627Contractor Surveying and Staking

MO · 2026 (Oct) Standard Specifications✓ Full text on BuildSpecBook pages 407–408 Save this section

Ask about Section 627

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

627.1 Description. This work shall consist of providing the necessary surveying and staking for the successful

prosecution of the work.

627.2 Staking Requirements. Staking work shall be in accordance with general accepted surveying practices

and provisions of the contract. The MoDOT's current Engineering Policy Guide (EPG), 238.4, may be used as guidance and is available on MoDOT’s web site.

627.2.1 The contractor shall preserve all right of way monuments, benchmarks control points and reference

marks set by the engineer. If any monumentation is damaged, destroyed or disturbed by the contractor, the cost of replacement will be at the contractor’s expense and will be deducted from the payment for the work.

627.2.2 All surveying shall be documented by the contractor in a written form acceptable to the engineer. During

performance of the work, all surveying documents shall be available and supplied to the engineer upon request, at the contractor’s expense. All documents shall be labeled with the route, state job number, county, contractor name, survey party supervisor and date.

627.2.3 The engineer will furnish and set control points with known coordinates. The engineer will furnish all

coordinate data to lay out the job and locate benchmarks as shown on the plans. The contractor shall provide all other staking necessary for the successful prosecution of the work, including all staking necessary to facilitate the relocation of utilities. All alignment control established by the contractor shall be referenced, and a copy of the references shall be furnished to the engineer.

627.2.4 Any surveying or measurements necessary for computing pay quantities will be performed by the

engineer. The contractor shall notify the engineer at least two working days prior to disturbing any areas used to calculate pay quantities.

627.2.5 All surveying work performed by the contractor shall be sufficient and accurate to construct the work in

accordance with the contract documents. Any delays or additional costs to the project which result from insufficient or inaccurate staking or time lost for corrective action will be considered as a nonexcusable and noncompensable delay.

627.2.6 The construction centerline shown on the plans shall be accurately established and the control points of

all curves shall be referenced. If it is necessary to introduce an equation in order to match the plan stationing or if a plan equation is changed, such changes will be at the written direction of the engineer.

627.2.7 Adjustments necessary to provide accurate staking or match improvements to existing features shall be

immediately brought to the attention of the engineer The engineer will determine the nature of the discrepancy and will make revisions as necessary. The contractor shall perform any restaking required by such revisions. Any reimbursement due to the contractor for additional staking due to design errors will be in accordance with Sec 109.4.3.

627.2.8 After the centerline has been established and referenced, centerline elevations shall be taken at all

stations and at any other points required to ensure the computation of accurate quantities. Centerline elevations shall be based on the plan datum. All benchmarks shown on the plans shall be checked.

627.2.8 1 In the event a difference of plus or minus 0.01 foot exists in elevation for any benchmark shown on

the plans, check levels shall be run and shown in the notes. The elevations shall be corrected to plan elevation at each benchmark where any difference occurs, and shall be noted in the field notes. If a plan benchmark has been disturbed or if correction of the plan elevation is not feasible, a full explanation shall be made in the notes. The contractor shall furnish to the engineer a listing of benchmarks prior to beginning construction.

627.2.8 2 If original plan cross sections differ from existing conditions by an average deviation in excess of one

foot, the contractor shall immediately notify the engineer. The engineer will be responsible for taking cross- sections where deviations are determined to exist.

627.2.9 After completing any bridge, box culvert or retaining wall staking, the contractor shall furnish to the

engineer structural layout plan sheets which show the location of all points that have been staked. At the time of furnishing the marked layout sheets, the contractor shall meet with the engineer to review the layout a minimum of two working days before construction begins.

627.2.10 Upon completion of the project, the contractor shall provide to the engineer all original surveying field

notes, layouts and computations in standard bound survey notebooks or in a form acceptable to the engineer.

627.3 Method of Measurement. No measurement will be made for contractor surveying and staking. This work

shall be considered a lump sum unit when a pay item is provided in the contract.

627.4 Basis of Payment. When a pay item is provided in the contract, contractor furnished surveying and

staking will be paid for at the contract lump sum price and will be considered full compensation for the following:

a.Performing this work.
b.All material, labor, tools, equipment and incidentals necessary to complete the work.
c.For all effects, impacts, cumulative impacts, incidental and consequential costs, loss or damage arising from, relating to or produced by error or discrepancies in surveys or staking and plans based on such surveys or staking, and any cost, including time effects, to correct the errors or discrepancies.

627.4.1 Payment for surveying and staking will only be made when a pay item is provided in the contract. If no

pay item is provided, all costs associated with surveying and staking shall be considered included in the cost of other bid items.

627.4.2 Payment for contractor furnished surveying and staking completed, not to exceed the contract item

amount, will be made upon written request by the contractor. Such a request shall be submitted to the engineer two business days prior to the progress estimate date.

627.4.3 Complete payment will not be made until the contractor has provided all of the original surveying field

notes, layouts, computations and notebooks to the engineer.

Referenced in this section

Get an email when 627 changes

Missouri revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Missouri Standard Specifications for Highway Construction, 2026 (Oct) Edition. Pages 407–408 of 874. View official source ↗

Ask about this section

Scoped to Missouri Missouri Standard Specifications for Highway Construction, Section 627 — Contractor Surveying and Staking. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.