6-66 SECTIO N 619 – MARKERS
619.0 1 DESCRIPTION . This work shall consist of furnishing and placing boundary markers, marker
posts, and bollards , and removing and resetting of existing property markers.
619.0 2 MATERIALS . Materials shall meet the requirements of the following subsection s:
Crushed Gravel for Subbase ................................ ................................ ...................... 704.05 Mortar, Type I ................................ ................................ ................................ ............ 707.01 (b) Bar Reinforcement ................................ ................................ ................................ .....713.01 Wood Posts ................................ ................................ ................................ ................ 728.01(a) Steel Posts and Anchors ................................ ................................ ............................. 751.01(a) Paints and stains shall meet the requirements of Subsection 708.01 . Concrete shall meet the requirements of Section 541 for Concrete, Class B.
619.0 3 Placing .
619.0 4 METHO D OF MEASUREMEN T. The quantity Boundary Markers, Bollards, Wood Marker
Posts , and Yielding Marker Posts to be measured for payment will be the number of markers, bollards, or posts set in the complete and accepted work . The quantity of Removing and Resetting Property Markers to be measured for payment will be the number of property markers removed and reset in the complete and accepted work.
619.0 5 BASIS OF PAYMENT . The accepted quantity of Boundary Markers, Bollards, Wood Marker
Posts, Yielding Marker Posts, and Removing and Resetting Property Markers will be paid for at the Contract unit price each. Payment will be full compensation for furnishing, transporting, han dling, and placing the material s specified, including object markers, paint, locking devices, excavation, backfill, mortar, concrete, and subbase , and for furnishing all labor, tools, material s, equipment , and incidentals necessary to complete the work . The Contract unit price s for the items Wood Marker Posts and Yielding Marker Posts will also include the costs of removing the remaining portion of the existing marker post, when the designated new marker post is used as a replacement for an existing marker post. Payment will be made under: Pay Item Pay Unit
619.10 00 Boundary Markers ................................ ................................ .................... Each
619.14 00 Bollards ................................ ................................ ................................ .....Each
619.15 00 Wood Marker Posts ................................ ................................ ................... Each
619.17 00 Yielding Marker Posts ................................ ................................ .............. Each
619.20 00 Removing and Resetting Property Markers ................................ .............. Each
6-68 SECTIO N 620 – FENCES AND HAND RAILINGS
620.0 1 DESCRIPTION . This work shall consist of the construction of fences , gates , and hand railings .
620.0 2 MATERIALS . Materials shall meet the requirements of the following subsection s:
Mortar, Type I ................................ ................................ ................................ ............ 707.01 (b) Structural Steel ................................ ................................ ................................ ........... 714.02 Carbon Steel Bolts, Nuts, and Washers ................................ ................................ .....714.04 Steel Tubing ................................ ................................ ................................ ............... 714.11 Galvanizing ................................ ................................ ................................ ................ 726.0 6 Metalizing ................................ ................................ ................................ .................. 726.0 7 Woven Wire Fence ................................ ................................ ................................ ....727.01 Chain -Link Fence ................................ ................................ ................................ .......727.02 Snow Barrier Fence ................................ ................................ ................................ ....727.0 5 Plank Rail Fence ................................ ................................ ................................ ........ 727.06 Posts ................................ ................................ ................................ ........................... 728.01 Cable, W -Beam, and Thrie Beam Guardrail Hardware ................................ ............. 728.03(a) Metal Hand Railing ................................ ................................ ................................ ....732.01 Grounding Electrodes ................................ ................................ ................................ 752.11 Barbed wire for barbed wire fence shall be in accordance with Subsection 727.01(b) . Posts and braces for barbed wire fence shall be wood in accordance with Subsection 727.01(c) or steel in accordance Subsection 727.01(d) as specified on the Plans. Miscellaneous hardware for barbed wire fence shall be in accordance with Subsection 727.01(f) . When split -rail fence is specified on the Plans, rails and posts shall be made of premium white cedar. Rails and posts shall be free of any chemicals or toxic preservatives or treatments. The Contractor may use preformed 1/16 inch × 3/8 inch flat aluminum wire bands to attach the chain -link fabric to the galvanized pipe support framework . The bands shall be made of 5052 -H32 alloy having a minimum tensile strength of 30 ksi, and an approved closure, as an alternative to the stainless steel clips shown on the Plans. Concrete shall meet the requirements of Section 541 for Concrete, Class B. Unless otherwise specified, all material for hand railings shall be galvanized. Hand railing base plate s shall meet the requirements of Subsection 727.01(d) and h and railing hardware shall meet the requirements of Subsection 727.01(f) .