603.1-DESCRIPTION: This work consists of the construction of precast/prestressed concrete members, pretensioned in accordance with these specifications and in conformity with the plan details and notes. This work shall include manufacturing, inspection, handling, storing, tr ansporting and erecting of structural members of precast/prestressed concrete, and, when specified, shall also include precast concrete members which do not contain pretensioning steel components. Concrete floors, curbs, parapets, curtain walls, and diaphragms shall be cast in place on the project unless otherwise provided for on the plans. When the above elements are specified as precast members, they shall be manufactured in accordance with this specification. 603.2-MATERIALS: Materials shall meet the requirements specified in the following Sections/Subsections: Precast/Prestressed Concrete Materials Sections/Subsections +Admixtures Air Entraining Admixtures 707.1 Retarding Admixtures 707.2 Water Reducing Admixtures 707.3 Supplementary Cementitious Materials (SCMs)** 707.4 Specific Performance Admixtures 707.17 Cement ASTM C150, 701.3 Coarse Aggregates* 703.1, 703.2, & 703.3 Concrete Sealant 707.12 Elastomeric Bearing Pads 715.14 Fine Aggregates # 702.1 Hot-Poured Elastic Type Concrete Joint Sealer 708.3 Mixing Water 715.7 Preformed Expansion Joint Filler 708.1 Prestressing Steel 709.2 Reinforcing Steel 709.1 Shear-Key Grout 715.5 Steel Bolts and Nuts 709.23 Welded Wire Fabric 709.4 # When the top surface of a prestressed member is designed as the bridge wearing surface * The maximum size of coarse aggregate shall not exceed the minimum horizontal or vertical clear spacing between pretensioned or reinforcing steel elements divided by 1.33. Lightweight aggregates shall not be used unless their use is permitted by the Engineer in writing. For Class S -P concrete, a blend of two AASHTO gradations of coarse aggregates can be used. The maximum aggregate size permitted is ¾ inches (19 mm). A coarse aggregate gradation using a #67 aggregate is allowed only if 100% of the material passes the ¾ inch (19 mm) sieve ** The use of a SCM is not permitted when a blen ded hydraulic cement is used. For the purposes of cement material substitution with SCMs, Type IL cement shall not be treated as a blended cement, and a SCM may be used with Type IL cement. For Class S -P concrete, a combination of up to two SCMs are perm itted, as shown in Table 603.6.3.1. The maximum percent of total cementitious materials permitted in Class S -P concrete mix designs is shown in Table 603.6.3.1. + Calcium chloride or any admixture containing chloride ion in excess of 0.1 percent by weigh t shall not be used in prestressed concrete members. 603.2.1-Inspection and Testing: A representative of the Engineer shall have free entry at all times, while the work on the Contract is being performed, to all parts of the manufacturer’s works which concern the manufacture of the materials ordered. The manufacturer shall afford the representative of the Engineer, without charge, all reasonable facilities to satisfy themselves that the material is being furnished in accordanc e with these specifications. Inspection and acceptance procedures for prestressed concrete bridge members shall be in accordance with MP 603.10.40. The Fabricator’s QC Personnel, as a minimum, shall be a certified ACI Grade I Concrete Field Testing Technician and/or a WVDOH PCC Inspector. In addition, if Self-Consolidating Concrete (SCC) is used, Fabrication Plant QC Personnel shall be a certified ACI SCC Testing Technician. Component materials used in the fabrication of precast and prestressed concrete members, and any ship loose materials pertaining to precast and prestressed concrete items, shall be approved in accordance with MP 603.02.10. 603.3-PLANT REQUIREMENTS AND APPROVAL: 603.3.1-Plant Approval: All fabricators of prestressed concrete members shall be certified in the appropriate Group and Category in accordance with the Precast/Prestressed Concrete Institute (PCI) Plant Certification Program. Fabricators shall be certified in Group B3 or B4 for manufacture of prestressed straight strand bridge members. For prestressed draped strand bridge members, the fabricator shall be certified in Group B4. The En gineer or his authorized representative shall approve all plants manufacturing prestressed and precast reinforced concrete bridge members before manufacture of the members may be started. Requests for such approvals shall be submitted to the Engineer at least three weeks prior to the date of manufacture of the members. Requests shall include details of the plant facilities, materials, and the production methods the manufacturer intends to use. The manufacturer shall have an established quality control program in effective operation at the plant. This program shall be submitted to the Engineer for approval at least 30 days prior to the start of the production. If a contractor/fabricator is found to consistently deviate from PCI guidelines, the contractor/fabricator will be required to use independent laboratory quality control testing and inspection until it can be shown that conformity with PCI guidelines has been reestablished. The laboratory used is subject to the approval by the Engineer. The cost of the independent laboratory is to be borne by the contractor/fabricator. 603.3.2-Supervision: The contractor/fabricator shall provide a PCI Level II certified technician, skilled in the use of the system of prestressing to be used, who shall supervise the work and give the Engineer or his representative such assistance as may be considered necessary. 603.3.3-Equipment and Tools: 603.3.3.1-General: All equipment, tools and machinery used in the work shall be adequate for the purpose for which it is to be used and shall be maintained in a satisfactory working condition. The use of portable prete nsioning beds for the manufacture of prestressed concrete members is not acceptable. The contractor/fabricator shall provide all other equipment and tools necessary for the construction and the prestressing. 603.3.3.2-Equipment: The jacks shall be eq uipped with instruments for monitoring the hydraulic pressure. Electronic pressure transducers with digital indicators may be used. All pressure gauges or electronic pressure indicators shall indicate the load directly to one percent (1%) of the maximum gauge or sensor/indicator capacity or two percent (2%) of the maximum load applied, whichever is smaller. Each jack and its gauge shall be calibrated as a unit with the cylinder extension in the approximate position that it will be at final jacking force. The calibration of the jack and gauge shall be done while the jack is in the identical configuration as will be used on the site, e.g., same length hydraulic lines. An independent laboratory shall furnish certified calibration charts with each jack and gauge used in the work. Certified calibration of each ram shall be made prior to the start of stressing operations and every six (6) months thereafter, or as requested by the Engineer. Any repair of the rams, such as replacing seals, changing length of hydraulic lines, changing type of pump or using gauges which have not been calibrated with the ram, shall be cause for recalibration of the jack and gauge with a load cell. No extra compensation will be allowed for the initial or subsequent ram calibrations. 603.3.3.3-Forms and Casting Beds: Forms and casting beds shall be subject to the approval of the Engineer. Unless otherwise approved, only metal forms on concrete founded casting beds shall be used. The forms and casting beds shall be well constructed, carefully aligned, substantial and firm, securely braced and fastened together, sufficiently tight to prevent leakage of mortar and strong enough to withstand the action of mechanical vibrators. The forms shall be constructed to permit movement of the member s without damage during release of the prestressing force or movement caused by thermal expansion during curing. The casting beds and all form work will be approved before any concrete is placed, but such approval shall not relieve the contractor/fabricator of responsibility for the results obtained. 603.4-WORKING DRAWINGS: 603.4.1-General: The contractor/fabricator shall expressly understand that the Engineer’s approval of the working drawings submitted by the contractor/fabricator covers the requirements for "strength and detail," and that the Engineer assumes no responsibility for errors in dimensions. Working drawings must be approved prior to performance of the work involved and such approval shall not relieve the contractor/fabricator of any responsibility under the contract for the successful completion of the work. All working drawings shall be in English units. Use of dual (metric and English) units is not allowed. 603.4.2-Shop Drawings: The contractor/fabricator shall submit copies of the detailed shop drawings to the Engineer for approval. Shop drawings shall be submitted sufficiently in advance of the start of the work to allow time for review by the Engineer and correct ions by the contractor/fabricator without delaying the work. The size of the original drawings shall be twenty-two (22) inches x thirty-four (34) inches including margins, unless otherwise permitted. The shop drawings submitted for approval may be reduced. Shop drawings for concrete structures shall give full detailed dimensions and sizes of component parts of the structure and details of all miscellaneous parts. Design camber for all members shall be shown on the shop drawings. 603.4.3-Erection Drawings: The contractor shall submit drawings illustrating fully their proposed method of erection. The drawings shall show details of all falsework bents, bracing, guys, dead-men, lifting devices, and attachments to the bridge members: sequence of erection, location of cranes and barges, crane capacities, location of lifting points on the bridge members, and weights of the members. The plan and drawings shall be complete in detail for all anticipated phases and conditions during erection. Design calculations , sealed by a Registered Professional Engineer, shall be submitted by the contractor/fabricator to the Engineer for approval which will demonstrate that allowable stresses for falsework and concrete members being erected are not exceeded and that member ca pacities and final geometry shall be correct. When the designated concrete deck overhang exceeds thirty ( 30) inches, the erection drawings submitted by the contractor/fabricator shall include complete details of the forming and bracing for the overhang and shall transmit the concrete deck dead load to an area of the beam or stringer which will prevent distortion. All forming and bracing procedures are subject to approval of the Engineer. 603.5-REINFORCEMENT: All reinforcing bars and welded wire fabric shall meet all requirements of Section 602 and shall be free of frost, loose rust, grease, dirt, oil, paint, mill scale, corrosion or other deleterious substances. Any steel which cannot be satisfactorily cleaned shall not be used. When splicing is required, all reinforcing bars shall be lapped for a length of at least 30 bar diameters. Reinforcing bars, welded wire fabric and other embedded fixtures shall be accurately placed as indicated on the Plans and shall be maintained in their correct position during the manufacture of the unit. Reinforcement shall not be held in position by tack welding. The minimum concrete cover for reinforcing steel shall be as follows, unless otherwise shown on the Plans: Main Reinforcement......................................1½ inches Slab Reinforcement, top of slab ....................1½ inches Slab Reinforcement, bottom of slab ..............1 inch Stirrups and Ties............................................1 inch The longitudinal or main wires of welded wire fabric shall be placed transverse to the longitudinal axis of the unit. Laps of welded wire fabric shall be a minimum of six (6) inches unless otherwise approved by the Engineer. 603.6-CONCRETE: 603.6.1-General: The composition, proportioning, and mixing of concrete shall be such so as to produce a homogeneous concrete mixture of a quality that will conform to the test and design requirements specified and as noted on the Plans. Concrete for all prestressed members shall have a minimum compressive strength as may be specified on the plans or in the special provisions. Materials used to form voids in the members shall be fabricated from form material acceptable to the Engineer or from cardboard, which has been treated with a waterproofing agent. Any void made from more than one piece of material shall be glued and banded to prevent separation during concreting operations. Any evidence of separation will be cause for rejection. All concrete materials including admixtures shall meet requirements specified in subsection 603.2 and/or as indicated in the plans. 603.6.1.1-Class S-P Concrete: Class S-P concrete shall be self-consolidating concrete for precast/prestressed applications and may be used for the fabrication of prestressed concrete box beams. If Class S -P concrete is to be used in the fabrication of prestressed concrete I-Beams or Bulb Tee Beams, additional testing, as outlined in Section 603.6.1.1.1, shall be required. Class S-P concrete shall meet the requirements of this Section. Class S-P concrete shall consist of a homogeneous, flowable mixture of cement, fine aggregate, coarse aggregate, chemical admixtures and water. Class S-P concrete may also contain fly ash, slag cement, and silica fume. The mixture proportions shall be such that the Class S-P concrete will resist segregation, bleeding, and the generation of foam during placement, and will need no external compaction or vibration, unless the mix is qualified as outlined in Section 603.6.1.1.1. While the properties of fresh SCC differ significantly from that of conventional fresh concrete, the quality in terms of strength, durability, an d performance of the hardened SCC shall be equal to or better than that of a similar specified conventional concrete mix. Establishment of the mixture proportions shall be coordinated with the manufacturer of the admixtures which will be used in the Class S-P concrete. SCC exhibits self -leveling capabilities. Creating a successful SCC mix requires combining ingredients to achieve a highly-flowable product that also has the capability to resist dynamic segregation and foaming during placement while resisting static segregation and bleeding once in place. SCC mix designs are often achieved using high -range water reducing (HRWR) admixtures, and by carefully selecting a proper aggregate gradation, incorporating high volumes of powder in the mix, through the u se of viscosity-modifying admixtures (VMAs), or a combination of the previously mentioned. For Class S -P concrete, a combination of admixtures which may be used includes water-reducing admixtures, air -entraining agents, water -reducing and retarding admixtures, VMAs, shrinkage -reducing admixtures (SRAs), and other specific performance admixtures, provided they are on the WVDOH approved list of admixtures. These admixtures used shall all come from the same manufacturer, and measures should be taken to ensu re that no adverse reactions occur. Also, for Class S -P concrete, it is permitted to use a combination of up to two AASHTO gradations of coarse aggregate to obtain an optimal combination of strength, self -consolidating ability, and passing ability. Likewise, a combination of up to two SCMs may be used in combination with Portland cement for Class S-P concrete in order to achieve ideal characteristics for the mix. 603.6.1.1.1-Pre-Qualification of Class S -P Concrete Construction Methods: If Class S -P is to be used in the fabrication of prestressed concrete I -Beams or Bulb Tee Beams, or if vibration is to be used during fabrication, the Class S -P concrete mix and proposed method of construction must be pre-qualified prior to fabrication. A full-size test me mber, at least ten (10) feet in length shall be constructed with the Class S- P concrete mix which will be used during fabrication. The full -size test member shall represent the “worst-case” member which the Fabricator shall be allowed to fabricate, using Class S-P concrete. This “worst-case” member shall consist of the tallest I-beam or Bulb Tee shape and shall contain the maximum amount of prestressing strand and reinforcing steel which would be encountered in such a member. The type and maximum duration of vibration, which will be used during fabrication, shall also be used during construction of this test member. All other aspects of construction of this test member, including the free fall height of concrete above the beam, shall be identical to those which will be used during fabrication of members during production. After the completion of curing of this test member, three four (4) inch diameter cores shall be taken from the member at mid-length. One core shall be taken from the top flange of the member, one core shall be taken from the web of the member at mid-height, and one core shall be taken from the bottom flange or bulb of the member. A point count, in accordance with MP 700.03.50 or other equivalent test method approved by the Engineer, shall be performed on each of these cores in order to determine if segregation is occurring due to the vibration. If the results of the point counts show that the percentages of coarse aggregate, fine aggregate, air content, and paste vary by more than 15% between any of these three cores, that type of member shall not be permitted to be constructed with Class S-P concrete. If, at some time after the above mentioned “worst-case” test member is fabricated and tested, the Fabricator needs to fabricate a me mber larger than this “worst -case” member (which would now be a new “worst-case” member), the Engineer shall determine, based on the test results from the previous “worst-case” member, whether or not the testing required in this section will again be requi red for this new “worst -case” member. If the test results from the previous “worst-case” member are within an acceptable margin below the allowable test criteria, and if the new “worst -case” member is not significantly larger than the previous “worst-case” member, then the Engineer may allow this new “worst - case” member to be constructed with Class S -P concrete without additional pre - qualification testing required in this section. 603.6.2-Mix Design: Concrete mixtures shall be established initially by methods in accordance with ACI 301, Chapter 4. Class S -P concrete mixtures shall be developed in accordance with MP 711.03.23 and the requirements of this Section, not the ACI methods. Mixes may be designed either by a commercial laboratory or by PCI certified concrete plant personnel. Prior to adoption of a mix design as a plant standard, it shall be field tested by use of the production plant batching and mixing equipment, construction methods, and curing to be used in production of the members. All design mixes shall be developed using the type of cement, the type and gradation of aggregates, and admixtures proposed for use in plant mixes. The mix design shall also include either compressive strength tests or a penetration resistance test (in accordance with ASTM C403) that verify the amount of time it takes to achieve a compressive strength of 500 psi. The Engineer shall approve the mix design. When any of these variables are changed, or after a three-year time period, the mix shall be re-evaluated and submitted to the Engineer for approval. Any design mix with an aggregate(s) that has a reactivity class R1, R2, or R3, as shown as in Approved Aggregates Source List, shall be developed in accordance with subsection 601.3.1.1. If an aggregate Source is not listed on the Approved Aggregates Source List, the Division will test the fine and coarse aggregate from the Source, in accordance with AASHTO T 303, to determine the reactivity class of the aggregate prior to its use on a ny WVDOH project. The Division will inform the Fabricator of the reactivity class of aggregates that they are proposing to use. If a cement Source and/or a SCM Source are not listed on the Approved Source List, the Division will test cement and/or SCM from that Source prior to its use on any WVDOH project. 603.6.2.1-Class S -P Concrete Mix Design Testing: To ensure repeatability of production, two batches of concrete with the same mix proportions shall be created for mix qualification testing. The results of this testing shall be submitted to the Division for approval at least 45 days prior to the use of the mix in construction. Personnel performing testing on Class S -P concrete shall be certified by ACI as a Self -Consolidating Concrete Testing Technician. The two trial batches at the target cement factor plus one bag (see Section 3.3 of MP 711.03.23), are not required for Class S-P concrete mixes. Batching equipment and curing procedures for test specimens fabricated from these test batches should be as close as possible to the techniques that will be used by the Fabricator during production. The minimum batch size for these trial batches shall be 2.0 yd 3, or the largest possible batch when using the mixer that will be used for production, if approved by the Division. The fresh properties measured at the proposed time of casting for each trial batch shall include air content, consistency, Visual Stability Index (VSI), T 50, J -Ring Value, Unit Weight, Yield, Rapid Assessment of Static Segregation Resistan ce, and Segregation Resistance. Target values and their tolerances for the fresh properties of the trial batches shall conform to the requirements in the following table: TABLE 603.6.2.1A Fresh Property Mix Design Batch Acceptance Criteria Air Content ***Target minus 0.5% ≤ Air Content ≤ ***Target plus 1.5% Slump Flow (ASTM C1611) Target ≤ Spread ≤ Target plus 1.5 inches 2 seconds ≤ T50 ≤ 7 seconds Visual Stability Index ≤ 1.0 Passing Ability (ASTM C1621) J-Ring Value ≤ 1 inch Rapid Assessment of Static Segregation Resistance (ASTM C1712) Penetration Depth (PD) ≤ 0.5 inch Segregations Resistance (ASTM C1610) Segregation ≤ 12% Unit Weight and Yield ± 2% of Theoretical *** The target air content of Class S-P concrete shall be determined in accordance with Table 603.6.2.1B TABLE 603.6.2.1B Nominal Maximum Aggregate Size in the Class S-P Mix Target Air Content of Class S-P Concrete 3/8 inch (9.5 mm) 7.5% ½ inch (12.5 mm) 7.0% ¾ inch (19 mm) 6.0% After the properties of the trial batches of fresh concrete have been established to be within the specification limits in Table 603.6.2.1A, specimens will be cast for compressive strength, modulus of elasticity, creep, length change (total shrinkage), rapid chlorid e permeability and freeze -thaw testing. Casting of all Class S -P specimens to be used for hardened property testing shall be done in one lift without rodding. Compressive strength testing shall be conducted on both trial batches, but modulus of elasticity , creep, length change (total shrinkage), rapid chloride permeability and freeze -thaw testing is only required on one of the trial batches. If steam curing is to be used during the production, the same curing procedure (time, temperature, etc.) shall be used on all of the above test specimens except for the shrinkage specimens. After discontinuation of steam curing, all specimens shall be cured as noted in the footnotes in the table below. Target values and their tolerances for the hardened properties of the trial batches shall conform to the requirements in Table 603.6.2.1C: TABLE 603.6.2.1C Hardened Property Test Total # Specimens Specimen Size Age at Testing Magnitude of Loading Approval Condition Compressive 7 4”x8” 1 @ 24 ± 2 hrs. Load Until per Design Strength or 6”x12” 1 @ 3days ± 2 hrs. Failure (AASHTO T 22) cylinders 1 @ 7days ± 2 hrs. 1 @ 14days ± 2 hrs. 3 @ 28days ± 4 hrs. Modulus of 7 6”x12” 1 @ 3days ± 2 hrs. 40% of a≥ 57,000√f ' c Elasticityb cylinders 1 @ 7days ± 2 hrs. compressive (ASTM C469) 1 @ 14days ± 2 hrs. strength 3 @ 28days ± 4 hrs. (obtained above) Creepb (ASTM C512) 8 total (3 loaded, 6”x12” cylinders 72 ± 2 hours at age of initial loading 40% of compressive Creep Coefficient c 3 remain unloaded, strength at time of ≤ 1.19 at 90 days a 2 tested for loading compressive strength) Length Change 3 3”x3”x11” 56 days 28-day cure ≤ 0.0002 at 28 (ASTM C157) prisms per ASTM C157 then days of Air Storage a Air Storage for 28-days Rapid Chlorideb 3 4”x2” 56 days 60.0 ± 0.1 V ≤ 1500 Permeability disc or coulombs (AASHTO T specimen 28 days (56 days) or 277) ≤ 2000 coulombs (28 days) Freeze-Thaw 3 3”x4”x16” 28 day cure prior to 300 cycles Durability Resistance prisms testing (0oF to 40oF) Factor ≥ 80 (ASTM C666- Procedure A)b

a.If the values obtained from testing the Class S-P mix do not meet the specified values in Table 603.6.2.1C, then the Fabricator’s Engineer may submit calculations for prestress losses, camber, and long term deflections to the Division for review in accorda nce with Section 105.2.1.1, the Division Approval Method for shop drawings. If the Fabricator’s calculations show that the values exceeding the specified values in Table 603.6.2.1C will not adversely affect the prestress losses, camber, and long term deflections, and the Division approves these calculations, then the Class S-P mix in question may be used to fabricate prestressed bridge members.
b.After the discontinuation of steam curing, test specimens shall be removed from the molds within 23.5 ± 0.5 h ours and moist cured in the laboratory at a temperature between 73.5 ± 3.5 °F until the time of test. Freeze-Thaw Resistance testing shall begin when the specimens are at an age of 28 days.
c.The Creep Coefficient shall be defined as the Creep Strain at 90 days divided by the Initial Elastic Strain at the Time of Initial Loading. The Initial Elastic Strain shall be determined within 2 minutes after the application of the initial load. In addition to the hardened property tests above, at least one trial batch shall be subjected to the prestressing strand bond strength testing as outlined in MP 603.06.20. The Class S-P mix in question must pass this test. Although a concrete mix may meet the necessary strength requirements and exhibit acceptable fresh properties at the time of initial testing, the Engineer can require a re-design of the mix based on other criteria, such as insufficient retention of the slump flow for the mix, excessive foam buildup, etc. The slump flow of the mix must be retained, within the limits specified in Table 603.6.4.1, throughout the duration of the concrete placement. The submittal for a proposed mix design shall include completed copies of Attachments 1S -P, 2S-P and 3S-P of MP 711.03.23. All pertinent information suppor ting these attachments and pertaining to the information in them should also be submitted. 603.6.3-Proportioning of Normal (Non-SCC) Concrete: Materials shall be proportioned by weight, unless otherwise authorized by the Engineer. The concrete shall c ontain the minimum water -to-cementitious materials (w/c) ratio required to obtain satisfactory workability and the specified minimum strength, but in no case shall this (w/c) ratio exceed 0.44, including the free water in the aggregate and/or admixtures. The minimum cement factor shall be 658 lbs. per cubic yard. Concrete for all members shall be air -entrained with a target air content of seven percent (7%). A working tolerance of plus or minus two percentage points will be allowed. When the ambient tem perature is 90°F or higher, a mix using a retarding admixture shall be used. Slump shall not exceed eight (8) inches with the use of high range water reducers. 603.6.3.1-Proportioning of Class S-P Concrete: The water-to-cementitious materials (w/c) ratio for Class S -P concrete shall fall within a range of 0.32 to 0.40. A water -to- cementitious materials (w/c) ratio less than 0.32 may be used if approved by the Engineer. The minimum cementitious material factor for Class S -P concrete shall be 658 lbs. p er cubic yard. Unless otherwise approved by the Engineer, the maximum cementitious material factor for Class S-P concrete shall be 799 lbs. per cubic yard. Concrete for members cast with Class S-P concrete shall be air-entrained with a target air content as shown in Table 603.6.2.1B. A working tolerance of plus or minus 1.5 percentage points will be allowed during fabrication. Material proportions should be selected to ensure an optimal combination of fresh and hardened properties. A standard Class S-P concrete shall be designed to have a slump flow of 25 ± 2 inches in diameter. This twenty-five (25) inch slump flow diameter will be referred to as the target value for mix qualification and site approval. The contractor may request that the Engineer approve a different target slump, which must be less than twenty-five ( 25) inches. If approved, this requested value will be used as the target value for mix qualification and the approval of batches during production. TABLE 603.6.3.1 Cementitious Materials Maximum Percent of Total Cementitious Materials in Class S-P Concrete by Mass Class F Fly Ash 25 Slag Cement 50 Silica Fume 10 Total of Class F Fly Ash and Silica Fume 35 Total of Slag Cement and Silica Fume 50 NOTE: Class F Fly Ash shall constitute no more than 25 percent (25%) of the total weight of cementitious materials. Silica fume shall constitute no more than 10 percent (10%) of the total weight of cementitious materials. 603.6.4-Sampling and Test Methods: Sampling Freshly Mixed Concrete AASHTO T 141 Slump of Hydraulic-Cement Concrete AASHTO T 119 Unit Weight and Yield of Concrete AASHTO T 121 Air Content of Freshly Mixed Concrete AASHTO T 152 or AASHTO T 196 Standard Practice for Making and Curing Concrete Test Specimens in the Field AASHTO R 100 Compressive Strength of Cylindrical Concrete Specimens AASHTO T 22 Temperature of Concrete ASTM C1064 Static Modulus of Elasticity and Poisson’s Ratio of Concrete in Compression ASTM C469 Fabricating Test Specimens with Self-Consolidating Concrete ASTM C1758 Slump-Flow of Self-Consolidating Concrete ASTM C1611 Passing Ability of Self-Consolidating Concrete using J-Ring ASTM C1621 Rapid Assessment of Static Segregation Resistance of Self- Consolidating Concrete Using Penetration Test ASTM C1712 Static Segregation of Self-Consolidating Concrete using Column Technique ASTM C1610 Standard Method of Test for Electrical Indication of Concrete’s Ability to Resist Chloride Ion Penetration AASHTO T 277 Standard Test Method for Resistance of Concrete to Rapid Freezing and Thawing ASTM C666 Standard Test Method for Creep of Concrete in Compression ASTM C512 Length Change (Drying Shrinkage) of Hardened Concrete ASTM C157 Standard Test Method for Microscopical Determination of Parameters of the Air-Void System in Hardened Concrete ASTM C457 Standard Method of Microscopical Determination of Air-Void Content MP 700.03.50 Cylinders shall be manipulated and cured by methods identical to those used in curing the concrete members. Slump, Temperature, and Air Content tests shall be conducted on the first batch of concrete each day and every time that cylinders are fabricated. Slump, Temperature, and Air Content tests shall also be conducted whenever Quality Control Personnel or the Inspector see a variation in the mix. Unit Weight and Yield tests shall be conducted on the first batch of concrete each day and thereafter, as deemed necessary by Quality Control or Quality Assurance Personnel. The Fabricator's Quality Control Personnel shall maintain records of the beam number(s) into which each batch of concrete is placed. 603.6.4.1-Acceptance Testing of Class S-P Concrete: During production, Class S-P concrete shall be tested to determine the air content, slump-flow, passing ability using the J-Ring, rapid segregatio n resistance, and temperature. All five of those tests shall be performed on at least the first three batches of concrete produced each day, and thereafter until satisfactory control is established. Satisfactory control is established when all the results of three consecutive sets of tests meet the performance criteria in Table 603.6.4.1, without any mix adjustments. Once satisfactory control is established, the testing frequency may be reduced to one set of tests for each member cast in a form that day. If any mix adjustments are required or performed, testing shall continue until three consecutive sets of tests meet the performance criteria without any mix adjustments. Unit Weight and Yield tests shall be conducted on the first batch of concrete each day and thereafter, as deemed necessary by the Quality Control or Quality Assurance Personnel. The fresh concrete properties shall meet performance criteria as shown in Table 603.6.4.1. TABLE 603.6.4.1 Fresh Property Production Acceptance Criteria Air Content (ASTM C173) Target ±1.5% Consistency (ASTM C1611) Target Spread ± 2.0 inches 2 seconds ≤ Measured T50 ≤ 7 seconds Visual Stability Index ≤ 1.0 Passing Ability (ASTM C1621) J-Ring Value ≤ 1.5 inch Rapid Segregation Resistance (ASTM C1712) Penetration Depth (PD) ≤ 0.5 inch Temperature < 90°F Unit Weight and Yield ± 2.0% of Theoretical 603.6.5-Strength of Concrete: Each strength test (i.e. strand release and 28 -day) shall consist of the average strength of a minimum of two compressive strength test cylinders fabricated from a single randomly selected batch of concrete, as it is being placed in the forms. A minimum of one set of cylinders shall be fabricated (at random) for each member cast in a form, with a maximum of one set of cylinders per batch of concrete. These cylinders, molded during fabrication, shall be the same size specimens as were used in the approved mix design. Any member, for which the average concrete compressive strength at 28 -days is less than the 28-day design compressive strength value, may be rejected at the option of the Contractor. If the Contractor elects to use such a member, it will be evaluated as to its adequacy for the use intended. Any member evaluated as unsatisfactory will be rejected by the Division, and the Contractor shall fabricate another member to replace the one which was evaluated as unsatisfactory. When the evaluati on indicates that the member will be satisfactory for its intended use, the Engineer will provide for an appropriate price adjustment under the provisions of subsection 603.14.2.1. Whenever the compressive strength of a member at 28-days is less than the 28-day design compressive strength value, the subject member may still be accepted without a price adjustment if the compressive strength at any time prior to shipment (up to a maximum of 56- days from the date of fabrication) exceeds the 28-day design compressive strength value. The Division shall not be responsible for any project delays incurred due to the delayed strength attainment, and time extensions under Section 108 of the Specifications are not applicable to this scenario. 603.6.6-Batching and Mixing: Concrete batching plants and their operation shall be in conformance with ASTM C94, “Specifications for Ready-Mix Concrete”. Concrete batch plants shall be capable of producing concrete of the quality required and they shall be adequately equipped and properly operated. Concrete supplied to the plant by an outside batch plant shall meet the same requirements of batch plant facilities. Evidence of conformance will be certification of the outside plant by the National Ready -Mix Concrete Association (NRMCA). Fine and coarse aggregates and cement shall be measured by weight. Water and liquid admixture may be measured by either weight or volume. Measurement of the various components of concrete, and measuring equipment shall be in accordance with ASTM C94. Concrete shall be mixed by one of the following methods:
1.Central mixed concrete-concrete mixed in a central stationary mixer and delivered to the casting area by appropriate methods.
2.Shrink mixed concrete-concrete that is partially mixed in a stationery mixer, then mixed completely and delivered to the casting site in a truck mixer.
3.Truck mixed concrete -concrete that is completely mixed in a truck mixer as it is delivered to the casting site. Mixing times shall be established by u niformity tests in accordance with procedures in ASTM C94. Class S-P concrete shall be batched at the site of fabrication of the prestressed members. For Class S-P concrete, all wash water must be completely discharged from the mixing drum prior to addition of any materials for the subsequent batch. When using Class S -P concrete, under no circumstances shall water be used to adjust the consistency of the mix. If it is necessary to adjust the Class S-P concrete’s consistency, this shall be done through the addition of chemical admixtures only, and adequate mixing after the adjustment, must occur before any Class S-P concrete is discharged into the formwork. Two compressive strength specimens, from this adjusted batch, shall be fabricated and tested. A lso, the concrete tests required in Table 603.6.4.1, with the exception of the unit weight and yield tests, shall be performed on this adjusted batch. These results must meet the requirements shown in Table 603.6.4.1. 603.6.7-Placing Concrete: Suitable means shall be used for placing concrete without segregation. The concrete mixture shall not be dropped from a distance of more than four (4) feet, relative to the top of the form or the reinforcement. Special care shall be taken to deposit the concrete in its final position in each part of the form. Working of flowing concrete along the forms from the point of deposit will not be permitted. Care must be taken to work the concrete under and around the prestressing strands and reinforcement. The plastic concrete shall be consolidated in place by either external or internal vibration, or both when necessary. The vibrators shall be of a type and design approved by the Engineer, and the size of the vibrating head will be governed by the spacing of the prestr essing cables and reinforcement. Vibrators may be used only to consolidate the concrete after it has been properly placed. Internal vibrators shall be operated vertically and shall be slowly pushed into and pulled out of the concrete and shall not be held in one spot long enough to cause segregation. Concrete segregated by the vibrator shall be removed and discarded. Partially hardened layers of concrete shall not be penetrated or disturbed by the vibrator. Transmission of vibration into prestressing cable or reinforcement embedded in partially hardened concrete by the vibrating equipment will not be permitted. The plans for delivery and placement of Class S -P concrete to the casting beds should ensure that construction of the entire member is completed during the workable period of the concrete established in MP 711.03.23, such that no vibration of the concrete is necessary at any point during construction. If vibration is to be used at any time during fabrication, the Class S-P concrete mix a nd the method of construction must be pre -qualified as outlined in Section 603.6.1.1.1. Batching, transportation and delivery of the Class S -P shall be planned by the manufacturer such that there is a reasonably continuous feed into the formwork and, therefore, at no time shall there be a large pause or delay in the casting process which causes the fresh concrete properties to exceed the limits set forth in Table 603.6.4.1. 603.6.8-Cold Weather Production: In addition to the requirements of Subsection 601.9.1, the following requirements shall apply to outdoor casting operations. When ambient temperatures below 40° F are anticipated, the following shall be used as necessary to keep the temperature of concrete within the prescribed limits:
1.Minimum concrete temperature shall be 50º F after placement.
2.Concrete shall not be placed on cold forms, steel, or appurtenances. When the temperature of these facilities are below 40º F, steam heat or other means shall be provided to maintain the temperature to at lea st 50° F unless concrete is delivered above 60º F and no frost, snow or ice is present in the form.
3.Placing concrete under covers or in suitable enclosures.
4.Use of heated mixing water.
5.Avoidance of the use of frozen aggregate or aggregate containing frost, snow or ice.
6.Use of insulated forms. 603.6.9-Hot Weather Production: In addition to the requirements of Subsection 601.9.2, the following requirements shall apply to outdoor casting operations: When the ambient temperature is above 100 F, or other adverse weather conditions are present, it is recognized that plastic shrinkage of concrete, or loss of strength below specification requirements, or both may occur. If such conditions do occur, the following procedures or combination of procedures s hall be used as necessary to correct these deficiencies:
1.Water fog spraying of forms, prior to placement of concrete. Forms exposed to direct sunlight can be misted for cooling prior to placement of concrete.
2.Shaded storage for aggregates.
3.Burying, insulating or shading water supply facilities.
4.Sprinkling or fog spraying of aggregates.
5.Use of shaved or crushed ice for a portion of the mixing water. Only so much ice shall be used as will be entirely melted at the completion of the mixing period.
6.Use of cold water in batching. Water can be chilled and stored in an insulated tank or pulled from a source if temperatures are low enough to aid mix temperature reduction.
7.Application of wet burlap or mats or fog spraying as soon as the water sheen disappears from the concrete. This is especially important for hot, windy, exposed locations.
8.Use of white pigmented curing compound for its heat -reflective properties except on composite surfaces.
9.Use of self-retarding admixtures.
10.Avoidance of the use of cement with temperatures over 170F.
11.Shading of product surface during and after casting to avoid heat buildup in direct sunlight. Concreting operations shall be discontinued when concrete temperatures exceed 100F at the time of placing. 603.7-PRESTRESSING: 603.7.1-Protection of Prestressing Steel: All prestressing steel shall be protected against physical damage and rust at all times during storage and manufacturing. Prestressing steel shall also be free of deleterious material such as grease, oil, wax, or paint, except where called for on the plans. Prestressing steel that has sustained physical damage at any time shall be rejected. The use of prestressing reinforcement having kinks, bends, nicks, or other defects will not be permitted. The development of pitting, other than slight rusting shall be cause for rejection. Prestressing steel shall be packaged in containers or shipping forms for the protection of the strand against physical damage and corro sion during shipping and storage. A corrosion inhibitor which prevents rust or other results of corrosion shall be incorporated in a corrosion inhibitor carrier type packaging material, or when permitted by the Engineer, may be applied directly to the stee l. The corrosion inhibitor shall have no deleterious effect on the steel or concrete or bond strength of steel to concrete. The shipping package or form shall be clearly marked with a statement that the package contains high strength prestressing steel, and the type of corrosion inhibitor used, including the date packaged. All anchorages, end fittings, couplers, and exposed strands, which will not be encased in concrete or grout in the completed work, shall be permanently protected against corrosion. If an anti -bonding agent is used on the forms to facilitate member removal, every precaution shall be taken to protect the prestressing strands against any ° of coating by the anti- bonding agent. 603.7.2-Storing of Prestressing Steel: Prestressing steel shall be stored in a protected area which includes a roof (and sides if necessary) to keep moisture off the strand. In addition the cover must have a floor or at least the strand must be placed on supports to keep it out of mud and water until it is to be used. It shall not be removed from its protective packaging until immediately prior to installation in the forms and placement of concrete. Openings in the packaging shall be resealed as necessary to protect the unused steel. While expos ed, the steel shall be protected to prevent corrosion. 603.7.3-Placement of Prestressing Steel: Prestressing shall be accurately installed in the forms and held in place by the stressing jack or temporary anchors and, when tendons are to be draped, by hold-down devices. The hold down devices used at all points of change in slope of tendon trajectory shall be of a low-friction type. 603.7.4-Safety Measures: Effective safety measures shall be taken to prevent injuries to personnel due to the breakage of strands or failure of anchorage devices during the tensioning operations. The protection provided shall be adequate and shall permit the inspector to perform his normal duties. When the safety precautions, in the opinion of the Engineer, are inadequate the contractor will revise the procedures or equipment to the satisfaction of the Engineer. The inspector will abide by the safety rules established by the producer. 603.7.5-Stressing Requirements: 603.7.5.1-General: The provisions set forth in this section refer to the application and measurement of stresses to prestressed concrete members manuf actured by the process of pretensioning. Prestressing forces shall not be transferred to any member nor shall end anchors be released before the concrete has attained a minimum compressive strength as specified on the plans or in the special provisions as determined by tests of standard cylinders cured identically as the member. An initial force shall be applied to each strand such as to develop a load of approximately 10% of the final prestressing load as shown on the plans. A record shall be maintained of the jacking force and elongations thereby. Several prestressed members may be cast in one continuous line and stressed at one time. Forms shall be removed and members detensioned immediately after steam curing or heat curing is discontinued while the co ncrete is still warm and moist. The elements shall be cut or released in an order such that lateral eccentricity of prestress forces will be a minimum. 603.7.5.2-Tensioning of Strands: In all methods of tensioning, stress induced in the strands shall b e determined by monitoring applied force and independently by measurement of elongation. Applied force may be monitored by direct measurement using a pressure gauge piped into the hydraulic pump and jack system. The elongation measurements shall agree with their computed theoretical values within a tolerance of ±5%. If discrepancies are in excess of 5% between the calculated forces, determined by elongation measurement and gauge reading, the tensioning operation shall be suspended and the source of error determined, evaluated, and corrected by qualified personnel before proceeding. Calculations for elongation and gauge readings must include appropriate allowances for friction in the jacking system, strand seating, movement of bulkheads, bed shortening if under load, thermal corrections, and any other compensation for the setup. 603.7.5.3-Methods of Stress Measurement: Methods of measurement of the stressing force consist of pressure gauges to measure force from the pressure applied to hydraulic jacks or any other method approved by the Engineer. 603.7.5.4-Gauging Systems: Hydraulic gauges shall conform to the provisions set forth in Section 603.3.3. All gauges measuring the stressing load shall be graduated so they can be read within a tolerance of ±2%. Tensioning methods employing hydraulic gauges shall have appropriate bypass valve snubbers and fittings so that the gauge pointer will not fluctuate but will remain steady until the jacking load is released. 603.7.5.5-Control of Jacking Force: Pressure bypass valves may be used for stopping the jack at the required load or for manually stopping the load with the valve. The accuracy of setting of automatic cutoff valves shall be verified by running to the desired cutoff load whenever there is reason to suspect improper results, and at a minimum, at the beginning of the operation each day. 603.7.5.6-Wire Failure in Strands: Failure of wires in a pretensioning strand is acceptable provided the total area of wire failure is not more than 2% of t he total area of strands in a member, and providing the breakage is not symptomatic of a more extensive distress condition. Failure of any individual wire prior to placing concrete will require replacement of the strand. 603.7.5.7-Calibration Records for Jacking Equipment: All jacking and load measuring equipment shall be calibrated as specified in Section 603.3.3. Calibration records should show the following data.
1.Date of calibration.
2.Agency, laboratory or registered WV Professional Engineer (PE) super vising the calibration.
3.Method of calibration; i.e. proving ring, load cell, testing machine, etc., and its calibration reference.
4.The full range of calibration with gauge readings indicated against actual load. Calibration records for all tensioning sys tems being used shall be available for preparing theoretical tensioning values. Personnel involved in preparing tensioning calculations shall have a copy of these records for reference. 603.7.6-Pretensioning and Strand Debonding: Pretensioning shall co nform to the provisions set forth in Article 2.2, “Pretensioning” of the latest edition of the PCI Quality Control Manual MNL-116. Plastic sheathing shall be used for strand debonding and shall be approved by the Engineer prior to use. Items such as ani mal fat, reactive greases, or PVC pipes shall not be used. Any other material shall be approved by the Engineer prior to use. 603.7.7-Detensioning: Detensioning shall conform to the provisions set forth in Article 2.3, “Detensioning” of the latest edition of the PCI Quality Control Manual MNL-116. 603.7.8-Concrete Cover : Minimum concrete cover for prestressing steel shall be 1 ½ inches unless otherwise shown on the plans. 603.8-CURING: 603.8.1 General: Careful attention shall be given to the proper curing of concrete. Prior to placing of concrete, the contractor shall submit the proposed curing methods and procedures to the Engineer for approval. Elevated temperature curing facilities shall be tested pr ior to approval. Approved equipment and materials for curing shall be available for use prior to casting. Inadequate curing facilities or lack of attention to the proper curing of concrete shall be sufficient cause for the Engineer to stop all concrete p lacement until approved curing is provided. Inadequate curing may be cause for rejection of the member. All test cylinders shall be cured in the same environment as the precast/prestressed concrete members. Curing shall be commenced prior to the formation of surface shrinkage cracks. The curing mats, sheets, or blankets shall be carefully placed in contact with the concrete member to avoid damage to the freshly finished concrete. The following curing requirements shall apply for precast/prestressed members. Any other special method of curing shall meet with the approval of the Engineer. Concrete shall not be exposed to temperatures below freezing until the specified minimum strength as shown in plan notes has been attained. All concrete shall be cured by water curing, accelerated temperature curing, or any other method approved by the Engineer. 603.8.2-Water Curing: All exposed surfaces of the concrete shall be kept wet continuously for the required curing time. The water used for curing shall meet the requirements of subsection 603.2. Water curing shall be permitted as follows: 603.8.2.1-Wet Mat Method: For water curing by the mat method, cotton mats, polyethylene sheeting, or polyethylene burlap blankets may be used. The mats, sheets or blankets shall be adequately anchored and weighted to provide continuous contact with all concrete surfaces. Any concrete surfaces which cannot be cured by contact shall be enclosed by mats, adequately anchored, so that outside air cannot enter the enclosure. Sufficient moisture shall be provided inside the enclosure to keep all of the surfaces of the concrete wet for the required curing time, but in no case less than 36 hours. 603.8.2.2-Saturated Cover Curing: The member, covered as specified for the initial phase of curing, shall be maintained on the casting bed in an approved enclosure designed and equipped to insure complete saturation of the covering. The temperature within the enclosure and that of the covering material shall be maintained to provide a uniform curing temperature at the surface of the member, within the limits of 80 F to 130 F, until the specified strength is attained, but in no case less than 36 hours. The covering shall be kept thoroughly saturated throughout the entire curing period an d the temperature of the water used shall be controlled uniformly to maintain the selected curing temperature of the surface of the member. 603.8.2.3-Water Spray Curing: The member, covered as specified for the initial phase of curing, shall be maintained in the casting bed in an approved enclosure. When the concrete is sufficiently hardened to resist damage, the covering shall be removed and the exposed surfaces of the unit shall be subjected to a continuous fine spray of water. The temperature within the enclosure and that of the water used shall be controlled to provide a uniform curing temperature at the surface of the member, within the limits of 80 F and 130F until the specified member strength is attained, but in no case less than 36 hours. 603.8.3-Accelerated Curing: Accelerated curing of the concrete shall be done by low pressure steam curing, or radiant heat curing. Transfer of stress shall be accomplished immediately after the heat curing has been discontinued. Accelerated curing shall b e applied at a controlled rate following initial set of the concrete as per ASTM C403. Accelerated curing shall be done under suitable enclosures which minimize all heat losses and maintain uniform cure conditions within the enclosed area. Members must be maintained wet during accelerated curing time. If accelerated curing is used, the contractor/fabricator shall furnish recording thermometers showing the time-temperature relationship of the concrete throughout the entire curing period. Recording thermometers shall be kept in proper calibration and recalibrated at least annually. 603.8.3.1-Low-Pressure Steam Curing: Low-pressure steam curing shall be done under a suitable enclosure to contain the live steam and minimize moisture and heat losses. The concrete shall be allowed to attain its initial set before application of the live steam. Application of live steam shall not be directed on the concrete or forms such as to cause localized high temperatures. During the initial application of live steam, the concrete temperature shall be raised at an average rate not exceeding 80°F /per hour, until the curing temperature is reached. The maximum sustained concrete temperature during the curing cycle shall not exceed 160F. The maximum temperature shall be held until the concrete has reached the required release strength. The maximum peak concrete temperature during the curing cycle shall be 190°F. The concrete temperature shall be maintained uniformly throughout the extremities of the prestressed member. A t the end of curing, the concrete temperature shall be reduced at an average rate not exceeding 50°F /per hour. 603.8.3.2-Radiant Heat Curing: Radiant heat may be applied by means of pipes circulating steam, hot oil or hot water, or by electric heating elements. Radiant heat curing shall be done under a suitable enclosure to contain the heat, and moisture loss shall be minimized by covering all exposed concrete surfaces with a plastic sheeting or by applying an approved liquid membrane curing compound to all exposed concrete surfaces. The heat application shall be maintained to create a uniform concrete temperature throughout the extremities of the member. After the waiting period prior to application of the heat, the concrete temperature shall increase at an average rate not exceeding 80 F /per hour until the curing temperature is reached. The maximum sustained concrete temperature within the curing cycle shall not exceed 160F. The maximum temperature shall be held until the concrete has reached the required release strength as shown in plan notes. The maximum peak concrete temperature during the curing cycle shall be 190°F. The maximum cooling rate from sustained concrete curing temperature shall be 50°F /per hour. 603.9-FINISHING: To assure the production of well-formed matching members, all surfaces of the concrete shall be finished, shall be true and even, and shall be free from rough, open, or honeycombed areas, depressions or projections. The ed ges shall be finished or chamfered, or both. Care shall be exercised in removing forms to avoid spalling or otherwise damaging the concrete. Top surfaces of prestressed members shall be screeded or rough floated to bring mortar to the surface and cover a ll aggregate. The top surface of members that will receive cast -in-place concrete on the project site shall be finished as noted on the project plans, or if no finish is noted, they shall have either a raked or stiff broom finish. Aggregate shall not be loosened when roughening the surface. The fascia surfaces of bridge members shall be finished with a PCI Grade A Formed Finish. All other members shall be finished with a PCI Standard Grade Formed Finish. Concrete on exposed reinforcing steel and loose laitance on concrete surfaces to be in contact with cast-in-place concrete shall be removed from all members. Fabrication holes, except box beam vent holes, in the bottom of all beams, shall be filled with nonshrink mortar and made flush with the surround ing surface. No patching is required for small holes and irregularities on the sides of adjacent box beams that are to be sandblasted prior to shipment. Care shall be taken in final cutting the ends of strands to avoid damaging the concrete surface.

603.10 Workmanship:

603.10.1 General: Holes and voids in the surface of concrete resulting from bolts, ties, or

large air pockets shall be wetted and filled with mortar having the same proportion of fine aggregate and cement as in the concrete, after which exposed mortar surfaces shall be finished smooth and even with a wood float. Surfaces to be repaired and finished shall be kept wet for at least one hour before hydraulic cement mortar is applied. Immediately following patching work, repaired areas shall be wet cured for at least 48 hours. The wet cure may be accomplished by the use of steam, wet burlap or continuous spray wetting. A liquid membrane -curing compound may be used on non - composite surfaces. Beams or girders having honeycomb of such extent to affect their strength or resistance to deterioration will not be accepted.

603.10.2 Defects and Breakage: Defective or damaged members which cannot be

satisfactorily repaired, o r which are not acceptable to the Engineer will not be incorporated into the work. All other members that sustain damage during fabrication, handling, storage or transportation shall be evaluated in accordance with Chapter three of PCI Journal Vol. 30, # 3 entitled “Fabrication and Shipment Cracks in Precast or Prestressed Beams and Columns”, hereinafter referred to as “specification”. This specification is to be used to determine the severity of cracks. All cracks with a width of 4 mils or less may be repaired by silane treatment if the repair section of the specification allows repairs. All cracks over 4 mils to and including 16 mils shall be repaired by epoxy injection if allowed by the specification. Members with cracks over 16 mils shall not be incorporated into the work unless approved by the Engineer.

603.10.2 1-Epoxy Injection of Cracks: The work shall consist of repairing cracks

with a width greater than 4 mils and up to and including 16 mils on prestressed concrete bridge beams.

603.10.2 1.1-Materials: The epoxy material used for epoxy injection crack repair shall

meet the requirements specified for epoxy resin adhesives in ASTM C881, Type IV, Grade 1, and Classes B or C. For the epoxy paste or material used to bond and cover the injection ports to the substrate, use the epoxy resin manufacturer’s recommendation.

603.10.2 1.2-Equipment: The equipment to be used to inject the epoxy shall meet the

recommendations of the epoxy injection material manufacturer and/or the following requirements:

1.Use equipment that has the ability to automatically proportion the material components within the mix ratio tolerances set by the epoxy materials manufacturer.
2.Use equipment that has the ability to automatically mix the epoxy component materials within the pump and injection apparatus.

603.10.2 1.3-Crack Surface Preparation and Cleaning Requirements: After the

concrete beam has achieved 28 day shipping strength, clean the concrete surface along the crack of all deteriorated concrete, efflorescence and other contaminants which would be detrimental to the adhesion of the surface sealing epoxy compound. The substrate must be sound, dry on the surface, and free from oil and grease. Blow out the crack with oil free and dry compressed air.

603.10.2 1.4-Epoxy Injection: Place the base of the injection ports directly over the

crack and bond to the substrate with an epoxy paste or the recommended product by the epoxy resin manufacturer. The injection ports should be spaced over the length of the crack at a spacing that will allow the epoxy resin to seal the entire crack traveling from one port to another. The ports spacing is dependent upon the viscosity of the resin. Use an epoxy adhesive to seal over the surface ports and exposed cracks. The entire exposed crack is to be covered with the epoxy adhesive leaving only the port holes uncovered. The cure time for the epoxy will be based upon concrete temperature. The temperature requirements of the concrete for the injected resin must be satisfied before the process can begin. Begin injecting at the lowest port on the beam and continue until the epoxy resin begins to “ooze” out of the port above it. The “ooze” out of the port above it is a sign that the crack has been filled to that level. Plug the first port with a cap and move up to the next port, repeating this procedure until the entire crack has been filled with epoxy. Use slow, constant pressure to in ject the epoxy into the crack which will reduce the possibility of leaks or blow -outs and allow time for the repair material to fully penetrate the crack.

603.10.2 1.5-Post Epoxy Injection: After a minimum of 24 hours, the injection ports

can be removed from the beam. Clean the concrete surface areas of excess epoxy injection work. Clean so as to not damage the concrete by scraping, light sand blasting, grinding, use of solvents, or any other appropriate method approved by the engineer. Clean the excess materials so that no epoxy material or injection ports extend beyond the plane surface of the concrete.

603.11 Dimensional Tolerances:

All tolerances shall be applied with respect to the theoretical positions and dimensions shown in the plans. The tolerances listed in this article represent the total allowable tolerance that will be accepted in the finished product. The limits of tolerance do not necessarily represent fully acceptable construction; they are the limits at which construction becomes unacceptable. In general, workmanship shall be at a level of quality that wil l be well within the tolerance limits. Out of tolerance dimensions shall be handled in accordance with MP 603.10.40.

603.11.1 Prestressed Concrete I-Beams and Bulb Tee Beams:

Characteristics Value Depth (flanges) ±1/4 inch Depth (Overall) +1/2 inch, to -1/4 inch Width (flanges) +3/8, to -1/4 inch Width (Web) +3/8, to -1/4 inch Length of Beam ±1/8 inch per 10 feet, ±1 inch max. Sweep (variation from straight line parallel to centerline of member) ± 1/8 inch per 10 ft Camber variation from design camber ± 1/8 inch per 10 feet ± 1/2 inch max up to 80 feet length ± 1 inch max. over 80 length Camber variation from design camber ±3/16 inch per 12 inches ± 1 inch Position of plates ± 1 inch Position of bearing plates ± 5/8 inch Diaphragm Inserts (spacing between centers of inserts and from centers of inserts to the ends of the beams.) ± 1/2 inch Stirrup bars ( Projection above top of beam) ± 3/4 inch Stirrup bars ( Longitudinal spacing) ± 2 inches Concrete Cover ± 1/4 inch Position of inserts for structural connections ± 1/2 inch Position of hold-down points for draped strands ± 5 inches Position of Inserts ± 1/2 inch Position of handling devices: Parallel to length Transverse to length ± 6 inches ± 1 inch Prestressing strand position (vertical or horizontal). ± 1/4 inch

603.11.2 Precast/Prestressed Concrete Box Beams and Plank Beams:

Characteristics Value Depth (Overall) 1/4 inch Depth (top flange) +1/2 inch Depth (bottom flange) +1/2 inch to -1/8 inch Width (Overall) ±1/4 inch Width (Web) ±3/8 inch Length  3/4 inch Sweep (variation from straight line parallel to centerline of member) Up to 40 feet length member 1/4 inch 40 to 60 feet length member ±3/8 inch Greater than 60 feet length member  1/2 in Camber variation from design camber ±1/8 inch per 10 feet, ±1/2 inch Max. Variation from specified end Squareness of skew: Horizontal Vertical  5/8 inch ±1/8 inch per 12 inches ± 1/2 inch Max. Position of tendons Individual  1/4 inch Position of Inserts for structural connections  1/2 inch Position of handling devices: Parallel to length Transverse to length  6 inches  1 inch Position of stirrups: Longitudinal spacing Projection above top  1 inch + 1/4 inch, - 3/4 inch Position of dowels tubes  5/8 inch Position of hold-down points for draped strands  5 inch Position of tie rods tubes: Parallel to length Vertical  1/2 inch ±3/8 inch Position of slab void: End of void to center of tie hole Adjacent to end block  1/2 inch  1 inch Concrete Cover  1/4 inch per 10 feet long. Bars

603.11.3 Prestressed Concrete Deck Panels:

Characteristics Value Length  1/2 inch Width  1/2 inch Nominal Depth + 1/4 inch - 1/8 inch Horizontal Alignment – Deviation from straightness of matting edge of panels 1/8 inch Deviation of ends from plan dimension Horizontal Alignment  1/2 inch Position of strands : Vertical Horizontal ±1/8 inch  1/2 inch Concrete Cover  1/4 inch per 10 feet long. Bars

603.12 Handling, Storing, Transporting, and Erection:

The Contractor shall be responsible for proper handling, lifting, storing, hauling, and erection of all members so that they are placed in the structure without damage. Prestressed members shall be maintained in an upright position at all times and shall be handled and supported in a manner which prevents torsion. No member shall be moved from the casting yard until the member has been accepted. Storing of members shall be done with adequate blocking so that warpage or cracking will not occur. Blocking will be such that at least six (6) inches clearance is maintained above the surface on which the blocking is placed. Placement of the blocking from beam en ds shall be at locations not greater than three percent (3%) of the beam length. Concrete box beams shall be supported by the solid end block area during handling, storage, hauling, and erection. Members which are improperly stored and which become cracked, warped, or otherwise damaged in storage will be subject to rejection. Members when stacked, shall be separated by blocking capable of supporting the members. The blocking shall be arranged in vertical planes. Stacking of members shall be arranged such that lifting devices will be accessible and undamaged. Stacking shall not exceed two members high. All concrete beams or girders when erected, shall be securely tied and/or braced unless otherwise shown on the plans. When railroad or roadway traffic must b e maintained beneath girders or beams already placed, traffic shall be protected against falling objects during the erection of diaphragms and other structural members, during the placing of cast -in-place concrete, and during the erection and dismantling o f forms. Protection shall consist of nets or flooring with openings not larger than one (1) inch. When precast / prestressed concrete adjacent box beams are erected, the fit of mating surfaces will be such that excessive grout leakage will not occur. If s uch fit is not provided the joint shall be filled with grout or sealed with an acceptable caulking suitable to the Engineer.

603.13 Construction of Deck:

The variation in heights between beams shall not be more than ½ inch between adjacent box beams where there is no wearing surface. For adjacent box beam bridges with wearing surfaces, the differential shall not exceed ¾ inches. Dowel bar and lifting bolt holes shall be filled with non-shrink grout. Adjacent box beam units shall be transverse post tensioned by the use of high strength threaded bars, or by other methods as shown on the Plans.

603.14 Measurement and Payment:

603.14.1 Method of Measurement: Precast/Prestressed concrete structural members will

be measured along the member centerline in linear feet. Deck panels shall be measured by area in square feet complete in place. Precast reinforced concrete three-sided structures shall be measured along the centerline of the erected structure in linear feet. Precast reinforced concrete headwalls and wingwalls for use with precast reinforced concrete three-sided structures shall be measured in square feet as measured on the exterior face of the member.

603.14.2 Basis of Payment: Precast/Prestressed concrete beams, deck panels, precast

reinforced concrete three -sided structures, and precast reinforced co ncrete headwalls and wingwalls will be paid for at the contract unit price bid for the items listed below, which price and payment shall be full compensation for furnishing all the materials and doing all the work prescribed in a workmanlike and acceptable manner including the cost of furnishing and manufacturing the concrete members; for labor, concrete, forms, conventional reinforcing steel, prestressing strands, inserts, anchorage devices, bearing pads, shims, grout, wingwalls and headwall connection har dware, joint sealing/waterproofing, and other devices, and for moving, transporting and erecting the finished product in accordance with the Plans and Specifications. For precast reinforced concrete three -sided structures where the headwall is cast integral with the end structure unit, the headwall will be paid for in square feet as if it were not integral cast. Cast -in-place concrete diaphragms, curb, parapet, railing, and reinforcing steel for cast-in-place concrete are not included in this item.

603.14.2 1-Price Adjustments: Members found not in compliance with the

requirements of subsection 603.6.5 for compressive strength, but for which the evaluation indicates may still be used, will be paid for at a reduced price in accordance with the following formulas, depending on who purchased the members: FORMULA 1: Use the following price reduction formula when the members are used in a project constructed by a Contractor: Price Reduction = x 40% of the Contract Unit Bid Price         − ' _ ' 5 . 0c c f X f FORMULA 2: Use the following price reduction formula when the beams are used in a project constructed by the Division: Price Reduction =         − ' _ ' 5 . 0c c f X f x IC Where: = 28-Day Design Compressive Strength, psi ' cf _ X = Average 28-day Compressive Strength as determined in 603.6.5 IC(Formula 2 only) = The invoiced cost of the member itself, as billed to the Division by the Fabricator. This cost shall not include other items associated with the member such as guardrail, bearing pads, etc.

603.15 Pay Items:

ITEM DESCRIPTION UNIT 603016-* “size” Prestressed Concrete Box Beam Linear Feet 603017-* “size” Prestressed Concrete Plank Beam Linear Feet 603018-* “size” Prestressed Concrete I Beam Linear Feet 603019-* “size” Prestressed Concrete Bulb T Beam Linear Feet 603020-* “size” Prestressed Concrete Deck Panel Square Feet 603021-* “size” Precast Concrete Deck Panel Square Feet * Sequence number

Get an email when 603 changes

West Virginia revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Roads and Bridges, 2023 Edition. Pages 377–402 of 1,006. View official source ↗