General Provisions (00100-00999)

601Structural Concrete

MS · 2017 Standard SpecificationsBook pages 392394View official source ↗

Division 600 — Division 600

Division 600 — Incidental Construction

600.01 General . Unless otherwise specified, all testing of hydraulic cement concrete in

Division 600 — shall be in accordance with the requirements of Subsection 601.02.1.

SECTION 601 - STRUCTURAL CONCRETE

601.01 Description . This work consists of furnishing and placing hydraulic cement

concrete for specified structures in accordan ce with these specificatio ns and in reasonably close conformity with the lines, grades, and dimensions shown on the plans or established by the Engineer. Structural concrete will be divided into two groups. One group will be designated as Structural Concrete. The other group will be designated as Structural Concrete, Minor Structures. Unless otherwise specified in the contract, Structural Concrete, Minor Structures, will include inlets, catch basins, junction boxes, pipe headwalls, and pipe collars, regardless of the concrete quantity re quired for each of these structures; and other small structures containing less than 3.00 cubic yards of concrete each.

601.02 Materials .

601.02.1 General . Materials for structural concrete and their use, care, and handling shall

be in accordance with Subsection 804.02. Sa mpling and testing will be in accordance with TMD-20-04-00-000 or TMD-20-05-00-000, as applicable.

601.02.2 Classification of Concrete . Concrete for this work shall be the class specified

on the plans or in the bid schedule of the cont ract. Classes of concrete are identified in Subsection 804.02.6.

601.02.3 Precast Units . Design standards normally contem plate that structural concrete

will be cast in place. However, the Contractor may request approval from the Engineer to furnish and install precast units in lieu of cast-in-place units. The request shall be accompanied by detailed drawings of the pr ecast units and design data certified by a registered Professional Engineer as to structural and functional adequacy. The foundation for precast units shall be carefu lly shaped to the precise contour and grade of the bottom of the unit before the unit is placed. Precast units which are to be joined to other units shall be designed and manufactured with proper and adequate joints. Joints shall be sealed with a joint material meeting the applicable requirements of Section 707. MDOT Drawing Sheet Nos. PCU-1 and PCU-2 address Department’s approved precast drainage units. The Contractor must make a request to the Project Engineer for approval to use precast units other than the ones show n on Drawing Sheet No . PCU-1 or PCU-2. Precast drainage unit tops are only allowed on units shown on Drawing Sheet No. PCU-1. Cast-In-Place drainage unit tops are required on units shown on Drawing Sheet No. PCU-2. No additional payment will be allowed for precast units approved for use. Pay items and quantities will be as in cast in place in accordance with design standards.

601.03 Construction Requirements .

601.03.1 Composition of Concrete . The composition of the concrete shall be in

accordance with Section 804.

601.03.2 Batching . Measuring and batching of component materials shall be in

accordance with the ap plicable provisions of Section 804.

601.03.3 Mixing and Conveying Concrete . Concrete shall be mixed and conveyed in

accordance with the app licable provisions of Subsection 804.03.5.

601.03.4 Cold or Hot Weather Concreting . Requirements for placement, protection,

and curing of concrete during cold or hot weather are stipulated in Subsection 804.03.16. 601.03.5--Consistency. The slump of the concrete, determined in accordance with the provisions of Subsection 700.03, shall confor m to the applicable requirements of Section 804.

601.03.6 Falsework and Forms .

601.03.6 1--Falsework . Falsework shall be in accordance with the appli cable provisions

of Subsection 804.03.13. 601.03.6.2--Forms . Forms shall conform to the requirements of Subsection 804.03.14.

601.03.6 3--Removal of Falsework, Forms, and Housing . The removal of falsework,

forms, and the discontinuance of heating, shall be in accordance with the provisions and requirements of Subsection 804.03.15, excep t that the concrete shall conform to the following compressive strength requirements: Wingwall and Wall Forms not Un der Stress ....................................... 1000 psi Wall Forms under Stre ss ..................................................................... 2200 psi Backfill and Cover cl ear ...................................................................... 2400 psi In lieu of using concrete strength cylinders to determine when falsework, forms, and housings can be removed, an approved maturity meter may be used to determine concrete strengths by inserting probes into concrete placed in a structure. The minimum number of maturity meter probes required for each stru ctural component shall be in accordance with Subsection 804.03.15. Procedures for using the maturity meter and developing the strength/maturity relationship shall follow the requirements of Subsection 804.03.15. Technicians using the maturity meter or calculating strength/maturity graphs shall meet the requirements of Subsection 804.03.15. When the walls and top slab of box culverts and box bridges are not to be poured monolithically, extreme care shall be used when forming and pouring the top slab on walls in which the concrete has not attained its full design strength. In order to prevent damage to fresh concrete, either of the following methods of forming and pouring may be used:

a.Subject to approval by the Engineer, the wall forms and deck forms may be so constructed and separately supported and braced that the walls may be poured and the wall forms removed as for wall forms not under stress. The Engineer may require a detailed plan of the proposed method of forming for approval. When this method of forming is used, the deck forms shall be in place and adequately and independently supported throughout before pouring the walls. Deck forms shall overlay the top edge and be flush w ith the face of the inside wall forms, but shall not be dependent upon any part of the inside wall forms for support. The intersection of the wall and deck forms shall be mortar tight. The wall forms may be constructed slightly less than the specified inside clear height of the structure and wedged upward from the bottom of the riser wall to permit easier removal. When this method is used, the concrete in the wall shall be poured flush with the top of the deck form.
b.At the option of the Contractor, the walls may be formed, adequately braced, and poured before the deck forms are in place. In this case the forms may be removed as for walls not under stress. Before erecting any part of the forming for the top slab, the concrete in the walls shall have attained the age or the strength specified for the removal of wall forms under stress.
c.The Contractor may elect to form and adequately support and brace the wall and deck forms as a composite unit before pouring the walls. In this case the outside forms may be removed as indicated for wall forms not under stress provided adequate provisions are made for form ing the outer (vertical) surfaces for the subsequent deck pour. The inside wall forms shall remain in place as indicated for wall forms under stress.

601.03.6 4--Damage to Previously Placed Concrete . In the event previously placed

concrete is damaged, all work on the affe cted structure shall cease immediately for an engineering assessment of the damage and the corrective work to be performed. No additional work shall be performed until this determination has been made, and the Engineer has given the Contractor approval to proceed with the corrective work and subsequent construction. All corrective work required shall be performed by the Contractor at no additional cost to the State.

601.03.7 Foundations and Footings . Foundations for structures shall be prepared in

accordance with the requ irements and provisi ons of Section 206. All footings shall be poured "dry." Where f ootings can be placed in the "dry" without the use of cribs or cofferdams, the Engineer may permit back forms to be omitted, and concrete poured against the faces of the excavation.

601.03.8 Placing Reinforcing Steel. Reinforcing steel shall be placed in accordance with

the requirements of Section 602 and as shown on the plans. 601.03.9--Handling an d Placing Concrete . Handling and placing concrete shall be in accordance with the provisions of Subsecti on 804.03.6.

601.03.10 Expansion and Fixed Joints . All expansion and fixed joints shall conform to

the applicable provisions of Subsection 804.03.18. 601.03.11--Finishing Concrete Surfaces . Unless otherwise author ized, the surface of the concrete shall be finished immediately after form removal. Surface finishes shall conform to the appli cable provisions of Su bsection 804.03.19.

601.03.12 Curing Concrete . Concrete shall be cured in accordance with the provisions

of Subsection 804.03.17. 601.04--Method of Measurement . Accepted quantities of structural concrete will be measured by the cubic yard. Except for changes ordered in writing by the Engineer, the neat dimensions shown on the plans will be used for computing volumes. The quantity of concrete in fillets, scorings, and chamfers one square inch or less in cross sectional area will be neglected in measurements. No deductions will be made for the volume of concrete displaced by reinforcement, pipe or other conduits less than eight inches in nominal diameter, pipe posts, structural steel posts, or joint material. When both Pay Item Numbers 601-A and 601- B are included in the contract, measurement of concrete for Pay Item No. 601-B will be limited to inlets, catch basins, junction boxes, pipe headwalls, and pipe collars, regardless of the concrete quantity required for each of these structures; and other small structures containing less than 3.00 cubic yards of concrete each.

601.05 Basis of Payment . Structural concrete will be paid for at the contract unit price

per cubic yard which shall be full compensation for completing the work. Payment will be made under: 601-A: Class ___ Structural Concrete - per cubic yard 601-B: Class ___ Structural Concrete, Minor Structures - per cubic yard SECTION 602 - REINFORCING STEEL

602.01 Description . This work consists of furnishing and placing reinforcing steel in

accordance with these specifications and in reasonably close conformity with the dimensions, bending, spacing, and other requirements shown on the plans. Synthetic structural fibers meeting the requirements of Subsection 711.04 may be used in lieu of wire mesh in some items of construction. Substitution of fibers for wire mesh will be allowed in the construction of paved ditches, paved flumes, paved inlet apron, driveways, guard rail anchors and pile encase ments. Substitution in any other items of work must be approved by the State Construction Engineer prior to use.

602.02 Materials . Reinforcing steel shall conform to the requirements of Section 711

and Subsection 805.02.

602.03 Construction Requirements .

602.03.1 Bar List and Order Lists . The bar lists and bending schedules shown on the

plans are primarily for the purpose of estima ting quantities. Lengths of box culverts and box bridges, and depths of inlets, etc. shown on the plans are also approximate. The Contractor shall verify the quantity, size, and shape of the reinforcement for compliance

Source: Mississippi Standard Specifications for Road and Bridge Construction, 2017 Edition. Pages 392394 of 1,113.