5-26 measured as provided for in Article 520- 11. Incidental stone base which has been stockpiled
will not be measured more than one time. Payment will be made under : Pay Item Pay Unit Incidental Stone Base Ton
560-1 Description
Perform the work covered by this section including, but not limited to , furnishing the source of the borrow; building; maintaining and obliterating haul roads; clearing and grubbing the borrow source; removal, hauling and disposition of overburden and other unsuitable material; excavation; hauling; formation of roadway shoulders include the reshaping and finishing of slopes adjacent to the shoulders and roadway ditches; restoration of the source and haul roads to an acceptable condition; disposal of surplus stockpiled material; and seeding and mulching.
560-2 Materials
Refer to Division 10. Item Section Shoulder Borrow 1019 -2 Aggregate Shoulder Borrow 1019 -3
560-3 Construction Methods
Construct the top 6 inches of shoulders with soils capable of supporting vegetation in accordance with Article 1019 -1. Construct the shoulders in proper sequence with the type of base and pavement being constructed. Perform the work so as to provide proper drainage at all times. Shape and roll the shoulder material during placement to provide for bonding of layers and compact ion to the satisfact ion of the Engineer. Before placing any earth material on existing graded shoulders, remove all existing vegetation and scarify the existing shoulders to ensure a proper bond. Perform the final shaping of the shoulders, adjacent sl opes and ditches in accordance with the typical section shown on the plans. Provide adequate equipment to perform the work. Do not damage base, surface, pavement or drainage features during the construction of the shoulders. Should damage occur because of the Contractor's operations, repair the damaged portions or remove and replace them as directed by the Engineer at no cost to the Department.
560-4 Measurement and Payment
5-27 (B) Measured in Original Position
The quantity of shoulder borrow to be paid will be the actual number of cubic yards of approved material, measured in its original position in the borrow source or stockpile by cross sectioning and computed by the average end area method, which has been incorporated into the completed and accepted work. No measurement wil l be made of any overburden or unsuitable material removed from the borrow source, nor of any material excavated before cross sections being taken.