General Provisions (00100-00999)

804Concrete Bridges and Structures

MS · 2017 Standard SpecificationsBook pages 9501013View official source ↗

Section 803 Section 803

803.05.18 Casings. Casings, measured as prescribed above, will be paid for at the

contract price per linear foot, which price shall be full compensation for furnishing, placing, and removing (when required) the casing in the shaft excavation. The prices thus paid shall be full compensation for all materials, tools, equipment, labor, and incidentals required to complete work. Payment will be made under: 803-A: Test Pile * - per each 803-B: Conventional Static Pile Load Test - per each 803-C: ___” Prestressed Concrete Piling - per linear foot 803-D: ___ Steel Piling -per linear foot 803-E: Concrete Piling Cut-off, Size - per each 803-F: ___” Pre-formed Pile Hole - per linear foot 803-G: PDA Test Pile and Special In strumentation Load Test - per each 803-H: PDA Test Pile and Conventional Load Test - per each 803-I: PDA Test Pile - per each 803-J: Pile Restrike - per each 803-K: Drilled Shaft, ___” Diameter - per linear foot 803-L: Test Shaft, ___” Diameter - per each 803-M: Trial Shaft, ___” Diameter - per linear foot 803-N: Exploration - per linear foot 803-O: ** Casing, ___” Diameter - per linear foot 803-P: ___” Steel Pipe piling, Wall Thickness ___” - per linear foot * Indicate Size and Type ** Temporary or Permanent SECTION 804 - CONCRETE BRIDGES AND STRUCTURES

804.01 Description. This work consists of constructing concrete bridges and structures

in accordance with these specifications and in reasonably close conformity with the dimensions, designs, lines, and grades indicated on the plans or established. Construction of box bridges shall be in accordance with Sections 601 and 602.

804.02 Materials.

804.02.1 General. Concrete produced and controlled from this specification shall be

accepted upon proper certification of concre te production through an approved quality control program and verification by job site acceptance criteria. The Contractor shall develop and implement a quality control program that shall be used to maintain the required properties of concrete. For projec ts with 1000 cubic yards and more, quality control and acceptance shall be achieved through statistical evaluation of test results. For projects of more than 200 but less than 1000 cubic yards, quality control and acceptance shall be achieved by individual test results. For projects less than or equal to 200 cubic yards, refer to the requirements of TMD-20-05-00-000 “Sampling and Testing of Small Quantities of Miscellaneous Materials” for mixture design and testing requirements. The materials for concrete bridges and struct ures, when sampled and tested in accordance with Subsection 700.03, shall meet the requirements of the following Subsections: Cement ....................................................................................... 701.01 and 701.02 Blended Cement ......................................................................... 701.01 and 701.04 Admixtures .................................................................................................... 713.02 Fly Ash .......................................................................................................... 71 4.05 Ground Granulated Blast Fu rnace Slag (GGB FS) ......................................... 714.06 Silica Fume ................................................................................................. 714.09.2 Water .................................................................................... 714.01.1 and 714.01.2 Fine Aggregat e .............................................................................................. 703.02 Coarse Aggregat e .......................................................................................... 703.03 Lightweight Aggreg ate .................................................................................. 703.19 Curing Material s ............................................................................................ 713.01 Joint Materials ............................................................. 707.01, 707.02, and 707.07 Structural Steel Joints and Bearing Devices .................................................. 717.01 Bearing Pads .................................................................................................. 714.10 Wire Rope or Wire Cable for Prestre ssed Concrete ................... 711.01 and 711.03 Sprayed Finish for Conc rete Surface ............................................................. 714.12 Reinforcing Steel ........................................................................................... 711.02

804.02.2 Use, Care, and Handling. The use, care, and handling of materials shall

conform to the applicable requirements of Subsection 501.03.10 and the specific requirements of Subsections 804.02.4 and 804.02.5. Unless otherwise authorized, only fine aggregate or coarse aggregate of one type and from the same source shall be used in the construction of any one unit of a structure. Should the Contractor, with written permission of the Engineer, elect to substitute high early strength cement for cement of the type specified, the Contractor will not receive additional co mpensation for the substitution.

804.02.3 Non-Qu ality Control / Quality Assurance Concrete. The following concrete

items will not be accepted based on the Qu ality Control / Quality Assurance (QC/QA) requirements. The acceptance of these conc rete items will be based on sampling and testing at the project site by Department personnel. The Contractor is required to submit mix designs to accomplish this work in accor dance with Section 80 4 and perform normal Quality Control functions at the concrete plant. Acceptance will be in accordance with the requirements of Section 601, Structural Concrete, and TMD-20-04-00-000. At the discretion of the Engineer, the Contractor may request that the concrete be accepted based on QC/QA requirements. Section Description 221 Paved Ditches 601 Minor Structures - manholes, inlets, catch basins, junction boxes, pipe headwalls, and pipe collars. 605 Edge Drain and Underdrain Outlet Pads 606 Guardrail Anchors 607 Fence Post Footings 608 Sidewalks 609 Curb and Gutter 614 Driveways 616 Median and Island Pavement 630 Sign Footings, except Overhead Sign Supports 815 Slope Paving

804.02.4 Care and Storage of Concrete Aggregates. The handling and storage of

aggregates shall be such as to prevent segrega tion or contamination with foreign materials. The Engineer may require that aggregates be stored on separate platforms at satisfactory locations. If specified, coarse aggregates shall be separate d into two or more sizes in order to secure greater uniformity of the concrete mixture. Different sizes of aggregate shall be stored in separate stock piles sufficiently removed fro m each other to prevent the material at the edges of the piles from becoming intermixed. 804.02.5--Storage of Cementitious Materials. All cementitious materials shall be stored in suitable weather-proof buildings or bins. These buildings or bins shall be placed in locations approved by the Engineer. Provision for storage shall be ample, and the shipments of cementitious materials as recei ved shall be stored separately or other provisions made to the satisf action of the Engineer for eas y access for the identification, inspection, and sampling of each shipment as deemed desirable. Stored cementitious materials shall meet the test requirements at any time after storage when a retest is ordered by the Engineer. On small jobs, open storage consisting of a raised platform and ample waterproof covering may be permitted by written authorization from the Engineer. When specified, the Contractor shall keep a ccurate records of deliveries of cementitious materials and of their use in the work. Copies of these records shall be supplied in the form required by the Engineer.

804.02.6 Classification and Uses of Concrete. When a specific class of concrete is not

specified on the plans or in the contract docu ments, the structure or parts thereof shall be constructed with the class of concrete as directed by the Engineer. The classes and their uses are as follows:

1.Class AA - Concrete for bridge construction and concrete exposed to seawater.
2.Class B - General use, heavily reinforc ed sections, cast-in-place concrete piles, and conventional concrete piles.
3.Class BD - Concrete for bridge decks
4.Class C - Massive sections or lightly reinforced sections.
5.Class D - Massive unreinforced sections and riprap.
6.Class F - Concrete for prestressed members. 7) Class FX - Extra strength concrete for prestressed members, as shown on plans.
8.Class S - For all seal concrete deposited under water. 9) Class DS - Drilled Shaft

804.02.7 Blank .

804.02.8 Laboratory Accreditation. The Contractor shall be responsible for furnishing

the laboratory used to perform concrete quality control tests. The laboratory may be the Contractor’s facility, the concrete producer’s facility, or a certified independent testing laboratory. Only laboratories certified by the Department ar e qualified to perform material testing. Certification by AASHTO Accreditation Pr ogram (AAP) will be acceptable if the laboratory is listed in the latest AAP pub lication and maintains accreditation to completion of concrete work. The Contractor’s laboratory designated for quality control testing shall have equipment necessary to test aggregates and concrete for the test methods listed in Table 1. Table 1 AASHTO: R 39 Making and Curing Concrete Test Specimens in the Laboratory AASHTO: R 60 Sampling Freshly Mixed Concrete AASHTO: T 2 Sampling Aggregates AASHTO: T 19 Bulk Density (“Unit Weight”) and Voids in Aggregates AASHTO: T 22 Compressive Strength of Cylindrical Concrete Specimens AASHTO: T 23 Making and Curing Concrete Test Specimens in the Field AASHTO: T 27 Sieve Analysis of Fine and Coarse Aggregates AASHTO: T 84 Specific Gravity and Absorption of Fine Aggregate AASHTO: T 85 Specific Gravity and Absorption of Coarse Aggregate AASHTO: T 119 Slump of Hydraulic Cement Concrete AASHTO: T 121 Density (Unit Weight), Yield, and Air Content (Gravimetric) of Concrete AASHTO: T 152 Air Content of Freshly Mixed Concrete by Pressure Method * AASHTO: T 196 Air Content of Freshly Mixed Concrete by the Volumetric Method * AASHTO: T 231 Capping Cylindrical Concrete Specimens AASHTO: T 248 Reducing Field Samples of Aggregate to Testing Size AASHTO: T 255 Total Evaporable Moistu re Content of Aggregate by Drying AASHTO: T 325 Standard Method of Test for Estimating the Strength of Concrete in Transportation Construction by Maturity Tests ** AASHTO: T 309 Temperature of Freshly Mixed Portland Cement Concrete ASTM: C 1074 Standard Practice for Estimating Concrete Strength by the Maturity Method ** * Equipment necessary for either pressure or volumetric air content. ** Equipment necessary for estimating concrete strength following the maturity method. Testing equipment shall be inspected by the Department or through the AASHTO Accreditation Program. Testing equipment calib ration files shall be made available upon request by the Department.

804.02.9 Testing Personnel. Technicians testing hydraulic cement concrete, for either

acceptance or production control purposes, shall be certified by an accepted certification program. Recertification is required for each Class after five years. Certification requirements are listed in Table 2. Table 2 Concrete Technician’s Tasks Test Method Required Certification Required** Sampling or Testing of Plastic Concrete AASHTO R 60, T 23, T 119, T 121, T 152, T 196, and T 309 MDOT Class I certification Compressive Strength Testing of Concrete Cylinders AASHTO T 22 and T 231 MDOT Concrete Strength Testing Technician certification Sampling of Aggregates AASHTO T 2 Work under the supervision of a MDOT Class II certified technician Testing of Aggregates AASHTO T 19, T 27, T 84, T 85, T 248, and T 255 MDOT Class II certification Proportioning of Concrete Mixtures* AASHTO M 157 and R 39 MDOT Class III certification Interpretation and Application of Maturity Meter Readings AASHTO T 325 and ASTM C 1074 Two hours maturity method training * Technicians making concrete test sp ecimens for meeting the requirements of Subsection 804.02.10.1.2 shall be MDOT Class I certified and under the direct supervision of an MDOT Class III certified technician. ** MDOT Class I certification encompasses th e same test procedures and specifications as ACI Concrete Field Testing Technician-Grade I. MDOT Class II certification encompasses the same test procedures and specifications as ACI Aggregate Testing Technician-Level 1. MDOT Concrete Strength Testing Technician encompasses the same test procedures and specifications as ACI Concrete Strength Testing certification. Specific requirements for each level of certifica tion are in the latest edition of the Department’s Concrete Field Manual . Current MDOT Class I, MDOT Class II, and/or MDOT Class III certifications shall be acceptab le until those certifica tions expire. Upon expiration of a current certification, recertification with the cer tifications listed in Table 2 shall be required. Technicians performing either specific gravity testing of aggregates or compressive strength tests shall be required to either:

a.have the required MDOT certification listed in Table 2, or
b.have a current MDOT Class III certification or work under the direct supervision of current MDOT Class III technician, and have demonstrated the specific gravity and/or compressive strength test during the inspection of laboratory equipment by the Materials Division, Concrete Section.

804.02.10 Hydraulic Cement Concrete Mixture Design. At least 10 working days prior

to production of concrete, the Contractor shall submit to the Engineer proposed concrete mixture designs complying with the Department’s Concrete Field Manual . Materials shall be from approved sources meeting the requirements of the Standard Specifications. Proportions for the mixture designs shall be for the class concrete required by the plans and shall meet the requirements of the “Master Proportion Table for Structural Concrete Design” listed in Table 3. The concrete producer shall assign a permanent unique mixture number to each mixture design. Each mixture design shall be field verified as required in Subsection 804.02.10.3. Acceptable field verification data shall be required for final approval of a mixture design. All concrete mixture designs will be reviewed by the Materials Division prior to use. Concrete mixture designs disapproved will be returned to the Contractor with a statement explaining the disapproval. If the Contractor chooses to cure the concrete in accordance with the requirements listed under Length of Time Defined by Development of Compressive Strength in Subsection

804.03 17, the compressive strength/maturity relationship shall be developed for the

mixture design for a minimum of 28 days following the requirements of Subsection

804.03.15 The compressive strength/maturity relationship information shall be submitted

with the mixture design information. Table 3 MASTER PROPORTION TABLE FOR STRUCTURAL CONCRETE DESIGN Class Application Coarse Aggregate Size No. Maximum w/cm RatioSpecified Compressive Strength (f' c) psi Maximum Permitted Slump, or Slump Flow inches3 Nominal Total Air Content (%) Maximum Static Segregation (%) AA General and Structural 57 or 67 0.45 4000 3 [-1.5] 4-8 [-2.5] 4.5±1.5 N/A B Minor Structures 57 or 67 0.50 3500 4-8 [-2.5] 4.5±1.5 N/A BD Bridge Deck1 57 or 67 0.43-0.45 4000 5 [-2.5] 4.5±1.5 6.5±1.5 N/A C Massive sections 57 or 67 0.55 3000 4-8 [-2.5] 4.5±1.5 N/A D Massive unreinforced sections 57 or 67 0.70 2000 4-8 [-2.5] 4.5±1.5 N/A F2 Prestressed members 67 0.40 5000 3 [-1.5] 4-8 [-2.5] See note2 NA F2 Prestressed members SCC 67 0.40 5000 28 [-4] See note2 15 FX2 Extra strength for prestressed members 67 As per mixture design As shown on plans 3 [-1.5] 4-8 [-2.5] See note2 NA FX2 Extra strength for prestressed members 67 As per mixture design As shown on plans 28 [-4] See note2 15 S Seal concrete deposited under water 57 or 67 0.45 3000 8 [-2.5] 4.5±1.5 N/A DS2 Drilled shaft 67 0.45 4000 8±1 See note2 N/A DS2 Drilled shaft SCC 67 0.45 4000 24 [-6] See note2 15 1 For Class BD concrete for bridge decks, the water/cementitious material ratio range shall be 0.43-0.45 and the maximum cemen titious material content shall be 550 pounds per cubic yard. Also, an approved synthetic structural fiber m eeting the requirements of Subsection 711.04 shall be incorporated into the mixture at 1.25 tim es the approved dosage rate. For each additional pound of fibers per cubic yard added in excess of the requirement stated above, an additional inch of slump will be allowed up to a maximum permitted slump of eight (8) inches. 2 Entrained air is not required for Class F, FX, an d DS concrete unless expos ed to seawater. For concrete not exposed to seawater, the total air content shall not exceed 6.0%. For concrete exposed to seawater, th e nominal total air content shall be 4.5%. Note: Brackets [#] indicate minus slump tolerances. 3 The design slump selected by the Contractor for the mix design approval is the maximum slump permitted. Lightweight aggregate (LWA) meeting the requirements of Subsection 703.19.2 may also be used as a partial replacement for fine aggr egate. The replacement limits of hydraulic cement by weight by other cementitious materi als (such as fly ash, GGBFS, silica fume, or others) shall be in accordance with the values in Subsection 701.02. Other hydraulic cements may be used in accordance with the specifications listed in Section 701 At least one water-reducing admixture or water-reducing/set-retarding admixture shall be used in all classes of concrete in accordance with the manufacturer’s recommended dosage range. Admixtures providing a specific performance characteristic other than those of water reduction or set retardation may be used in accordance with the manufacturer’s recommended dosage range. Accelerating admixt ures shall not be used unless approved by the State Materials Engineer. Any combinations of admixtures shall be approved by the Engineer before their use.

804.02.10 1--Proport ioning of Hydraulic Cement Concrete Mixture Design.

Proportioning of hydraulic cement concrete shall be based on an existing mixture of which the producer has field experience and docum entation or based on a recently batched laboratory mixture tested according to the required specifications.

804.02.10 1.1--Proportioning on the Basi s of Previous Field Experience of Trial

Mixtures. Where a concrete production facility has a record, based on at least 10 consecutive strength tests from at least 10 different batches within the past 12 months from a mixture not previously used on Department projects, the standard deviation shall be calculated. The record of tests from which the standard deviation is calculated shall:

a.Represent similar materials and conditions to those expected. Changes in materials and proportions within the test record shall not have been more closely restricted than those for the proposed work.
b.Represent concrete produced to meet a specified strength.
c.Consist of 10 consecutive tests, average of two cylinders per test, tested at 28 days. For concrete categorized as a self-consolidating concrete (SCC) mixture, the test data for the plastic concrete shall include the slump flow data, instead of the slump data, and at least one test to determine the static segregation. For all mixture designs, for each of these tests on the plastic concrete the test data shall meet the acceptance criteria of Subsection 804.02.13.1. The standard deviation, s, shall be calculated as: െ1ሻቃଵ/ଶ where: Xi = the strength result of an individual test X = the average of individual tests in the series N = number of tests in the series When the concrete production facility does not have a record of tests for calculation of standard deviation, as required in the a bove formula, the requirements of Subsection

804.02.10 1.2 shall govern.

The required average compressive strength ( f’ cr) used as the basis for selection of concrete proportions shall conform to the inequality listed below, while using a standard deviation, s, calculated as shown above. X  f’cr where: f’ cr = f’ c + 1.43s where: f’ c = specified compressive strength of concrete, psi f’cr = required average compressive strength of concrete, psi s = standard deviation, psi 1.43 represents the Lower Quality Index necessary to assure that 93% of compressive strength tests are above f’ c.

804.02.10 1.2--Proportioning on the Ba sis of Laboratory Trial Mixtures. When an

acceptable record of field test results is not available, concrete proportions shall be established based on laboratory trial mixtures meeting the following restrictions:

a.The combination of materials shall be those intended for use in the proposed work.
b.Trial mixtures having proportions and consistencies suitable for the proposed work shall be made using the ACI 211.1 as a guide to proportion the mixture design.
c.Trial mixtures shall be designed to produce a slump within ¾ inch of the design slump allowed, and for air-entrained concrete, 0.5 percent of the maximum permitted air content in Table 3. The temperature of freshly mixed concrete in trial mixtures shall be reported.
d.For each proposed mixture, at least three compressive test cylinders shall be made and cured in accordance with AASHTO R 39 . Each change of water-cement ratio shall be considered a new mixture. The cylinders shall be tested for strength in accordance with AASHTO T 22 and sh all be tested at 28 days.
e.The required average strength of laboratory trial mixes shall exceed f’c by 1200 psi for concrete mixture designs less than 5000 psi and by 1400 psi for concrete mixture designs of 5000 psi or more.
f.The laboratory trial batch mixtures shall have been made within the previous 12 months before being submitted for approval and shall not have been previously used on Department projects.
g.For concrete categorized as a SCC mixture, the mixture shall be designed to produce a slump flow within ±2 inches of the maximum permitted and a maximum static segregation of 15.0 percent. The concrete shall not be rodded or vibrated during casting the test specimens.
h.For concrete categorized as a SCC mixture, test specimens shall be made in accordance with the above listed specifica tions with the exception that the concrete shall not be rodded or vibrated during casting the test specimens.

804.02.10 2--Documentation of Average Strength. Documentation that the proposed

concrete proportions will produce an average strength equal to or greater than the required average shall consist of the strength test record s from field tests or results from laboratory trial mixtures.

804.02.10 3--Field Verification of Concrete Mixture Design. Concrete mixture designs

will only be tentatively reviewed pending field verification submission and are not approved for payment by the Department until field verification is submitted. The requirements for yield, slump, or total air co ntent shall be successfully met within the first three (3) production days. Mixture designs may be transferred to other projects without additional field verification testing if the mixture design is less than twelve (12) months old, once the mixture design has passed the field verification process. All concrete mixtures will have a complete field verification performed and submitted to the Department’s Materials Division every 12 months. The Contractor’s Certified Quality Control T echnicians shall test each concrete mixture design upon the first placement of the mix. Ag gregates and concrete tests during the first placement shall be as follows. Aggregates Concrete Bulk Specific Gravity Water Content Moisture Slump or Slump Flow Gradation Air Content Unit Weight Yield Static Segregation For all Classes of concrete, the mixture shall be verified to yield within 2.0% of the correct volume when all the mix water is added to the batch. For concrete categorized as a SCC mixture, the mixture shall produce a slump flow within minus four inches (4”) of the maximum permitted and a static segregation less than 15.0%. For all Classes of concrete other than DS, F, and FX, the mixture shall produce a slump within a minus 1½-inch tolerance of the design for mixtures with a design slump of three inches (3") or less or within a minus 2½-inch tolerance of the design for mixtures with a design slump of greater than three inches (3"), and producing a total air content tolerance within the maximum allowable air content in Table 3. For Class DS, the slump range shall be 8 inches ±1 inch. For Class DS exposed to seawater, the total air content shall be within the tolerance of the maximum allowable air content in Table 3. For Class DS not exposed to seawater the total air content shall be within the requirements in Table 3. For Classes F and FX, the slump shall be within a minus 1½-inch tolerance of the design for mixtures with a design slump of three inches (3") or less or within a minus 2½-inch tolerance of the design for mixtures with a desi gn slump of greater than three inches (3"). For Classes F and FX exposed to seawater, the to tal air content shall be within the tolerance of the maximum allowable air content in Table 3. For Classes F and FX not exposed to seawater the total air content shall be within the requirements in Table 3. The mixture shall be adjusted and retested, if necessary, on subsequent placements until the above mentioned properties are met. If the requirements for yield, slump, or total air content are not met within the first three

3.production days, subsequent field verification testing shall not be permitted on Department projects, and the mixture design shall not be used until the requirements listed above are met. Any mixture design adjustments, changes in the mixture proportions, are to be made by a Class III Certified Techni cian representing the Contractor. After the mixture design has been verified and adjustments made, verification test results will be reviewed by the Engineer.

804.02.10 3.1--Slump Loss of Class DS Concrete Mixture Designs. Prior to concrete

placement, the Contractor shall provide test results of a slump loss test using approved methods to demonstrate that the mixture meets the four hour requirement in Subsection 803.03.2.7.1. The Contractor shall notify the Department 48 hours prior to performing the slump loss test. These tests shall be con ducted successfully by an approved testing laboratory during the installation of the trial shaft, with personnel from the Department present. As an alternative, the slump loss test can be performed prior to the installation of the trial shaft. The slump loss test shall be conducted at temperatures and conditions similar to those expected at the job site at the time of the installation of the trial shaf t. The sample for the slump loss test shall be from a minimum batch size of four (4) cubic yards of concrete. If the temperature between a successful slump loss test and the installation of the production shaft exceeds 10ºF above the conc rete temperature, an other successful slump loss test shall be performed on the first truckload of concrete as part of the installation of the trial shaft. The requirement to limit the time between the previous slump loss test and an installation of the trial shaft also applie s to Class DS concrete mixture designs being transferred from another project. During any shaft installation a slump loss test shall be conducted by the Contractor at the direction of the Engineer from the concrete at the site for verification of slump loss requirements using a sample from a minimum batch size of four cubic yards of concrete. For concrete categorized as a SCC mixture, the Class DS SCC mixture shall not require a slump loss test.

804.02.10 4--Adjustments of Mixtures. The mixture design may be adjusted by the Class

III Certified Technician representing the C ontractor in accordance with the allowable revisions listed in paragraph 5.7 of the Department’s Concrete Field Manual . Written notification shall be submitted to the Engineer a minimum of seven (7) days prior to any source or brand of material change, aggregate size change, allowable material type change, or decrease in any cementitious material content. Any adjustments of the concrete mixture design shall necessitate repeat of field veri fication procedure as described in Subsection

804.02.10 3.1 and approval by the Engineer.

804.02.11 Concrete Batch Plants. The concrete batch plant shall meet the requirements

of the National Ready Mixed Concrete Association Quality Control Manual, Section 3, Plant Certification Checklist as outlined in the latest edition of the Department’s Concrete Field Manual . The Contractor shall submit a copy of the approved checklist along with proof of calibration of batching equipment, i.e., scales, water meter, and admixture dispenser, to the Engineer 30 days prior to the production of concrete. For projects with 1000 cubic yards and more, the concrete batch plant shall meet the requirements for an automatic system capable of recording batch weights. It shall also have automatic moisture compensation for the fine ag gregate. For projects of more than 200 but less than 1000 cubic yards the plant can be equipped for manual batching with a fine aggregate moisture meter visible to the plant operator. The concrete batch plant shall have available adequate facilities to cool concrete during hot weather. Mixer trucks to be used on the project are to be listed in the checklist and shall meet the requirements of the checklist.

804.02.12 Contractor’s Quality Control. The Contractor shall provide and maintain a

quality control program that will provide assurance that all materials and products submitted to the Department for acceptance w ill conform to the contract requirements, whether manufactured or processed by the Contractor or procured from suppliers, subcontractors, or vendors. The Contractor's Quality Control program shall implement the minimum quality control requirements shown in Table 4, "CON TRACTOR’S MINIMUM REQUIREMENTS FOR QUALITY CONTROL”. The quality control ac tivities shown in the ta ble are considered to be normal activities necessary to control the production an d placing of a given product or material at an acceptable quality level. To facilitate the Department’s activities, all completed gradation samples shall be retained for a maximum of sixty (60) days by the Contractor until further disposition is designated by the Department. The Contractor shall perform, or have performed, the tests required to substantiate product conformance to contract document requirements and shall also perform, or have performed, all tests otherwise required. The Contractor’s Quality Control program shall encompass the requirements of AASHTO M 157 into concrete production and control, equipment requirements, testing, and batch ticket information. The requirement of AASHTO M 157, Section 11.7 shall be followed except, on arrival to the job site, a maximum of 1½ gallons per cubic yard shall be allowed to be added. Water shall not be added at a later time. Job site adjustment of a batch using chemical admixtures or the mechanical adju stment of a batch may be performed by the Contractor if the requirements of Subsection 804.02.12.1.1 have been satisfactorily addressed in the Quality Control Plan. If ei ther the maximum permitted slump is exceeded or the total air content is not within the required range after all adjustments are made at the job site, the concrete shall be rejected. The Contractor's quality control tests shall be documented and shall be available for review by the Engineer throughout the life of the contract. As set out in these specifications, quality control sampling and testing performed by the Contractor will be used by the Department for determination of acceptability of the concrete. The Contractor shall maintain standard equipment and qualified personnel as required to assure conformance to contract requirements.

804.02.12 1--Quality Control Plan. The Contractor shall prepare a Quality Control Plan

that identifies the personnel responsible for the Contractor’s quality control including the company official who will act as liaison with Department personnel. The Quality Control Plan shall be submitted in writing to the Engineer for approval 30 days prior to the production of concrete. The class(es) of concrete involved will be liste d separately. If an existing mixture design(s) is to be used, the mixture design number(s) as previously approved shall be listed. It is intended that sampling and testing be in accordance with standard methods and procedures, and that measuring and testing equipment be standard and properly calibrated. If alternative sampling methods and procedures and alternative inspection equipment are to be used, they shall be detailed in the Quality Control Plan.

804.02.12 1.1--Elements of Plan. The Plan shall address all elements that affect the

quality of the structural concrete including, but not limited to, the following items:

a.Stockpile Management
b.Procedures for Corrective Actions fo r Non Compliance of Specifications
c.Procedure for Controlling Concrete Temperatures
d.Job Site Batch Adjustments by Addition of Chemical Admixtures:
1.The Plan shall address whether the Cont ractor intends to adjust either the slump and/or total air content of a batch on the job site by adding chemical admixture(s) to a batch. The Contractor shall include the names of the personnel designated to perform this batch adjustment, the equipment used to add the chemical admixture(s), and the procedure by which the batch adjustment will be accomplished. On ly the Contractor’s designated personnel shall adjust a batch. Only calibrated dispensing equipment shall be used to add chemical admixture(s) to a batch. Only the procedure described in this section of the Plan shall be utilized.
2.If either the maximum perm itted slump is exceeded or the total air content is not within the required range after all adjustments are made at the job site, the concrete shall be rejected.
3.If the Contractor elects to utilize Job Site Batch Adjustments by Addition of Chemical Admixture within Item 2, Procedures for Corrective Actions for Non Compliance of Specifications, to adjust batches that do not meet the minimum specification requirements for slump and/or total air content, no more than three batches on any one project shall be allowed to be adjusted regardless of the number of mixtures associated with the project.
e.Construction of Concrete Bridge Decks, including the following:
1.the description of the equipment used for placing concrete on the bridge deck in accordance with Subsection 804.03.6 and, as applicable, Subsections 804.03.7 and 804.03.8 includ ing any accessories added to the pump to ensure the entrained air in th e concrete mixture remains entrained during pumping and depositing of the concrete mixture;
2.the description of and the number of pi eces of equipment used to consolidate the concrete in accordance w ith Subsection 804.03.6.2;
3.the description of the equipment used to finish the bridge deck in accordance with Subsection 804.03.19.7;
4.the plan for ensuring a continuous rate of finishing the bridge deck without delaying the application of curing materials within the time specified in Subsection 804.03.17, including ensuring a continuous supply of concrete throughout the placement with an adequate quantity of concrete to complete the deck and filling diaphragms and end walls in advance of deck placement;
5.the plan for applying the curing materials within the time specified in Subsection 804.03.17;
6.the description of the powered fo gging equipment in accordance with Subsection 804.03.17;
7.a sample of the documentation used as the daily inspection report for ensuring maintenance of the continuous wet curing in accordance with Subsection 804.03.17, as required;
8.the description of the equipment used to apply the liquid membrane, including but not limited to, the nozzles, pumping/pressurization equipment, and liquid membrane tanks, in accordance with Subsection 804.03.17;
9.the method for determining the rate of applied liquid membrane meets the application rate requirements in acco rdance with Subsection 804.03.17; and
10.a sample of the documentation used fo r the application rate verification of the liquid membrane in accordance with Subsection 804.03.17.
f.Mechanical Adjustment of Trucks

804.02.12 2--Personnel Requirements . The Contractor’s Designated Certified

Technician shall perform and use quality control tests and other quality control practices to assure that delivered materials and proporti oning meet the requirements of the mixture design including temperature, slump, air conten t, and strength and shall periodically inspect all equipment used in transporting, proportioning, and mixing. The Contractor’s Designated Technician shall periodically inspect all equipment used placing, consolidating, finishing, and curing to assure it is operating properly and that placement, consolidation, finish ing, and curing conform to the mixture design and other contract requirements. 804.02.12.3--Documentation. The Contractor shall maintain adequate records of all inspections and tests. The records shall indicate the nature and number of observations made, the number and type of deficiencies found, date and time of samples taken, the quantities approved and rejected, and the nature of corrective action taken as appropriate. The Contractor's documentation procedures will be subject to approval of the Department prior to the start of the work and to compliance checks during the progress of the work. All conforming and non-conforming results shall be kept complete and shall be available at all times to the Department during the performance of the work. Forms shall be on a computer-acceptable medium. Batch tickets and gradation data shall be documented in accordance with Department requirements. Batch tickets shall contain all the informa tion in AASHTO M157, Section 16, including the additional information in Subsection 16.2 with the following exception: the information listed in paragraphs 16.2.7 and 16.2.8 is not required. All material added to a batch by both the batch plant or added manually shall be documented on the ticket. Batch tickets shall also contain the concrete producer’s permanent unique mixture number assigned to the concrete mixture design. Copies shall be submitted to the Department as the work progresses. Test data for concrete, including gradation, shall be charted in accordance with the applicable requirements. The Contractor may use additional control char ts as deemed appropriate. It is normally expected that testing and charting will be co mpleted within 24 hours after sampling. All records documenting the Contractor's quality control tests shall become the property of the Department upon completion of the work.

804.02.12 4--Corrective Action. The Contractor shall take prompt action to correct

conditions that have resulted, or could result, in the submission to the Department of materials and products that do not conform to the requirements of the contract documents. All corrective actions shall be documented.

804.02.12 5--Non-Conforming Materials. The Contractor shall establish and maintain an

effective and positive system for cont rolling non-conforming material, including procedures for its identification, isolation and disposition. Reclaiming or reworking of non-conforming materials shall be in acco rdance with procedures acceptable to the Department. All non-conforming materials and products sha ll be positively identified to prevent use, shipment, and intermingling with conforming materials and products. Holding areas, mutually agreeable to the Department and the Contractor, shall be provided by the Contractor. TABLE 4 CONTRACTOR’S MINIMUM REQUIREMENTS FOR QUALITY CONTROL Hydraulic Cement Concrete Control Requirement Frequency AASHTO/ASTM

A.PLANT AND TRUCKS
1.Mixer Blades
2.Scales
a.Tared
b.Calibrate c. Check Calibration
3.Gauges & Meters - Plant & Truck a. Calibrate b. Check Calibration
4.Admixture Dispenser
a.Calibrate b. Check Operation & Calibration Monthly Daily Every 6 months Weekly Every 6 months Weekly Every 6 months Daily
B.AGGREGATES
1.Sampling
2.Fine Aggregate
a.Gradation / FM
b.Moisture
c.Specific Gravity / Absorption 3. Coarse Aggregates
a.Gradation
b.Moisture
c.Specific Gravity / Absorption 250 yd 3 concrete Check meter against test results weekly 2500 yd3 concrete 250 yd 3 concrete Minimum of once daily or more as needed to control production. Check meter against test results weekly. 250 yd3 Concrete if the coarse aggregate oven dry specific gravity is less than 2.450, or 2500 yd3 Concrete if the coarse aggregate oven dry specific gravity is greater than or equal to 2.450 T 2 T 27 T 255 T 84 T 27 T 255 T 85
C.PLASTIC CONCRETE
1.Sampling
2.Air Content 3. Slump or Flow*
4.Static Segregation*
5.Compressive Strength
6.Yield
7.Temperature First load then one per 50 yd First load then one per 50 yd3 2500 yd3 Concrete A minimum of one set (three cylinders) for each 100 yd 3 inclusive and one set for each additional 100 yd3 or fraction thereof for each class concrete delivered and placed on a calendar day from a single supplier. A test shall be the average of three cylinders. Each 400 yd 3 Concrete With each sample R 60 T 152* or T 196* T 119* or C 1611* C 1610* T 22*, T 23*, T 231 T 121* T 309 Note: For concrete categorized as a SCC mixtur e, the following requir ements shall apply:
a.Substitute the appropriate AASHTO for re ferences to other ASTM Designations listed in ASTM C1610 and C1611.
b.Test specimens shall be made in accordance with the above listed specifications with the exception that the concrete shall not be rodded or vibrated during casting the test specimens.
c.The slump flow test shall only be performed on SCC mixtures in accordance with ASTM C1611. For these mixtures AASHTO T119 is not required. For the slump flow test, the filling procedure used sha ll be Procedure B. Additionally, for each slump flow test, determine the T50 an d VSI values in accordance with the information in Appendix X1 of ASTM C 1611. There are no acceptance criteria for the T50 or VSI determinations.
d.The static segregation test shall only be performed on SCC mixtures.

804.02.13 Quality Assuran ce Sampling and Testing. Quality Assurance (QA)

inspection and testing will be provided by the Department to assure that the Contractor’s Quality Control (QC) testing meets th e requirements of these specifications. Acceptance of the material is based on the inspection of the construction, monitoring of the Contractor's QC program, QC and QA test results per Subsection 804.02.13.1, and the comparison of the QA test results with the QC test results. The Department may use the results of the Contractor’s QC tests as a pa rt of the acceptance procedures instead of the results of QA tests, provided:

a.The Department's inspection and monitoring activities indicate that the Contractor is following the approved QC program and, respectively,
b.For aggregates, the results from the Cont ractor's QC and the Department’s QA testing of aggregate gradations compar e by both meeting the aggregate type’s gradation requirements;
c.For concrete, the Contractor's QC and Department’s QA testing of concrete compressive strengths compare when using the data comparison computer program with an alpha value of 0.01 for projects with 1000 cubic yards and more; or, strength comparisons are within 990 psi for projects of more than 200 but less than 1000 cubic yards. The minimum frequency for QA testing of aggregate and plastic concrete by the Department will follow the frequencies listed in Table 5, Below. TABLE 5 DEPARTMENT’S MINIMUM REQUIREMENTS FOR QUALITY ASSURANCE Quality Assurance Tests Frequency AASHTO/ASTM
A.AGGREGATES
1.Sampling
2.Fine Aggregate Gradation and FM 3. Coarse Aggregates Gradation
4.Coarse Aggregate
a.Specific gravity / Absorption 250 yd 3 concrete 250 yd3 concrete 250 yd 3 Concrete if the coarse aggregate oven dry specific gravity is less than 2.450, or 2500 yd 3 Concrete if the coarse aggregate oven dry specific gravity is greater than or equal to 2.450 T 2 T 27 T 27
B.PLASTIC CONCRETE
1.Sampling
2.Air Content
3.Slump or Slump Flow*
4.Compressive Strength
5.Temperature Every 100 yd Every 100 yd3 One set (three cylinders) for every 100 yd3 inclusive. A test shall be the average of three cylinders. With each sample R 60 T 152* or T 196* T 119 or C 1611* T 22*, T 23*, T 231 T 309 Note: * For concrete categorized as a SCC mixture, the following requirements shall apply:
a.Substitute the appropriate AASHTO for references to other ASTM listed in ASTM C1611.
b.Test specimens shall be made in accordan ce with the above listed specifications with the exception that the concrete shall not be rodded or vibrated during casting the test specimens.
c.The slump flow test shall only be performed on SCC mixtures in accordance with ASTM C1611. For these mixtures AASHTO T119 is not required. For the slump flow test, the filling procedure used shall be Procedure B. Periodic inspection by the Department of the Contractor’s QC testing and production will continue through the duration of the projec t. Weekly reviews will be made of the Contractor’s QC records and charts. For aggregates, comparison of data of the Contractor’s QC aggregate gradation test results to those of the Department’s QA aggregate gradation test results will be made weekly during concrete production periods according to Department SOPs. When it is determined that the Contractor’s QC test results of aggreg ate gradations are comparative to that of the Department’s QA test results, then the Department will use the Contractor’s QC results as a basis for acceptance of the aggregates and the Department’s QA testing frequency of aggregates may be reduced to a frequency of no less than three QA tests to every 10 QC tests. If the Contractor’s QC aggregate gradation test results fail to compare to those of the Department’s QA aggregate gradation test results, Department testing for aggregate gradations will revert to the frequency shown in Table 5 for aggregates until the Contractor’s and Department’s aggreg ate gradation test data compare. For concrete compressive strength, comparison of data of the Contractor’s QC compressive strength test results to those of the Department’s QA compressive strength test results will be made monthly during concrete production periods according to Department’s Concrete Field Manual . When it is determined that the Contractor’s QC test results of concrete compressive strengths are comparative to that of the Department’s QA test results, then the Department will use the Contractor’s QC results as a basis for acceptance of the concrete and the Departme nt’s QA testing frequency of concrete compressive strengths may be reduced to a frequency of no less than three QA tests to every 10 QC tests. If the Contractor’s QC compressive strength test results fail to compare to those of the Department’s QA compressive strength test results, Department testing will revert to the frequency shown in Table 5 for plastic concrete until the Contractor’s and Department’s compressive strength test data compare.

804.02.13 1--Job Control Testing.

804.02.13 1.1--Sampling. Sampling of concrete mixture shall be performed in accordance

with the latest edition of the Department’s Concrete Field Manual .

804.02.13 1.2--Slump. Slump of plastic concrete shall meet the requirements of Table 3. A check test shall be made on another portion of the sample before rejection of any load.

804.02.13 1.3--Air. Total air content of concrete shall be within the specified range for the class of concrete listed in Table 3. A check test shall be made on another portion of

the sample before rejection of any load.

804.02.13 1.4--Yield. If the yield of the concrete mix design is more than plus or minus

three percent (±3%) of the designed volume, the mix shall be adjusted by a Class III Certified Technician representing the Contractor to yield the correct volume plus or minus three percent (±3%). If batching of the proportions of the mixture design varies outside the batching tolerance range of the originally approved proportions by more than the tolerances allowed in Subsection 804.02.12, the new proportions shall be field verified per Subsection 804.02.10.3.

804.02.13 1.5--Temperature. Cold weather concreting shall follow the requirements of

Subsection 804.03.16.1. Hot weather conc reting shall follow the requirements of Subsection 804.03.16.2. Concrete with a temperature more than the maximum allowable temperature shall be rejected an d not used in Department work. The maximum acceptance temperature for Class DS concrete mixtures is 95°F. The maximum acceptance temperatur e of Class C concrete mixtures is 100°F for mixtures meeting the cement replacemen t requirements of Subsection 701.02.2. For Class C concrete mixtures that do not meet the ce ment replacement requirements of Subsection

701.02 2, the maximum acceptan ce temperature is 95°F.

The maximum acceptance temperature for all ot her concrete mixtures meeting the cement replacement requirements of Subsection 701.02.2 is 95 °F. The maximum acceptance temperature for all other concrete mixtures that do not meet the cement replacement requirements of Subsection 701.02.2 is 90°F.

804.02.13 1.6--Compressive Strength. Standard cured concrete compressive strength

tests shall conform to th e specified strength ( f’

c.listed in the specifications. Concrete represented by compressive strength test below the specified strength ( f’c) may be removed and replaced by the Contractor. If the Contract or elects not to remove the material, it will be evaluated by the Department as to the adequacy for the use intended. All concrete evaluated as unsatisfactory for the intended use shall be removed and replaced by the Contractor at no additional cost to the Depa rtment. For concrete allowed to remain in place, reduction in payment will be as follows: Projects with 1000 Cubic Yards and More. When the evaluation indicates that the work may remain in place, a statistical analysis w ill be made of the QC and QA concrete test results. If this statistical analysis indicates that at least 93% of the material would be expected to have a compressive strength equal to or greater than th e specified strength ( f’ c) and 99.87% of the material would be expected to have a compressive strength of at least one standard deviation above the allowable design stress ( f c), the work will be accepted. If the statistical analysis indicates that either of the two criteria is not met, the Engineer will provide for an adjustment in pay as foll ows for the material re presented by the test result. Total Pay on Material in Question = Unit Price - (Unit Price x % Reduction) % Reduction =  100   s fc c fX c f x M where: f’c = Specified 28-day compressive strength, psi X = Individual compressive strength below f’c, psi s = standard deviation, psi* fc = allowable design stress, psi M = pay reduction multiplier, per the Concrete Field Manual , paragraph 7.3 * Standard deviation used in the above re duction of pay formula shall be calculated from the applicable preceding compressive st rengths test results plus the individual compressive strength below f’c. If below f’c strengths occur during the project’s first ten compressive strength tests, the standard deviation shall be calculated from the first ten compressive strength tests results. Projects of More Than 200 but Less Than 1000 Cubic Yards. When the evaluation indicates that the work may remain in place , a percent reduction in pay will be assessed based on a comparison of the deficient 28-day test result to the speci fied strength. The Engineer will provide for an ad justment in pay as follows fo r the material represented by the test result. Total Pay on Material in Question = Unit Price - (Unit Pr ice x % Reduction) % Reduction = 100  c fX c f x M where: f’c = Specified 28-day compressive strength, psi X = Individual compressive strength below f’c, psi M = pay reduction multiplier, per the Concrete Field Manual , paragraph 7.3

804.02.13 1.7--Static Segregation. For concrete categorized as a SCC mixture, the static

segregation of the plastic concrete shall meet the requirements of Subsection 804.02.10.1.2. If the static segregation of the concrete mix design exceeds this requ irement, the mix shall be adjusted by a Class III Certified Technician representing the Contractor to ensure a static segregation less than the maximum allowable. If batching of the proportions of the mixture design varies outside the batc hing tolerance range of the or iginally approv ed proportions by more than the tolerances allowed in Subsection 804.02.12.1, the new proportions shall be field verified per Subsection 804.02.10.3.

804.02.14 Dispute Resolution. Disputes over variations between the Contractor’s QC

test results and the Department’s QA test resu lts shall be resolved at the lowest possible level using the latest edition of the Department’s Concrete Field Manual . When there are significant discrepancies between the QC te st results and the QA test results, the Contractor’s QC Manager, the Project Engine er, and/or the District Materials Engineer shall look for differences in the procedures, and correct the inappropriate procedure before requesting a third party resolution. If the dispute cannot be resolved at the project or District level, the Department’s Materials Division will serve as a third party to reso lve the dispute. The Materials Division’s decision shall be binding. The Contractor shall be responsible for the co st associated with th e third party resolution if the final decision is such that the Department’s QA test results were correct. Likewise, the Department will be responsi ble for the cost when the fina l decision is such that the Contractor’s QC test results were correct.

804.03 Construction Requirements.

804.03.1 Measuremen t of Materials.

804.03.1 1--General. The accuracy for measuring materials shall be in accordance with

AASHTO M 157.

804.03.1 2--Measureme nt by Weighing. Except when otherwise specified or authorized,

the materials shall be measured by weighing. The apparatus provided for weighing materials shall be suitably designed and constructed for th is purpose. Cementitious materials and aggregates shall be weighed sepa rately. Cement in standard bags need not be weighed, but bulk cement an d other cementitious material s shall be weighed. The mixing water shall be measured by volume or by weight. All measuring devices shall be subject to approval.

804.03.2 Blank.

804.03.3 Blank.

804.03.4 Hand Mixing. Hand mixing of concrete will not be allowed.

804.03.5 Delivery. The plant supplying concrete shall have sufficient capacity and

transporting apparatus to ensure continuous de livery at the rate requ ired. The rate of delivery shall be such as to provide for the proper continuity in handling, placing, and furnishing of the concrete. The rate shall be such that the interval between batches shall not exceed 20 minutes. The methods of deliveri ng and handling the concrete shall be that which will facilitate placing with minimum re-handling and without damage to the structure or the concrete.

804.03.6 Handling and Placing Concrete.

804.03.6 1--General. Prior to placing concrete, a ll reinforcement shall have been

accurately placed in the position shown on the plans and fastened as set out in Section 805. All sawdust, chips, and other construction debris and extraneous matter shall have been removed from the interior of the forms. Temporary struts, braces, and stays holding the forms in correct shape and a lignment shall be removed when the concrete placing has reached an elevation rendering their service unnecessary. These temporary members shall be entirely removed from the forms and shall not be buried in the concrete. No concrete shall be placed until the form s and reinforcement ha ve been inspected. Except as provided for truck mi xers and truck agitators, concrete shall be placed in the forms within 30 minutes afte r the time that the cement is first added to the mixture. Concrete shall be placed so as to avoid se gregation of materials and displacement of reinforcement. The use of troughs, chutes, and pipes over 25 feet in length for gravity conveyance of concrete to th e forms will not be permitted ex cept when authorized by the Engineer and subject to the production of quality concrete. Only approved mechanical co nveyors will be permitted. Open troughs and chutes shall be metal or metal lined. The use of aluminum pipes, chutes, or other devices made of aluminum that come into direct contact with the concrete shall not be used. Where steep slopes are required, the chutes shall be equipped with baffles or be in short sections that change the direction of movement. All chutes, troughs, and pipes shall be kept clean and free from coatings of hardened concrete by thoroughly flushing with water af ter each run. Water used for flushing shall be discharged clear of the structure. When placing operations involve dropping the concrete more than five feet, it shall be deposited through sheet metal or other approved pipes to prevent segregation and unnecessary splashing. The pipes shall be ma de in sections to permit discharging and raising as the placement progresse s. A non-jointed pipe may be used if sufficient openings of the proper size are provided to allow for the flow of the concrete into the shaft. As far as practicable, the pipes shall be kept full of concrete during placing, and their ends shall be kept buried in the newly placed concrete. Except as herein provided, concrete shall be placed in horizontal layers not more than 12 inches thick. When, w ith the Engineer's approval, less th an the complete length of a layer is placed in one operation, it shall be terminated in a vertical bulkhead. Each layer shall be placed and compacted before the preceding la yer has taken its initial set and shall be compacted so as to avoid the formation of a construction joint with the preceding layer. If the Department determines that there is an excessive number of projections, swells, ridges, depressions, waves, voids, holes, honey combs, or other defects in the completed structure, removal of the entire structure may be required as set out in Subsection 105.12.

804.03.6 2--Consolidation. Immediately after depositing the concrete mixture, the

concrete mixture shall be thoroughly consolidated by the use of approved mechanical vibrators and suitable spading t ools. Only concrete mixtur e that has not achieved initial set shall be consolidated. Hand spading alone will be pe rmitted on small structural members such as railing, small culvert head walls, and as necessary to ensure smooth surfaces and dense concrete along form surfaces , in corners, and in locations impossible to reach with vibrators. When hand spading is used for consolidation, a sufficient number of workmen with spading tools shall be provided. For hand spading, flush a thin layer of mortar to all the surfaces and thoroughly and satisfactorily consolidate the concrete. SCC concrete shall not be consolidated by vibration. The Contractor shall conduct operations of depositing and consolidating the concrete mixture such that the operation produces concrete that is uniformly smooth and dense, having no honeycombing or pockets of segregated aggregate. Movement of personnel through the consolidated concrete shall not be permitted. If it is determined that it is necessary to step into previously consolidated concrete, the concrete in the stepped into area sha ll be consolidated again.

804.03.6 2.1--Requireme nts for Vibrators. Mechanical vibrators shall be subject to the

following: (a) To verify compliance with these requirements, the Contractor shall provide the Engineer with a copy of the manufacturer’s specifications for each type and brand of vibrator used on the project.

b.The Contractor shall provide a sufficient number of personnel with vibrators to properly consolidate each batch immediately after the concrete is placed in the forms. The Contractor shall provide at least one stand-by vibrator and required power source. (c) Concrete that has been consolidated shall not be walked in or th rough. If it is determined it is necessary to step into prev iously consolidated concrete, the concrete in the stepped into area sha ll be consolidated again.
d.Internal vibrators shall be of the spud or tube type, meeting the following characteristics and performance:
1.The diameter of the head of the vibrator shall be 1¼ to 2½ inches.
2.The frequency of vibration shall be 8000 to 12000 vibrations per minute (Hz) while operating in the concrete.
3.The average amplitude shall be 0.025 to 0.05 inch while operating in air.
4.The minimum radius of influence shall be seven (7) inches.
5.The length of the vibrator head shall be nearly equal to the depth of the layer of concrete placed.
e.When the reinforcing steel is coated with epoxy, internal vibrators with heads of rubber or other resilient material shall be used. Rubber covers securely fastened over steel heads shall be acceptable.
f.For consolidation of concrete used in concrete bridge decks, the following additional requirements shall apply: (1) Only internal vibra tion shall be used.
2.Internal vibrators shall all be of the same type and size.
3.The configuration of the internal vibr ators shall meet the requirements of Subsection 804.03.6.2.3.

804.03.6 2.2--Operation of Internal Vibration. Mechanical vibrators used for internal

vibration shall be operated as follows:

a.Vibrators shall not be dragged or moved laterally through the concrete to transport concrete. Vibrators shall not be used in such a manner that the concrete segregates or forms pockets of grout. Vibrators shall not be applied directly or through the reinforcement to sections or layers of concrete that have taken initial set.
b.Vibrators shall only be inserted into the co ncrete while operating and at the point of placement to consolidate the concrete for such a length of time that there is a general cessation in the escape of large entr apped air bubbles at the surface.
c.Vibrators shall be inserted sl owly into the concrete and a llowed to penetrate into the concrete under their own weight.
d.Vibrators shall be inserted into the concrete while they are in a vertical position with enough flexibility to work themselves around th e reinforcing steel.
e.The head of the vibrator shall be completely submerged in the concrete for a time of consolidation between 3 and 15 seconds prior to removal, unless otherwise defined by the Engineer.
f.For consolidation of two or more layers of concrete, the vibrator shall be inserted into the bottom most layer at least six (6) inches. The vibrator shall be manipulated in a series of up-and-down motio ns to knit the layers together.
g.Vibrators shall be removed slowly from the concrete after the consolidation has been accomplished. However, once the head of the vibrator has become only partially immersed in the concrete, vibrators shall be removed rapidly. (h) The insertions of the vibrators shall be sy stematically spaced such that the entire surface of the concrete comes under th e influence of the vibrator during consolidation. This includes areas around the reinforcing steel, imbedded fixtures, the corners and angles of forms, and an y irregular areas. The distance between insertions shall not exceed 1.5 times the radius of influence such that the area visibly affected by the vibrator overlaps the adjacent, just-vibrated area.
i.For additional information, refer to ACI 30 9-07, Chapter 7, Sec tions 7.1 through 7.3

804.03.6 2.3--Method of Consolidation. The Contractor will accomplish consolidation

by internal vibration using vibrators mounted on a mechanical device or an orchestrated effort utilizing personnel. Regardless of the chosen method, the method shall be included in the QCP in accordance with Subsection 804 .02.12.1 and shall on ly receive tentative approval until the method is demonstrated as effectively meeting the requirements of Subsection 804.03.6.2.

804.03.6 3--Discontinuance of Placing. When placing is tem porarily discontinued, the

concrete, after becoming firm enough to retain its form, shall be cleaned of laitance and other objectionable material to a sufficient depth to expose sound concrete. To avoid visible joints insofar as possible upon expo sed faces, the top surface of the concrete adjacent to the forms shall be smoothed with a trowel. Where a "feather edge" might be produced at a construction joint, such as in the sloped top surface of a wing wall, an inset form work shall be used in the preceding laye r to produce a blocked out portion that will provide an edge thickness of at least six inch es (6”) in the succeeding layer. Work shall not be discontinued within 18 inches of the top of any face unless provision has been made for a coping less than 18 inches thick. In this case, and if permitted by the Engineer, the construction joint may be made at the underside of the coping. Immediately following the discontinuance of pl acing concrete, all accumulations of mortar splashed on the reinforcement and the surface of forms shall be removed. Dried mortar chips and dust shall not be pu ddled into the unset concrete. If the accumulations are not removed prior to the concrete becoming set, care shall be exercised not to break or injure the concrete-steel bond at and near the surface of the concrete while cleaning the reinforcement. After initial set the forms shall not be jarred, and no strain shall be placed on the ends of projecting reinforcement until the concrete ha s sufficiently set to ensure against any damage by such jarring or strain.

804.03.6 4--Placing Bridge Concrete. The method and sequence of placing concrete shall

conform to the prov isions and requirements set forth for the particular type of construction.

804.03.6 4.1--Foundations and Substructures. Concrete seals shall be placed in

accordance with Subsection 804.03.9. All othe r concrete for foundations shall be poured in the dry unless otherw ise stipulated or authorization is given in writing by the Engineer to do otherwise. Concrete shall not be pl aced in foundations until the foundation area has been inspected and approved. Unless otherwise specified, the placement of c oncrete in the substructure shall be in accordance with the general requirements of Subsection 804.03.6. Unless otherwise directed, concre te in columns shall be placed in one continuous operation, and shall be allowed to set at least 12 hours before the caps are placed.

804.03.6 4.2--Superstructure. For simple spans, concrete shall preferably be deposited

by beginning at the center of the span and working toward the ends. For continuous spans, concrete shall be deposited as shown on the pl ans. Concrete in girders shall be uniformly deposited for the full length of the girder and brought up evenly in horizontal layers. Concrete in areas below the bridge deck but whic h is deposited at the same time as concrete for the bridge deck like a diaphragm, shall be placed and consolidated sufficiently ahead of placing the concrete for the bridge deck such that the placing, consolidating, finishing, and curing of concrete for the bridge deck shall not be impeded or slowed. Unless otherwise permitted by the Engineer, concrete shall not be placed in the superstructure until the column forms have been stripped sufficien tly to determine the character of the concrete in the columns. Unless otherwise permitted by the Engineer, the load of the su perstructure shall not be pl aced on pile bents until the caps have been in place at least seven (7) days and shall not be place d on other type s of bents until the bents have been in place at least 14 days. In placing concrete around steel shapes, it shall be placed on one side of the shape until it flushes up over the bottom flange of the shape on the opposite side, after which it shall be placed on both sides to completion. Concrete in girder haunches less than three feet (3’) in height shall be placed at the same time as that in the girder stem . Whenever a haunch or fillet has a height of three feet (3’) or more at the abutment or columns, the haunch and the girder shall be poured in three successive stages: (a) up to the lower side of th e haunch; (2) to the lowe r side of the girder; and (3) to completion. Except when intermediate construction joints are specified, concrete in slab, T-beam, or deck-girder spans shall be placed in one continuous operation for each span. The floors and girders of through-girder superstructures shall be placed in one continuous operation unless otherwise speci fied, in which case specia l shear anchorage shall be provided to ensure monolithic ac tion between girder and floor. Concrete in box girders shall be placed as shown on the plans. Concrete shall not be chuted directly into the forms of the span and shall be placed continuously with sufficient speed to be monolithic and to allow for finishing before initial set.

804.03.6 4.3--Bridge Deck. When using the Transverse Method in accordance with

Subsection 804.03.19.7.3, the period of time between concrete placement and completion of the final curing shall be kept to a mi nimum, as directed by the Engineer.

804.03.7 Pneumatic Placing. Pneumatic placing of concrete will be permitted only if

specified in the contract or if authorized by the Engineer. The equipment shall be so arranged that no vibrations result that might damage fresh ly placed concrete. Where concrete is conveyed and placed by pneumatic means, the equipment shall be suitable in kind and adequate in capacity for the work. Th e machine shall be located as close as practicable to the place of deposit. The position of the discharge end of the line shall not be more than 10 fe et from the point of deposit. The discharge lines shall be horizontal or inclined upwards from the machin e. At the conclusion of placement the entire equipment shall be thoroughly cleaned.

804.03.8 Pumping Concrete. Placement of concrete by pumping will be permitted only

if specified in the contract or if authorized in writing by the Engineer. If used, the equipment shall be arranged so that no vibra tions result that might damage freshly placed concrete. Where concrete mixture is conveyed and pl aced by mechanically applied pressure (pumping), the equipment shall be suitable in kind and adequate in capacity for the work. The Contractor shall select concrete mixture pr oportions such that the concrete mixture is pumpable and placeable with the selected equipment. The pumping equipment shall be thoroughly cleaned prior to concrete placement. Excess form release agent shall be removed from the concrete pump hopper. The Contractor shall prime the pump at no additional cost to the Department by pumping and discarding enough concrete mixture to produce a uniform mixture exiting the pump . At least 0.25 cubic yard of concrete mixture shall be pumped and discarded to prime the pump. Only concrete mixture shall be added directly into th e concrete pump hopper after placement has commenced. If anything other than concrete mixture is added to the concrete pump hopper, all concrete mixture in the concrete pump hopper and pump line shall be discarded and the pump re-primed at no additional cost to the Department. The discharge end of the pump shall be of such a configuration that the concrete does not move in the pump line under its own weight. The intent of this requirement is to ensure that entrained air in the conc rete mixture remains entrained during pumping and depositing the concrete mixture. This shall be accomplished with one or both of the following: (a) a minimum 10-foot flexible hose attached to the discharge end of a steel reducer having a minimum length of three (3) feet and a minimum reduction in area of 20% which is attached to the discharge end of the pump line, or

b.a flexible reducing hose to the discharge end of the pumpline with a minimum reduction in area of 20% over a minimum 10-foot hose length. Regardless of the configuration chosen, the Cont ractor shall ensure that the concrete is pumped and does not free-fall more than five (5) feet within the en tire length of pump line and after discharge from the end of pump line. The Contractor shall not have any type of metal elbow, metal pipe, or other metal fitting within five (5) feet of any person during discharge of concrete mixture. Boom pumps shall have a current Concrete Pump Manufacturers Association’s ASME/ANSI B30.27 certification. Equipment added to the boom and pump line shall meet the pump manufacturer’s specifications and shall not exceed the manufacturer’s maximum recommended weight limit for equipment added to the boom and pump line. The operation of the pum p shall be such that a continuous stream of concrete without air pockets is produced. When pumping is complete d, the concrete remaining in the pipe line, if it is to be used, shall be ejected in such a manne r that there will be no contamination of the concrete or separation of the ingredients. After this operatio n, the entire equipment shall be thoroughly cleaned. The use of aluminum pipe as a conveyance for the concre te will not be permitted.

804.03.9 Depositing Concrete Under Water. Concrete shall not be deposited in water

except with the approval of the Engineer. Concrete deposited under water shall be Class S. Concrete deposited under water shall be care fully placed in a compact mass in its final position by means of a tremie, a bottom dump bu cket, or other approved method and shall not be disturbed after being deposited. Speci al care shall be exerci sed to maintain still water at the point of deposit. No concrete shall be placed in running water and all form work designed to retain concrete under water shall be water-tight. The consistency of the concrete shall be carefully re gulated, and special care sh all be exercised to prevent segregation of materials. Concrete seals shall be placed continuously from start to finish, and the surface of the concrete shall be kept as nearly horizontal as practicable at all times. To ensure thorough bonding, each succeeding layer of a seal sha ll be placed before the preceding layer has taken initial set. When a tremie is used, it shall consist of a tube having a diameter of at least 10 inches and constructed in sections having flanged couplings fitted w ith gaskets. The means of supporting the tremie shall be such as to permit the free movement of the discharge over the entire top surface of the work and to permit it to be lowered rapidly when necessary to choke off or retard the flow of concrete. The discharge end shall be closed at the start of the work so as to prevent water entering the t ube and shall be entirely sealed. The tremie tube shall be kept full to the bottom of the hopper. When a batch is dumped into the hopper, the flow of concrete shall be induced by slightly raising the discharge end, always keeping it in the deposited concrete. The flow is then stopped by lowering the tremie. The flow shall be continuous until the work is completed. Depositing of concrete by the drop bottom bucket meth od shall conform to the following:

a.The top of the bucket shall be open.
b.The bottom doors shall open freely downward and outward when tripped.
c.The bucket shall be completely filled and slowly lowered to av oid backwash. It shall not be dumped until it rests on the surf ace upon which the concrete is to be deposited and when discha rged shall be withdrawn slowly until we ll above the concrete. Dewatering may proceed when the concrete seal is sufficiently hard and strong. As a general rule, this time will be 48 hours for co ncrete made with high -early-strength cement and three days for concrete made with other types of cement. All laitance and other unsatisfactory material shall be removed from the exposed surface by scraping, chipping, or other means that will not inju re the surface of the concrete.

804.03.10 Construction Joints.

804.03.10 1--General. Unless otherwise approved by the Engineer, construction joints

shall be made only where located on the plans or shown in the pouring schedule. If not detailed on the plans, or in the case of emerge ncy, construction joints shall be placed as directed by the Engineer. Shear keys or inclined reinfo rcement shall be used where necessary to transmit shear or to bond the two sections together. For continuous spans, bridge deck concrete shall be deposited as shown on the plans. Deviation from the pouring schedule shown in the plans is not permitted.

804.03.10 2--Bonding. Before depositing new concrete on or against concrete that has

hardened, the forms shall be retightened. The surface of the hardened concrete shall be roughened as required by th e Engineer and in a manner th at will not leave loosened particles of aggregate or damaged concrete at the surface. It shall be thoroughly cleaned of foreign matter and laitance and saturated w ith water. When directed by the Engineer, the cleaned and saturated surfaces, including ver tical and inclined surfaces, shall first be thoroughly covered with a coating of mortar or neat cement grout against which the new concrete shall be placed before the grout has attained its initial set. The placing of concrete shall be carried continuously from join t to joint. The face edges of all joints that are exposed to view shall be carefully finish ed, true to line and elevation. In order to bond successive courses suitable depressed or raised keys of the designated size shall be constructed. Raised keys shall be m onolithic with the concrete of the lower course.

804.03.11 Concrete Ex posed to Seawater. Unless otherwise specifically provided,

concrete for structures exposed to seawater sh all be Class AA concrete as referenced in Subsection 804.02.10. The clear distance from the face of the concrete to the nearest face of reinforcing steel shall be at least four inches. The mixing time and the water content shall be carefully controlled and regulated so as to produce concrete of maximum impermeability. The concrete shall be thoroughly compacted, and stone pockets shall be avoided. No construction joints shall be formed between the levels of extreme low water and extreme high water as determined by the Engineer. Between these levels, seawater shall not come in direct contact with the new concrete until at least 30 days have elapsed. The surface concrete as left by the forms shall be left undisturbed.

804.03.12 Blank.

804.03.13 Falsework. The Contractor shall submit to the Engineer four copies of

structural design analysis and detail drawi ngs that show the method of falsework or centering. These designs and detail plans shall be prepared and bear the seal of a Registered Professional Engineer with experience in falsework design. Falsework plans shall include falsework elevati ons together with all other dimensions and details that are considered nece ssary for the construction. Ot her pertinent data needed is size and spacing of all falsework members and minimum bearing requirements for false piles. Upon completion of falsework erection, the Registered Profe ssional Engineer shall certify that the erected falsework is capable of supporting the load for construction. Falsework piling shall be spaced and driven so that the bearing value of each pile is sufficient to support th e load that will be imposed upon it. The bearing value of the piles should be calculated according to the appropriate formula given in Section 803. For designing falsework and centering, a wei ght of 150 pounds per cubic foot shall be assumed for green concrete. All falsework shall be designed and constructed to provide the necessary rigidity and to support the loads without appreciable settlement or deformation. The Contractor may be required to employ screw jacks or hardwood wedges to take up slight settlement in the falsework eith er before or during th e placing of concrete. An allowance shall be made for anticipated compressibility of falsework and for the placement of shims, wedges, or jacks to pro duce the permanent structural camber shown on the plans. If during construction, any weakness develops and the falsework shows any undue settlement or distortion, th e work shall be stopped, the pa rt of the structure affected removed, and the falsework strengthened before work is resumed. Falsework that cannot be founded on a satisfactory footing shall be supported on piling, which shall be spaced, driven, and removed, as referenced in Subsection 804.03.15, in a manner approved by the Engineer. All structures built across a pub lic street or highway on whic h maintenance of traffic is required, shall have falsework so arranged that a vertical clearance of at least 12' 6" is provided. Unless otherwise specified, a horizon tal clearance of at least the width of the traveled way shall be provided at all times. If the vertical cl earance is less than 13' 6" or the horizontal clearance is less than the full cr own width of the roadway, the Contractor shall install and maintain appr opriate safety devices, clearance signs and warning lights, and shall notify the Engineer su fficiently in advance of rest ricting the clearance for the Engineer to advise both the Traffic Engineerin g and the Maintenance Divisions. All traffic control and safety devices shall be in accordance w ith the MUTCD.

804.03.14 Forms.

804.03.14 1--General. Forms shall be wood, metal, or other material approved by the

Engineer. All forms shall be built mortar-tight and sufficien tly rigid to prevent distortion due to pressure of the concrete and other loads incident to the construction operations. Forms shall be constructed and maintained so as to prevent warping and the opening of joints due to shrinkage. The forms shall be substantial and unyield ing and shall be so designed that the finished concrete will conform to the proper dimensions and contours. The design of the forms shall ta ke into account the effect of vibration of concrete as it is placed. Minimum requirements for slab overhang forms shall be 3/4-inch plywood supported on 2-inch x 6-inch S4S wood timbers placed flatwise on 16-inch centers. Adjustable brackets for support of slab overhang forms shall be spaced at a maximum distance of 3' 0" center to center unless spec ifically approved otherwise. Grade points for forms shall coincide with the location of the adjustable form brackets. Forms for surfaces exposed to view shall be of uniform thickness with a smooth inside surface of an approved type. Joints in forms for exposed surfaces shall be closely fitted to eliminate fins, stone pockets, or other variations in the surf ace of the concrete that would mar a smooth and uniform texture. Forms shall be filleted at all sharp corners and shall be given a bevel or draft in the case of all projections, such as girders and copings, to ensure easy removal. Metal ties or anchorages within the forms shall be so constr ucted as to perm it their removal, without injury to the concrete, to a depth of at least the reinforcing steel clearance shown on the plans. In case ordinary wire ties are permitted, all wires, upon removal of the forms, shall be cut back at least 1/4 inch from the face of the concrete with chisels or nippers. Nippers shall be used for green concrete. All fittings for me tal ties shall be designed so that upon their removal the cavities that are left will be th e smallest practicable size. The cavities shall be filled with cement mortar and the surface left sound, smooth, even, and uniform in color. Forms shall be set and maintained to the lines designated until the concrete is sufficiently cured for form removal. Forms shall remain in place for periods determined as hereinafter specified. If forms are deemed to be unsatisfact ory in any way, either before or during the placing of concrete, the Engineer will order th e work stopped until th e defects have been corrected. The shape, strength, rigidity, water-tightness, and surface smoothness of reused forms shall be maintained at all times. Wa rped or bulged lumber shall be resized before being reused. Forms that are unsatisfactory in any respect shall not be reused. Access to the lower portions of forms for narrow walls and columns shall be provided for cleaning out extraneous material imme diately before placing the concrete. All forms shall be treated with an approved oil or saturated with water immediately before placing the concrete. For rail members or other members with exposed faces, the forms shall be treated only with an approved oil to prevent the adherence of concrete. Any material that will adhere to or disc olor the concrete shall not be used. When metal forms are used they shall be kept free from rust, grease, or other foreign matter that will discolor the c oncrete. They shall be of sufficient thickness and so connected that they will remain true to shape and line, and shall conform in all respects as herein prescribed for mortar tightness, filleted corners, beveled projections, etc. They shall be constructed so as to ensure ea sy removal without injury to concrete. All inside bolt and rivet heads shall be countersunk. All chamfer strips shall be dressed, straight, and of uniform width and shall be maintained as such at all times.

804.03.14 2--Stay-In-Place Metal Forms. Stay-in-place (SIP) metal forms are corrugated

metal sheets permanently installed between the supporting superstructu re members. After the concrete has cured, these forms shall rema in in place as perman ent, non-structural members of the bridge. Pay quantities for deck concrete will be computed from the dimensions shown in the contract plans with no allowance for changes in deflection and /or changes in dimensions necessary to accommodate the SIP metal forms. There will be no direct payment for the cost of the forms and form supports, or any material, tools, equipment, or labor incidental thereto, but the cost shall be considered absorbed in the contract unit price for concrete. Before fabricating any material, three (3) comple te sets of SIP metal form shop drawings and design calculations, bearing the Design Engineer’s seal, shall be submitted to the Director of Structures, State Bridge Engineer, through the Engineer, for review. The Contractor’s SIP metal form Design Engineer shall be a Mississi ppi Registered Professional Engineer who is knowledgeable in the field of structural design. In no case shall additional dead load produced by the use of SIP meta l forms overstress any bridge component. Design calculations shall indicate any additional dead load from SIP metal form self-weight, form support hangers, concrete in flutes, concrete due to form deflection, etc., that are not included in the plans. The additio nal dead loads shall be clearly labeled and tabulated on the shop drawings. Bridge Division will ev aluate the additional load for overstress of the bridge components. In the event that the additional dead load produces an overstress in any bridge co mponent, Bridge Division will reject the Contractor’s design. Deflection and loads pr oduced by deflection of the SIP metal forms shall be considered and indicate d in the design calculations. The cambers and deflections prov ided in the plans do not cons ider the effects of SIP metal forms. The Contractor’s Engineer shall take into account the weight of the forms and any additional dead load when developing the “Bridge Superstructure Construction Plan”. For the purpose of reducing any additional dead load produced by the SIP metal forms, the flutes of SIP metal forms may be filled with polystyrene foam. When polystyrene foam is used to fill the forms, the fo rm flutes shall be filled co mpletely. No portion of the polystyrene foam shall extend beyond the limits of the flutes. The Contractor shall ensure that the polystyrene foam remains in its required position within flutes during the entire concrete placement process. The Contractor shall not use reinforcing steel supports or other accessories in such a manner as to cause damage to the polystyrene foam. All damaged polystyrene foam shall be replaced to the satisfaction of the Engineer. All welding of formwork shall be completed prior to placement of polystyrene foam. For bridges not located in horizontal curves, the Contract or may reduce the additional dead load by matching the flute spacing with the tr ansverse steel spacing of the bottom layer. The bottom longitudinal layer of steel shall have one (1) inch of minimum concrete cover measured from the bottom of the reinforcing to the top of th e flute. The Contractor will not be allowed to vary the reinforcing steel sp acing or size from the plans for the purpose of matching flute spacing.

804.03.14 2.1--Materials. SIP metal forms and supports shall meet the requirements of

ASTM A653 having a coating designation G165. Form materials that are less than 0.03- inch uncoated thickness shall not be allowed.

804.03.14 2.2--Certification. The Contractor shall provid e written certification from the

manufacturer stating that the product meets th e requirements of this specification to the Engineer along with the delivery of the coated forms to the job site.

804.03.14 2.3--Polystyrene Foam. The polystyrene foam shall be comprised of expanded

polystyrene manufactured from virgin resin of sufficient density to support the weight of concrete without deformation. The polystyr ene foam shall be extruded to match the geometry of the flutes and provide a snug fit. The polystyrene foam shall have a density of not less than 0.8 pounds per cubic foot . The polystyrene foam shall have water absorption of less th an 2.6% when tested according to ASTM C272. The Contractor shall provide written certification from the manufactur er stating the polyst yrene foam product meets the requirements of this specification to the Engineer along with the delivery of the coated forms to the job site.

804.03.14 2.4--Design. The design of the SIP metal form s shall meet the following criteria.

a.The maximum self-weight of the stay in pl ace metal forms, plus the weight of the concrete or expanded polystyren e required to fill the form flutes (where used), shall not exceed 20 psf.
b.The forms shall be designed on the basis of dead load of form, reinforcement, and plastic concrete plus 50 pounds per square foot for construction loads. The design shall use a unit working stress in the stee l sheet of not more than 0.725 of the specified minimum yield strength of the materi al furnished, but not to exceed 36,000 psi.
c.Deflection under the weight of the forms, reinforcement, and plastic concrete shall not exceed 1/180 of the form span or 1/2 inch, whichever is less, for form spans of 10 feet or less, or 1/240 of the form span or 3/4 inch, whichever is less, for form spans greater than 10 feet.
d.The design span of the form shall equal the clear span of the form plus two (2) inches. The span shall be meas ure parallel to the form flutes.
e.Physical design properties shall be comput ed in accordance w ith requirements of the AISI Specifications for the Design of Cold Formed Steel Structural Members, latest published edition.
f.The design concrete cover required by the plans shall be maintained for all reinforcement.
g.The plan dimensions of both layers of primary deck reinfor cement from the top surface of the concrete deck shall be maintained.
h.The SIP metal form shall not be consid ered as lateral br acing for compression flanges of supporting structural members.
i.SIP metal forms shall not be used under closure pours or in bays where longitudinal slab construction joints are located. SIP metal forms shall not be used under cantilevered slabs such as the over hang outside of fascia members.
j.Forms shall be secured to the supportin g members by means other than welding directly to the member. Welding to the t op flanges of steel stri ngers and/or girders shall not be allowed. Alternate installati on procedures shall be submitted addressing this condition.

804.03.14 2.5--Construction. SIP metal form sheets shall not rest directly on the top of

the stringer of floor beam flanges. Sheets sha ll be fastened securely to form supports, and maintain a minimum bearing length of one (1) inch at each end for metal forms. Form supports shall be placed in direct contact with the flange of the stringer or floor beam. All attachments for coated metal forms shall be ma de by bolts, clips, screws, or other approved means.

804.03.14 2.6--Form Galvanizing Repairs. Where forms or their installation are

unsatisfactory in the opinion of the Engineer, eith er before or during plac ement of the concrete, the Contractor shall correct the defects before proceeding with the construction work. The cost of such corrective work shall be at the sole expense of the Contractor. Minor heat discoloration in areas of welds shall not be touched up.

804.03.14 2.7--Concrete. The Contractor shall ensure concrete placement does not

damage the SIP metal forms. Approved pouring sequences shall be used. The completed SIP metal form system shall be sufficiently tight to prevent leakage of mortar or concrete. The concrete shall be consolidated to avoid honeycomb and voids, especially at construction joints, expansion joints, valleys, and ends of form sheets. Calcium chloride or any other admixture containing chloride salts sh all not be used in the concrete.

804.03.14 2.8--Inspection. The Engineer will observe th e Contractor’s method of

construction during all phases of the construc tion of the bridge deck slab, including the installation of the SIP metal form system, location and fastening of the reinforcement, composition of concrete items, mixing procedur es, concrete placement, and vibration, and finishing of the bridge deck. Should the Engineer determine that the procedures used during the placement of the concrete warrant inspection of the unders ide of the deck, at least one section of the metal forms shall be removed in each span for this purpose. This shall be done as soon after placing the concrete as practical in order to provide visual evidence that the concrete mix and the proced ures are obtaining the desired results. An additional section shall be removed in any span if the Engineer dete rmines that there has been any change in the concrete mix or in th e procedures warranting ad ditional inspection. If, in the Engineer’s judgment, inspection is needed to check for de fects in the bottom of the deck or to verify soundness, the SIP meta l forms shall be sounded with a hammer after the deck concrete has been in place a minimum of two days. If sounding discloses areas of doubtful soundness to the Engineer, the SIP metal forms shall be removed from such areas for visual inspection after the concrete has attained ade quate strength. The SIP metal bridge deck forms shall be removed at no expense to the State. At locations where sections of the metal forms have been re moved, the Engineer will not require the Contractor to replace the metal fo rms. The adjacent metal forms and supports shall be repaired to present a neat appearance a nd to ensure their satisfactory retention. As soon as the form is removed, the Engineer will examine the concrete surfaces for cavities, honeycombing, and other defects. If irregularities are found and the Engineer determines that these irregularities do not justify rejection of the work, th e concrete shall be repaired as directed by the Engineer. If the Engineer determines that the co ncrete where the form is removed is unsatisfactory, additional meta l forms as necessary shall be removed to inspect and repair the slab, and the Contractor ’s method of construction shall be modified as required to obtain satisfactory concrete in th e slab. All unsatisfact ory concrete shall be removed and replaced as directed at no expense to the State. If the method of construction and the results of the inspections as outlined above indicate that sound concrete has been obtained throughout the slabs, the amount of sounding and form removal may be reduced when approved by the Engineer. The Contractor shall provide a safe and co nvenient means of condu cting the inspection.

804.03.15 Removal of Falsework, Forms, and Housing. In the determination of the

time for the removal of falsework, forms a nd housing and the discontinuance of heating, consideration shall be given to the location an d character of the structure, the weather and other conditions influencing the setting of the co ncrete, and the materials used in the mix. No forms or supports shall be removed prior to approval by the Engineer. During cold weather, removal of housing and the disconti nuance of heating shall be in accordance with Subsection 804.03.16.1. Concrete in the last pour of a continuous s uperstructure shall have attained a compressive strength of 2,400 psi, as determined by cy linder tests or maturity meter probe, prior to striking any falsework. It is important that falsework be removed as evenly as possible to prevent excessive deflectio n stresses in the spans. At the Contractor's option and with the approval of the Engineer, the time for removal of forms may be determined by cylinder tests, in accordance with the re quirements listed in Table 6, in which case the Cont ractor shall fu rnish facilities for testing the cylinders. The facilities shall include an appr oved concrete testing machin e of sufficient capacity and calibrated by an acceptable commercial labora tory. Tests shall be conducted in the presence of a Department representative to witness and record strengths obtained on each break or performed by a Department certified technician in an approved testing laboratory. The cylinders shall be cured under conditions that are not more favorable than those existing for th e portions of the structur e that they represent. Table 6 Minimum Compressive Strength Requirements for Form Removal Forms: Columns ..................................................................... 1000 psi Side of Beams ............................................................. 1000 psi Walls not under pres sure ............................................ 1000 psi Floor Slabs, overh ead ................................................. 2000 psi Floor Slabs, between beams ....................................... 2000 psi Slab Spans .................................................................. 2400 psi Other Parts .................................................................. 1000 psi Centering: Under Beams .............................................................. 2400 psi Under Bent Caps ........................................................ 2000 psi Limitation for Placing Beams on: Pile Bents, pile unde r beam ........................................ 2000 psi Frame Bents, two or more columns ............................ 2200 psi Frame Bents, single co lumn ....................................... 2400 psi For bridges, non-SIP metal forms for bridge deck slabs overhead and bridge deck slabs between beams shall be removed with the approval of the Engineer, between two weeks and four weeks after the removal of the wet burlap applied in accordance with Subsection

804.03.17 1, or the application of liquid membrane applied in accordance with Subsection 804.03.17.2.

In lieu of using concrete strength cylinders to determine when falsework, forms, and housings can be removed, an approved maturity meter may be used to determine concrete strengths by inserting probes into concrete placed in a structure. The minimum number of maturity meter probes required for each stru ctural component shall be in accordance with Table 7. Falsework, forms, and housings may be removed when maturity meter readings indicate that the required concrete strength is achieved. Procedures for using the maturity meter and developing the strength/maturity re lationship shall follow the requirements of AASHTO T 325 and ASTM C 1074 specifications. Technicians using the maturity meter or calculating strength/m aturity graphs shall be required to have at least two hours of training prior to using the maturity equipment. Table 7 Requirements for use of Maturity Meter Probes Structure Component Quantity of Concrete No. of Probes Slabs, beams, walls, & miscellaneous items 0 - 30 yd3 2 > 30 to 60 yd3 3 > 60 to 90 yd3 4 > 90 yd3 5 Footings, Columns & Caps 0 - 13 yd3 2 > 13 yd3 3 Pavement, Pavement Overlays 1200 yd2 2 Pavement Repairs Per repair or 900 yd2, 2 whichever is smaller Methods of form removal likely to cause overstressing of the concrete shall not be used. Forms and supports shall be removed in a manne r that will permit the concrete to uniformly and gradually take the stresses due to its own weight. Centers shall be gradually and uniformly lowered in a manner that will avoid injurious stresses in any pa rt of the structure. As soon as concrete for railings, ornamental wo rk, parapets and vertical faces that require a rubbed finish has attained a safe strength, the forms shall be carefully removed without marring the surfaces and corners, the required finishing performed, and the required curing continued. Prior to final inspection of th e work, the Contractor shall re move all falsework, forms, excavated material or other material placed in the stream channel during construction. Falsework piles may be cut or broken off at least one foot below the mudline or ground line unless the plans specifically indicate that they are to be pulled and completely removed from the channel.

804.03.16 Cold or Ho t Weather Concreting.

804.03.16 1--Cold Weather Concreting. In cold weather, the temperature of the concrete

when delivered to the job site shall conform to the temperatur e limitations of “Temperature Limitations on Concrete when De livered to Job Site” listed in Table 8 below. Cold weather is defined as three c onsecutive days when th ere is a probability that the daily average of the highest and lowest ambient te mperatures is expected to be less than 40°F. This three- day forecast shall be based on the latest in formation available from the National Weather Service. When the Contractor proposes to place concrete during seasons when there is a probability of ambient temperatures lower than 40°F, the Contractor shall have available on the project the approved facilities necessary to enclose unc ured concrete and to keep the temperature of the air inside the enclos ure within the ranges and for the minimum periods specified herein. When there are indications of temperatures of less than 40°F during the first four days after placement of the concrete, the concrete sha ll be protected from cold temperatures by maintaining a temperature between 50°F and 10 0°F for at least four days after placement and between 40°F and 100°F for at least three additional days . The Contractor shall use such heating equipment such as stoves, salamanders, or steam equipment as deemed necessary to protect the concrete. When dry heat is used, m eans of maintaining atmospheric moisture shall be provided. At the option of the Co ntractor with the approval of the Engineer, when concrete is placed during cold weather a nd there is a probability of ambient temperatures lower than 40°F, an approved maturity meter may be used to determine concrete strengths by inserting probes into concrete placed in a structure. Th e minimum number of maturity meter probes required for each structural component shall be in accordance with Table 7. An approved insulating blanketing material shall be used to protect the work when ambient temperatures are less than 40°F an d shall remain in place until the re quired concrete strength in Table 6 is achieved. Procedures for using the maturi ty meter and developing the strength/maturity relationship shall follow the requirements of AASHTO T 325 and ASTM C 1074 specifications. Technicians using the matur ity meter or calculating strength/maturity graphs shall be required to have at least two hours of training prior to using the maturity equipment. One or more of the aggregates and/or mixing water may be heated. The aggregates may be heated by steam, dry heat, or by placing in the mixing water that has been heated. Frozen aggregates shall not be used. When either aggregates or water are heated above 100°F, the aggregates and water shall be combined first in the mixer before the cement is added to avoid flash set. Cement shall not be mixed with water or with a mixture of water and aggregate having a temperat ure greater than 100°F. The use of salt or other chemical admixtures in lieu of heating will not be permitted. Before placing concrete, all ice or frost shall be removed from the forms and reinforcement. In the case of concrete placed directly on or in the ground, such as for footings or bottom slabs, protection and curing during cold weather may be provided as set for concrete pavement under Subsection 501.03.20.3. The Contractor shall assume all risk and added cost connected with the placing and protecting of concrete during cold weather. Permission given by the Engineer to place concrete during such time will in no way relieve the Contractor of responsibility for satisfactory results. Should it be determined at any time that the concrete placed under such conditions is un satisfactory, it shall be remove d and replaced with satisfactory concrete by the Contractor without extra compensation. TABLE 8 COLD WEATHER TEMPERATURE LIMITATIONS ON CONCRETE WHEN DELIVERED TO JOB SITE Section thickness in the least dimension inches Jobsite Acceptance Temperature Range °F Less than 12 55 to 75 12 to 36 50 to 70 36 to 72 45 to 65 Greater than 72 40 to 60

804.03.16 2--Hot Weather Concreting. The manufacture, placement, and protection of

concrete during hot weather requires special a ttention to ensure that uniform slump ranges and satisfactory placement qualitie s are maintained, that surface cracking is held to a minimum, and that design strengths are produced. For bridge decks when the ambi ent temperature is above 90°F, the forms, reinforcing steel, steel beam flanges, and other surfaces which will come in contact with the concrete shall be cooled to below 90°F by means of a water spray or other approved methods. Additionally, when the atmospheric temperature is predicted to be 90°F or above based on the latest information available from the Na tional Weather Service any time during the day of placement or day after placement, the time of placement shall not begin until 5:00 p.m. on the day of placement and shall be completed by 6:00 a.m. the following day.

804.03.17 Curing Concrete. Curing is defined as all actio ns taken to ensu re the moisture

and temperature conditions of freshly placed concrete exist so the concrete may develop strength and result in a long la sting, durable, structural memb er. Curing shall take place from the time of placement until the developed st rength is such that the concrete is not damaged by rapid drying or temperature gradie nts. The Contractor shall use the guidance in ACI 308R-01 to: (a) cure the concrete in such a manner as to prevent premature mois ture loss from the concrete,

b.supply additional moisture to the concrete as required in order to ensure sufficient moisture within the concrete, and
c.maintain a concrete temperatur e beneficial to the concrete. Curing in accordance with the requirements of Subsection 804.03.17.1 or Subsection

804.03.17 2 shall be establishe d within 20 minutes after finishing, except as noted for

bridge decks. Finishing is considered to be complete when the pan drag, burlap drag, or other finishing methods are complete. The required method of curing for bridge deck concrete is dependent on the method of strike-off, the type of formwork used, and wh ether or not lightweight aggregate (LWA) is used for internal curing. The required method of curing for each alternative is as follows:

a.When removable forms are used, the bridge deck concrete may be cured in accordance with Subsection 804.03.17.1 - Water With Waterproof Cover or Subsection 804.03.17.2 - Liquid Membrane.
b.When stay-in-place (SIP) metal forms are us ed in conjunction with the Transverse Method of strike-off, the bridge deck co ncrete shall be cured in accordance with Subsection 804.03.17.1 - Water With Waterproof Cover. See Subsections

804.03.14 2 - Stay-In-Place Metal Forms an d 804.03.19.7.3 - Transverse Method.

c.When the Longitudinal Method or the Transverse Method of strike-off is used for repairs to bridge decks or bridge widening, the bridge deck concrete may be cured in accordance with Subsect ion 804.03.17.1 - Water Wi th Waterproof Cover or Subsection 804.03.17.2 - Liquid Membrane. Additionally, the time in which the curing is applied to the bridge deck surface may be increased to 30 minutes after finishing due to the nature of the work. When the bridge deck concrete contains LWA meeting the requirements of Subsection 703.19.2 and the mixture contains an internal curing water content of 8.0 pounds or greater per 100 pounds of total cementitious materials, the bridge deck concrete may be cured in accordance with Subsection 804.03.17.1 - Wa ter With Waterproof Cover or Subsection

804.03.17 2 - Liquid Membrane. The length of time for curing shall be maintained on the bridge deck surface in accordance

with either of the following:

a.Prescribed Length of Time:
1.Curing following the requirements of Subsection 804.03.17.1 - Water With Waterproof Cover shall continue uninte rrupted for at least 17 days. This includes a 10-day period in which the co ncrete is kept wet continually through the use of wet burlap, soaker hoses , and white polyethylene sheets. Immediately following is a 7-day period in which a single layer of liquid membrane is applied to a llow the concrete to dry sl owly. For bridge decks, construction traffic may utilize the deck during the 7-day drying period, but the Contractor is required to immediately reapply liquid membrane to any marred surfaces.
2.Curing following the requirements of Subsection 804.03.17.2 - Liquid Membrane shall continue uninte rrupted for at least 10 days.
b.Length of Time Defined by Deve lopment of Compressive Strength: Curing following the application requirements of Subsection 804.03.17.1 or Subsection 804.03.17.2 sha ll continue uninterrupted for concrete within an individual pour until the compressive strength of the concrete exceeds 75% of the 28- day compressive strength submitted as the Basis of Proportioning per Subsection

804.02.10 1.

If cured following the requirements of Subsection 804.03.17.1 - Water With Waterproof Cover, once the concrete achieves 75% of the 28-day compressive the polyethylene sheeting and wet burlap may be removed and a single layer of liquid membrane applied. For bridge decks, construction traffic may utilize the deck during the 7-day drying period but the Contractor is required to immediately reapply liquid membrane to any marred surfaces.

804.03.17 1--Water with Waterproof Cover. All burlap shall be completely saturated and

wet prior to placing it on the concrete. The burlap shall have been fully soaked in water for a minimum of 12 hours prior to placement on the concrete. For bridge decks, the Contractor shall apply one (1) layer of saturated burlap within 20 minutes of the initial strike-off for bridges without a skew and 25 minutes of the initial strike- off for bridges with a skew. For all other conc rete, the Contractor shall apply one (1) layer of saturated burlap within 20 mi nutes of completing finishing. For bridge decks, following the first layer of bur lap, the Contractor sh all apply a second layer of saturated burlap within five (5) mi nutes of applying th e first layer. The applied burlap shall completely cover all exposed concrete surfaces. In areas where the burlap may not be directly applied due to the concrete surface, for example, in areas where reinforcing steel protrudes thru the concrete surf ace, like in the areas of a bridge deck where the bridge railing will be constructed at a later time, the saturated burlap shall be draped over the steel. The concrete surface shall not be allowed to dry afte r strike-off or at any time during the curing period. The Contractor shall maintain the burlap in a fully wet condition using powered fogging equipment capable of producing a fog spray of atomized droplets of water until the concrete has gained sufficient strength to allow foot tr affic without the foot traffic marring the surface of the concrete. Burlap shall not be mainta ined in the fully wet condition using equipment that does not produce a fog spray of atomized droplets of water or by use of manually pressurized sprayers. For bridge decks, once the concrete has gained sufficient strength to allow foot traffic that does not mar the surface of the concrete, soaker hoses shall be placed on the burlap. The soaker hoses shall then be supplied with running water continuously to maintain continuous saturation of all burlap and the entire concrete surface. If there is a delay in the placement of the first layer of saturated burlap outside the time limit, the struck-off and finished concrete shall be kept wet by use of the powered fogging equipment used to k eep the burlap wet. White polyethylene sheets shall be placed on top of the wet burla p and, as applicable, soaker hoses, covering the entire concrete surface as soon as practical and not more than 12 hours after the placement of the concrete. White polye thylene sheets of the widest practical width shall be used, overlapping adjacent sheets a mini mum of six inches (6”) and tightly sealed with an adhesive like pressure sensitive tape, mastic, glue, or other approved methods to form a complete waterproof cover of the entire conc rete surface. White polyethylene sheets that overlap a minimum of two feet (2’) may be held in place using means other than an adhesive. The white polyethylene sheets shall be secured so that wind will not displace them. The Contractor shall immediately repair the broken or damaged portions or replace sections that have lost their wate rproof qualities. If burlap and/or white polyethylene sheets are temporarily removed for any reason during the curing period, the Contractor shall keep th e entire exposed area continuously wet. The saturated burlap and white polyethylene sheets shall be replaced, resuming the specified curing conditions, as soon as possible. The Contractor shall inspect th e bridge deck surface once every eight (8) hours for the entirety of the curing period, so that all areas remain wet for the entire curing period and all curing requirements are satisfied and document th e inspection in accordance with Subsection

804.03.17 1.1.

At the end of the curing period, one coating of liquid membrane shall be applied following the requirements of Subsection 804.03.17.1.2. The purpose of the coating of liquid membrane is to allow for slow drying of the concrete. The application of liquid membrane to any area shall be complete within 30 minutes of the beginning of removal of the white polyethylene sheets, soaker hose s, and burlap from this area.

804.03.17 1.1--Documentation for Bridge Decks. The Contractor shall provide the

Engineer with a daily insp ection report that includes:

a.documentation that identifies any defi ciencies found (inc luding location of deficiency);
b.documentation of corrective measures taken;
c.a statement of certification that all areas ar e wet and all curing material is in place on the entire bridge deck;
d.documentation showing the time and date of all inspections and the inspector’s signature; and
e.documentation of any temporary removal of curing materials incl uding location, date and time, length of time curing was removed, and means taken to ensure exposed area was kept continuously wet.

804.03.17 1.2--Liquid Membrane. At the end of the 14-day wet curing period the wet

burlap and polyethylene sheets shall be remove d and within 30 minutes, the Contractor shall apply white liquid membrane to the deck. The liquid membrane shall be thoroughly mixed within the time recommended by the liquid membrane producer but no more than an hour before use. If the use of liquid membrane resu lts in a streaked or blotched appearance, the method shall be stopped and water curing applied until the cause of defective appearance is corrected. The liquid membrane shall be applied when no free water remains on the surface but while the surface is still wet. Th e liquid membrane shall be applied according to the manufacturer’s instructions with a minimum spreading rate per coat of one (1) gallon per 200 square feet of concrete surface. If the concrete is dry or becomes dry, the Contractor shall thoroughly wet it with water applied as a fo g spray by means of approved equipment. The application of liquid membrane shall be accomplished by the use of power applied spray equipment using nozzles and other equipment recommended by the liquid membrane producer. Manually pressurized or manual pump-up type sprayers shall not be used to apply the first application of liquid membrane. As a visual guide, the color of concrete covered with the required amount of liquid membrane should be indistinguishable from a sheet of commercially available standard “letter” size white copier paper placed on top of it when viewed from a distance of about five feet (5’) away horizonta lly if standing on the same grade as the concrete. The appearance of the concrete does not supersede applying the minimum spreading rate. The coating shall be protected against marri ng for at least seven (7) days after the application of the curing compound. The co ating on bridge decks shall receive extra attention and may require additional protection as required by the Engineer. All membrane marred or otherwise disturbed sh all be given an additional coa ting. Manually pressurized or manual pump-up type sprayers may be used for giving marred areas the required additional application of liquid membrane. Should the surface co ating be subjected repeatedly to injury, the Engin eer may require that the water curing method be applied at once. The 7-day period during which the liquid memb rane is applied and protected shall not be reduced even if the period of wet curing is extended past the required 14 days.

804.03.17 1.2.1--Liquid Membrane Documentation. The Contractor shall make available

to the Engineer an applica tion rate verification method and any information necessary during application of the liquid membrane to ve rify that the rate of application meets the prescribed rate for the various surfaces of the concrete, including, but not limited to, the top surface of the bridge deck and exposed sides of the bridge deck after any forms are removed. The Contractor shall submit this ap plication verification me thod to the Engineer in accordance with Subsec tion 804.02.12.1.1. One method of verifying the rate of application is as follows: (a) Determine the volume of liquid membrane in the container. For a container with a uniform cross-sectional area, for example a 55-gallon drum, determine the area of the cross-section. Determin e the height of the surface of the liquid membrane from the bottom of the container. This may be accomplished by inser ting a sufficiently long, clean dip-stick parallel with the axis of the container into the liquid membrane until the inserted end of th e dip-stick contacts the bottom of the container. On removing the dip-stick, measure the length from the end that was inserted to the point on the dip-stick where the liquid membrane ceases to coat the dip-stick. Multiply the area of th e cross-section by the height of the level of liquid membrane, maintaining consistent units, to determine the volume.

b.Perform step 1 prior to beginning applica tion of the liquid membrane to establish the initial volume.
c.During the period of application, perform st ep 1 each 100 square feet of bridge deck.
d.In order to meet the required application rate of one (1) gallon per 200 square feet, the amount in the container shall be at least 0.5 gallon less than the previous volume in the previous 100 square feet. Other changes in volume may apply depending on the manufacturer’s recommended application rate. (e) Additional applications to an area shall be applied until the required rate is satisfied. Areas that are not visually satisfactory to the Engineer shall have additional liquid membrane applied as directed by the Engineer. The amount of liquid membrane applied shall be determined each day using the application verification method. This information shall be submitted to the Engi neer within 24 hours of applying the liquid membrane.

804.03.17 2--Liquid Membrane Method. All surfaces on which curing is to be by liquid

membrane shall be given the required surface finish prior to the application of liquid membrane. Concrete surfaces cured by liquid membrane shall receive two applications of white liquid membrane. Neither application sha ll be made from a position supported by or in contact with the freshly placed concrete . Both applications shall be applied perpendicularly to the su rface of the concrete. When using liquid membrane, the liquid membrane shall be thoroughly mixed within the time recommended by the liquid membrane producer but no more than an hour before use. If the use of liquid membrane results in a streaked or blotched appearance, the method shall be stopped and water curing a pplied until the cause of defective appear ance is corrected. The application of liquid membrane shall be accomplished by the use of power applied spray equipment using nozzles and other equipment recommended by the liquid membrane producer. Manually pressurized or manual pump-up type sprayers shall not be used to apply the first two applica tions of liquid membrane. The liquid membrane shall be applied when no free water remains on the surface but while the surface is still wet. Th e liquid membrane shall be applied according to the manufacturer’s instructions with a minimum spreading rate per coat of one (1) gallon per 200 square feet of concrete surface. If the concrete is dry or becomes dry, the Contractor shall thoroughly wet it with water applied as a fog spray by means of approved equipment. The first application of the liquid membrane shall be made as the work progresses. For bridge decks, the first application shall be completed in each area of the deck, including the area in which the bridge railing will be late r constructed, within 20 minutes of initial strike-off for bridges with no skew and within 25 minutes of initial strike -off for bridges with skew. For all other concrete, the first application of the liquid membrane shall be completed within 20 minutes of finishing. The second application shall be applied within 30 minutes afte r the first application. The liquid membrane shall be uniformly applied to all exposed concrete surfaces. As a visual guide, the color of concrete covered with the required amount of liquid membrane should be indistinguishable from a sheet of commercially available standard “letter” size white copier paper placed on top of it when viewed from a distance of about five feet (5’) away horizonta lly if standing on the same grade as the concrete. The appearance of the concrete does not supersede applying the minimum spreading rate. The Contractor shall make available to the Engineer an application rate verification in accordance with Subsection 804.03.17.1.2.1. The coating shall be protected against marring fo r at least 10 days after the application of the curing compound. The coating on bridge decks shall receive extra attention and may require additional protection as required by the Engineer. All membrane marred or otherwise disturbed shall be given an additional coating. Manually pressurized or manual pump-up type sprayers may be used for giving marred areas the required additional application of liquid membrane. Should the surface coating be subjected repeatedly to injury, the Engineer may requi re that the water curing method be applied at once. After the specified time for curing, but prior to constructing the bridge railing, all liquid membrane shall be removed from both the exposed surfaces of the reinforcing steel and the concrete surfaces on which bridge rail w ill be constructed. This removal of liquid membrane may be accomplish by high pressure washing or other methods approved by the Engineer.

804.03.18 Expansion and Fixed Joints, Bearings, Anchor Bolts, Plates, Castings,

Pipes, Drains, Conduits, Etc. All joints shall be constr ucted according to details shown on the plans. The edges of the concrete at open or filled joints shall be chamfered or edged as indicated on the plans.

804.03.18 1--Open Joints. Open joints shall be placed in the locations shown on the plans

and shall be constructed by the insertion and subsequent removal of a wood strip, metal plate, or other approved material. The inse rtion and removal of th e template shall be accomplished without chipping or breaking the corners of th e concrete. Reinforcement shall not extend across an open joint unless so specified on the plans.

804.03.18 2--Filled Joints. Poured expansion joints and joints to be sealed with premolded

materials shall be constructed similar to open joints. When premolde d types are specified, the filler shall be placed in correct position as the concrete on one side of the joint is placed. When the form is removed, the concrete on the other side shall be placed. Adequate water stops of metal, rubber, or plastic shall be carefully placed as shown on the plans.

804.03.18 3--Premolded an d Preformed Joint Seals. When preformed elastomeric

compressive joint seals are speci fied, the previously formed and cured op en joint shall be thoroughly cleaned of all foreign matter, the re quired adhesive uniformly applied, and the seal installed in accordance with the reco mmendations of the manufacturer of the seal. When premolded filler is used for the joints in the roadway slab , the tops shall be adequately sealed with poured joint filler in accordance w ith details on the plans. Premolded filler shall be permanently fasten ed to an adjacent concrete surface by appropriate use of copper wire, copper nails, or galvanized nails.

804.03.18 4--Steel Joints. The plates, angles, or other structural shapes shall be accurately

shaped at the shop to conform to the section of the concrete floor. Fabrication and painting shall conform to the specifications covering those items. When called for on the plans or in the special pr ovisions, the material shall be galvanized in lieu of painting. Care shall be taken to ensure that th e surface in the finished plane is true and free of warping. Positive methods shall be employed in placing the joints to keep them in correct position during the placing of the concrete. The opening at expans ion joints shall be that designated on the plans at normal temperature, and care shall be taken to avoid impairment of the clearance in any manner.

804.03.18 5--Water Stops. Adequate water stops of meta l, rubber, or pl astic shall be

placed as shown on the plans. Where movement at the joint is provided for, the water stops shall be of a type permitting movement without injury. They shall be spliced, welded, or soldered to form conti nuous watertight joints.

804.03.18 6--Bearing Devices. Bearing plates, rockers, and other bearing devices shall be

constructed according to details shown on the plans. Unless otherwise specified or set in plastic concrete, they shall be set in grout to ensure uniform bearing. Structural steel and painting shall conform to the re quirements of Sections 810 and 814. When specified, the material shall be galvanized in lieu of painting. The rockers or other expansion bearing devices shall be set, considerin g the temperature at the time of erection, so that the required position of the device is provided. At all points of bearing contact, concrete members shall be separated from underlying members by dimensioned bearing pads or by methods and/or materials specified on the plans. When not otherwise specifically provided, contact areas between concrete super-structures and substructures shall be separated by three layers of No. 15, Type I, roofing felt.

804.03.18 7--Friction Joints. Metal friction joints shall consist of plates as indicated on

the plans and shall be securely anchored in co rrect position. All sliding surfaces shall be thoroughly coated with an approved graphite grease. Movement shall not be impeded by the concrete in which the plates are embedded.

804.03.18 8--Placing Anchor Bolts, Pl ates, Castings, Grillage, Conduits, Etc. All

anchor bolts, plates, castings, grillage, conduits, etc. indicated on the plans to be placed in or on the concrete shall be placed, set, or embedded as indicated or as directed. These items of the construction shall be set in hy draulic cement mortar as referenced in Subsection 714.11.5, except that anchor bolts may, as permitted by the Engineer, be built into the masonr y, set in drilled holes, or placed as the concrete is being constructed by inserting encasing pipe or oiled wooden forms of sufficient size to allow for adjustment of the bolts. After removal of the pipe or forms, the space around the bolts shall be filled with hydraulic cement mortar comple tely filling the holes. The bo lt shall be set accurately and perpendicular to the plane of the seat. Anchor bolts to be set in the masonry prior to the erection of the superstructure shall be carefully set to proper locatio n and elevation with a template or by other suitable means. When bed plates are set in mortar, no superstr ucture or other load shall be placed thereon until this mortar has been allowed to set for a period of at least 96 hours, subject to the restrictions for cold weather concreting in Su bsection 804.03.16.1. The mortar shall be kept well moistened during this period. Weep hole drains shall be installed in abut ments and retaining walls, and roadway drains or scuppers shall be installed in the roadway slabs in accorda nce with the details shown on the plans. Where backfill is to be made at weep holes or ope nings in the structur e, sand or stone chimneys or French drains shall be constructed as specified and shall extend through the portion of the backfill to be dr ained. Except as otherwise pr ovided, the sand, stone, or slag used in this construction shall meet the requirements of Subsection 704.04.

804.03.19 Finishing Concrete Surfaces.

804.03.19 1--Classes of Finishes. Surface finishes of exposed concrete surfaces shall be

classified as follows: Class 1 - Ordinary Surface Finish Class 2 - Rubbed or spray Finish Class 3 - Tooled Finish Class 4 - Sand-Blast Finish Class 5 - Wirebrush or Scrubbed Finish Class 6 - Floated Surface Finish

804.03.19 2--Class 1, Ordinary Surface Finish. Immediately following the removal of

forms, all fins and irregular projections shal l be removed from all surfaces except from those that are not to be exposed or not to be waterproofed. On all surfaces, the cavities produced by form ties and all other holes, hon eycomb spots, broken corners or edges, and other defects shall be thoroughly cleaned, and after having been kept saturated with water for at least three hours, shall be carefully pointed and trued with a mortar of cement and fine aggregate mixed in the proportions used in the class of the concrete being finished. Mortar used in pointing shall be not more than one hour old. The mortar patches shall be cured as specified under Subsection 804.03.17. All construction and expansion joints shall be left carefully tooled and free of mortar and concrete. The joint filler shall be left exposed for its full length with clean and true edges. The resulting surfaces shall be true and uniform. All surfaces that cannot be repaired to the satisfaction of the En gineer shall be given a Class 2 rubbed finish.

804.03.19 3--Class 2, Rubbed or Spray Finish.

804.03.19 3.1--Rubbed Finish. After removal of forms, the Class 1 finish shall be

completed and the rubbing of conc rete shall be started as soon as its condition will permit. Immediately before starting this work, the concrete shall be kept thoroughly saturated with water for at least three hours. Surfaces sha ll be rubbed with a medium course Carborundum stone using a small amount of mortar on its f ace. The mortar shall be composed of cement and sand mixed in the proportions used in the concrete being finished. Rubbing shall be continued until all form marks, projections, and irregularities ha ve been removed, all voids are filled, and a uniform surface has been obta ined. The paste produced by this rubbing shall be left in place at this time. After all concrete above the surface being treat ed has been cast, the final finish shall be obtained by rubbing with a fine Carborundum stone and water. This rubbing shall continue until the entire surface is of a smooth texture and uniform color. After the final rubbing is completed and the surface has dried, it shall be rubbed with burlap to remove loose powder and objectionable marks.

804.03.19 3.2--Spray Finish. Prior to the spray finish, the concrete shall be given a Class

1 finish in accordance with Subsection 804.03.19.2, supplemented if necessary with a grout meeting the requirements of S ubsection 714.11 with fine aggregate modified to require 100 percent passing the No. 16 Sieve. Grout shall be applied with burlap pads or float sponges. As soon as the grout has dried, the surface shall be brushed to remove all loose grout and the surface left smooth and free of air holes. Surfaces to be sprayed shall be free of efflorescence, flaking coatings, dirt, oil, and other foreign substances. Prior to application of the spray finish, the surfaces shall be free of moisture, as determined by sight and touch, and in a c ondition consistent with the manufacturer's published recommendations. The spray finish material shall meet the re quirements of Subsection 714.12 and shall be listed on the Approved Sources of Materials. The spray finish shall be applied with heavy duty spray equipment capable of maintaining a constant pressure as necessary for proper application. The material shall be applied as recommended by the manufacturer except the rate of application shall not be less than one gallon per 50 square feet of surface area without prior written appr oval of the Engineer. The completed finish shall be tightly bonded to the structure and present a uniform appearance and texture equal to or better than a rubbed finish. If necessary, additional coats shall be sprayed to produce the desired surface texture and uniformity. Upon failure to adhere positively to the stru cture without chipping or cracking or to attain the desired surface appearance, the coatings shall be completely removed and the surface given a rubbed finish in accordance with Subsection 804.03.19.3.1, or other approved methods shall be used to obtain the desired surface fini sh to the satisfaction of the Engineer without additional cost to the State.

804.03.19 4--Classes 3, 4, and 5 Finishes. If required, specifications for these finishes

will be contained in the special provisions.

804.03.19 5--Class 6, Floated Surface Finish. After the concrete has been deposited in

place, it shall be consolidated and the surface shall be struck off by means of a strike board and floated with a wooden or cork float. An edging tool shall be used on edges and expansion joints. The surface shall not vary more than 1/8 inch under a 10-foot straightedge. The surface shall have a granul ar or matte texture that will not be slick when wet.

804.03.19 6--Required Fini shes for Various Surfaces.

804.03.19 6.1--General. Unless otherwise specified, the top surface of sidewalks, the top

horizontal surfaces of footings, and the top slabs of box bridges, box culv erts, or other structures shall be given a Class 6 finish. A ll formed concrete surfaces shall be given a Class 1 finish, except on surfaces that are comp letely enclosed, such as the inside surfaces of cells of box girders, the removal of fins and form marks and the rubbing of mortared surfaces to a uniform color will not be required. In reference to finishing, exposed surfaces are surfaces or faces that may be seen after all backfill has been placed. Expos ed surfaces requiring a Class 2 finish shall be finished at least one foot below the ground line or the low water elevation, whichever is higher. The Class 2 finish shall be made upon a Cla ss 1 finish. After the removal of forms, the Class 1 finish shall be completed and the rubbing of concrete shall be started as soon as the condition of the concrete will permit. Bridge floors shall be finished in accordance with Subs ection 804.03.19.7.

804.03.19 6.2--Finishing Fo rmed Concrete Surfaces of Box Bridges, Box Culverts,

Pipe Headwalls, and Minor Structures. The exposed surfaces of wing walls and parapets of box bridges and box culverts to be used as vehicular or pedestrian underpasses shall be given a Class 2 finish. Exposed surfaces of ot her box culverts or box bridges, pipe culvert headwalls, and other minor structures shall be given a Class 1 finish unless otherwise indicated on the plans. The exposed surfaces of retaining walls including copings and parapets shall receive a Class 2 finish.

804.03.19 6.3--Finishing Formed Concrete Surface of Bridges. All exposed formed

concrete bridge surfaces shall have a Class 1 or 2 finish as set forth in this subsection unless designated otherwise on the plans. Bridges with designated surfaces for Cla ss 2 finish are classified as follows: Group A - Bridges over highways, roads and streets. Group B - Bridges over waterways and railroads. Group BB - Twin or adjacent bridges of Group B category. When a Group B or BB bridge also spans a highway, road or street, exposed concrete surfaces shall be finished in acco rdance with Group A requirements.

A.Superstructures. Concrete surfaces to be given a Class 2 finish shall be the exposed surfaces of wings and rails and other exposed su rfaces indicated by a double line in Figures 804-1, 804-2, and 804-3. When a Group B or BB also spans a highway, ro ad or street, the superstructure of spans over and extending one span in each direction beyond the lowe r level highway, road or street shall be given a Class 2 finish as shown for Group A.
B.Substructures. Concrete surfaces to be given a Class 2 finish are as follows: Group A. Exposed surfaces of abutments, end be nts, end bent posts, wing walls, railing, retaining walls, parapets , copings, piers, columns, piles, caps, struts or walls between columns or piles, encasemen t of steel piles, arch rings and spandrel walls. Group B and BB. Exposed surfaces of abutments, wi ng walls, end bent posts, railing, retaining walls, parapets and copings. CONCRETE SLAB SPAN & HOLLOW SLAB SPAN PRECAST HOLLOW SLAB SPAN CONCRETE GIRDER SPAN STEEL BEAM SPAN Vertical Face Slope Face CONCRETE BOX GIRDER SPAN For Finishing On The Remainder Of Superstructure, See The Appropriate Section On This Page. PRESTRESSED CONCRETE BEAM SPANSTYPICAL SIDEWALK SECTION GROUP "A" BRIDGES OVER HIGHWAYS, ROADS & STREETS CLASS 2 FINISH - BRIDGE SUPERSTRUCTURES - FIG. 804-1 CONCRETE SLAB SPAN & HOLLOW SLAB SPAN PRECAST HOLLOW SLAB SPAN CONCRETE GIRDER SPAN STEEL BEAM SPAN Vertical Face Slope Face CONCRETE BOX GIRDER SPAN For Finishing On The Remainder Of Superstructure, See The Appropriate Section On This Page. PRESTRESSED CONCRETE BEAM SPANS TYPICAL SIDEWALK SECTION GROUP "B" BRIDGES OVER WATERWAYS AND BRIDGES OVER RAILROAD TRACKS CLASS 2 FINISH - BRIDGE SUPERSTRUCTURES - FIG. 804-2 GROUP "B B" - ADJACENT BRIDGES GROUP "B B" TWIN or DUAL BRIDGES CLASS 2 FINISH - BRIDGE SUPERSTRUCTURES - FIG. 804-3Rub All Surfaces Of Rail100 ' or Less

804.03.19 7--Finishing Bridge Decks.

804.03.19 7.1--General. Concrete bridge decks shall be struck off and finished by the

method(s) designated on the plans. In the event a method is not designated, the Contractor may use either the longitudinal or transverse method subject to the requirements contained in these specifications. Except when indicated otherwise on the plans, th e finish of the bridge deck shall be a belt finish, a broom finish, or one of the followi ng drag methods: pan, double pan, burlap, or pan and burlap. Manual finishing of the bridge deck shall be performed only in areas inaccessible by the finishing equipment mounte d to the strike-off screed, but shall not hinder the requirements for curing in accordance with Subsection 804.03.17.1. The surface texture specified and surface requirements sh all be in accordance with the applicable requirements of Subsections 501.03.17 and 501. 03.18 modified only as the Engineer deems necessary for bridge deck construction operations. At no time shall water on the surface of the co ncrete from bleeding, fogging, curing, or other sources be worked into the concrete or used as an aid for finishing. Regardless of the method of finishing select ed, requirements for curing per Subsection

804.03.17 shall be completed within the spec ified time limits. If the requirements in

Subsection 804.03.17 are not completed within th e specific time limits, the Contractor shall cease operations, revise his operations up to and including acquiring new or additional equipment or additional person nel in order to satisfy th e requirements in Subsection

804.03 17, and, on approval from the Engineer, resume operations.

804.03.19 7.2--Longitudinal Method. The longitudinal method may be used for repairs

to bridge decks or bridge widening projects. For bridge widening projects, curing in accordance with Subsection 804. 03.17 shall be completed w ithin 30 minutes of initial strike-off for bridges without skew and within 35 minutes of initial strike-o ff for bridges with skew. The longitudinal method requires that the stri ke-off screed be supported on accurately graded and supported bulkheads or templates placed across the full width at the end(s) of the pour. Before the concrete is placed, ap proved fixed templates or wooden bulkheads of not less than 1¼-inch lumber shall be placed perpendicular to the centerline of the roadway, or in the case of skew bridges at the angle of skew. At least one dry run shall be made the length of each pour with a "tell- tale" device attached to the screed to assure the specified clearance to the reinforcing steel. The upper surface of the template or bulkheads shall be accurately set to conform to the required grade and crown. Special attention shall be given to the gutter lines where the strike-off sc reed cannot reach. The gutters shall be finished by hand and tested with the straight edge. Floor drains shall be set lower than the finished gutter line and fi nished over. After initial set, the concrete shall be dished out and finished around the drains to form an outlet. After the concrete has been deposited and rough graded, it shall be struck off by means of a strike-off screed resting on the bulkheads or fixed templates. The strike-off screed shall be of a type satisfactory to the Engineer and shall have sufficient streng th to retain its shape under all working conditions. The final surf ace shall comply with the applicable requirements of Subsections 501.03.17.6 and 501.03.18, and unless otherwise specified in the contract, the final finish under th is method shall be the belt finish. In general, the overall strike-off screed shou ld be trussed, with bracing heavy enough to support the weight of a man without deflecti ng, and should be adjustable for camber and correction of sag. The strike-off screed w ill ride on the bulkheads or fixed temp lates at the ends of the section being finished. Care shall be taken to see th at the bulkhead or fixed template elevations are accurately set since the entire span surface will be contro lled by them. The manipulation of the screed shall be such that neither end is raised from the bulkheads or templates during the process. The concrete shall be struck off by beginning at one curb and proceeding entirely across the span. A slight excess of conc rete shall be kept in front of the cutting edge at all times. This operation shall be repeated at least three times. In e ach case, the strike-off screed shall be picked up and carried back to the point of beginning. No backward strokes will be allowed. The strike-off screed shall be moved along the bulkheads or fixed templates with a combined longitudinal and transverse motion. This operation may be manual or mechanical. Standing or walking in the fresh co ncrete ahead of the strike-off screed will not be permitted.

804.03.19 7.3--Transverse Method. The transverse method requires that the screeding

equipment be supported on accurately graded and supported rails placed beyond the gutter lines and parallel with th e centerline of the bridge. The machine shall be constructed and operated in a manner that produces a bridge deck of uniform density with minimum manipulation of the fresh concrete in the shortest possible time. Manual transverse methods of screeding will not be permitted. The finishing machine shall be supported on vertically adjustable rails set a sufficient distance from the gutter line to allow free moveme nt of the screed from gutter line to gutter line. Satisfactory means of load distribut ion with minimum rail deflection shall be provided. The screed rails for a deck pour sh all be completely in place for the full length of the pour and shall be firmly secured prior to placing concrete. The screed rails shall be adjusted as necessary to co mpensate for settlement and deflection occurring during the screeding operations. Supports for the screed rail shall be located directly over slab overhang support brackets as referenced in Subsection 804.03.14.1. At least one dry run shall be ma de the length of each pour with a "tell-tale" device attached to the screed carriage to assure the specified clearan ce to the reinforcing steel. The screed shall be equipped with a metal cutting edge or other approved mechanical means for accurately fine grading the plastic concrete to the requir ed grade and surface smoothness and shall be supported by a bridging structure sufficiently rigid and heavy to perform operations satisfactorily on concrete of minimum slump without vibration, distortion, and wrecking of forms. The screed shall be mechanically actuated to deliver the screeding action and for travel in a long itudinal direction at a uniform rate along the bridge deck. The screed shall complete sufficient passes to strike off all of the excess concrete with ample mortar along the entire leading edge to assure filling of low spots. Care shall be taken to remove all objectionable material fro m the gutters where final hand finishing will be required. The selection of the transverse method may requ ire the Contractor to furnish bridge deck concrete that contains an ap proved water-reducing set-retard ing admixture in the quantities approved by the Engineer at no additional cost to the State. See Subsection 713.02 for more information. Other finishing requirements shall be in acco rdance with the general requirements in Subsection 804.03.19.7.1 and as specified on the plans.

804.03.19 7.4--Acceptance Procedu re for Bridge Deck Smoothness. After the bridge

decks and bridge end slabs are completed and preferably before th e construction of the bridge railing, they shall be tested for ride quality using a Contractor furnished profilograph. Profile Index Va lues shall be determined in accordance with Department SOPs and these specifications. The profilograp h shall meet the requir ements of Subsection

804.03.19 7.5. Profiles will be obtained in th e wheel paths of the main thru lanes and,

where conditions allow, in the wheel paths of any auxiliary la nes or tapers. Profile Index Values for bridge decks and bridge end slabs shall be obtained for all State roads with four lanes or more, on State roads three lanes or less where the current tr affic count is 2000 ADT or higher, or as designated on the plans. Ride quality tests will begin at a point where the rearmost wheel of th e profilograph is as close to the beginning of the bridge end slab as possible and shall proceed forward across the remainder of the bridge end slab, across the bridge deck and continue across the next bridge end slab to a point where the front- most wheel of the profilograph reaches the far-most edge of the bridge end slab. In addition to the Profile Index test, all bridge decks and bridge end slabs shall meet a 1/8 inch in 10- foot straightedge requirement in both the longitudinal and traverse directions. Bridges and bridge end slabs not requiring a ride quality test must meet a 1/8 inch in 10-foot straightedge requirement in both the longitudi nal and transverse directions. Bridges in horizontal curves having a radius of less than 1000 feet at the center line and bridges within the superelevation transition of such curves ar e excluded from a test with the profilograph. The Profile Index Value for bridge decks incl uding the bridge end slabs shall be averaged for the left and right wheel path for each lane and where applicable, each auxiliary lane and taper, and shall not exceed 65 inches per m ile for each lane. Auxiliary lanes, tapers, shoulders and other areas that are not checked with the profilograph, shall meet a 1/8 inch in 10-foot straightedge check made transversely and longitudinally across the deck or slab. In addition, individual bumps or depressions exceeding 0.3 of an inch, when measured from a chord length of 25 feet, shall be corrected and the surface shall meet a 1/8 inch in 10-foot straightedge check made transversely across the deck or slab. Bridge decks and bridge end slabs not m eeting the preceding requirements shall be corrected. Corrective work shall be done at no additional cost to the Department. Corrective work shall consis t of grinding the bridge deck in accordance with this specification. All corrective work shall pre cede final surface texturing. After completion of final surface texturing, all surface areas corrected by grinding shall be sealed with a nonstaining 40% minimum alkylalkoxysilane penetrating sealant applied per the manufacturer’s directions. In case the bridge end slabs are to be constructed on a future project, the bridge deck(s) alone shall be tested for ride quality using the acceptance procedure outlined above, except that the ride quality test will begin at a poin t where the rearmost wh eel of the profilograph is as close to the beginning of the bridge as possible and shall proceed forward across the bridge deck to a point where the front-most wheel of the profilograph reaches the far-most edge of the bridge. Expansion joint installation shall be delayed an d the joint temporarily bridged to facilitate operation of the profilograph and grinding e quipment across the join t wherever feasible. It shall be the Contractor’s responsibility to schedule profilog raph testing. The Contractor shall notify the Department at least five (5) days in advance of profilograph testing. The Contractor shall ensure that the area to be tested has been cleaned and cleared of all obstructions. Profilograph testing of bridge decks and bridge end slabs shall be performed by the Contractor under supervision of the Engineer. All profilograph testing shall be performed at no additional cost to the Depart ment. The Contractor will be responsible for traffic control associated w ith this testing operation.

804.03.19 7.4.1--Grinding Bridge Decks.

804.03.19 7.4.1.1--Equipment. The grinding equipment shall be a power driven, self-

propelled machine that is specifically desi gned to smooth and texture hydraulic cement concrete pavement with diamond blades. The effective wheel base of the machine shall not be less than 12.0 feet. It shall have a set of pivoting tandem bogey wheels at the front of the machine and the rear wheels shall be arra nged to travel in the track of the fresh cut pavement. The center of the grinding head shall be no further than 3.0 feet forward from the center of the back wheels. The equipment shall be of a size that will cut or plane at least 3.0 feet wide. It shall also be of a shape and dimension that does not encroach on traffic movement outside of the work area. The equipment shall be capable of grinding the surface w ithout causing spalls at cracks, joints, or other locations.

804.03.19 7.4.1.2--Grinding. The grinding areas will be dete rmined by the Contractor and

approved by the Engineer. The Contractor shall develop and submit to the Engineer for approval a Grinding Plan. The Contractor shall allow up to 45 days for the Department to review the Plan prior to starting any grinding operations. This plan shall include as a minimum: (a) Name of the project superintendent in charge of the grinding operation.

b.List and description of a ll equipment to be used.
c.Maximum depth of each pass allowed by the grinding equipment.
d.Maximum width of each pass allowed by the grinding equipment.
e.Details of a sequence of the grinding operation.
f.Complete data from Profilograph runs, ba sed on a 0.3 inch bump height, for each wheel path over the entire bridge including bridge end slabs, which shall include profile index, bump locations (in stations), bump heights and proposed final cross-slopes. When a computerized profilograph is used, a complete printout of the profile including the header information for each wheel path will be required. (g) Data showing reinforcing steel clear ance in all areas to be ground.
h.A detailed drawing of the deck showing areas to be ground with station numbers and grinding depths clearly indicated.
i.A description of grinding in areas where drains are in conflic t with grind areas.
j.Details of any changes in deck dr ainage, anticipated ponding, etc. The Engineer will evaluate the grinding pl an for conformance with the plans and specifications, after which the Engineer will notify the Contractor of any additional information required and/or changes that may be needed. Any part of the plan that is unacceptable will be rejected and the Contractor shall submit changes fo r reevaluation. All approvals given by the Engineer shall be subject to trial and satisfactory performance in the field, and shall not relieve the Contractor of the responsibility to satisfactorily complete the work. The construction operation shall be scheduled and proceed in a manner that produces a uniform finished surface. Gri nding will be accomplished in a manner that eliminates joint or crack faults while providing positive latera l drainage by maintain ing a constant cross- slope between grinding extremities in each la ne. Auxiliary or ramp lane grinding shall transition as required from the mainline edge to provide positive drainage and acceptable riding surface. The operation shall result in a finished surface that conforms as close as possible to the typical cross-section and the requirements specified in S ubsection 804.03 .19.7.4.1.3. The Contractor shall establis h positive means for removal of grinding resi due. Residue shall not be permitted to flow across lanes used by public traffic or into gutters or drainage facilities.

804.03.19 7.4.1.3--Final Surface Texture. The grinding process shall produce a finish

surface that is as close as po ssible to grade and uniform in appearance with a longitudinal line type texture. The line type texture shall contain parallel longitudinal corrugations that present a narrow ridge corduroy type appearance. The peaks of the ridges shall be approximately 1/16 inch higher than the bottoms of the grooves with approximately 53 to 57 evenly spaced grooves per foot. Grinding chip thickness shall be a minimum of 0.080 inches thick. The finished bridge decks and bridge end slabs shall be retested for riding quality using a Contractor furnished profilograph meeting the requirements of Subsection 804.03.19.7.5. The finished results shall me et the followi ng conditions:

a.Individual bumps or depressions shall not exceed 0.3 inches when measured from a chord length of 25 feet.
b.The final index value for the bridge deck and bridge end slabs shall be an average of both the right and left wheel paths of each lane and shall not exceed 65 inches per mile. The final profilogram will be furnished to the Engineer for informational purposes.

804.03.19 7.5--Prof ilograph Requirements . The smoothness of the bridge deck will be

determined by using a California Profilograph to produce a profilogram (profile trace) at each designated location. The surface shall be tested and corrected to a smoothness index as described herein with the exception of those locations or specific projects that are excluded from a smoothness test with the profilograph. The profilograph, furnished and operated by the Contractor under supervision of the Engineer, shall consist of a frame at least 25 feet in length supporte d upon multiple wheels having no common axle. The wheels shall be arranged in a staggered pattern so that no two wheels will simultaneously cross the same bump. A profile is to be recorded from the vertical movement of a sensing mechanism. This profile is in re ference to the mean elevation of the contact points established by the support wheels. Th e sensing mechanism, located at the mid-frame, may consist of a single bicycle-type wheel or a dual-wheel assembly consisting of either a bicycle-type ( pneumatic tire) or solid rubber tire vertical sensing wheel and a separate bicycle-type (pneumatic tire) longitudinal sensing wheel. The wheel(s) shall be of such circumference(s) to produce a profilogram recorded on a scale of one (1) inch equal to 25 feet longitudinally and one (1) inch equal to one (1) inch (full scale) vertically. Motive power may be provided manually or by the use of a propulsion unit attached to the center assembly. In operation, the profilograph shall be moved longitudinally along the pavement at a speed no greater than 3 MPH so as to reduce bounce as much as possible. The testing equipm ent and procedure sha ll comply with the requirements of Department SOP. The Contractor may elect to use a computerized version of the profilo graph in lieu of the standard profilograph. If the computerized version of the profilograph is used, it shall meet the requirements of Subsection 804.03.19.7.5.1.

804.03.19 7.5.1--Computerized Profilograph.

804.03.19 7.5.1.1--General.

The computerized profilograph, furnished and operated by the Contractor under the supervision of the Engineer, shall be equipped with an on-board computer capable of meeting the follo wing conditions of this subsection. Vertical displacement shall be sampled every th ree (3) inches or less al ong the bridge deck. The profile data shall be bandpass filtered in the computer to remove all spatial wavelengths shorter than two (2) feet. This shall be accomplished by a third order, low pass Butterworth filter. The resulting band limi ted profile will then be computer analyzed according to the California Profilograph reduc tion process to produce the required inches per mile index. This shall be accomplished by fitting a linear regression line to the length of bridge. This corresponds to the perfect placement of the blanking band bar by a human trace reducer. Scallops above and below the blanking band are then detected and totaled according to the California prot ocol. Bump/Dip analysis sha ll take place according to the California Profilograph reduction process. The computerized profilograph shall be capabl e of producing a plot of the profile and a printout that gives the following data: Stations every twenty five (25) feet, bump/dip height and bump/dip length of specification (3/10 of an inch and 25 feet respectively), the blanking band width, date of measurement, total profile index in inches per mile for the measurement, total length of the measuremen t, and the raw inches for each segment.

804.03.19 7.5.1.2--Me chanical Requirements. The profilograph sha ll consist of a frame

twenty five (25) feet long supported at eac h end by multiple wheels. The frame shall be constructed to be easily dismantled for transpor ting. The profilograph shall be constructed from aluminum, stainless steel and chromed parts. The end support wheels shall be arranged in a staggered pattern such that no tw o wheels cross a transverse joint at the same time. The relative smoothness shall be measured by the vertical movement of an eight (8) inch or larger diameter sensing wheel at the midpoint of the 25-foot frame. The horizontal distance shall be measured by a twenty (20) inch or larger diameter pneumatic wheel. This profile shall be the mean elevation referenced to the twelve points of contact with the pavement established by the support wheels. Recorded graphical tra ce of the profile shall be on a scale of one inch equals one inch (f ull scale) vertical motion of the sensing wheel and one inch equals 25 feet horizontal motion of the profilograph.

804.03.19 7.5.1.3--C omputer Requirements. The computer sha ll have the ability to

produce output on sight for verification. The computerized output shall indicate the profile index for each specified section of bridge d eck. Variable low and high pass third-order Butterworth filtering options shall be available. The printout shall be capable of showing station marks automatically on the output. Bl anking band positioning for each specified section of the bridge deck shall be placed a ccording to the least squares fit line of the collected data. Variable bump and dip tests shall be available to show “must correct” locations on the printout. The computer must have the ability to display on screen “must correct” conditions and alert the user with an audible warning when a “must correct” location has been located. The computer must ha ve the ability to store profile data for later reanalysis. The measurement program must be menu driven and PC compatible. User selected options, identification, calibration factors, and time and date stamps shall be printed at the top of each printed report for verification. The control software must be upgradeable. A power source shall be included for each profilograph and be capable of supplying all power needs for a full days testing.

804.03.19 8--Finishing Horizontal Surfaces of Footings or Top Slabs of Box Bridges,

Culverts, or Other Structures. The finishing of ho rizontal surfaces of footing or top slabs of box bridges, culverts, or other structures shall be achieved by placing an excess of material in the form and removing or striki ng off the excess with a template, forcing the coarse aggregate below the mortar surface. After the concrete has been struck off the surface shall be given a Class 6 finish.

804.03.19 9--Finishing Expo sed Surfaces of Sidewalks. After the concrete has been

deposited in place it shall be consolidated and the exposed surface shall be given a Class 6 finish. An edging tool of the required radius sh all be used on all edges and at all expansion joints. The surface shall have a granular texture that will not be slick when wet. Sidewalk surfaces shall be laid out in blocks with an approved grooving tool as shown on the plans or as directed.

804.03.20 Opening Bridges.

804.03.20 1--Public Traffic. Unless otherwise specified, concrete bridge decks shall be

closed to public highway traffic for a period of at least 21 days after placing concrete.

804.03.20 2--Construction Traffic. Unless otherwise specifie d, concrete bridge decks

shall be closed to construction traffic for the time required for curing in Subsection

804.03.17 and the minimum required compressive strength for the concrete placed is obtained.

804.03.21 Final Cleanup. Upon completion of the work all equipment, surplus materials,

forms, and waste material shall be removed, th e bridge cleaned, and the site of the work given a final cleanup.

804.03.22 Precast-Prestresse d Concrete Bridge Members.

804.03.22 1--General. All installations and plants for the manufacture of precast-

prestressed bridge members shall be PCI (P recast / Prestressed Concrete Institute) Certified. Bridge members manufactured in pl ants or installations no t so approved will not be accepted for use in the work. The Contr actor or other manufacturer shall employ a technician skilled in the adop ted system of prestressing to supervise the manufacturing operations. This technician shall be cer tified according to the guidelines of this specification. The Contractor shall develop and implement a Quality Control Program as per Division I of PCI Quality Control Manual , Latest Edition. The Quality Control Program shall be submitted to the District Materials Engineer for approval.

804.03.22 2--Stressing Requirements. The jacks for stressing shall be equipped with

accurate calibrated gauges for registering the jacking pressure. Mean s shall be provided for measuring elongation of strands to at least the nearest 1/16 inch. Prior to beginning work, the Contractor or manufacturer shall have all jacks to be used, together with their gauges, ca librated by an approved labora tory. All jacks and gauges shall have an accuracy of read ing within two percent. The te sting agency shall furnish the Engineer a statement certifying that the jacks and gauges meet this requirement. During the progress of the work, if a gauge appears to be giving erratic results or if the gauge pressure and elongations indicate materially differing stresses, recalibration will be required. Calibration of jacks and gauges shall be rep eated at intervals deemed necessary by the Engineer. These intervals for calibration shall not exceed one year. Shop drawings of prestressed beams, including an erection plan, shall be submitted in duplicate to the Bridge Engineer for approval prior to manufacture of members.

804.03.22 2.1--Methods. Plans for the particular bridge members will show prestressing

by one of the following methods:

A.Pretensioning. The prestressing strands are stressed initially . After the concrete is placed, cured, and has attained the compressive strength shown on the plans, the stress is transferred to the member. The method used for pretensions shall be in accordance to

Division V — of PCI Quality Control Manual, Latest Edition.

B.Posttensioning. The posttensioning tendons are installed in voids or ducts and are stressed and anchored after development of the compressive strength specified on the plans. The voids or ducts are then pressure grouted.
C.Combined Method. Part of the reinforcing is pretensioned and part posttensioned. Under this method all applicable requirements for the two methods specified shall apply to the respective stressing elements being used.

804.03.22 2.2--Alternate Details for Prestressed Members. In the event that the

Contractor / Manufacturer desires to use mate rials or methods that differ in any respect from those shown on the plans or described in these specifications, the Contractor shall submit for approval full plan details on accept able tracings suitable for reproduction and specifications that shall become the property of the Department. In order for alternate materials and/or methods to be considered, th ey will be required to comply fully with the following:

a.Provisions equal to those stipul ated in these specifications.
b.Current AASHTO Specifications.
c.Recommendations of materials manufacturer.
d.Camber tolerance of beams and spans shown on plans. Note: Alternate materials and methods will not be authorized on Federal-Aid Projects. The Engineer shall be the sole judge as to the adequacy and propriety of any variation of materials or methods.

804.03.22 2.3--Stressing Procedure.

A.General. Stressing shall be performed by su itable jacks working against unyielding anchorages and capable of maintaining the requi red stress for an inde finite period without movement or yielding. Strands may be stressed singularly or in a group. The tension to be applied to each strand shall be as shown on the plans. The tension shall be measured by both jacking gauges and elongations in the strands and the result shall check within close limits. It is anticipated that there will possibly be a difference in indicated tension between jack pressure and elongation of about five (5) percent. In this event, the discrepancy shall be placed on the side of slight over stress rather than understress. In the event of an apparent discrepancy between gauge pressure and elongation of as much as five (5) percent, the entire operation shall be carefully checked, and the source of error determined before proceeding further. Elongation is to be measured after the strands have been suitably anchored, and all possible slippage at the anchorages has been eliminated. In all stressing operations, the stressing force shall be kept as nearly symmetrical about the vertical axis of the member as practicable.
B.Pretensioning. All strands to be prestressed sh all be brought to a uniform initial tension prior to being given their full preten sioning. This uniform initial tension of approximately 1000 to 2000 pounds shall be measured by suitable means such as a dynamometer so that its value can be used as a check against elongation computed and measured. After the initial tensioning, the strand or group shall be stressed until the required elongation and jacking pressure is within the li mits specified. When the strands are stressed in accordan ce with the plan requirements and these specifications and all other reinforcing is in place, the concrete shall be placed in the prepared forms. Strand stress shall be maintain ed until the concrete between anchorages has attained the required compressive strength as determined by cylinder tests, after which the strands shall be cut off flush with the ends of column members, and cut as shown on the plans for beams, girders, etc. Strands shall be cut or released in such a manner that eccentricity of prestress will be kept to a minimum and no damage to the member will result. The strand cutting pattern shall be as shown on the plans or as approved by the Bridge Engineer.
C.Posttensioning. For all posttensioning tendons/bars the anchor plates shall set exactly normal in all directions to the axis of the tendon/bar. Parallel wire anchorage cones shall be recessed within the beams. Tensioning shall not take place until the concrete has reached the compressive strength shown on the plans. Elongation and jacking pressures shall make ap propriate allowance for all possible slippage or relaxation of the anc horage. Posttensioning tendons/bars shall be stressed in the order and manner shown on the plans. The units shall be tensioned until the required elongations and jacking pressures are attained and reconciled within the limits sp ecified in Subsection 804.03.22.2.3(A) with such overstresses as approved by the Engineer for anchorage relaxation. Independent references shall be established adjacent to each anchorage to indicate any yielding or slippage that may occur between th e time of initial stressing and final release of the strands. Straight tendons/bars may be tensioned from one end. Unless otherwise specified, curved tendons shall be stressed by jacking from both ends of the tendons.
D.Combined Method. In the event that girders are manufactured with part of the reinforcement pretensioned and part posttensioned, the applicable portions of the requirements listed herein shall apply to each type.

804.03.22 3--Manufacture.

804.03.22 3.1--Forms. The forms used for precast-prestressed bridge members shall meet

the requirements of Division II of the PC I Quality Control Manual, Latest Edition.

804.03.22 3.2--Placing and Fastening Steel. Placing and fastening of all steel used for

precast-prestressed bridge members shall meet the requirements of Division V of the PCI Quality Control Manual, Latest Edition.

804.03.22 3.3--Holes for Prestressing Tendons/Bars. Holes provided in girders for

prestressing tendons/bars shall be formed by means of inflatable rubber tubing, flexible metal conduit, metal tubing, or other approved means.

804.03.22 4--Pla cing and Curing Concrete.

804.03.22 4.1--Placing. The placing of concrete shall meet the applicable requirements of

Division III — of PCI Quality C ontrol Manual, Latest Edition.

804.03.22 4.2--Curing. Initial and accelerated curing of all members shall meet the

applicable requirements of Division IV of PCI Quality Control Manual, Latest Edition except for the requirements listed in this subsection. The source of heat for accelerated cure shal l be steam. Calibrated thermocouples shall be implanted into the concrete members to m onitor areas expected to have maximum and minimum heat. Curing methods and procedures listed in the prestress producer’s PCI Quality System Manual shall be approved by the Department before their im plementation.

804.03.22 4.3--Removal of Side Forms. Side forms may be removed after the concrete

has attained sufficient strength to maintain a true section. In order to obtain "sufficient strength," it may be necessary to cure members for 12 hours or more as prescribed in Subsection 804.03.22.4.2, or to attain a minimum compressive strength of 1000 psi. If high-early-strength concrete is obtained by use of low slump (0 to 1.5-inch) concrete, vacuum process, or other approved methods, side forms may be removed earlier; however, approval of the methods and revision from normal schedules will be made only after inspections by the District Materials Engineer and Materials Di vision have determined that satisfactory results will be attained by the methods and sc hedules proposed.

804.03.22 4.4--Grouting. The holes through posttensione d members in which the tendons

are installed shall be equipped with approved grouting vents. All prestressing tendons to be bonded shall be free of dirt, loose rust, greas e, or other deleterious substances. Before grouting, the ducts shall be free of water, dirt, and other foreign substances. The ducts shall be blown out with compressed air until no water come s through the duc ts. For long members with draped tendons, an open tap at low points may be necessary. After completion of stressing, the annular space between sides of tendon and sides of hole shall be grouted as outlined in the following paragraphs. With the grouting vent open at one end of the core hole, grout shall be applied continuously under moderate pre ssure at the other end until all entra pped air is forced out through the open grout vent, as evidenced by a steady stream of grout at the vent. The open vent shall then be closed under pressure. The grouting pressure shall be gradually increased to a refusal of at least 75 psi and held at this pressure for approximately 10 seconds, and the vent shall then be clos ed under this pressure. Hydraulic cement grout shall consist of a mixture of: 1 part Type 1 hydraulic cement 1/4 part fly ash 3/4 part washed sand * 4 to 6 gallons of water per bag of cement. * all passing No. 16 sieve and not more than 5% retained on No. 30 Water-reducing admixtures, subject to approval by the Engineer, shall be used in accordance with the manufacturer's recommendations. The grout shall be mixed in a mechanical mixer, shall have the consistency of heavy paint, and shall be kept agitated until placed. Members shall not be moved before the grout ha s set, ordinarily at least 24 hours at 80°F or higher.

804.03.22 5--Finishing and Marking. Units shall be given a Class 1 finish at the plant

and shall be given a Class 2 finish after erection when required. Recesses in girders at end of diaphragm bars , holes left by form ties, and other surface irregularities shall be caref ully cleaned and patched w ith an approve d non-shrink commercial grout or a non-shrinkage mortar of th e following composition: 1 part Type 1 hydraulic cement 1 1/2 to 2 parts fine sand 1/2 to 3/4 ounces aluminum powder per bag of cement Approved admixture per Subsection 713.02. Sufficient water to produce a wo rkable but rather stiff mix. The units shall be clearly marked in accordance with Department’s Materials Division Inspection, Certification and Testing Manual .

804.03.22 6--Handling, Storage, and Installation. Posttensioned members may be

handled immediately after completion of stressi ng and grout has set. Pretensioned members may be handled immediately after release of te nsioning. In either case, the members shall have developed a minimum compressive strength of 4000 psi prior to handling. In the event stressing is not done in a continuous operation, members shall not be handled before they are sufficiently stressed, as determined by the Engineer, to sustain all forces and bending moments due to handling. In the handling, storage, and transporting of beams or girders, they shall be maintain ed in an upright position (pos ition as cast) at all times and shall be picked up from points within distance from beam ends equal to beam depth or at pick-up points designated on the plans. Disreg ard of this requirement and dropping of units may be cause for rejection, whether or not inju ry to the unit is apparent. Piles shall be picked up and loaded for shipment at points shown by the suspension diagram on the plans. Extreme care shall be used in handling and stor ing piles to prevent damage. The dropping of a pile may be cause for rejection of same, wh ether or not there is ap parent injury to the member. Care shall be exercised during the storage, ho isting, and handling of precast units to prevent damage. Damaged units shall be replaced by the Contractor at no additional costs to the State. When members are stacked for storage, each la yer shall be supported at or near the pick- up points. Supports sh all be carefully placed in a vertical line in order that the weight of any member will not stress an underlying member. To preven t damage in moving members it is suggested that rigid supports be covere d with a cushion of w ood or other resilient material. Members shall not be transported until at leas t one day after the concrete has reached a compressive strength of 5000 psi or greater strength when shown on the plans. Piles used in salt water shall not be driven until concrete is seven days old, and air-entrained concrete shall be used in such piles. After prestressed concrete void ed slab units are set, dowel ed and bolted in their final position, the keyways and dowel holes shall be filled with an approv ed non-shrink grout. Traffic shall not be permitted on the spans for 24 hours after grouting, and heavy construction equipment exceedin g 15 tons will not be permitted on the spans for a period of 72 hours after grouting. Adjacent slab units that mismatch more than one-fourth inch shall be adju sted prior to grouting of the shear keys. The maximum deviation from cross-section and grade (exclusive of camber) at any point shall not exceed one-fourth inch. When the surface is checked with a ten-foot straightedge app lied both parallel and perpendicular to the centerline, the variance shall not exceed one-fourth inch. In addition to the requirements set out in this section, th e applicable requirements of Section 803 shall apply.

804.03.22 7--Tolerances for Accepting Precast Prestressed Concrete. Members shall

meet the dimension tolerances set by Division VII of PCI Quality Control Manual, Latest Edition.

804.03.22 8--Testing of Materials. Concrete and aggregate testing shall meet the

requirements of Division VI of PCI Quality Control Manual , Latest Edition, except that the concrete mixture design shall meet the re quirements of Subsection 804.02.10. Also, in addition to concrete compressive tests samples made for detensioning and 28-day strength, test samples shall be made and tested in or der to prove compliance to the requirements of Subsection 804.03.22.6 for handling and shipping prestressed members. Compressive strength test cylinders for detensioning, hand ling and shipping shall receive the same type curing as the prestressed members for which they represent. Compressive strength samples shall be made each day for each prestress casting bed.

804.03.22 9--Testing Personnel. Technicians testing hydraulic cement concrete used in

the production of precast-prestressed me mbers shall be PCI Quality Control Technician/Inspector Certified. Each producer of precast-prestressed members shall have at least one PCI Level II certified technici an on site during production for Department projects.

804.03.22 10--Documentation. The Precast-Prestressed Producer for each precast-

prestressed concrete bridge member shall ma intain documentation as set forth in the Department’s Materials Division Inspection, Certification and Testing Manual . Testing and inspection record forms shall be approved by the Central Laboratory and as a minimum contain information listed in Di vision VI of PCI Quality C ontrol Manual, Latest Edition.

804.03.22 11--Use in the Work. Before any precast-prestressed member is incorporated

into the work, documentation as described in Subsection 804.03.22.10 is required along with visual inspection of the member at th e bridge construction site. Project Office personnel as per the Department’s Materials Division Inspection, Certification and Testing Manual will make visual inspection of the pr ecast-prestressed member at the bridge construction site.

804.04 Method of Measurement. Concrete, complete and accepted, will be measured in

cubic yards. The concrete volume will be co mputed from the neat dimensions shown on the plans, except for such variations as may be ordered in writing by the Engineer. The quantity of concrete involved in fillets, scorings, and chamfers one square inch or less in cross-sectional area will be neglected. De ductions shall be made for the following:

a.The volume of structural steel, including steel p iling encased in concrete.
b.The volume of timber piles encased in concrete, assuming the volume to be 0.80 cubic foot per linear foot of pile.
c.The volume of concrete p iles encased in concrete. The volume of concrete in the fillets between the bottom of nominal slab and the top of the beams has been estimated by using one half (1/2) of the fillet height at the bearing multiplied by the top flange width for the full length of the beam. This volume shall be used for final pay quantity. Th e calculated volume of concrete may or may not be equal to the actual volume of concrete that is placed in the fillet. The volume of fillet concrete used for final pay quantity is based upon the plan f illet height at bearing and a zero inch (0”) plan fillet height at midspan. If the Contractor feels that variations from these dimensions will be encountered, th ey should adjust th eir bid accordingly. No deduction will be made for the volume of concrete displaced by steel reinforcement, floor drains, or expansion joint material that is one inch or less in width normal to the centerline of the joint. Where railing is bid as a separate item, that portion of the railing above the top of the cu rb, above the surface of the sidewalk , or above the bridge roadway, as the case may be, will not be included in the measurement of concrete, but will be measured as railing. Massive pylons or posts that are to be excluded from payment for railing and are intended to be measured for as concrete will be so noted on the plans. When shown on the plans or directed by th e Engineer, concrete placed as a seal for cofferdams will be measured by the cubi c yard actually in place, except that no measurement will be made of seal concrete pl aced outside of an area bounded by vertical planes 18 inches outside the neat lines of th e footing as shown on the plans or as directed and parallel thereto. Reinforcing steel will be measured and paid for in pounds as set out in Section 805. Unless otherwise specified, stru ctural steel will be measured and paid for as set out in Section 810. Excavation for bridges will be measured and paid for as in Section 801. Piling will be measured and paid for as set out in Sections 802 and 803. Railing will be measured and paid for as set out in Section 813. Prestressed concrete beams and plank will be measured by the linear foot. Prestressed concrete voided sl ab units, interior and exteri or with railing, and precast concrete caps, intermediate and end cap with winged abutment wall, of the size and type specified will be measured by the unit complete in place an d accepted. Railing, winged abutment walls, grout, tie rods, nuts, washers, bearing pads and other appurtenances will not be measured for separate payment.

804.05 Basis of Payment. Concrete will be paid for at the contract unit price per cubic

yard for the class or classes specified, complete in place. Prestressed concrete beams and plank will be paid for at th e contract unit per linear foot of specified size and type. Prestressed concrete voided slab units and precas t caps will be paid for at the contract unit price per each for the specified types and sizes, complete in place and accepted, which price shall be full co mpensation for furnishing, hauling and erecting the members, including all prestressing reinforcement and other reinforcement in the members. Payment at the contract unit price shall be full compensation for furnishi ng all materials, equipment, tools, labor and incidentals n ecessary to complete the work. Payment will be made under: 804-A: Bridge Concrete, Class ____ - per cubic yard 804-B: Box Bridge Concrete, Class ___ - per cubic yard 804-C: Length Prestressed Concrete Beam, Type ___ - per linear foot 804-D: Length Prestressed Concrete Plank - per linear foot 804-E: Length Prestressed Concrete Voided Slab, Size Interior - per each 804-F: Length Prestressed Concrete Voided Slab, Size Exterior - per each 804-G: Length Precast Concrete Caps, End Unit with Wall - per each 804-H: Length Precast Concrete Ca ps, Intermediate Unit - per each SECTION 805 - REINFORCEMENT

805.01 Description. This work consists of furnishi ng and placing steel reinforcement for

bridges in accordance with these specifications and in reasonably close conformity with the dimensions, bending, spacing, and other requirements shown on the plans.

805.02 Materials. Materials used shall conform to the requirements of Section 711.

Supports for bar reinforcement shall meet the requirements of Subsection 711.02.7.

805.02.1 Order Lists. Before ordering reinforcement, all order lists and bending

diagrams shall be furnished by the Contractor for the approval of the Engineer, and no materials shall be ordered until the lists and bending diagrams have been approved. All expense incident to the revision of material furnished in accordance with such lists and diagrams to make it comply with the design drawings shall be borne by the Contractor.

Source: Mississippi Standard Specifications for Road and Bridge Construction, 2017 Edition. Pages 9501013 of 1,113.