602.1 Description. This work shall consist of constructing drain markers or steel right of way markers as
specified in the contract documents, at the locations shown on the plans or as directed by the engineer.
602.2 Material.
602.2.1 All material shall be in accordance with Division 1000, Material Details, and specifically as follows:
Item Section Steel Post for Markers 1044
602.2.2 Right of way and drain marker plaques and fasteners will be furnished at the job site at no cost to the
contractor.
602.3 Construction Requirements. Steel markers shall be set with the legend facing the centerline of the
highway. Posts shall be set vertically and the plaques firmly attached. Posts shall be driven in accordance with Sec 903. Posts having battered or mushroomed tops will not be accepted.
602.4 Method of Measurement. Measurement of drain markers and right of way markers will be made per
each.
602.5 Basis of Payment. The accepted quantity of markers will be paid for at the contract unit price.