B
HomeLibrariesCopilotSearchProjectsBookmarks
FeedbackHelp Desk
Libraries
Building Codes
Code LibraryIBC — BuildingIRC — ResidentialIFC — FireIPC — PlumbingIMC — MechanicalIFGC — Fuel GasIECC — EnergyNEC — ElectricalModel Codes
Specifications
CSI SpecificationsDOT SpecsTransit SpecsUSACE
Standards
TransportationRailroadFire SafetyAccessibilityStructural
Tools & References
DiagramsAssembliesProductsCalculatorsChecklistsPermits
PricingLog in
Division 10 — Utilities

1078PRESTRESSED CONCRETE MEMBERS

NC · 2024 Standard SpecificationsBook pages 550574View official source ↗

Manufacture sound wall post within the tolerances indicated in Table 1078 -2 and Figure 1078- 1. PRESTRESSED CONCRETE MEMBERS -1 GENERAL This section covers the materials for and the production of precast, prestressed concrete members produced in accordance with the contract. Use prestressing of the pretensioning type in which steel prestressing strands are initially stressed and anchored; the concrete is then placed, vibrated and cured; and when the concrete reaches the required strength, the load is transferred from the ancho rages to the concrete. The intent of this section is to require the producer to provide prestressed concrete members that meet the Standard Specifications and exhibit characteristics that are not objectionable to the Department.

(A)Producer Qualification

Producers of precast, prestressed concrete members are required to establish proof of their competency and responsibility in accordance with the Precast/Prest ressed Concrete Institute’s (PCI) Plant Certification Program to perform work for the project. Certification of the manufacturing plant under the PCI program and submission of proof of certification to the State Materials Engineer is required before begin ning fabrication. Maintain certification at all times while work is being performed for the Department. Submit proof of certification following each PCI audit to the State Materials Engineer for continued qualification. These same requirements apply to p roducers subcontracting work from the producer directly employed by the Contractor. Employ producers PCI certified in Product Group B, Bridge Products and in one of the appropriate categories as listed below:

(1)B2 Prestressed Miscellaneous Bridge Products in cludes solid piles, sheet piles and

bent caps;

(2)B3 Prestressed Straight -Strand Bridge Members includes all box beams, cored slabs,

straight- strand girders and bulb- tees, bridge deck panels, hollow piles, prestressed culverts and straight strand segmental co mponents; or

(3)B4 Prestressed Deflected -Strand Bridge Members includes deflected strand girders

and bulb- tees, haunched girders, deflected strand segmental superstructure components and other post -tensioned elements. Categories for elements not listed above will be as required by the project special provision or plans.

(B)Working Drawing Submittals

Before casting members , submit complete working drawings to the Engineer for approval. The working drawings shall detail the exact location and description of all ca sting holes, attachments and inserts cast in the member for both temporary and permanent applications. The casting holes, attachments and inserts are in association with, but not limited to: fall protection, overhang falsework, metal stay- in-place forms, solar platforms, temporary girder bracing, transit, erection, lifting and handling. If the plan notes indicate that the structure contains the necessary corrosion protection required for a corrosive site, epoxy coat, galvanize or metalize all metallic com ponents except stainless steel and malleable iron components. Electroplating will not be allowed.

-2 MATERIALS Refer to Division 10. Item Section Air Entraining Agent 1024 -3 Chemical Admixtures 1024 -3 Coarse Aggregate 1014 -2 Epoxy Protective Coating 1081 -1 Fine Aggregate 1014 -1 Fly Ash 1024 -5 Ground Granulated Blast Furnace Slag 1024 -6 Miscellaneous Metals 1074 Portland Cement 1024 -1 Prestressing Strand 1070 -5 Reinforcing Steel 1070 Blended Cement 1024 -1 Silica Fume 1024 -7 Structural Steel 1072 Water 1024 -4 Do not make changes in the source of aggregates, cements or admixtures during the casting of members in any one span or substructure unit unless approved by the Engineer. -3 INSPECTION The Department reserves the right to place a duly authorized inspector in the plant at any or all times work related to the production of members for the Department is performed. Notify the Engineer at least 15 business days in advance when such work is scheduled. Provide an office area with an approximate floor space of 100 sf, a desk or drafting table, t wo chairs, telephone, separate dial -up or faster internet access, facilities for proper heating and cooling and adequate lighting at the plant for the exclusive use of the inspector. The I nspector has the authority to reject any or all members not manufactured in accordance with theses pecifications . Approval of any member by the inspector at the plant is in no way final, and further inspection is made at the structure site both before and after the member is placed in the final position. Any member foun d to be defective in any manner at any time is rejected and requires replacement by an acceptable member or repair in a manner approved by the Engineer. Do not transport any member from the plant to the job site before approval of that member by the plant inspector. Provide access to all surfaces of the member so the plant inspector has the opportunity to properly inspect the member before approval. Such approval will be indicated by the compliance with the Department’s RFID tag/label tagging policy in ac cordance with

(FIR)or NCDOT alternate ID .

-4 PORTLAND CEMENT CONCRETE

(A)Composition and Design

Supply Portland cement concrete composed of Portland cement, coarse aggregate, fine aggregate, water and an approved air -entraining agent. Add other cementitious materials and/or chemical admixtures if approved by the Engineer. Whe n admixtures are used, use them in the proper proportions to obtain the optimum effect. Do not use set accelerating admixtures, calcium chloride or admixtures containing calcium chloride. If approved by the Engineer , high range water reducer may be used at a rate not to exceed the manufacturer’s recommended dosage.

Supply concrete with a minimum compressive strength of 5,000 psi at the age of 28 days, unless otherwise required by the plans or Standard Specifications . Ensure that all coarse aggregate used in prestressed concrete passes a 1 inch sieve. Maintain a cement content of at least 564 lbs. per cubic yard. Air entrain concrete to provide an air content of 5 ± 2% . Supply concrete with a maximum slump of 3.5 inches. A slump of 8 inches is permitte d only when obtained with the use of an approved high range water reducer . As an option, reduce the cement content of the mix design and replace with fly ash or ground granulated blast furnace slag in accordance with Article 1024 -1. For concrete with a 2 8 day design strength greater than 6,000 psi, if approved by the Engineer , substitute microsilica for cement, in conformance with Article 1024 -1. Submit to the Engineer proposed concrete mix designs for each strength of concrete used in the work. Determin e quantities of fine and coarse aggregates necessary to provide concrete in accordance with the Standard Specifications by the method described in ACI 211 using the absolute volume basis. Submit mix designs, stated in terms of saturated surface dry weights , on Materials and Tests Form 312U at least 35 days before using the proposed mix. Adjust batch proportions to compensate for surface moisture contained in the aggregates at the time of batching. Changes in the saturated dry mix proportions are not permi tted unless revised mix designs are submitted to the Engineer and are determined to be acceptable for use. Create laboratory trial batches to confirm the proposed mix design meets the requirements of the plastic and hardened concrete. Provide with Materia ls and Tests Form 312U a listing of laboratory test results of aggregate gradation, air content, slump and compressive strength. List the compressive strength of at least three 6 inches x 12 inches or 4 inches x 8 inches cylinders. Show the age of the cy linders at the time of testing and a detailed description of the curing procedure. Perform laboratory tests in accordance with the following test procedures: Property Test Method Aggregate Gradation AASHTO T Air Content AASHTO T 152 Slump AASHTO T 119 Compressive Strength AASHTO T 22 and R100 If the design 28 day compressive strength is greater than 6,000 psi, submit the compressive strength of at least six cylinders. Ensure that the average strength of the six cylinders is at least 1,500 psi above the minimum 28 day compressive strength requi red by the plans. The Engineer will review the mix design for compliance with the s pecifications and notif y the Contractor as to its acceptab ility. Do not use a mix until written notified has been received . Acceptance of the mix design does not relieve t he Contractor of his responsibility to furnish a product that meets the contract .

(B)Self-Consolidating Concrete (SCC) and Intermediate Flow Concrete

When a flowable concrete consistency is required, the use of an SCC or Intermediate Flow concrete is permitte d with an approved concrete mix design. SCC is a specialized concrete mix that utilizes various admixtures to obtain a fluid consistency without negatively impacting the strength or homogeneity of the mix. SCC is designed to flow under its own weight and fill the formwork completely, even in the presence of dense reinforcement and without the need for consolidation. SCC is characterized by a plastic concrete mixture with a flow that achieves a spread of 22 -30 inches, when tested in accordance with ASTM C1611. Intermediate Flow Concrete is a concrete mix that exceeds the slump of standard concrete but does not have the same high flow characteristics of an SCC concrete mix. Intermediate Flow Concrete is characterized by a plastic concrete mixture with a flo w that achieves a spread of 16- 22 inches, when tested in accordance with ASTM C1611.

When submitting a proposed SCC or Intermediate Flow concrete mix design on a Materials and Tests Form 312U, include the test results obtained using the following test procedures: Property Test Method Aggregate Gradation AASHTO T Air Content AASHTO T 152 Slump Flow ASTM C1611 Visual Stability Index (VSI) ASTM C1611 Passing Ability ASTM C1621 (Filling Procedure B) Segregation ASTM C1610 Compressive Strength AASHTO T 2 2 and R100 Supply concrete that develops a minimum compressive strength of 5,000 psi at the age of 28 days, unless otherwise required by the plans or Standard Specifications . SCC and Intermediate Flow mixes shall have a difference in slump flow and passing ability not to exceed 2 inches, a Visual Stability Index no greater than 1, and a static segregation limit of 15%.

(C)Testing

Employ a certified concrete technician to perform all testing required by this subarticle at the bed site in the presence of the plant inspector unless otherwise approved by the Engineer . Certification of technicians is awarded upon satisfactory completion of examinations prepared and administered by the Department or other approved agency.

(1)Air Cont ent

Before allowing placement of the first load in a bed, determine the air content by AASHTO T 152, T196 or T121. During the placement of the first load, determine the air content by AASHTO T 152, T 196 or T 121. Determine the air content in each subsequent 10 cubic yards by AASHTO T 152, T196 or T121 before allowing placement. Determine the air content by AASHTO T 152, T196 or T121 from all loads from which cylinders are made. If the air content does not meet the Standard Specifications , a secon d test on the same load is conducted using AASHTO T 152, T196 or T121. Acceptance or rejection of the load is based on the results of this test.

(2)Slump

Determine slump in accordance with AASHTO T 119.

(3)Spread

Determines pread on SCC and intermediate flow co ncrete in accordance with ASTM C1611 or AASHTO T 347.

(4)Strength

For the purpose of testing for the required 28 day compressive strength and also for the required compressive strength for the transfer of load, furnish, at no cost to the Department, cylinders made from a sample of concrete placed near the live end of the bed and additional cylinders made from a sample of concrete placed near the dead end of the bed. Make cylinders in accordance with AASHTO R 100, except cure the cylinders in the same manner as the members represented until the strands are released. Place cylinders in clusters at random points along the casting bed. After the strands are released, air cure the cylinders in an approved common area near the testing apparatus for the remainder of the 28 day curing period. Test the cylinders in accordance with AASHTO T 22. Provide approved apparatus for testing the transfer strength of the cylinders. Maintain this apparatus to within 1.0% accuracy and calibrate at intervals not to exceed 12 mo nths by an approved testing company at no cost to the Department. The Engineer reserves the right to require verification

immediately after a testing machine is relocated and whenever there is reason to doubt the accuracy of the indicated load, regardless of the time interval since the last verification. The testing requirements for the 28 day compressive strength for all prestress members required by the plans are as follows:

(a)Release Strength

Test four cylinders, two sets of two cylinders from each end of the bed, for the purpose of determining whether the concrete has reached the required strength for transfer of load. The strengths from the dead end cylinders are averaged and the strengths from the live end cylinders are averaged. Ensure that both of these averages meet or exceed the required release strength and the lowest cylinder is not more than 200 psi below the required strength.

(b)Acceptance Strength

Test a set of three cylinders from each end to determine the 28 day compressive strength. The stre ngths from the dead end cylinders are averaged and the strengths from the live end cylinders are averaged. Ensure that both of these averages meet or exceed the 28 day compressive strength. Ensure that no cylinder indicates a compressive strength less than 400 psi less than the required 28 day compressive strength. Failure to meet the above requirements is cause for rejection of the members represented.

(D)Temperature Requirements

Maintain a concrete temperature at the time of placing in the forms between 5 0°F and 95°F. Place concrete when the air temperature, measured at the location of the concreting operation in the shade away from artificial heat, is a minimum of 35°F and rising. Place concrete when the form temperature is between 35 °F and 110° F.

(E)Elapsed Time for Placing Concrete

Ensure that the elapsed time for placing concrete is in accordance with Subarticle 1000- 3(E). The requirements of Subarticle 1000- 3(E) pertaining to Class AA concrete apply to prestressed concrete.

(F)Use of Set Retarding Admixtures

By permission of the Engineer, use an approved set retarding admixture if choosing to take advantage of the extended time interval between adding mixing water and placing the concrete. Use a quantity of set retarding admixture per 100 lbs. of cement within the range recommended on the current list of approved set retarding admixtures issued by the Materials and Tests Unit.

(G)Use of Water Reducing Admixtures

Use water -reducing admixtures in accordance with Subarticle 1000 -3(G).

(H)Use of Calc ium Nitrite Corrosion Inhibitor

Add an approved calcium nitrite corrosion inhibitor (30% solids) to the concrete mix at the batch plant for the bridge elements identified by the plan notes. Clearly mark the prestressed concrete members that contain calciu m nitrite. Use the inhibitor at a minimum rate of 3.0 gal/cy . Ensure that the hardened concrete contains at least 5. 8 lbs/cy Nitrite (NO2) when tested in accordance with Materials and Tests Method Chem. C -20.0 with the exception of concrete used in prestr essed members. Test prestressed members as follows:

The Department will perform the complete C -21.0 Field Test Procedure for the NitriteIon in Plastic Concrete on plastic concrete samples obtained randomly from a truck used to pour concrete near each end (live end and dead end) of a prestressed concrete casting. Powder samples will be taken from hardened cylinders made at the time C -21.0 is run for any concrete that fails the C -21.0 (plastic test) method. The Chemical Testing Laboratory will test the pow der using method C -20.0 Determination of Nitrite in Hardened Concrete. Acceptance of the concrete is dependent in the results of method C -20.0 (hardened test) when any sample fails the C -21.0 (plastic test method). The Department will perform a qualitativ e nitriteion check by method C -22.0 (Field Spot Test) on each load of concrete batched for a prestressed concrete casting bed. Acceptance of the concrete is dependent on the results of method C -20.0 (hardened test) when any sample fails the C -22.0 (Field Spot Test). The producer may elect to not incorporate concrete that fails Method C -22.0 (Field Spot Test) instead of waiting for C -20.0 (hardened test) test results to determine the acceptability of the member. Once per each week’s production of prestr essed concrete with corrosion inhibitor, random samples of hardened concrete powder will be taken from cylinders used for method C -21.0 (plastic test). These samples will be submitted to the Chemical Testing Laboratory for analysis using method C -20.0 (hardened test). Units with calcium nitrite in a quantity less than specified are subject to rejection. Furnish powder drilled from concrete cylinders to the Engineer, in a quantity to be specified, to verify the concentrations of calcium nitrite in hardene d concrete. Concrete failing to contain calcium nitrite at the required concentrations as tested is subject to rejection. Use only air -entraining, water -reducing and/or set -controlling admixtures in the production of concrete mixtures that are compatible with calcium nitrite solutions. Strictly adhere to the manufacturer’s written recommendations regarding the use of admixtures including storage, transportation and method of mixing. If preferred, use calcium nitrite, which acts as an accelerator, in conju nction with a retarder to control the set of concrete, as per the manufacturer’s recommendation.

(I)Measuring Materials

Measure materials in accordance with Article 1000 -9.

(J)Mixers and Agitators

Use mixers and agitators meeting Article 1000 -11.

(K)Mixing and Deli very
(1)General

Mix and deliver concrete to the site of the work by one of the following methods, except where other methods are approved by the Engineer. The Engineer approves the mixing of concrete by methods other than those listed below provided the proposed method is capable of satisfying job requirements and there is adequate evidence that the proposed method produces concrete complying with the Standard Specifications . Assume responsibility for controlling the materials and operations so as to produce uniform concrete meeting the Standard Specifications . Have present during all batching operations at the concrete plant a certified concrete technician employed by the Contractor, prestressed concrete producer or concrete supplier while concrete is batched and delivered to the site of the work. The sole duty of this employee is to have charge of and exercise close supervision of the production and control of the concrete. Ensure the technician performs moisture tests, adjusts mix proportions of aggregates for free moisture, completes batch tickets on Materia ls and Tests Form 903 or approved delivery tickets, signs batch tickets or approved delivery tickets and assures quality control of the batching operations. Delivery tickets are

permitted instead of batch tickets on M&T Form 903 provided they are reviewed and approved by the Materials and Tests Unit. Certification of technicians is awarded upon satisfactory completion of examinations prepared and administered by the Department or other approved agency.

(a)Central Mixed Concrete

Mix completely in a stationary mixer and transport the mixed concrete to the point of delivery in a truck agitator or in a truck mixer operating at agitating speed or in non- agitating equipment approved by the Engineer. Mix within the capacity and at the mixing speeds recommended by t he equipment manufacturer.

(b)Transit Mixed Concrete

Mix completely in a truck mixer while at the batching plant, in transit or at the work site.

(2)Mixing Time for Central Mixed Concrete

The mixing time starts when all the solid materials are in the mixing comp artment and ends when any part of the concrete begins to discharge. Charge the ingredients into the mixer such that some of the water enters in advance of cement and aggregate, and substantially all the water is in the drum before 1/3 of the specified mix ing time elapses. Transfer time in multiple drum mixers is counted as part of the mixing time. Establish the minimum mixing time by one of the following:

(a)Mixer performance tests as described herein,
(b)The manufacturer of the equipment, or
(c)The requirement of one minute for mixers of 1.0 cy capacity or less with

an increase of 15 seconds for each cubic yard or fraction thereof in increased capacity. The Engineer reserves the right to require a mixer performance test at any time. The minimum mixing time as determined by the mixer performance test is that which produces concrete in accordance with Table 1078- 1. Sample and test for mixer performance as provided below. Charge the mixer to its rated capacity with the materials and proportions used in the work and mix at the recommended mixing speed to the target time. Stop mixing then and begin discharging. Take two samples of sufficient size to make the required tests after discharge of approximately 15% and 85% of the load by an appropriate method of sampling which provides representative samples of the concrete. Separately test each of the two samples of concret e for the properties listed in Suba rticle 1078- 4(A) or 1078 -4(B). Conduct tests in accordance with the standard methods shown in Suba rticle 1078- 4(A) or 1078 -4(B) or procedures established by the Materials and Tests Unit. Perform the mixer performance tes t described above on at least two batches of concrete. For the performance test to be acceptable, ensure that all tests in each batch meet the requirements listed in Table 1078 -1. The Engineer rechecks mixer performance at any time when in his judgment acceptable mixing is not accomplished. Where acceptable mixing cannot be accomplished in the established mixing time, the Engineer increases the mixing time or requires that the mixer be repaired or replaced before any further mixing.

TABLE 1078 -1 REQUIREMENTS FOR UNIFORMITY OF CONCRETE WITHIN A BATCH Property Requirement Test Method Difference in Test Samples Air Content, Percent by Volume of Concrete 1.0% AASHTO T 152 Slump 1.0" AASHTO T 119 Coarse aggregate content, portion by weight of each sample retained on the No. 4 sieve 6.0% - Weight per Cubic Foot (Density) 1.0 lb/cf AASHTO T 121 Average Compressive Strength at 7 days, Percent of Average 7.5%A AASHTO T and R100

A.Obtain tentative approval pending 7 day compressive strength tests.
(3)Truck Mixers and Truck Agitators

Use truck mixers and truck agitators meeting Subarticle 1000- 11(C). For concrete with a design 28 day compressive strength greater than 6,000 psi, load trucks to within 1 cy of rated capacity and mix at a speed of 16 to 18 rpm.

(4)Delivery

For central mixed concrete delivered in truck agitators, truck mixers, or transit mixed concrete, use a ticket system for recording the transportation of batches from the proportioning plant to the site of the work. Fill out the tickets on Materials and Tests Form 903 or approved delivery tickets in accordance with the instructions issued by the Engineer. Issue the tickets to the truck operator at the proportioning plant for each load and have them signed by the certified concrete technician, which signifies that the concrete in the truck is inspected before departure. Show on each ticket the time batching is complete and if transit mixed, the number of revolutions at mixing speed , if any, at the plant. Deliver the tickets to the inspector at the site of the work. For central mixed concrete delivered in non -agitating equipment, alternate methods of documenting batch proportions are considered by the Engineer. Loads that do not arrive in satisfactory condition within the time limits specified are not acceptable for use in the work.

(L)Ready Mixed Concrete Plant

Ensure ready mixed concrete plants are inspected and approved by the Department before they are used to produce concrete for the project. Ensure that plants meet all applicable requirements of the Standard Specifications and in addition have at least two acceptable concrete delivery vehicles that are in working condition. Plants approved by the Department are placed on a list of approved plants that is made available. All plants are subject to reinspection at intervals selected by the Engineer. Reapproval after each inspection is contingent on continuing compliance with the Standard Specifications . -5 CASTING BED AND FORMS Use metal forms, including headers or end forms, except where other materials are approved by the Engineer. Use forms of adequate thickness, brace d, stiffened, anchored and aligned adequately to consistently produce members within the limits of dimensional tolerances. Design and align the forms so they do not restrict longitudinal movement of the casting when the prestressing force is transferred. Provide corners and angles that are chamfered or rounded. Provide joints in forms that are smooth and tight enough to prevent leakage of mortar. Plug holes and slots in forms, pallets, headers and bulkheads neatly to prevent leakage of mortar. Make the inside surfaces of forms accessible for cleaning. Thoroughly clean the beds and forms after each use. Before casting, clean the inside surfaces of the forms from rust, grease or other foreign matter. Remove all foreign substances from inside the forms, including any standing water. Do not allow coatings used for release of members to build up. Do not use forms that do not present a smooth surface.

When casting holes through the top flange of girders for overhang or interior bay falsework hanger rods, use rigid PVC conduits with a wall thickness of approximately 1/8 inch. Do not use thin wall material. Secure conduits in the forms so they do not migrate out of the proper location. Other methods of forming holes may be proposed but are subject to the Engineer’s approval. When casting dowel rod holes in cored slab or box beam members, use material that creates round, vertical holes of the specified diameter and in the correct location. Do not use material that deforms, collapses or shifts position duri ng casting of the member. Apply form release agents to the forms either before or after stringing of strands. If applied before stringing, provide a release agent of a type that dries to a degree so it cannot contaminate any strand that comes in contact w ith it. If the release agent is applied after stringing, exercise great care and provide a sheet metal or similar type shield for protection of the strands. -6 TENSIONING DEVICES Use tensioning devices adequate to produce and maintain the required tension in all strands until the concrete reaches the required transfer strength. Equip all jacks with accurate and calibrated gauges for registering jacking loads. Calibrate ga uges with the jacks with which they are used. Calibrate all jacks and gauges by an approved testing company at no cost to the Department at intervals not to exceed 12 months. During progress of the work, if gauge readings and elongations indicate materia lly differing loads, recalibrate as required. Use gauges with a full load capacity of 1 1/2 to 2 times their normal working load, unless otherwise approved by the Engineer . Do not use loads less than one -fourth or more than 3/4 of the total graduated gau ge capacity unless calibration data clearly establishes consistent accuracy over a wider range. Use gauges with indicating dials at least 6 inches in diameter and gauge pointers that do not fluctuate, preventing an accurate reading, but remain steady unti l the jacking load is released. Ensure that all gauges have an accuracy of reading within 2%. Provide means for measuring the elongation of strands within 1/4 inch. -7 PLACING STRANDS, TIES AND REINFORCING STEEL Position strands, ties, supports, reinforcing bars of the sizes shown in the plans and bearing plates in accordance with the detailed dimensions shown in the plans and effectivelyse cure against displacement from their correct positions. The use of previously tensioned strands is not permitted. For prestressing strands, do not allow deflections or displacements of any kind between the end anchorages unless shown in the plans. Place the steel reinforcing in final position after tensioning of the strands. Bend all tie wires to the inside of the member so the ends are farther from the edge than the material tied. Support bottom strands spacings not to exceed 20 f eet by supports meeti ng Article 1070 -4 or by other approved means. Plastic supports may be used when approved by the Engineer. Strands with kinks, bends, nicks, scale, excessive rust or other defects are not permitted. No more than one broken wire per casting bed is permitte d. Slight rusting is not cause for rejection, provided it is not sufficient to cause visible pits. Take precautions to prevent contamination of strands and reinforcing steel. Clean the strands and reinforcing steel to an acceptable condition before pouring concrete. Do not place concrete in the forms until the strand and reinforcement condition and arrangement are inspected by the plant inspector. Strand splices are only permitted at the end of a reel and when using a single strand jack. Ensure that th e strand lengths to be spliced together have the same lay of wire to avoid unraveling and position the splice so it does not fall within a member. Do not torch cut the ends of the spliced strand lengths. Cut by shears, abrasive grinders or other means approved by the Engineer. No more than one strand splice per bed is allowed on an individual strand and the use of previously tensioned strands for splicing is not permitted. Where debonding of strands is required, accomplish by encasing the strand in a tubular conduit capable of resisting the pressure exerted by the concrete. Do not use slit conduit. Use a conduit of HDPE or polypropylene with a minimum wall thickness of 0.025 inch. Ensure that the inside

diameter of the conduit is of sufficient size to allow free movement of the encased strand but not greater than the diameter of the strand plus 1/8 inch. Secure the conduit so longitudinal movement along the strand is prevented, and bonding of the strand is prevented at the required location ± 1 inch. When conduit is added after initial tensioning, prevent concrete from entering the conduit by taping all joints and cuts along the length of the conduit . Use tape manufactured from a non -corrosive material compatible with the concrete, conduit and steel. -8 TENSIONING PROCEDURE A producer quality control representative shall be present during strand tensioning. Tension each strand to the load shown in the plans before pla cing the concrete. Measure the load induced in the prestressing strand both by jacking gauges and strand elongations on at least the first five strands and every third strand thereafter on each pour. Measure loads on all other strands by either jacking ga uges or strand elongations. When both methods of measurement are used, if a discrepancy between gauge and elongation of more than 5% is apparent, carefully check the entire operation and determine the source of error before proceeding. Make appropriate allowances in the computed elongation and jacking loads for load losses due to friction and all possible slippage or relaxation of the anchorage. Establish references periodically at each strand anchorage to indicate any yielding or slippage that may occur between the time of initial tensioning and final release of the strands. In determining the applied load by measuring the elongation of the strand, use a modulus of elasticity taken from the typical stress -strain curve for the brand, size and type of stra nd tensioned. Submit stress -strain curve data for the actual heats of material used in the strands to the plant inspector before using the strands. Identify each reel or strand by tagging in accordance with AASHTO M 203. Mark the outer layer of each reel pack of strand with a wide color band . In addition, attach a metal tag to each reel pack labeled in accordance with AASHTO M 203. Tension strands in a group or individually. Before full tensioning, bring each strand to an initial tension of 2,000 lbs. for all beds under 150 f eet in length, 3,000 lbs. for all beds 150 f eet to 300 feet in length and 4,000 lbs. for all beds longer than 300 f eet in length. Measure this initial tension by a calibrated gauge or other approved means, and then compute the e longation due to initial tensioning. Use the difference between the required final tension and the initial tension to compute the expected additional elongation. For precast prestressed deck panels, use a final prestressing force of 14,000 lbs. per strand for Grade 250 strand and 16,100 lbs. per strand for Grade 270 strand. After initial tensioning, tension the strands until the required elongation and jacking load are attained and reconciled within the limits specified above. Keep a permanent record of t he initial jacking load, the final jacking load, and the elongation produced thereby. In single strand tensioning, rotation of the jacking ram is not allowed. When draped strands are used, submit the bed layout showing the method of draping and tensioning the draped strands and also calculations determining the loads required for tensioning the draped strands. Drape the strands for all members to be cast in any one tensioning operation before casting any beam. Have end templates or bulkheads at ends of beams remain vertical or as otherwise shown in the plans. Perform draping for all members either simultaneously or in single or incremental lifts beginning at the center of the bed and working outward toward each end of the bed. Complete tensioning in the fully draped position is not allowed unless approved in writing. Requests to tension in the draped position will only be considered if the producer has the ability to tension from both the l ive and d ead end of the casting bed. When the tensioning of draped strands is approved in writing verification of the proper stresses in the draped strands will be required. The verification of the stresses in the draped strands shall be completed according to the Materials and Tests Standar d Operating Procedures for Tensioning Draped Strands i n the Final Position .

Use round steel rollers of a type and dimensions approved by the Engineer for deflecting the draped strands. Round the part in contact with the strand to a diameter of not less than 3/4 inch. Use support and hold- down devices of sufficient rigidity with adequate support so the final position of the strands is as shown in the plans. Ensure that all parts are in good working order and roll freely to ensure equal distribution of stress in the draped strands. With strands tensioned in accordance with the above requirements and with other reinforcement in place, cast the concrete members so as to achieve the required lengths. Maintain strand load between anchorages until the concrete reaches the required compressive strength for transfer of load from the anchorages to the members. For personnel engaged in the tensioning operation, provide protection by effective shields adequate to stop a flying strand. Provide shields produced from steel, reinforced concrete, heavy timbers and other approved material at both ends of the bed. -9 PLACING CONCRETE Place concrete in accordance with Article 1077 -8 and the additional requirements of this article. Upon completion of stressing strand, place concrete within a reasonable time to prevent contamination of the strands and reinforcing steel. Place concrete for girders 54 inches or less in height, and concrete for all cored slabs and box beams, in two or more equal horizontal layers. Place concrete for girders over 54 inches in height in three horizontal layers. When placing concrete in three layers locate the top of the first layer approximately at the top of the bottom flange and locate the top of the second layer approximately at the top of the web. To prevent separation of surfaces between layers, do not allow the time between successive placements onto previously placed co ncrete to exceed 20 minutes, unless the previously placed concrete has not yet stiffened, as evidenced by the continuous effective use of vibration. Should shrinkage or settlement cracks occur, the Engineer reserves the right to require additional layers and/or vibration. The requirement of the above paragraph may be waived with the permission of the Engineer if SCC or intermediate flow concrete is used. Vibration may be required to produce uniformly dense concrete without honeycomb while maintaining the integrity of the concrete mix without causing segregation. Segregation of the concrete within a member may be cause for rejection by the Engineer . Place concrete in cold weather in accordance with Article 1078 -10. Place concrete in daylight unless an adequate lighting system meeting the approval of the Engineer is provided. Do not exceed a temperature of 95° F in the freshly mixed concrete when placed in the forms. Place the concrete in the bed in one continuous operation, finishing each member before proceeding to the next one. If the pour stops before the concrete in all the members in the bed is placed, start curing immediately. Do not place concrete in any remaining members in that bed setup once curing at elevated temperatures has begun. When cored slabs and box beams are cast, employ an approved internal hold -down system to prevent the voids from moving. At least 6 weeks before casting cored slabs or box beams, submit to the Engineer for review and comment, detailed drawings of the proposed void material and hold -down system. In addition to structural details, indicate the location and spacing of the holds -downs. Submit the proposed method of concrete placement and of consolidating the concrete under the void. The use of an approved external hold-down system may be used in conjunction with an approved internal hold- down system with the understanding that the external hold- down system shall be removed while the concrete remains plastic. The areas where an external hold -down

system exits the su rface of the member shall be consolidated and finished with the surrounding area as specified in Article 1078- 16. -10 PLACING PRESTRESSED CONCRETE IN COLD WEATHER

(A)General

Place concrete when the air temperature, measured at the location of the concreting operation in the shade away from artificial heat, is 35°F and rising. When the temperature allows, uniformly heat the aggregates and or water to a temperature not higher th an 150°F. Place the concrete when the temperature of the heated concrete is at least 55°F and not more than 95°F . Use aggregates that are free of ice, frost and frozen particles. Do not place concrete on frozen foundation material and ensure that the for ms are free of ice. Follow the guidelines set forth in Article 1078- 11 for proper curing methods when placing concrete in cold weather. Protect all concrete with heated enclosures or by insulation when the concrete is placed when the air temperature, measu red at the location of the concreting operation in the shade away from artificial heat is between 35°F and 50°F. Provide and place, at directed locations, a sufficient number of maximum -minimum recording thermometers to provide an accurate record of the temperature surrounding the concrete during the entire protection /curing period. Place maximum -minimum recording thermometers within 50 feet of each end of the bed and at points not to exceed 100 feet between the end thermometers. Provide at least two the rmometers for bed lengths of 100 feet or less. Assume all risks connected with the placing of concrete under the cold weather conditions referred to herein .

(B)Heated Enclosures

Immediately enclose concrete that is placed when the air temperature is below 50°F. Enclose the concrete with a housing consisting of canvas or other approved material supported by an open framework which allows for the heat to be evenly circulated within the enclosure. Maintain the air surrounding the concrete at a temperature of at least 50°F and no more than 90°F when using dry heat. When using dry heat, provide means of preventing loss of moisture from the concrete . -11 CURING CONCRETE

(A)General

Cure concrete by steam curing, radiant heat curing , portable heaters or water curing, as set forth below. As an option, cure concrete for prestressed piles with membrane curing compound as set forth below. Use a method or methods that prevent the concrete from losing moisture at any time before curing is complete. Use methods that do not deface or injure the concrete. Use curing procedures that prevent cracks from occurring in the members. Cure all members in any one bed by the same method. Continue the curing period until the concrete reaches sufficient strength to permit transfer of load from the anchorage to the members. As soon as the concrete attains release strength, im mediately release all forms in a continuous operation, without delay for other activities such as the cleaning of forms. As soon as the forms are removed, and after the Department’s Inspector has had a reasonable opportunity to inspect the member, transfe r the load from the anchorages to the members as quickly as possible in one continuous operation using the approved detensioning sequence.

(B)Curing at Elevated Temperatures

Perform radiant heat curing under a suitable enclosure that contains the heat and prevent moisture loss. Apply moisture by a cover of moist burlap, cotton matting, or similar approved material. Retain moisture by covering the member with an approved waterproof sheeting in combination with an insulating cover. Support the cover at a sufficient distance above the member being cured to allow circulation of the heat. Provide steam curing enclosures essentially free of steam leakage to minimize moisture and heat losses. Do not allow the enclosure to come in contact with the members or forms for the members. Do not direct steam jets on the forms so as to cause localized high temperatures. After placing and vibrating, allow the concrete to attain its initial set before the application of heat or steam. The concrete is considered to obtain it s initial set when it has a penetration resistance of at least 500 psi when tested in accordance with AASHTO T 197. Take the sample of concrete tested for penetration resistance from the last load cast in the bed. Store the sample of concrete with the pr ecast member and maintain in the same condition and environment as the member except for the periods of time necessary to prepare the test specimen and to perform the penetration resistance test. Conduct the penetration resistance test. As an option, subm it data indicating that an approved concrete mix attains its initial set after some particular time period. Different periods may be required for different weather conditions. If such data is submitted, consideration is given to permitting heat or steam introduced after the time indicated by such data instead of having to perform the penetration resistance test. Consideration is given to determining the time of initial set by methods other than AASHTO T 197 provided data supporting such other methods is submitted. When the ambient air temperature is below 50°F, cover the forms after the placement of concrete and apply sufficient heat to maintain the temperature of the air surrounding the unit between 50° and 70°F. When the ambient air temperature is above 70°F, start a water cure as set forth below or other approved method as soon as the concrete is able to receive the water without physical damage to its surface. Discontinuation of the cure is allowed upon introduction of steam, provided that a relative humidity of 100% is maintained. The temperature within the curing enclosure shall not exceed 160°F. Maintain a relatively uniform rate of increase of the temperature within the curing enclosure of approximately 40°F per hour, not to exceed 15°F per 15 minutes. Ensure that the temperature increase is relatively uniform throughout the length and on both sides and top of the concrete unit. Place recording thermometers within 50 f eet of each end of the bed and at points not to exceed 100 f eet between the end thermometers. Provide at least two thermometers for bed lengths of 100 f eet or less. Calibrate recording thermometers at intervals not to exceed 6 months. Ensure that the temperature differential within the curing enclosure does not exceed 15°F. Submit complete temperature records for all cures before final approval of the members. Continue steam curing until the concrete reaches the required transfer strength.

(C)Water Curing

Keep the concrete members damp by the application of water as soon as possible wi thout damage to the concrete surface, and before the concrete obtains an initial set of 500 psi. Apply the water using soaker hoses and wet burlap or other approved means for the full length of each member. Apply water evenly along the entire length of t he bed and as needed to maintain damp conditions .

When the ambient air temperature is below 50°F cover the forms after the placement of the concrete and apply sufficient heat in an approved manner to maintain the temperature of the air surrounding the me mber between 50°F and 70°F. After the concrete obtains an initial set of 500 psi, the air temperature surrounding the member is allowed to increase to 100°F while continually maintaining moisture on the surface of the concrete. Whenever heat is applied to the member, place temperature recording clocks on the bed as required when curing at elevated temperatures. The requirements for rate of temperature increase apply. Maintain the application of heat (if used) and water until the concrete obtains release strength.

(D)Curing with Membrane Curing Compound

As an option, cure prestressed concrete piles with a membrane curing compound. Spray the entire surface of the concrete uniformly with a wax -free, resin -base curing compound conforming to Article 1026- 2. Use clear curing compound to which a fugitive dye is added for color contrast. Apply the membrane curing compound after the surface finishing is complete, and immediately after the free surface moisture disappears. In the event the application of curing compound is delayed, start another curing method immediately and continue until the application of the curing compound is started or resumed or until the concrete reaches the required detensioning strength. Seal the surface with a single uniform coating of the specified type of curing compound applied at the rate of coverage recommended by the manufacturer or as directed by the Engineer, but not less than one gallon per 150 sf of area. At the time of use, thoroughly mix the compound in a condition with the pigm ent uniformly dispersed throughout the vehicle. If the application of the compound does not result in satisfactory coverage, stop the method and apply water curing, as set out above, until the cause of the defective work is corrected. At locations where the coating shows discontinuities, pinholes, or other defects, or if rain falls on the newly coated surface before the film dries sufficiently to resist damage, apply an additional coat of the compound immediately after the rain stops at the same rate speci fied herein. When the ambient air temperature is below 50°F, cover the forms after the application of the curing compound and apply sufficient heat in an approved manner to maintain the temperature of the air surrounding the member between 50°F and 70°F. Whenever heat is applied to the members, place recording thermometers on the bed as required when curing at elevated temperatures. The requirements for rate of temperature increase also apply. Completely remove any curing compound adhering to a surface to which new concrete is bonded by sandblasting, steel wire brushes, bush hammers or other approved means. Protect the concrete surfaces to which the compound is applied from abrasion or other damage that results in perforation of the membrane film until the concrete achieves design strength and the members are de- tensioned. -12 TRANSFER OF LOAD A producer quality control representative or equivalent qualified personnel shall be present during removal of forms and during transfer of load. Transfer load from the anchorages to the members when the concrete reaches the required compressive strength shown in the plans. Loosen and remove all formwork in one continuous operation as quickly as possible as soon as release strength is obtained. As soon as the forms are removed, and after the Department’s Inspector has had a reasonable opportunity to inspect

the member, transfer the load from the anchorages to the members as quickly as possible in one continuous operation using the approved detensioning sequence. For any particular group of members cast in the same bed, do not transfer the load to any concrete until the test cylinder breaks indicate that the concrete in all these members has reached the required strength as outlined in Subarticle 1078- 4(C)(3). If these conditions are not met, delay the transfer of the prestressing load to the concrete until tests of additional cylinders show that the required strength is reached. When curing at elevated temperatures, begin the procedures for transferring prestressing load immediately after curing is discontinued and the forms are released, and while the concrete is still hot to prevent cooling shrinkage and cracking. If s o directed by the Engineer, cover members or otherwise protect so as to cool the concrete slowly after release to prevent thermal shock and the evaporation of moisture in the members. Transfer load to not cause cracks in members. Transfer load by gradual release of the strands as a group, by gradual release of part of the group, or by burning the fully tensioned strands at the ends of the members. If intending to release the strands by a method other than gradual release of the entire group, submit the pr oposed method and pattern of release, if not so shown in the plans, for approval by the Engineer . Rigidly follow the approved method and pattern of release. When the fully tensioned strands are burned, burn each strand or group of strands simultaneously at each end of the bed in its indicated order in the pattern and at each end of each member before proceeding to the strands in the next group in the pattern at any point. Because of the critical nature of the bond development length in prestressed concre te panel construction, if transferring of stress by burning the fully tensioned strands at the ends of the member, burn each strand first at the ends of the bed and then at each end of each member before proceeding to the next strand in the burning pattern. When detensioning all girders, box beams, cored slabs, piles, and panels do not burn strands quickly but heat with a low oxygen flame played along the strand for at least 5 inches until the metal gradually loses its strength. Apply heat at such a rate t hat failure of the first wire in each strand does not occur until at least 5 seconds after heat is first applied. When detensioning other members, follow the above procedure unless an alternate procedure is approved by the Engineer . Detensioning by arc w elder is not allowed. Incorporate the following in the method for single strand detensioning of members having draped strands:

(A)Release the pair of straight strands located in the uppermost position in the lower flange

first.

(B)Then release the tension in the draped strands at the ends and uplift points in accordance

with an approved pattern.

(C)Disengage all hold- down devices for draped strands and release the hold- downs.
(D)Then release the pair of straight strands located in the upper flange.
(E)Release the remainin g straight strands of the pattern in accordance with an approved

sequence.

(F)Release all strands in a manner meeting the Engineer’s approval that will cause a minimum

shock and lateral eccentricity of loading. Failure to follow the above procedures for trans fer of load is ground for rejection of the members involved.

-13 VERTICAL CRACKS IN PRESTRESSED CONCRETE GIRDERS BEFORE DETENSIONING This section addresses prestressed concrete members that have vertical casting cracks before strand detensioning. Certain types of these cracks have been determined by the Department to render the girders unacceptable. Unacceptable cracked members are those with two or more vertical cracks spaced at a distance less than the member depth which extend into the bottom flange. Such members are not serviceable and will be rejected by the Engineer . Members with two or more vertical cracks spaced at a distance less than the member depth but do not e xtend into the bottom flange are subject to an engineering assessment. Such members may not be serviceable and may be rejected by the Engineer . Members with one or more vertical cracks that extend into the bottom flange and are spaced at a distance greater than the member depth are subject to an engineering assessment to determine their acceptability. If this engineering assessment is required, submit, at no additional cost to the Department, a proposal for repairing the member and a structural evaluation of the member prepared by an engineer licensed by the State of North Carolina. In the structural evaluation, consider the stresses under full service loads had the member not cracked and the effects of localized loss of prestress at the crack as determine d by methods acceptable to the Department. All members, except those defined as unacceptable, which exhibit vertical cracks before detensioning, shall receive a 7 day water cure as directed by the Engineer. The water cure shall begin within 4 hours after detensioning the prestressing strands and shall be at least 3 f eet beyond the region exhibiting vertical cracks. The Department has the final determination regarding acceptability of any members in question. -14 PRESTRESSED CONCRETE GIRDER WEB SPLITTING After detensioning of certain girders with draped strands, cracks occasionally occur in the webs at the ends of the girders. Repair all cracks located in the web of girders appearing after detensioning that are 0.010 inches (0.25 mm) or greater in width by means of epoxy injection in accordance with the Standard Specifications and as approved by the Engineer. Repair any web cracks that are less than 0.010 inches (0.25 mm) a nd greater than 0.005 inches (0.15 mm) in width by coating them with an approved clear, water based a lkylalkoxysilane

(silane)penetrating sealant having 100% solids. Use a sealant that meets the requirement of

NCHRP 244 and Federal AIM VOC emissions standards and has been approved by the Engineer. Coat web cracks between 0.005 inches (0.15 mm) and 0.010 inches (0.25 mm) in width with silane within 2 weeks after they appear or before shipment to the site whichever occurs soonest. Cracks located in the web l ess than or equal to 0.005 (0.15 mm) in width need not be coated. Do not repair or coat any cracks without prior approval of the Engineer. No separate payment will be made for the treatment of cracks, as payment is included in the contract unit price bid for prestressed concrete girders. . -15 HANDLING, TRANSPORTING AND STORING Members damaged while being handled or transported are rejected or require repair in a manner approved by the Engineer. All members are allowed to be handled immediately after transfer of load from the anchorages to the members is complete. Store all prestressed members on solid, unyielding, storage blocks in a manner to prevent torsion or objectionable bending. In handling prestressed concrete girders 54 inches or less in height, including cored slabs and box beams, maintain them in an upright position at all times and pick them up within 5 f eet of the points of bearing and transport and st ore supported only

within 3 f eet of points of bearing. In handling prestressed concrete girders greater than 54 inches in height, maintain them in an upright position at all times and submit for approval the proposed method of lifting, transporting, and storing the girders. When requested, provide calculations to confirm girders are not overstressed by such operations. Prestressed concrete panels are weak in the direction perpendicular to the prestressing strands; therefore, they are subject to breakage d uring handling, storing or transporting. Provide adequate blocking during all of these construction phases. In handling, transporting, and storing prestressed members, use the number and location of supports in accordance with the plan requirements for the sizes, lengths and types of members involved, or as approved by the Engineer . When handling the prestressed concrete members, a temporary stress of cif5 is permitted, where cif is the strength of concrete at release, in pounds per square inch. Do not transport members away from the casting yard until the concrete reaches the minimum required 28 day compressive strength and a period of at least 5 days elapses since casting, unless otherwise permitted. Do not trans port any member from the plant to the job site before approval of that member by the plant inspector. Such approval will be indicated by the compliance with the Department’s RFID tag/label tagging policy in accordance wi th Section 1030 and verified product approval as noted by an authorized Field Inspection Report (FIR) or NCDOT alternate ID . -16 FINAL FINISH Finish prestressed concrete members that are intended for composite action with subsequently placed concrete or asphalt with a roughened surface for bonding. Make sure that no laitance remains on the surfaces to be bonded. Rough float the tops of girders with the exception of the cent erline and outside 4 inches of each girder which shall receive a smooth finish. Broom finish the top surface of the cored slab and box beam sections receiving an asphalt overlay. Rake the top surface of cored slab and box beam sections receiving a concrete overlay to a depth of 1/4 inch. No surface finish is required for sides and bottom of the slab and beam sections except the exposed side of the exterior unit as noted below. Provide a resulting surface finish essentially the same color and surface finish as the surrounding concrete. Provide a 3/4 inch chamfer along the bottom edges on ends and sides of all box beam and cored slab sections, top outside edges of exterior sections and acute corners of sections. Round the top edges on ends of all sections with a 1/4 inch finishing tool. Provide square corners along top edges on all sections along shear keys. Do not chamfer vertical edges at ends of sections. Fill all voids in the diagonal/curved face of the bottom flange of prestressed concrete girders and the outside face of exterior cored slabs and box beams with a sand- cement or other approved grout. Fill all voids in piles greater than 1/2 inch in diameter or depth as above. Provide a resulting surface finish essentially the same color and surface finish as the surrounding concrete. Repair voids greater than 1/4 inch in diameter or depth in other faces of these and other members except piles in a like manner. Where an excessive number of smaller voids exist in any member, the Engineer requires a similar repair. Repair honeycomb, excessively large fins, and other projections as directed by the Engineer . Submit, at no additional cost to the Department, a proposal for repairing members with honeycomb, cracks or spalls. Do not repair members containing honeycomb, cracks, or spalls until a repair procedure is approved and the member is inspected by the Engineer. Any appreciable impairment of structural adequacy that cannot be repaired to the satisfaction of the Engineer is cause for rejection.

Clean and fill holes caused by strand hold downs upon removal from the casting bed. Use an approved material for patching that is listed on the NCDOT APL . Ensure that members are clean and surfaces have a uniform appearance. Give the top surface of prestressed concrete panels a raked finish or other approved finish to provide an adequate bond with the cast -in-place concrete. As soon as the condition of the concrete permits, rake the top surface of the concrete making depressions of approximately 1/4 inch. Take care when raking not to catch and pull the coarse aggregate. Clean reinforcing bars exposed on the tops of girders and exterior cored slabs or box beams of mortar build up and excessive rust. Apply epoxy protective coating to the ends of prestressed members as noted in the plans. -17 ALIGNMENT AND DIMENSIONAL TOLERANCES

(A)Piles

Manufacture piles within the tolerances indicated in Table 1078- 2 and Figure 1078 -1.

(B)Cored Slabs

To ensure a good, neat field fit, assemble cored slab spans in the yard and have pieces matchmarked. Ensure that pieces fit together neatly and in a workmanlike manner. Manufacture cored slabs within the tolerances indicated in Table 1078 -3 and Figure 1078 - 2.

(C)Girders

Manufacture girders within the tolerances indicated in Table 1078 -4 and Figure 1078- 3.

(D)Prestressed Concrete Panels

Manufacture prestressed concrete panels within the tolerances indicated in Table 1078 -5.

(E)Box Beams

To ensure a good, neat field fit, assemble box beam spans in the yard and have pieces match -marked. Ensure that pieces fit together neatly and in a competent manner. Manufacture box beams within the tolerances indicated in Table 1078- 6 and Figure 1078- 4.

-18 IDENTIFICATION OF MEMBERS Permanently identify each prestressed member by number and date of manufacture, and paint this information, or otherwise mark as approved by the Engineer, on at least one end of the member as soon as practical after manufacture. In the case of girders or cored slabs, paint other identification as to station, span and position within the span on at least one end of the member. All members shall additionally be identified by the use of an RFID tag/label embedded into the member in accordance with Section 1030 applied in accordance with Subarticle 1030- 2(F).

Figure 1078 -1. Prestressed Piles. Dimensions shown are in Table 1078- 2. A A F F 10 ft E C B D

TABLE 1078 -2 TOLERANCES FOR PRESTRESSED PILES (Refer to Figure 1078 -1) Dimension Tolerance Width (A) -1/4" to +3/8" Length (B) ± 1 1/2" Horizontal alignment Deviation from a straight line parallel to the centerline of pile (C) 1/8" per 10 ft Squareness of ends (D) 1/8" per 12" of width, 3/16" max. Local smoothness (E) 1/4" in 10 ft Position of strands (F) 1/4" Position of mild reinforcing steel, including spiral pitch 1/2"

Figure 1078 -2. Prestressed cored slabs. Dimensions shown are in Table 1078-3.

A B M M E E D SECTION PLAN ELEVATION G 10 ft F F C J I I K L H

TABLE 1078 -3 TOLERANCES FOR PRESTRESSED CORED SLABS (Refer to Figure 1078 -2) Dimension Tolerance Depth (A) +3/8" to -1/8" Width (B) ± 1/4" Length (C) ± 1/8" per 10 ft Position of voids - Vertical (D) ± 3/8" Position of voids - Horizontal (E) ± 3/8" Position of void Ends – Longitudinal +1", -3" Square ends - Deviation from square (horizontal)or vertical) or designated skew (F) ±1/4" Horizontal alignment - Deviation from a straight line parallel to the centerline of member (G) 0-30 ft long: 1/4" ft long: 3/8" 50+ ft long: 1/2" Camber - Differential between adjacent units (H) 1/4" per 10 ft, 3/4" max. Camber - Differential between high and low members of same span (H) 3/4" ma x. Position of dowel holes - Deviation from plan position (I) 1/4" Width - Any one span Plan width +1/8" per joint Width - Differential of adjacent spans in the same structure 1/2" Bearing area - Deviation from plane surface 1/16" Local smoothness (J) 1/4" in 10 ft Position of holes for transverse strands Horizontal (K): ±1/2" Vertical (L): ±3/8" Position of strands (M) ± 1/4"

-19 QUALITY CONTROL Maintain a daily quality control record form approved by the Engineer including pertinent information concerning tensioning, concrete quality and placement, curing and detensioning. Have this form signed and dated by a certified concrete technician. Furnish a copy of the completed or up- to-date form to the Materials and Tests Unit upon request and before any members are approved. A sample form, indicating the minimum required information, is available from the Materials and Tests Unit.

Figure 1078 -3. Prestressed Girders. Dimensions shown are in Table 1078-4.

A I K K L L B D E E C ISOMETRIC PLAN ELEVATION 10 ft J F H G Center of Girder

TABLE 1078 -4 TOLERANCES FOR PRESTRESSED GIRDERS (Refer to Figure 1078 -3) Dimension Tolerance Length (A) Girders 80 ft. or shorter ± 1/8" per 10 ft Length (A) Girders longer than 80 ft. ± 1/8" per 10 ft Not to exceed 1 1/2" Width - Flanges(B) +3/8" to -1/8" Width - Web (C) +3/8" to -1/8" Depth - Overall (D) +1/2" to -1/4" Depth - Flanges (E) ± 1/4" Horizontal alignment (top or bottom flange) Deviation from a straight line parallel to the centerline of beam (F) ± 1/8" per 10 ft Not to exceed 1 .5" Bearing plate Deviation from plane surface 1/16" Girder ends Deviation from square or designated skew (G and H) Vertical (G): ± 1/8" per 12" of girder height Horizontal (H): ± 1/2 " Position of stirrups - Projection above top of girder

(I)± 1/2"

Position of stirrups – Placement along girder length ± 1" Local smoothness of any surface (J) 1/4" in 10 ft Position of holes for diaphragm bolts (K) ± 1/4" Position of strands (L) ± 1/4" Dimensions followed by an alphabetical suffix are shown in Figure 1078- 3. The length (A) is measured along the top of the top flange. The tolerances at girder ends (G and H) are increased to 1 inch if the girder end is to be encased in a full depth concrete diaphragm.

TABLE 1078 -5 TOLERANCES FOR PRESTRESSED CONCRETE PANELS Dimension Tolerance Length (Transverse direction to girders) -1/4" to +1/2" Width (Longitudinal direction to girders) -1/8" to +1/4" Depth 0 to +3/8" Position of Strand Horizontal Dimension Vertical Dimension ± 1/4" ± 1/4"

Figure 1078 -4. Prestressed Box Beams. Dimensions shown are in Table 1078-6.

C P B P K K CROSS -SECTION A 10 ft H o1 F o2 o1 D o2 N G A E PLAN ELEVATION

Source: North Carolina Standard Specifications for Roads and Structures, 2024 Edition. Pages 550574 of 857.