not expressly authorized, will not be compensable as part of any settlement.
108.11.2 1.2 The contractor and the engineer may agree upon the whole or any part of the amount to be paid
because of the termination. The amount may include a reasonable allowance for profit on work done. The agreed amount may not exceed the total contract price as reduced by the amount of payments previously made and the contract price of work not terminated. The contract will be amended, and the contractor paid the agreed amount.
108.11.2 2 Additional Cost Review. If the contractor and the engineer fail to agree on the whole amount to be
paid the contractor because of the termination of work, the Commission will pay the amounts determined as follows, but without duplication of any amounts agreed upon in Sec 108.11.2.1:
108.11.2 1.
108.11.2 2.1 In arriving at the amount due the contractor under this clause, there will be deducted:
108.11.2 2.2 If the termination is partial, the contractor may file a proposal with the engineer for an equitable
adjustment of the price or prices of the continued portion of the contract. The engineer will make any equitable adjustment agreed upon. Any proposal for an equitable adjustment under this clause shall be requested within 60 days from the effective date of termination unless extended in writing by the engineer.
108.11.2 2.3 The contractor shall maintain and make available all project cost records to the engineer for audit to
the extent necessary to determine the validity and amount for each item requested. This will include, but is not limited to, all items described in Sec 105.16. These records and documents shall be made available to the engineer at the contractor's office at all reasonable times, without any direct charge. If approved by the engineer, photographs, microphotographs or other authentic reproductions may be maintained instead of original records and documents.
108.11.3 Effect of Termination. Termination of the contract or portion thereof will not relieve the contractor of
contractual responsibilities for the work completed, nor will termination relieve the surety of the surety’s obligation for and concerning that part of the contract not terminated or any just claim arising out of the work performed.
108.12 Notice to Contractor and Surety. Notice to the contractor, in case of default or termination of the
contract, shall be deemed to be served when delivered to the person in charge of any office used by the contractor, the contractor's representative at or near the work or by certified mail addressed to the contractor's last known place of business. Notice to the surety shall be deemed served when mailed to the surety's address as shown in the contract by certified mail.
108.13 Termination of Contract for Misconduct. For the purposes of the following provision, "state" will
include the State of Missouri and any other state, commonwealth or territory of the United States. The Commission may declare the contract to be terminated at any time after the contract is awarded and prior to final acceptance of the project, for any one or more of the acts set forth below, if the act occurred after the bid opening or within two years immediately preceding the date of the bid opening, unless the act is a basis for an adverse action under 49 CFR, Part 29 in which case the time limit will not apply, on any Commission or other federal, state or local government or privately awarded contract:
108.13.1 The acts, omissions and liabilities of persons or firms affiliated with the contractor or of persons that
are principals of the contractor, are those of the contractor, unless the circumstances clearly negate that conclusion. Persons or firms are "affiliates" of each other if, directly or indirectly, either one controls or has the power to control the other or a third person controls or has the power to control both. Examples of control include, but are not limited to: interlocking management or ownership, identity of interests among family members, shared facilities and equipment, common use of employees on projects or a new business entity organized following the determination of ineligibility or non-responsibility of a person or firm which has the same or similar management, ownership or principal employees as the ineligible person. A "principal" will be defined as an officer, director, owner, partner or other natural person within a firm with primary management, supervisory or contracting responsibilities, including participating in, or formulating, bids.
108.13.2 The Commission will not declare the contract terminated pursuant to this section if the contractor made
a full and complete disclosure of the acts and circumstances described in Sec 108.13 to the Commission in the bid or in writings submitted with the bid and the Commission did not determine the contractor to be non- responsible prior to making the award of the contract. The Commission will not be precluded from terminating the contract under this section if the information provided by the contractor did not constitute a full and complete disclosure of all facts and circumstances pertinent to the issue of the responsibility and integrity of the contractor.
108.13.3 The procedures for notice of the proposed termination of the contract and the contractor’s right to be
heard regarding that proposed action will be those in accordance with a proposed disqualification or suspension under the provisions of 7 CSR 10-18. After notice and an opportunity to be heard, upon a finding of the existence of a basis to terminate a contract under this section, the Commission may terminate the contract immediately or at the occurrence of some specific date or event in the future, prior to project completion, upon delivery of a written notice to the contractor by actual service or by certified mail, return receipt requested, sent to the address of record of the contractor. Effective with the contract termination date, the contractor shall discontinue further work on the project and shall instruct subcontractors and suppliers to do the same, other than to remove promptly the contractor’s personnel, equipment and supplies from the project site. The contractor will be paid for all completed work to that date at the contract price. At the option of the engineer, the Commission may assume the possession and cost of any specially fabricated material or supplies for the project that have been ordered prior to notice of termination but have not been installed on the date of termination. The contractor and surety will be liable to the Commission for all costs and expenses incurred by the Commission in completing the project, including, but not limited to, the Commission's costs to redraft and rebid the project, which costs and expenses exceed the total of the contractor's bid price plus additional expenses allowed by the engineer during the contractor's work on the project, less the amount paid to the contractor by the Commission. The Commission will not be liable for damages for breach of contract or in any other action or respect for declaring a default if one exists under this section and for terminating the contract prior to completion by the contractor.
108.13.4 The satisfactory performance of a contract, prior to the notice to the contractor of the intent to
terminate the contract for misconduct, will not be a basis to determine whether the contract may be terminated for misconduct under this section.
108.13.5 The contractor shall file any claim the contractor has against the Commission within 60 days after the
effective date of termination, pursuant to the procedures of Sec 105. The Commission will file any claim the Commission has against the contractor or surety within 60 days of the date of final acceptance of the project, whether or not it is renumbered or redesigned, and whether completed by the surety, by a successor contractor retained by the Commission, or by the Commission itself. Any Commission claim will be filed pursuant to the procedures of Sec 105.
108.14 Determination of Compensation and Contract Time Extension for Excusable, Non-compensable
and Compensable Delays. An extension of the contract time may be granted under the following conditions provided documentation has been given to the engineer in accordance with Secs 108.14.3 through 108.14.5. Strict adherence to the provisions of this section will be a condition precedent to the contractor's entitlement to an extension of contract time or compensation because of project delays.
108.14.1 Excusable or Non-compensable Delay. Contract time allowed for the performance of the work may
be extended for delays caused by acts of God, acts of the public enemy, fires, floods, earthquakes, epidemics, quarantine restrictions, strikes, freight embargoes, unusually severe weather or other delays not caused by the contractor's fault or negligence.
108.14.2 Compensable Delay. Contract time allowed for performance of the work may be extended for delays
caused by the Commission. The contractor may be granted an extension of time and additional compensation only as provided by Sec 109.
108.14.3 Notification of Delay. Within seven days of the occurrence of a delay to the prosecution of any phase
of the work, the contractor shall notify the engineer in writing of such a delay and indicate that a request for delay consideration will be filed. Delay costs incurred prior to notifying the engineer that operations have been delayed will be non-compensable.
108.14.4 Procedures Following a Delay. The contractor shall keep daily records of all non-salaried labor,
material costs and equipment expenses for all operations affected by the delay.
108.14.4 1 The contractor shall maintain a daily record of each operation affected by the delay and the station
location of the operations affected. Daily records of the operations and stations will also be maintained by the engineer. Each Monday, the contractor shall compare the previous week's daily records with the records kept by the engineer. The contractor shall also prepare and submit written reports to the engineer each Monday containing the following information:
108.14.4 2 The contractor shall provide written notice to the engineer within seven days of the results of the
comparison of the detailed reports performed each Monday and shall define any disagreements between specific records.
108.14.4 3 Failure to meet to review the engineer's records or to report disagreements between the records will
be considered conclusive evidence that the engineer's records are accurate.
108.14.5 Procedures Following Completion of Work Allegedly Delayed. Within the earlier of 15 days of
completion of any phase of work allegedly delayed, or of project completion, the contractor shall submit a report to the engineer containing the following information:
108.14.5 1 All costs shown in the report submitted to the engineer must be directly caused by the delay event
and shall reflect the actual costs incurred as shown on the contractor's project cost records kept in the ordinary course of business.
108.14.5 2 The engineer will review the contractor's submission and any reports prepared for the engineer. A
written decision will be provided to the contractor within 60 days of the receipt of the complete contractor's submission. This time may be extended if the engineer requires additional information. The contractor shall state affirmatively in writing when the contractor has made a complete submission of information regarding a delay event.
108.14.5 3 In the case of compensable delays, if the engineer determines that the Commission is responsible for
delays to the contractor's operations, the engineer's written decision will reflect the nature and extent of any resulting equitable adjustment to the contract in accordance with Sec 109.
108.15 Suspension of Work Directed by the Engineer.
108.15.1 If the performance of all or any portion of the work is suspended or delayed by the engineer for an
unreasonable period of time not originally anticipated, customary or inherent to the construction industry, and the contractor believes that additional compensation or contract time is due as a result of such suspension or delay, the contractor shall submit to the engineer in writing a request for adjustment within seven days of receipt of the notice to resume work. The request shall set forth the reasons and support for such an adjustment. The procedures of Secs 108.14.4 and 108.14.5 will apply to requests for additional compensation or time claimed by the contractor as a result of a suspension of work directed by the engineer under this section.
108.15.2 Upon receipt, the engineer will evaluate the contractor's request. If the engineer agrees that the cost or
time required for the performance of the contract has increased as a result of such a suspension and the suspension was caused by conditions beyond the control of and not the fault of the contractor, suppliers or subcontractors, and not caused by weather, the engineer will make an adjustment, excluding profit, and modify the contract in writing accordingly. The engineer will notify the contractor of the engineer's determination whether or not an adjustment of the contract is warranted.
108.15.3 No contract adjustment will be made unless the contractor has submitted the request for adjustment
within the time prescribed.
108.15.4 No contract adjustment will be allowed under this clause to the extent that performance would have
been suspended or delayed by any other cause, or an adjustment is provided for or excluded under any other term or condition of the contract.