5-1 Division 5
SUBGRADE, BASES AND SHOULDERS FINE GRADING SUBGRADE, SHOULDERS AND DITCHES
500-1 Description
Perform the work covered by this section on all portions of the project which will be paved under the contract including , but not limited to , preparing, grading, shaping, manipulating moisture content and compacting either an unstabilized or stabilized roa dbed to a condition suitable for placement of base course, pavement and shoulders. Clean, shape and maintain roadway ditches; strip existing vegetation; and place and compact in accordance with Sections 235 and 560 all materials resulting from the shaping operation. Stockpile surplus material for the construction of shoulders and dispose of any necessary surplus stockpile material as waste. On those portions of the project where there is no pavement to be placed under the contract, perform the work of Section s 225 or 230, depending upon the source of the material. This section will not be applicable to such work.
500-2 Construction Methods
5-2 Compact the subgrade at a moisture content which is approximately that required to
produce the maximum density indicated by the above test method. Dry or add moisture to the subgrade when required to provide a uniformly com pacted and acceptable subgrade. Where the subgrade is to be stabilized with lime, aggregate or cement, the above density requirements will not apply before the incorp oration of the stabilizing material; however, perform compaction in accordance with Articles 501-10, 510 -3 or 542 -9, as appropriate.
500-3 Tolerances
A tolerance of ± 1/2 inch from the established grade will be permitted after the subgrade has been graded to a uniform surface. Subgrade tolerance of ± 1/4 inch from the established grade is required for subgrade under concrete pavement mainline lanes . Perform the grading operatio n such that the maximum difference between the established grade and the graded subgrade within any 100 foot section is 1/2 inch for normal subgrade and 1/4 inch for subgrade for concrete pavement .
500-4 Maintenance of Subgrade
Provide and maintain ditches and drains to drain the subgrade satisfactorily . Where previously approved subgrade is damaged by natural causes, hauli ng equipment or other traffic, restore the subgrade to the required lines, grades , typical sections and density.
500-5 Measurement and Payment
Fine Grading will be paid at the contract lump sum price. Such lump sum price will be full payment for all material excavated to a depth of 0.4 f eet below the existing graded surface. Any material which has been excavated from the subgrade at the depth greater than 0.4 f eet below the existing graded surface will be Unclassified Excavation and will be paid in accordance with Article 225 -7. As an exception to the above, on those areas in which the Contractor is responsible for constructing the embankment on which the subgrade is loc ated, no payment will be made for that excavation that may be necessary to bring the grade to the established subgrade elevation and typical section. Incorporate such surplus material into the project at no additional cost to the Department. When sufficie nt material is not available from the fine grading operation to complete the work of fine grading, additional material will be paid in accordance with Article 225 -7 for Unclassified Excavation or Article 230 -5 for Borrow Excavation, depending on the source of material. Surplus material stockpiled for shoulder construction and incorporated into the work will be paid in accordance with Article 560 -4 for Shoulder Borrow . No payment will be made for the removal and disposal of any surplus material remaining in the stockpile after the shoulders have been completed. Maintenance, repair and restoration of the subgrade to the required lines, grades, typical sections and density as it applies to fine grading is incidental to the work of this section. Payment will be made under: Pay Item Pay Unit Fine Grading Lump Sum