605.01 Description

This work is the construction and installation of concrete barrier rail.

605.02 Materials

605.02.1 Concrete

Furnish Class Deck concrete in accordance with Section 551.

605.02.2 Reinforcing Steel

Furnish reinforcing steel in accordance with Section 555 and Subsection 711.01.

605.02.3 Linear Delineation System

Furnish panels in accordance with Subsection 704.04.

605.03 Construction Requirements

605.03.1 Fabrication Submittals

Submit the following information:

1.A tentative fabrication schedule.
2.A mix design in accordance with Section 551.
3.The product data sheet for proposed cure and seal product.
4.Any other information necessary to fabricate and install the product. Do not begin fabrication until the Department approved submittals are received by both the Contractor and the Project Manager. Coordinate the fabrication schedule with the Project Manager.

605.03.2 Sampling, Handling, Batching, and Mixing

Sample, handle, batch, and mix materials for concrete in accordance with Subsection

551.03 3.

605.03.3 Forms and Forming

Meet the form requirements in Subsection 552.03.3.

605.03.4 Placing Concrete

Place concrete in accordance with Subsection 552.03.4 and 551.03.5.

605.03.5 Weather and Temperature Limitations.

Meet the requirements of Subsection 551.03.6 when constructing concrete barrier rail in hot or cold weather conditions.

605.03.6 Curing Concrete Barrier Rail

Cure concrete barrier rail in accordance with Subsection 551.03.7. Apply liquid membrane forming curing compound immediately after form removal. Furnish material in accordance with Subsection 717.01.4 requirements.

605.03.7 Testing and Acceptance of Concrete Barrier Rail

A.Sampling and Testing. Meet all requirements of Subsection 551.03.8(B).
B.Acceptance of Concrete Barrier Rail. Concrete Barrier Rail is evaluated on a lot-by-lot basis in accordance with Subsection 551.03.8(C) for Class Deck Concrete except for the following:
1.An individual lot is defined as 30 concrete barrier rail units or one day’s production, whichever is less. 605 –CONCRETE BARRIER RAIL 2020 EDITION V5.1 605-2
2.A minimum of one standard compressive strength set will be made for each lot.

605.03.8 Form Removal

Remove lateral support forms only when it does not damage the concrete. Do not interrupt curing and protection in excess of 30 minutes for form removal. Replace all damaged units at Contractor expense.

605.03.9 Finish on Exposed Surfaces

Apply an ordinary finish to surfaces not smooth and uniform in texture and appearance in accordance with Subsection 552.03.11.

605.03.10 Handling, Transporting, and Storage

Include on each fabricated piece of barrier rail a permanent identification number representing the date fabricated and Lot number associated with that days pour. Place the number in the same location on each piece. The ID must be visible when the barrier rail is pinned and in place on the project. The number may be cast into the concrete or attached after the curing period is complete. Numbers must be legible. Notify the Department when forms will be stripped, and markings applied. All numbers must be verified by inspection within 48 hours of removal of forms. Track all barrier rail supplied to Department projects. Submit the lots and identification numbers representing all barrier rail to be included for the project. The concrete barrier rail may be moved from the casting area to an adjacent staging area when they have reached 75% of design strength and the strength is adequate to prevent damage. Replace all cracked or broken items at Contractor expense. Handle, transport, and store precast concrete items without damage. Replace or repair all damaged units at Contractor expense. Transport the concrete barrier rail from their casting or adjacent staging location only after strength tests indicate the lot they represent has reached the design strength. If shipping is desired before the Department’s 28-day acceptance tests are performed, supply compressive strength results representing the lot of concrete to the Department indicating design strength has been met. Ensure this testing is conducted by an ACI certified technician. Final acceptance of the concrete barrier rail will be based on the Department’s test results for acceptance.

605.03.11 Install Concrete Barrier Rail

Install concrete barrier rail meeting the contract requirements and the Detailed Drawings .

605.03.12 Reset Concrete Barrier Rail

Reset concrete barrier rail as specified in the contract.

605.03.13 Linear Delineation Systems

Install linear delineation systems in accordance with Subsection 619.03.14.

605.04 Method of Measurement

605.04.1 Concrete Barrier Rail

Concrete barrier rail is measured by each 10-foot (3.05 m) section. Connections to the existing barriers are included in the cost of the rail. Measurement does not include those portions of barrier constructed as an integral part of sign foundations.

605.04.2 Reset Concrete Barrier Rail

Reset concrete barrier rail is measured by each 10-foot (3.05 m) section. 2020 EDITION V5.1 CONCRETE BARRIER RAIL – 605 605-3

605.04.3 Concrete Barrier Rail Transition

Concrete barrier rail transitions are measured by each 10-foot (3.05 m) section.

605.04.4 Concrete Barrier Rail Terminal Section

Concrete barrier rail terminal sections are measured by each 10-foot (3.05 m) section.

605.04.5 Remove Concrete Barrier Rail

Remove concrete barrier rail is measured by each 10-foot (3.05 m) section.

605.05 Basis of Payment

Payment for the completed and accepted quantities is made under the following: Pay Item Pay Unit Concrete Barrier Rail Each Concrete Barrier Rail Transition Each Concrete Barrier Rail Terminal Section Each Remove Concrete Barrier Rail Each

Get an email when 605 changes

Montana revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.