206.01 Description
This work consists of constructing, maintaining, and removing a detour within the prescribed corridor and as specified in the contract.
206.02 Reserved
206.03 Construction
206.03.1 General
Construct the detour to the lines and grades shown in the contract and cross sections. Provide surfacing materials and thicknesses as specified in the contract. Remove and stockpile topsoil within areas of the detour that require excavation prior to detour grading operations. Complete detour grading operations in accordance with Section 203. In wetland or riparian areas as shown in the contract, cut shrubs impacted by temporary detour construction flush with the ground, do not grub. Use geotextile, or other approved separation, between the natural ground and temporary detour fill to provide minimal disturbance to the existing ground.
206.03.2 Design
Construct the temporary detour within the R/W or permit area and to the lines and grades shown in the contract and cross sections or as approved by the Project Manager. Surface the detour as indicated in the contract. The method required for conveyance of a waterway is not included in the Preconstruction authorizations and permits issued by resource and regulatory agencies. Prior to commencing any work on the detour, determine a preferred method of conveyance and submit this with the Contractor’s temporary facilities joint application. The submittal will be forwarded to the appropriate resource and regulatory agencies for review and approval.
206.03.3 Submittals
206.03.4 Maintenance
Maintain the detour in accordance with Subsection 104.05 to provide the traveling public with a safe and smooth riding surface. Provide a satisfactory surface similar or better to that which existed on the PTW prior to beginning construction. Repair all damage to the detour and the PTW connections immediately and at no additional cost to the Department. This includes, but is not limited to, damage from washouts, chuckholes, soft spots, guardrail damage, or debris on the roadway. Failure to maintain the detour in a manner that provides the traveling public with a safe and smooth riding surface is cause for the Project Manager to stop work until corrective actions take place. All costs associated with the delay are the Contractor’s responsibility.
206.03.5 Removal
Remove the detour only after the mainline work has been completed and approved by the Project Manager. Fill areas excavated for detour construction and incorporate the material removed from the detour into the mainline embankment. Grade the location impacted by the detour to approximately match its original contours. Place salvaged topsoil over the disturbed area and seed as specified in the contract.
206.04 Method of Measurement
Detour - Construct, Maintain, and Remove will be measured as a lump sum quantity in accordance with Section 109 . Materials, labor, and equipment needed to construct, maintain, and remove the detour are considered incidental to this item of work and will not be measured for payment. No additional measurements will be made for finish grade control or traffic control devices associated with detour construction. Traffic control devices used to maintain traffic after 2020 EDITION V5.1 DETOURS – 206 206-3 detour construction is complete will be measured under the traffic control bid item specified in the contract.
206.05 Basis of Payment
Payment for the completed and accepted quantities is made under the following: Pay Item Pay Unit Detour - Construct, Maintain, and Remove Lump Sum Include all materials, labor, and equipment needed to construct, maintain, and remove the detour in the lump sum bid for Detour - Construct, Maintain, and Remove. Traffic control devices required to construct the detour are considered incidental and will not be paid separately. Traffic control devices required for operation of the detour will be paid under the traffic control item specified in the contract.
Get an email when 206 changes
Montana revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.