SECTION 814 - PAINTING METAL STRUCTURES
814.01 Description. This work consists of furnishing all materials and painting of metal
structures. It shall include, unless otherwise provided in the contract, the preparation of metal surfaces, application, protection and drying of the paint coatings, supplying of all tackle, scaffolding and other esse ntials necessary to complete the work in reasonably close conformity with the sp ecifications and as indicated on the plans. The Coating System will consist of one shop coat of inorganic zinc, one field intermediate coat of acrylic latex and one field top coat of acr ylic latex. The shop coat, field intermediate coat and top coat shall each have a dry film th ickness of not less than 3 mils or more than 5 mils. Touch-up paint for field repair of damaged areas in the inorganic zinc shop coat shall consist of epoxy mastic applie d to a uniform dry film thickne ss of not less than 4 mils nor more than 6 mils.
814.02 Materials.
814.02.1 Shop Coat. Paint for the shop or prime coat shall be an inorganic zinc primer
and meet the requirements of Subsection 710.03.
814.02.2 Acrylic Latex Intermediate Coat. Paint for the acrylic latex intermediate field
coat shall meet the requirem ents of Subsection 710.03.
814.02.3 Acrylic Latex Top Coat. Paint for the acrylic latex top field coat shall meet the
requirements of Subsection 710.03.
814.02.4 Epoxy Mastic Touch-Up Paint . Field touch-up paint for repair of damaged
inorganic zinc shop coat shall meet the requirements of Subsection 710.03.
814.03 Construction Requirements.
814.03.1 Mixing of Paint. All paint shall be mixed in accordance with the manufacturer's
printed instructions.
814.03.2 Weather Conditions. Solvent base paint shall not be applied when the
surrounding air temperature is below 40°F. Waterborne paint shall not be applied when the surrounding air temperature is below 50 °F. Paint shall not be applied when the surrounding air temperature is expected to drop to 32°F prior to drying of the paint. Paint shall not be applied when the metal is hot enough to cause blistering or produce a porous film. Paint shall not be applied when the stee l surface is less than 5°F above the dew point nor shall it be applied in rain, snow, wind, fog, mist or when, in the opinion of the Engineer, conditions are otherwise un satisfactory for the work.
814.03.3 Application.
814.03.3 1--Shop Coat. The coating shall be capable of being applied in accordance with
specification requirements and shall be app lied in accordance with the manufacturer's printed instructions. After initial mixing, the paint shall be stra ined through a metal 30-60 mesh screen. Stirring paddles on the mechanical mixing equipm ent shall reach to with in one inch of the bottom of the paint container. Airless spray equipment for application of inorganic zinc silicate paint shall provide pressure of not less than 2200 psi at the nozzle. The fluid hose between the pot and nozzle shall not be less than 3/8-inch inside diameter. Pressure may vary depending on tip size and pump. Conventional spray equipment for application of inorganic zinc silicat e paint shall provide pressure of not less than 10 psi at the pot and 30 psi at the nozzle.
814.03.3 2--Acrylic Latex Intermediate and Top Coats. All applications of the acrylic
latex intermediate and top coats shall be in accordance with the manufacturer's printed instructions. The primer coat and the intermediate coat sh all have dried a minimum of eight hours under normal conditions prior to ap plication of the intermediate and top coats, respectively. All surfaces shall be free of any soluble residue and surfaces on which the primer coat has been applied shall be free of excessive amounts of loose zinc before a subsequent coat is applied. Dust and dirt that may have accumulated on the surface shall be removed from the dried film with a soft brush or rag before application of a subsequent coat. When applied by brushing or spraying, the coating shall deposit a uniform dry film thickness without running or sagging.
814.03.4 Removal of Paint. If any painting is unsatisfact ory, it shall be removed and the
metal thoroughly cleaned and repainted.
814.03.5 Thinning Paint. Paint shall be thinned only in strict accordance with the
manufacturer's recommendations.
814.03.6 Painting Galvanized Surfaces. Prior to application of the acrylic latex field
coats, galvanized surfaces sha ll be primed with Epoxy Mastic Touch-Up Paint as specified in Subsection 814.02.
814.03.7 Cleaning of Surfaces. Surfaces to be painted sh all be thoroughly cleaned,
removing rust, loose mill scale, dirt, o il or grease and other foreign substances. All exposed and accessible surfaces of the me tal shall be cleaned by sandblasting in accordance with the requirements of Steel Structures Painting Council SSPC-SP-10, Near White Blast Cleaning. The surface, regardless of starting condition, sha ll in the opinion of the Engineer or the Engineer’s designated representative be at least equal to the appearance of Pictorial Swedish Standard Sa 2 1/2 of SIS 05 59 00, SSPC-VIS 1. All rust blooms shall be removed by re-blas ting before coating. The surface shall be constantly and diligently examined ahead of the coating operations for an y traces of rust, oil, grease or blemishes not permitte d by the blast cleaning specifications.
814.03.8 Shop Painting. Unless otherwise specified, the shop coat shall be applied
immediately after the steel work ha s been accepted by the inspector. Shop contact surfaces shall not be painted. Field contact surfaces except for machine finished pins and holes shall receive a shop coat with a minimum dry film thickness of 1½ mils. All other surfaces that will be inaccessible after assembly or erection shall be given all required coats. Surfaces that will be embedded or in contact with concrete shall no t require pa inting unless otherwise noted on the plans. They may be painted in whole or in part due to overspray provided the paint thickness does not exceed the requirements specified for adjacent areas. Structural steel that is to be field welded sh all not be shop painted within two inches of the field welds. All surfaces of iron and steel castings except fo r machine finished pins and holes, shall be given two shop coats of paint. Erection marks for field identification of me mbers and weight marks shall be painted on areas previously painted with the shop coat. Material shall not be loaded for shipment until it is thoroughly dry and no sooner than 24 hours after the paint has been applied.
814.03.9 Field Painting. When the erection work is co mplete, includin g all bolting and
straightening of bent metal, all rust, scale, dirt, grease and other foreign material shall be removed. As soon as the Engineer has approved all fiel d welding and bolting, the surfaces from which the shop coat of paint has worn off or otherw ise become defective shall be cleaned and re- primed with the specified touc h-up paint prior to applicati on of the intermediate coat. Spans with concrete decks shall not be painted until after the deck is placed. All concrete spills and stains shall be washed from the struct ural steel prior to the mortar taking a set. Surfaces to be bolted in contact and surfaces th at will be in contact with concrete shall not have a field coat applied. When the paint applied for retouching the shop coat has thoroughly dried and the field cleaning has been satisfactorily complete d, the intermediate coat shall be applied. After the intermediate coat has thorough dried, the top coat shall be applied. In no case shall a subsequent coat be applied until the pr evious coat has dried throughout the fu ll thickness of the paint film. To secure a maximum coating on edges of pl ates or shapes, bolt heads and other parts subjected to special wear and attack, the edges shall be stri pped with a longitudinal motion and bolt heads with a rotary motion of the brush followed immediately by the general painting of the whole surface, including recoating of the edges and bolt heads. If, in the opinion of the Engineer, traffic produces an objectionable amount of dust, the Contractor shall, at no additio nal cost to the State, allay th e dust for the necessary distance on each side of the bridge and take any other precautions necessary to prevent dust and dirt from coming in contact with freshly painted surfaces or surfaces prepared for painting. The Contractor shall protect pedestrian, vehicu lar and other traffic upon or underneath the bridge and also all portions of the bridge superstructure and substructure against damage or disfigurement by spatters, sp lashes and smirches of paint or paint material. Any such disfigurement shall be removed at the directi on of and to the satisf action of the Engineer.
814.03.10 Inspection. The completed shop coat shall be inspected by the Contractor for
thickness by means of elcometer or other approved magnetic detector thickness gauge. Detection of insufficiently coated sections sh all be marked and shall be coated over or touched up to establish the specified thickness. All areas of the finished system deficient in thickness shall be coated over with the acrylic latex top coat paint to establish the specif ied thickness. Excessive thickness in the application of any coating evid enced by mudcracking will be ca use for the aff ected area to be blast-cleaned and repainted. Where rejection is due to poor workmanship or deficiency in the qu ality of the work or materials, the Contractor may be required to blast clean the en tire defective sections of all previously applied materials prior to repainting. Inspection shall be done in the presence of an d to the satisfaction of the Engineer. The Engineer shall be provided acce ss to the work to allow for pr oper inspection of the cleaning and painting at both the fabricati on plant and the construction site.
814.04 Method of Measurement. Unless shown as a separate pay item in the proposal,
painting of metal structures or members will not be measured for separate payment and the cost thereof shall be incidental to and includ ed in the contract unit price(s) bid for other items.
814.05 Basis of Payment. When shown as a separate pa y item in the pr oposal, painting
of metal structures or members will be paid for at the contract lump sum price, which price shall be full compensation for completing the work. Payment will be made under: 814-A: Painting of Meta l Structure - lump sum 814-B: Painting of Description - lump sum SECTION 815 - RIPRAP AND SLOPE PAVING
815.01 Description. This work consists of furnishing and placing a protective covering
of erosion resistant material including geotex tile fabric, where shown on the plans for pier foundation protection, slope, or ditch protection. This work shall be in accordance with these specifications and in reasonably clos e conformity with the lines, grades and dimensions shown on the plans or established.
815.02 Materials. Materials for riprap and slope paving shall conform to the following.
Geotextile shall meet the requirements of Subsection 714.13. Aggregate for loose ripr ap, stone riprap for foundation protection, or that to be grouted shall consist of field stone, broken concrete, or rough, unhewn quarry stone as nearly