2-23 Section 235
235-1 Description
Place suitable material excavated under Sections 225, 226, 230 and 240 in embankments, backfills and earth berms, to conform with the lines, grades and typical cross sections shown in the plans. Fill and compact holes, pits and other depressions when unsuitable material has been removed. Work includes preparation, formation, c ompaction and maintenance of the embankment area as well as the formation of benches in the existing ground with rises less than 60 inches . Surcharges and waiting periods may be required for embankments and retaining walls to minimize and control the effects of settlement on structures, approach slabs, pavements, pipes, utilities, etc. Settlement gauges may be required to monitor settlement a t approximate locations shown in the plans and as directed by the Engineer .
235-2 Materials
Refer to Division 10. Use soil consisting of loose, friable, sandy material free of subsoil admixtures, refuse, stumps, rocks, roots, root mats or other unsatisfactory material. Do not use material that meets AASHTO M 145 for soil classification A -2-5 and A -5 with a PI of less than 8 within 12 inches of the subgrade. Wet, d ry or frozen material may be suitable when dried, wetted or thawed, respectively. Aerate and dry material containing moisture content in excess of what is required to achieve embankment stability and specified density. Waste suitable material only with w ritten authorization. Provide Schedule 40 black steel pipes and couplers with steel or wood bases for settlement gauges. Use steel plates with yield strength of at least 36 ksi and pressure treated wood boards for bases of settlement gauges.
235-3 Construction Methods
Coordinate work with excavation operations in accordance with Article s 107-12 and 225-2.
2-24 (B) Embankment Formation
Uniformly spread material in successive, approximately horizontal layers of not more than 10 inches depth, loose measurement, for the full width of the cros s section. Compact each layer in accordance with Subarticle 235 -3(C). Shape embankment surface to properly drain at all times. Route construction equipment uniformly over the full width of the embankment and prevent deep rutting. May construct the first layer of embankments across saturated or unstable material that does not support the weight of hauling equipment, by successively dumpi ng a uniformly distributed layer of a thickness not greater than necessary to support hauling equipment while placing subsequent layers. When placing material in swamp or in water, keep unsuitable surge material in a fluid state or remove to prevent trappi ng in or under embankment. When shown i n the plans or allowed by the contract, form a satisfactory base by end or side dumping in valleys, ravines and at the foot of slopes on side hills. Where embankments are being constructed principally of rock or broke n pavement, place in uniform layers with a maximum depth of 36 inches . Place rock or broken pavement so larger pieces are evenly distributed and are no larger than 36 inches in any dimension. Fill all voids. Place rock or broken pavement lifts at leas t 2 feet below finished subgrade or finished grade whichever is lower. Do not place rock or broken pavement 2 inches or greater in diameter within 12 inches of the subgrade or finished grade whichever is lower. Do not place rock or broken pavement in areas where foundations are to be placed. Place select material where indicated in the contract. Construct the top 6 inches of shoulder and fill slopes with material that meets Article 1019 -2. Construct stabilized embankment when required by the contract. Install pipe culverts as specified in Section 300. Construct subsurface drains adjacent to structures as required by Article 414- 8 for box culverts, except for that portion of the drain located below the elevation of the original ground. Do not disturb existing utilities within the project construction limits until released by the Engineer. Do not place rock or broken pavement in embankment areas where piles or drilled shaft foundations are to be constructed or where underground utilities exist . This requirement shall include , but not be limited to , piles and foundations for structures, metal signal poles, overhead sign structures and high mount lighting.
2-25 (D) Maintenance
Maintain all embankments made under the contract until final acceptance. Construct and maintain adequate drainage of surface runoff to prevent soil erosion. Replace damaged or displaced embankment .
235-4 Tolerances
Finish subgrade surface within ± 0.10 feet from the established grade after it has been graded to a uniform surface.