5-14 535-2 Construction Methods
Compact the base to a degree satisfactory to the Engineer. Dry or add moisture to the material when required to provide a uniformly compacted and acceptable base. Do not condition the existing base when it contains excess moisture or is frozen. Maintain th e base in accordance with Article 520 -10.
535-3 Measurement and Payment
Conditioning Existing Base will be measured and paid at the contract unit price per 1,000 square yards for the actual number of units of 1,000 square yards of base over which the work of conditioning existing base has been acceptably performed. The length will be measured along the centerline of the surface of the base. The width will be the width required by the plans or established by the Engineer measured across the top surface of the base. Payment will be made under : Pay Item Pay Unit Conditioning Existing Base 1,000 Square Yards CEMENT -TREATED BASE COURSE
540-1 Description
Perform the work covered by this section including, but not limited to , construction and curing a cement -treated base composed of aggregate, furnishing of water and aggregat e; the mixing, proportioning, hauling and spreading of the materials; furnishing Portland cement at the point where it is incorporated into the mix; manipulating, compacting and finishing the base; maintaining the base; making repairs or corrections to the base; and applying sand seal in accordance with Article 540 -3. Compact, shape and cure the base to conform to the lines, grades, depths and typical sections shown on the plans. When cement -treated base course is called for on the plans, the Contractor has the option of providing a plant mixed cement -treated base course or a road mixed cement -treated base course as specified below.
540-2 Mater Ials
Refer to Division 10. Item Section Aggregate 1010 Portland Cement, Type I 1024 -1 Water 1024 -4
540-3 Limitations
Do not construct cement -treated base when the air temperature is less than 40 °F nor when conditions indicate that the temperature may fall below 40 °F within 24 hours. Do not incorporate frozen materials into the mixture nor place material on frozen subgrade. Protect the base from freezing for 7 days after completion. Do not place cement -treated base that will not be covered with pavement by December 1 of the same year. Failure of the Contractor to cover the cement -treated base as required above will result in the Engineer notifying th e Contractor in writing to cover the cement -treated base with a sand seal. Apply the sand seal in accordance with Section 660, except Articles 660 -3 and 660- 12 will not apply. If the Contractor fails to apply the sand seal within 72 hours after receipt of such notice, the Engineer may proceed to have the work performed with other forces and equipment. The application of the sand seal by the Contractor or other forces will
5-15 in no w ay relieve the Contractor of the responsibility to maintain or repair the damaged base,
no matter what the cause of damage .
540-4 Preparation of Subgrade
Prepare the subgrade i n accordance with Section 500. Prepare the subgrade so that it is firm and able to support without displacement the construction equipment and the compaction operations hereinafter specified. Soft or yielding subgrade shall be corrected and made stable before construction proceeds. Moisten the subgrade as needed before spreading the base material.
540-5 Construction Methods
5-16 weights or rates of flow of water that are within a range of optimum to optimum
plus 1.5% moisture. Use batch weights or rates of feed of aggregate that are within 5 % of the amounts designated by the Engineer. Mix materials at least 20 seconds to assure a proper blend of materials.
5-17 in each layer, place the material using approved spreaders. Perfo rm the spreading
operations to eliminate pockets of material of non- uniform gradation resulting from segregation in the hauling or discharging operations. Spread each layer so that compaction can be started without further shaping. A single spreader may b e used provided it is capable of placing a uniform, full -depth layer of material across the full width of the base in one pass. Otherwise, 2 or more spreaders will be required and operate the spreaders so that the spreading progresses along the full width of the base in a uniform manner. Base placed on areas inaccessible to mechanical spreading equipment may be spread in one layer by approved methods. After spreading, compact the material thoroughly to the required lines, grades and typical sections by me ans of pneumatic tampers or with other compaction equipment which will constantly obtain the degree of compaction required.
540-6 Compaction
Begin compaction immediately after the plant mixed base has been placed on the prepared subgrade or immediately after cement and water has been incorporated into the previously placed aggregate. Compact any one layer of base so the thickness is between 4 inches and 8 inches.
5-18 After spreading, maintain the moisture content of the material within a range of optimum to
optimum plus 1.5% moisture during compaction. Accomplish compaction by the use of approved self -propelled rollers , except do not use a sheep -foot roller for more than 2 passes. Compact the base by the use of approved self-propelled rollers to a density equal to at least 97% of the maximum density obtained by compacting a sample of the material in accordance with AASHTO T 180 as modified by the Department. Copies of these modified testing procedures are available upon request from the Materials and Tests Unit. The Engineer may, at his option, utilize nuclear methods as described in the NCDOT Nuclear Density Testing Manual – Base Course, FDR and Select Materials to determine the density of the base instead of the methods required above. Copies of this manual are available upon request from the Mate rials and Tests Unit. Complete final compaction, including that necessary due to correction of high or low areas, within 3 hours after water has been added to the mixture. Do not leave any cement -aggregate mixture undisturbed for more than 30 minutes if i t has not been compacted and finished. When rain causes excessive moisture, reconstruct the entire section. When such reconstruction is necessary, perform the work of reconstruction and provide the cement required at no cost to the Department.
540-7 Construction Joints
Build the base for large, wide areas in a series of parallel lines of convenient length and width meeting the approval of the Engineer. Form straight longitudi nal joints at the edge of each day's construction by cutting back into the completed work to form a vertical face free of loose or shattered materials. Where traffic considerations require that a longitudinal joint be exposed for an excessive length of ti me, the Engineer may require that it be covered with a curing seal in accordance with Section 543.
540-8 Tolerances
After final shaping and compacting of the base, the Engineer will check the surface of the base for conformance to the grade and typical section and determine the base thickness. Construct the thickness of the base so that it is within a tolerance of ± 1/2 inch of the base thickness required by the plans. When the base course will be used under concrete pavement the tolerance will be ± 1/4 inch. Construct the base so that the maximum differential between the established grade and the base within any 100 foot section is 1/2 inch or 1/4 inch when used as a ba se course under concrete pavement .
540-9 Curing
After the cement -treated base has been finished as specified herein, cure it in accordance with Section 543.
540-10 Aggregate for Cement -Treated Base
Use aggregate for cement -treated base course from an approved source participating in the Department’s Aggregate Quality Control/Quality Assurance Program (Aggregate QC/QA Program) which has been sampled, tested and approved in accordance with Section 1006.
540-11 Traffic
Completed sections of the base may be opened when necessa ry to lightweight local traffic, provided the base has hardened sufficiently to prevent marring or distorting of the surface and provided the curing is not impaired. Do not operate construction equipment on the base , except as necessary to discharge into the spreader during paving operations.