4-87 (E) Repairs
Repair any damage that occurs as directed by the Engineer . Repair by patching when permitted by the Engineer . Extend the first ply of the patch at least 12 inches beyond the outermost damaged portion of the membrane and extend the second ply at least 3 inches beyond the first.
458-4 Method B Damp Proofing
458-5 Measurement and Payment
Method A Waterproofing will be measured and paid as the actual number of square yards of surface that is waterproofed. In measuring this quantity, measurement is made along the actual surface that is to be waterproofed before the waterproofing is applied. Method B Dampproofing will be measured and paid as the actual number of square yards of surface that is dampproofed. In measuring this quantity, measurement is made along the actual surface that is to be dampproofed before the dampproofing is applied. These prices and payments will be full compensation for all items required to waterproof and dampproof including, but not limited to, those items contained in Article 45 8-1. Payment will be made under: Pay Item Pay Unit Method A Waterproofing Square Yard Method B Dampproofing Square Yard CONCRETE AND METAL RAIL S
460-1 Description
Furnish and place metal, pipe or concrete barrier bridge rails, concrete curbs and concrete end posts in accordance with these specification s and as shown in the plan s. Provide concrete barrier rails with moment slabs above retaining walls in accordance with the contract and accepted submittals. Furnish posts, rail bars, pipe fittings, hardware, paint, barrier delineators, concrete, reinforcing steel, admixtures, form s, falsework and all other materials; galvanize; paint; fabricate and erect rail; and place, finish and cure concrete.
4-88 460-2 Materials
Refer to Division 10. Item Section Aluminum Rail 1074 -5 Barrier Delineators 1088 -2 Curing Material s 1026 Epoxy Coated Reinforcing Steel 1070 -7 Galvanized Steel Rail 1074 -5 Paint 1080 Pipe Rail 1074 -6 Portland Cement Concrete 1000 Reinforcing Steel 1070 Use Class AA c oncrete for concrete barrier rails , concrete curbs and end posts, and Class A concrete for moment slabs in accordance with Article 1000 -3. Use epoxy coated reinforcing steel for concrete barrier rails in accordance with Article 1070 -7.
460-3 Construction Methods
Adhere to the construction load limitations of Article 420 -20 while placing concrete for all bridge rails.
4-89 extrusion machine. Produce a dense and homogeneous barrier free of voids and honeycomb
with minimum hand finishing. Coordinate concrete delivery and placement to provide uniform progress while minimizing stopping and starting of the extrusion machine. When plans require horizontal deck drains through the barrier rails, use drain couplings with slip -formed rails. Correct all exposed surfaces that are not satisfactory to the Engineer as to uniformity of color and texture or because of excessive patching as required. Give the roadway face of barrier rails constructed using conventional forms a Class 2 surface finish in accordance with Subarticle 420 -17(F). Use a broom finish on the roadway face of slip -formed barrier rails. Provide barrier rail delineators in accordance with Section 854.
460-4 Measurement and Payment
____ Bar Metal Rail will be measured and paid as the actual number of linear feet of metal rail, measured along the top bar of the rail that is completed and accepted. 32" Alaska Rail and 42" Oregon Metal Rail will be measured and paid as the actual number of linear feet of bridge railing and concret e curb. Concrete end post payment shall be included in the cost to provide the concrete curb. The price and payment will be full compensation for all materials, labor, equipment, tools, and incidentals necessary to construct the bridge railing, the concr ete curb and concrete end posts. __" Galvanized Steel Pipe Rail will be measured and paid as the actual number of linear feet of pipe rail, measured along the top pipe of the installed pipe rail, that is completed and accepted. Concrete Barrier Rail will be measured and paid as the number of linear feet of concrete barrier rail shown in the plan s. Concrete Barrier Rail with Moment Slab will be measured and paid for in linear feet. Concrete barrier rails with moment slabs will be measured as the length of concrete barrier rail above retaining walls. The contract unit price for Concrete Barrier Rail with Moment Slab will be full compensation for earthwork, materials, hauling and any incidental labor for providing concrete barrier rails with moment slabs in accordance with the contract. Vertical Concrete Barrier Rail will be measured and paid as the number of linear feet of vertical concrete barrier rail shown in the plan s. Concrete Median Barrier will be measured and paid as the number of linear feet shown in the plans. ____ x ____ Concrete Parapet will be measured and paid as the number of linear feet of concrete parapet shown in the plans. There will be no direct payment for bridge rail delineators as they are incidenta l to the work being performed. These prices and payments will be full compensation for all items required to provide bridge railing including , but not limited to, those items contained in Article 460 -1.