109.1 Measurement of Quantities. All work completed under the contract will be measured by the engineer according to United States standard measure or will be paid for on a contract quantity basis as set out elsewhere in these specifications. The method of measurement and basis of payment will be made to the nearest whole number unless specified otherwise. When the contract quantity of any item is found to include appreciable errors, or when an authorized revision of the plans is made, the quantity will be corrected before making final payment. The method of measurement and computations to be used in determination of quantities of material furnished and of work performed under the contract will be those methods generally recognized as conforming to good engineering practice. 109.2 Scope of Payment. 109.2.1 Compensation. The contractor shall receive and accept compensation provided for in the contract as full payment for performing all work under the contract in a complete and acceptable manner, and for all risk, loss, damage or expense arising from the work or the prosecution thereof subject to Sec 109.8. 109.2.2 Completed Improvements. The payment of any current or final estimate, or the acceptance of any portion of the work as provided in the specifications, will not affect the obligation of the contractor to submit for final acceptance a completed improvement in accordance with the contract. 109.3 Compensation for Altered Quantities. When the accepted quantities of work vary from the quantities in the contract, the contractor shall accept payment at the original contract unit prices for the accepted quantities of work done. No allowance will be made for any increased cost, except as provided in Sec 104 and Sec 108. 109.4 Differing Site Conditions and Changes in the Work. Contract adjustments to compensate for changes in the work or extra work caused by differing site conditions or changes in the work performed in accordance with Sec 104 will be determined by use of one of the following methods, in order of precedence 109.4.1 Contract Unit Prices. Where contract unit prices exist, the contract unit price will always be applied without deviation, unless the effect of a differing site condition or a significant change in the character of the work requires an equitable adjustment to a contract unit price under the terms of this contract. Equitable adjustments will exclude any anticipated profits. 109.4.2 Unit Prices or Lump Sum Amount Agreed Upon in the Change Order Authorizing the Work. Where contract unit prices do not exist for the work to be done, the parties may agree to such unit prices or a lump sum price for that work. Where an equitable adjustment to a unit price is required, the parties may agree to the adjustment to be made to the contract unit price, excluding any anticipated profits. Prior to agreeing upon such unit or lump sum prices, the engineer may require from the contractor any information to which the engineer is authorized under Sec 104. 109.4.3 Equitable Adjustment. In all other cases, except work ordered to be performed under force account, the engineer will make an equitable adjustment to or determination of the affected contract prices for the work, based on the contractor's actual costs to perform the work. This determination will be consistent with the contractor's other proven costs to perform the contract work, as shown in the contractor's bid computations and project cost records, produced and kept in the ordinary course of business. Prior to making an equitable adjustment, the engineer may require from the contractor any information relevant to that determination, including the information authorized under Sec 104. The condition precedent to determination of contractor entitlement and amount of any contract adjustment and Commission liability will be that the adjustment:
109.10 Assignments. Neither the contract, nor any duties or obligations or rights of the contractor or the
contractor’s surety arising under, from or relating to the contract, or to be performed as required by the contract, and whether present or prospective, including, without limitation, money due at any time or any claim of any character arising from or relating to performance or nonperformance of the contract, whether for breach or otherwise, shall be assigned or transferred to any other person so as to bind or affect the Commission absent the express written consent of the surety and the Commission and upon a written request and compliance with such requirements as the engineer or Commission may provide.
109.11 Compensation for Project Delays. This provision will apply to and will control all contract
adjustments, change orders and claims for additional compensation that are time related, resulting from compensable project delays, inefficiency, standby, extended performance or described in any other term.
109.11.1 Only the actual and documented additional costs associated with the following items will be
recoverable by the contractor as an equitable adjustment for delay.
109.11.2 All costs claimed shall be adequately documented when measuring additional equipment expenses (i.e.
ownership expenses) arising as a direct result of a delay caused by MoDOT. Actual records kept in the usual course of business, measuring actual increased ownership expenses pursuant to generally accepted accounting principles, may be required at the discretion of the engineer for determining equipment costs. For delays that the engineer determines to be short-term, or when the engineer determines this method acceptable, equipment costs shall be calculated using the provisions for authorized standby time in Sec 109.5.4, except that no increase for overhead or profit will be allowed in excess of what is established in Sec 109.11.1.
109.11.3 The parties agree that, in any adjustment for delay costs, MoDOT will have no liability for the
following items of damages or expense.
109.12 Change Orders. Except as otherwise provided for in the change order, an adjustment of the contract
price or time of contract performance in a change order constitutes compensation in full to the contractor, subcontractors and suppliers for all costs and time effects directly or indirectly attributable to the matter described in the change order, for all delays related thereto, for all impact, cumulative impacts and for performance of the change within the time stated. The surety's liability under the contract bond and contract shall not be limited to the penal sum as set forth in the contract bond. The surety shall be liable and responsible to the Commission for the contractor's entire performance and of all obligations arising under or from the contract, which shall include, but not be limited to, any change orders issued under the contract that increase the cost of the contract.
109.13 Prompt Payment to Subcontractors and Suppliers. The requirements set forth in this section will
apply to all contracts where the federal government is participating in the cost of construction.
109.13.1 When the contractor receives any payment from the Commission, the contractor shall, within the
earlier of fifteen days of receipt of that payment, or the date provided by the subcontract or purchase order, pay each subcontractor or supplier a sum, less only any retention provided by the subcontractor or purchase order or sum withheld as allowed by Sec 109.13.3, equal to one of the following:
109.13.2 Notwithstanding any conflicting provision in a subcontract or purchase order and subject only to the
requirements of Sec 109.13.3, the contractor shall make final payment of the balance of all sums under a subcontract or purchase order, including any retention, within 30 days of the satisfactory completion of the subcontractor's work or services, or a supplier's final delivery of materials to be provided.
109.13.3 The contractor may withhold periodic payment or final payment to a subcontractor or supplier only for
the following causes and only if that subcontractor or supplier is directly involved:
109.14 Price Adjustment for Fuel. If the contractor accepts the option for fuel adjustment in the bid proposal,
the method of price adjustment for the fuel used on the items of work specified herein will be based on Fuel Usage Factors and the Monthly Fuel Index. The following table specifies the fuel usage factors for Production and On-Road Hauling. The On-Road Hauling Factor is based on an average 30-mile round trip and will be used regardless of the actual haul distance. Price adjustment for fuel does not apply to fixed-cost items listed in Job Order Contracts. Price adjustment for fuel shall only apply to items that are defined in the table below and listed in the Listing of Bid Items for Highway Construction at the time of bid. Non-standard bid items shall not be subject to price adjustment for fuel unless specified elsewhere in the contract. Item of Work Unit Fuel Usage Factor for Production Fuel Usage Factor for On-Road Hauling Total Fuel Usage Factor Class A Excavation gal/yd3 0.20 n/a 0.20 Unclassified Excavation gal/yd3 0.30 n/a 0.30 Class C Excavation (Includes Sandstone and Igneous Rock Excavation) gal/yd3 0.40 n/a 0.40 Embankment in Place gal/yd3 0.35 n/a 0.35 Bituminous Construction on Roadways, Shoulders and Entrances. Includes both full depth asphalt and overlays. Includes all asphalt mixes under Secs 401, 402 and 403, as well as Ultrathin Bonded Asphalt Wearing Surface (UBAWS). Asphalt mixes paid by SY will be converted to equivalent tons using a factor of 1.98 tons/yd3. gal/ton of total asphalt mix 2.65 0.67 3.32 Concrete Pavement Construction on Roadways, Shoulders and Entrances. Includes both full depth concrete and overlays. Includes roller compacted concrete. Round to nearest 1 in. increment. (e.g. if 7.5” pavement use 8 in. factor). If less than 6 in., use 6 in. factor. Concrete paid by CY will be converted to equivalent thickness. gal/yd2 6 in. 7 in. 8 in. 9 in. 10 in. 11 in. 12 in. 13 in. 14 in. 0.27 0.29 0.31 0.33 0.35 0.36 0.39 0.41 0.42 0.22 0.26 0.29 0.33 0.37 0.41 0.44 0.48 0.52 0.49 0.55 0.60 0.66 0.72 0.77 0.83 0.89 0.94 Aggregate Base Constructiona on Roadways, Shoulders and Entrances. gal/yd2 3in. 4 in. 5 in. 6 in. 7 in. 8 in. 9 in. gal/ton gal/yd3 n/a n/a n/a n/a n/a n/a n/a n/a n/a 0.11 0.15 0.19 0.23 0.26 0.30 0.34 0.67 1.35 0.11 0.15 0.19 0.23 0.26 0.30 0.34 0.67 1.35 a Includes all base in Secs 302 and 304, when hauled to the project, but does not include material in Secs 303 or 310. Does not include any base produced within project limits or adjacent to the project. Includes base shown in pay limits for optional shoulder designs (e.g. A3 shoulder), but not the portion identified as incidental base.
109.14.1 Monthly Fuel Index. Each month, the Monthly Fuel Index will be established as the average retail
price per gallon for Ultra Low Sulfur Diesel for the Midwest (PADD 2) area as posted on the first Monday of the month by the U.S. Energy Information Administration (EIA). Should the posted price not be available for any reason, the MoDOT State Construction & Materials Engineer will use reasonable methods, at their sole discretion, to establish the Monthly Fuel Index on an interim basis until the EIA resumes its publication.
109.14.2 Fuel Adjustment Calculation.
B = Base Fuel Index = Monthly Fuel Index in the month in which the project was let C = Current Index = Monthly Fuel Index in the month in which the work was performed U = Units of work performed within the current pay estimate period (applicable pay units) F = Total Fuel Usage Factor (gal./applicable pay units) Fuel Adjustment (Dollars) = (C – B) x U x F
109.14.3 Each pay estimate period, a fuel adjustment payment or deduction will be applied for the quantity of
work performed that period on each qualifying pay item. For calculation of the fuel adjustment, work performed on the first day of a month will generally be included with the second estimate in the previous month to keep fuel adjustments in sync with MoDOT’s normal payment estimate period schedule. The Commission reserves the right to include work performed on the first day of the month with the current month to accommodate financial accounting termini, such as the beginning of the state and federal fiscal years (July 1 and October 1).
109.14.4 If the bidder wishes to be bound by these specifications, the bidder shall execute the acceptance form
in the proposal. Failure by the bidder to execute the acceptance form will be interpreted to mean election to not participate in the price adjustment for fuel.
109.14.5 If adjustments are made in the contract quantities, the contractor shall accept the fuel adjustment as full
compensation for increases or decreases in the price of fuel regardless of the amounts of overrun or underrun.
109.14.6 The fuel adjustment will be computed each pay period work is performed, for the usage of fuel by the
following procedure: Fuel Adjustment = (Fuel Usage Factor) x (Monthly Fuel Index Adjustment Factor) x (Units of Work included in the payment estimate)
109.14.7 Payments or deductions for the fuel adjustments on the various items of work will be made on the
estimate as one "Fuel Adjustment". No change order will be required.
109.14.8 If the bidder wishes to be bound by these specifications, the bidder shall execute the acceptance form
in the proposal. Failure by the bidder to execute the acceptance form will be interpreted to mean election to not participate in the price adjustment for fuel.
109.15 Price Adjustment for Asphalt Cement.
109.15.1 Asphalt Cement Price Index. Adjustments will be made to the payments due the Contractor for any
plant mix bituminous base, plant mix bituminous pavement, plant mix bituminous surface leveling, asphaltic concrete pavement and ultrathin bonded asphalt wearing surface that contains performance graded (PG) asphalt binder when it has been determined that the Monthly Asphalt Index for the month prior to placement of the asphalt mixture has fluctuated from the Monthly Asphalt Index for the month the project was let. The Monthly Asphalt Index shall be established for each calendar month as the average of the midpoint selling prices of PG64-22 for St. Louis and Kansas City, Missouri areas, as published by Poten and Partners Inc. in the Asphalt Weekly Monitor®, on the first Monday preceding the date of the normal monthly MoDOT letting. For months when there is no normal monthly letting, the published price on the third Monday of that month shall be used for the Monthly Asphalt Index. Special lettings shall have no effect on determining the Monthly Asphalt Index. The asphalt base index shall be the Monthly Asphalt Index for the month of the bid opening. For calculation of the price adjustment, any asphalt placed on the first day of a month will generally be considered as placed the previous month to keep price adjustments in sync with MoDOT's normal payment estimate period schedule. The Commission reserves the right to include asphalt placed on the first day of the month with the current month to accomodate financial accounting termini, such as the beginning of the state and federal fiscal years (July 1 and October 1).
109.15.1 1 The price adjustment will be applied to the actual amount of virgin PG asphalt binder used by the
Contractor for all asphalt items specified in Sec 109.15.1. For asphalt mixtures that are paid for by the square yard, the price adjustments will be made for applicable equivalent tons, as calculated by the engineer, based upon the plan square yard quantity and thickness converted to tons, excluding the 1:1 wedge. The price adjustment will be applied to all Job Order Contract projects for all quantities of the wet ton and square yard asphalt mix. The percentage of virgin PG asphalt binder as shown in the job mix formula, in accordance with Sec 401, 402, Sec 403 and Sec 413, will be the basis for price adjustments for any asphalt mix type placed on the project. The effective asphalt binder obtained from the use of Recycled Asphalt Pavement (RAP) and/or Recycled Asphalt Shingles (RAS) will not be eligible for adjustment. The Monthly Asphalt Index for PG64-22 will be applied to the asphalt mix for mixes using any PG asphalt binder.
109.15.1 2 Price Adjustment Calculated. To determine the price adjustment for any asphalt mix specified in
this provision, the following formula will be used. A = (B x C/100) x (D-E) Where: A = Dollar value adjustment for mix placed during the payment estimate period B = Tons of asphalt mixture placed during the payment estimate period C = Percent of virgin PG asphalt binder as listed in the job mix formula in use D = The Monthly Asphalt Index for the month prior to the month the asphalt mix was placed E = The asphalt base index = the Monthly Asphalt Index for the month the project was let
109.15.1 3 The engineer will apply the price adjustments, as determined by the price adjustment calculation
established herein, for each payment estimate period in which asphalt is placed, except for any asphalt placed after the allowable contract time period as defined in Sec 108. For asphalt placed after the contract completion time limit, the "D" value used for the price adjustment calculated shall be either the last "D" value prior to the date that contract time was exceeded, or the current monthly "D" value, whichever is lower.
109.15.1 4 Optional. This provision is optional. If the bidder wishes to be bound by this provision, the bidder
shall execute the acceptance form in the Bid. Failure by the bidder to execute the acceptance form will be interpreted to mean election to not participate in the Asphalt Cement Price Index. If the Asphalt Cement Price Index is accepted, PG asphalt binder for the project will not be eligible for a material allowance as described in Sec 109.
109.15.2 Seal Coat Price Index. Adjustments will be made to the payments due the contractor for Seal Coat
placed in accordance with Sec 409. Adjustments will be calculated in accordance with Sec 109.15.1 Asphalt Cement Price Index, except as defined herein.
109.15.2 1 Basis of Payment. To determine the adjustment for any material specified in this provision the
following formula will be used. A = B X (0.68 X 8.58/2000) X (D – E) Where: A = adjustment for Seal Coat placed during the index period B = gallons of seal coat placed during the index period D = average index price at the beginning of the period E = average index price at the time of bid 0.68 = factor to reduce volume of emulsion to AC only (use average specific gravity of 1.03 for seal coat)
109.15.2 2 Optional. This provision is optional. If the bidder wishes to be bound by this provision, the bidder
shall execute the acceptance form in the Bid for the Seal Coat Price Index. Failure by the bidder to execute the acceptance form will be interpreted to mean election to not participate in the Seal Coat Price Index.
109.15.3 Asphalt Underseal Price Index. Adjustments will be made to the payments due the contractor for
Asphalt Underseal placed in accordance with Sec 625. Adjustments will be calculated in accordance with Sec
109.15 1Asphalt Cement Price Index, except as defined herein.
109.15.3 1 Basis of Payment. To determine the adjustment for any material specified in this provision the
following formula will be used. A = B X (8.66/2000) X (D – E) Where: A = adjustment for asphalt underseal placed during the index period B = gallons of asphalt underseal placed during the index period D = average index price at the beginning of the period E = average index price at the time of bid (use average specific gravity of 1.04 for underseal)
109.15.3 2 Optional. This provision is optional. If the bidder wishes to be bound by this provision, the bidder
shall execute the acceptance form in the Bid for the Asphalt Underseal Price Index. Failure by the bidder to execute the acceptance form will be interpreted to mean election to not participate in the Asphalt Underseal Price Index.
109.15.4 Polymer Modified Emulsion Membrane Price Index. Adjustments will be made to the payments due
the contractor for Polymer Modified Emulsion Membrane placed in accordance with Sec 413.30 (UBAWS), but not when used for other purposes. Adjustments will be calculated in accordance with Sec 109.15.1 Asphalt Cement Price Index, except as defined herein.
109.15.4 1 Basis of Payment. To determine the adjustment for any material specified in this provision the
following formula will be used. A = B X (0.9/2000) x (D – E) Where: A = adjustment for membrane placed during the index period B = square yards of membrane placed during the index period D = average index price at the beginning of the period E = average index price at the time of bid
109.15.4 2 Optional. This provision is optional. If the bidder wishes to be bound by the provision, the bidder
shall execute the acceptance form in the Bid for Polymer Modified Emulsion Membrane (UBAWS). Failure by the bidder to execute the acceptance form will be interpreted to mean election not to participate in the Polymer Modified Emulsion Membrane Price Index (UBAWS).
109.16 Fixed Cost Items. The following fixed prices shall be used when referenced in the specifications:
Sec Item No. Item of Work Unit Fixed Price 201.4.3 201-
30.00 Clearing and Grubbing Acre $3,500.00
203.9.4 203-
20.00 Class C Excavation ≤ 500 cy cy $75.00
206.6.2 206- 36.00 Supplemental Foundation Test Holes ft $6.00 206.6.3.1 206-
10.03 Class 1 Excavation in Rock cy $175.00
206.6.3.2 206-
20.03 Class 2 Excavation in Rock cy $200.00
206.6.3.3 206-
31.00 Class 3 Excavation in Rock cy $135.00
206.6.3.4 206-
34.00 Class 4 Excavation in Rock cy $135.00
214.5.1.2 214-
20.00 Furnishing Rock Fill cy $15.00
303.5.1.2 303-
06.00 Furnishing Rock Base Material sy $10.00
401.14 401-
05.00 Sample of Compacted Plant Mix Bituminous Pavement Each $75.00
403.23.2 403-
05.00 Sample of Compacted Asphaltic Concrete Pavement Each $75.00
505.10.14 505-
00.04 Supplementary Wearing Surface Material (Low Slump Concrete) cy $1,000.00
505.20.14 505-
00.04 Supplementary Wearing Surface Material (Latex Modified Concrete) cy $1,000.00
505.30.14 505-
00.04 Supplementary Wearing Surface Material (Silica Fume Concrete) cy $1,000.00
505.40.14 505-
00.04 Supplementary Wearing Surface Material (Latex Modified Very Early Strength Concrete) cy $1,400.00
505.50.14 505-
00.04 Supplementary Wearing Surface Material (CSA Cement Very Early Strength Concrete) cy $900.00
505.60.14 505-
00.04 Supplementary Wearing Surface Material (Steel Fiber Reinforced Concrete) cy $700.00
505.70.14 505-
00.04 Supplementary Wearing Surface Material (Polyester Polymer Concrete) cy $2,500.00
611.30.5 1611-30.10 Furnishing Type 1 Rock Blanket cy $24.00
611.30.5 1611-30.20 Furnishing Type 2 Rock Blanket cy $25.00
701.7.7 701-
15.00 Concrete Coring lf $100.00
618.3 618-
10.20 Additional Mobilization for Seeding Each $600.00
703.5.1 703-
20.02 Class B Concrete (Misc) (Concrete Fill > 2 cy) cy $500.00
703.5.1 703-
20.02 Class B Concrete (Misc) (Concrete Fill ≤ 2 cy) cy $750.00
706.4 706-
10.00 Reinforcing Steel lb $2.00
Measurement and Payment in other states