208.1General Description
This work includes placing embankments, backfilling structures, and constructing earth berms and surcharges with suitable material excavated under Section 204, Section 205, Section 206, and Section 207. Complete the work according to the lines, grades, and typical cross-sections shown on the plans or established by the Engineer. The work also includes preparing areas by backfilling stump holes and correcting surface irregularities where the embankment is to be constructed. This includes forming, compacting, and maintaining the embankment and placing and compacting approved material where unsuitable material has been removed. Payment for this work is included in other appropriate Pay Items unless a specific Pay Item is set up in the Contract. Apply all provisions of Section 161 to the work in this Section. Perform Shoulder Construction according to Section 216. 208.1.01 Definitions General Provisions 101 through 150. 208.1.02 Related References
GDT 7 GDT 20 GDT 21 GDT 24a GDT 24b GDT 59 GDT 67 209 209 209 209 209 209 209 209 209 209
208.1.03 Submittals General Provisions 101 through 150.
208.2Materials
Embankment material classes are defined in Section 810, Section 811, and Section 813. The material incorporated into the roadway will be subject to the following limitations:
Use embankment material classified as Class I, II, III, V, or VI except as noted below:
constructing embankments through reservoirs.
used in Districts 1, 6, and 7. Class IIIC2 or IIIC3 material may only be used in Districts 1, 6, and 7 if approved by the Office of Materials and Testing, Geotechnical Environmental Pavement Bureau. Ensure that materials do not contain rock larger than 3 in. (75 mm) for any dimensions.
Ensure that rock embankment placed as indicated on the Plans meets the requirements of Section 811 unless specified otherwise in the plans or in the Special Provisions.
Construct in-place embankment with Class I, II, III, V, or VI material.
Use Class I or Class II backfill material furnished and stockpiled as defined in Subsection 810.2.01.A. Class IIIC1 material may be used in Districts 1, 6, and 7. Class IIIC2 or IIIC3 material may only be used in Districts 1, 6, and 7 if approved by the Office of Materials and Testing, Geotechnical Environmental Pavement Bureau.
Use pond sand that meets the requirements of Section 813 as embankment material. Material is subject to the following approval limitations:
stabilized walls.
soil on top.
to the existing ground slope/fill slope, is less than 7 ft. (2.1 m), including 2 ft. (600 mm) of soil cover.
208.2.01 Delivery, Storage, and Handling General Provisions 101 through 150. 210 210 210 210 210 210 210 210 210 210
208.3Construction Requirements
208.3.01 Personnel General Provisions 101 through 150. 208.3.02 Equipment General Provisions 101 through 150. 208.3.03 Preparation General Provisions 101 through 150. 208.3.04 Fabrication General Provisions 101 through 150. 208.3.05 Construction
This work includes excavating material forming benches in the existing ground beneath proposed embankments. Form benches to increase the bond between the existing ground and the proposed embankment. This work is required where embankments are placed on hillsides or against existing embankments, which will be indicated on the plans. Construct the benches approximately 12 ft. (3.7 m) wide unless otherwise shown on the plans. Use material removed in the excavation in the embankments. The Department will make no additional payment for this work.
Follow these requirements when constructing embankments:
Before starting embankment construction, clear and grub the embankment area according to Section 201 and install Drainage Structures according to Section 550.
Fill depressions below the ground surface and undercut areas with suitable material. Remove unsuitable or unstable material and compact according to Subsection 208.3.05.B.1.c before beginning embankment construction.
Plow and scarify the entire area upon which the embankment is to be placed (except inundated areas) at least 6 in. (150 mm) deep. Before placing the embankment, recompact loosened soil to the approximate density of the underlying soil. Cut benches as specified in Subsection 208.3.05.A.
When the depth of fill and surfacing is 3 ft. (1 m) or less, compact the original ground compact at least 1 ft. (300 mm) deep to at least 95 percent of the maximum laboratory dry density as determined from representative samples of the compacted material using, GDT 7, GDT 24a, GDT 24b, or GDT 67 whichever applies. The in-place density of the compacted fill will be determined according to GDT 20, GDT 21, or GDT 59, whichever applies. 211 211 211 211 211 211 211 211 211 211
Thoroughly plow or scarify all portions of existing unpaved roads and flexible pavements. Destroy cleavage planes before placing the embankment. 1) Remove the old pavement with rigid surfaces if the new embankment is not more than 3 ft. (1 m) high. 2) Break remaining rigid pavements that are within 10 ft. (3 m) of the finished grade so that no section larger than 10 ft.² (1 m²) remains intact.
Use the following requirements when constructing the embankment formation:
Except as noted in Subsection 208.3.05.B.2.d, construct the embankments in parallel layers. Deposit the material and spread in horizontal layers not more than 8 in. (200 mm) thick, loose measurement, for the full width of the cross-section. Use motor graders, bulldozers, or other approved equipment to keep layers uniform. Compact the layers using a sheepsfoot roller. The Engineer may permit the use of vibratory rollers whenever the embankment soils consist of Class IA1, IA2, or IA3 materials.
Compact each layer within the range of optimum moisture content to achieve the compaction specified below. Do not construct successive layers on previous layers that exhibit excessive pumping under construction equipment regardless of compaction. Dry material if it contains too much moisture. Ensure the moisture content is sufficient for stability and compaction. Add water if the material is too dry and uniformly mix it with the soil for stability and compaction. The Department will not measure water added to the material under this requirement for payment. It is considered incidental to the satisfactory completion of the work.
Compact the embankment at bridge structures to at least 100 percent of the maximum laboratory dry density. Compact for the full depth of the embankment, beginning at the toe of the slope and extending 100 ft. (30 m) from the end of the bridge. Compact embankment other than at bridge structures to at least 95 percent of the maximum laboratory dry density to within 1 ft. (300 mm) of the top of the embankment. Compact the top 1 ft. (300 mm) of the embankment to at least 100 percent of the maximum laboratory dry density. If grading and paving are let in separate contracts, the paving Contractor shall recompact the top 6 in. (150 mm) to at least 100 percent of the maximum laboratory density. The maximum laboratory dry density will be determined from representative samples of the compacted material using GDT 7, GDT 24a, GDT 24b, or GDT 67, whichever applies. The in-place density of the compacted fill will be determined according to GDT 20, GDT 21, or GDT 59, whichever is applicable.
Follow these special requirements: 1) Build layers as parallel as possible. In certain cases, the Engineer may permit steeper slopes at ends of the embankments. 2) In swamp or inundated areas that will not support the equipment, build the lower part of the fill by dumping successive loads in layers no thicker than necessary to support the hauling equipment. 3) Build and compact the remainder of fills in layers as specified above. 212 212 212 212 212 212 212 212 212 212
Use Class I or II material when constructing embankments over and around pipes, culverts, arches, and bridges according to Subsection 810.2.01.A.1. Class IIIC1 material may be used in Districts 1, 6, and 7. 1) Compact the material as specified in Subsection 208.3.05.B.2.c. 2) Place the specified material on both sides of bridge structures for a distance of at least 10 ft. (3 m). NOTE: Do not place rock larger than 4 in. (100 mm) diameter within 2 ft. (600 mm) of any drainage structure. Before any traffic is allowed over any structure, provide a sufficient depth of material over and around the structure to protect it from damage or displacement.
Handle the different classes of soils using the following methods: 1) Class IIB3 and Better Soils Distribute and compact these soils in 8 in. (200 mm) uniform layers over the entire width of the embankment. Use these soils (when available in sufficient quantities) in the top 1 ft. (300 mm) of the roadbed. Reserve these soils for this purpose when directed by the Engineer 2) Class IIB4 Soils Distribute and compact these soils in 8 in. (200 mm) layers over the entire width of the embankment. Class IIB4 soils may be used in the top 12 in. (300 mm) of subgrade in Districts 1, 6, and 7. Class IIB4 soils may be used in the top 12 in. (300 mm) of subgrade in Districts 2, 3, 4, and 5 with a stabilizing agent if approved by the Office of Materials and Testing, Geotechnical Environmental Pavement Bureau. If Class IIB3 or better soils are available in borrow pits, use these soils in the top 12 in. (300 mm) of subgrade. 3) Class IIIC1 Soils Class IIIC1 soils excavated per Section 204, 205 or 207, which excludes Section 206 (Borrow), may be used in Districts 1, 6, and 7 in embankments and within the top 12 in. (300 mm) of subgrade if approved by the Office of Materials and Testing, Geotechnical Environmental Pavement Bureau. If Class IIB4 or better soils are available in borrow pits, use these soils in the top 12 in. (300 mm) of subgrade. .
used for subgrade.
4) Class IIIC2 and IIIC3 Soils
Class IIIC2 and IIIC3 soils excavated per Section 204, 205 or 207, which excludes Section 206
bottom of subgrade directly beneath the pavement, if approved by the Office of Materials and
Testing, Geotechnical Environmental Pavement Bureau.
5) Class IIIC4 Soils
Class IIIC4 chert clay soils in District 6 with less than 55 percent passing the No. 10 (2 mm) sieve may
be used in embankments and subgrade. All other Class IIIC4 soils may not be used.
6) Class IV Soils
Do not use these soils in embankments. Waste these soils or (when designated in the Plans or
directed by the Engineer) stockpile them and use them for blanketing fill slopes.
7) Class V Soils
Place these soils in the same manner as Class IIB4 soils. Pulverize large particles to obtain the
proper compaction. 213213213213213213213213213213
8) Class VI Rock
Place rock in uniform layers not over 3 ft. (1 m) thick and distribute it over the embankments to avoid
pockets. Fill voids with finer material.
Do not place rock larger than 6 in. (150 mm) in diameter within 3 ft. (1 m) of the finished surface of
the embankment.
Do not place rock larger than 6 in. (150 mm) in diameter within 2 ft. (600 mm) of the outer limits of
proposed posts or utility poles.
Do not place rock at bridge end bents within 10 ft. (3 m) of pile locations.
9) All Classes
Place mixtures of the above classes together with random material such as rock, gravel, sand,
cinders, slag, and broken-up pavement so that coarse particles are dumped near the outer slopes
and finer particles near the center of the roadway.
Produce a gradual transition from the center to the outside. If material is too large to place in 8 in.
(200 mm) layers, treat it as rock or break it down and place it in 8 in. (200 mm) layers.
When consolidating embankments at bridge ends, use the following specifications:
consolidation readings to indicate that both the fill and the natural ground have reached the desired
degree of stability.
required by a Special Provision.
The plans or the Special Provisions will indicate the estimated time required to reach consolidation.
The Engineer may extend or shorten this waiting period based on settlement readings taken on
points placed in the fills. The longer or shorter waiting period will not constitute a valid claim for
additional compensation.
Follow these specifications when extending a waiting period:
1) Extending an estimated waiting period may lead to increasing the Contract time. If the Contract is on
a calendar day or completion date basis, the Department may increase the calendar days equal to the
maximum number of calendar days involved in the extension.
2) When a time extension causes additional delay due to seasonal changes, the Engineer may
recompute the time extension on an available day basis.
When the Contract is on an available day basis, the time increase will be equal to the greatest number
of available days involved in the extension.
3) When time charges on separate Bridge Contracts are controlled by Special Provisions that set forth
the availability of bridge sites, extending an estimated waiting period controls the availability of that
bridge site only; time charges will be adjusted according to the Special Provision.
construction providing a bench for the end bent) unless otherwise stated in the Plans and compact
thoroughly before driving a piling at bridge ends.
fill between slope stakes at the end of the bridge. The Department will measure the minimum length of
full-depth embankment along the roadway centerline away from the end-of-bridge Station. 214214214214214214214214214214
Construct embankments designated on the plans and in the Proposal as “In-Place Embankment” using either a
hydraulic or conventional dry land construction method and using materials obtained from within the construction
limits of the Right-of -Way or from borrow pits, whichever is appropriate.
Regardless of the method of construction, the Department will measure the entire embankment for payment as in-
place embankment.
• Build embankments according to this Section when hydraulic or conventional dry land construction
methods are used.
• Furnish equipment suitable for the method chosen to complete the work. Equipment is subject to the
Engineer’s approval.
• When using a hydraulic method is used, conform to these additional requirements:
indicated on the plans.
Department. Provide the same depth of channel at mean low water as existed before the construction
of the embankment.
structures, unless otherwise shown on the plans.
beginning at one end of the excavated area and continuing to the other end of the operation. Avoid
forming of muck cores in the embankment.
progress to the end of the excavation area beyond the toe of the slope of end rolls at bridge ends.
slides, washouts, settlement, subsidence, or mishaps to the work while under construction.
entire Contract.
prescribed slopes in wetland areas.
Obtain (at no additional expense to the Department) necessary permits or licenses from the appropriate
authorities to operate dredges and other floating equipment in waters under their jurisdiction, unless otherwise
provided for in the Contract.
In addition to the provisions of Section 161, follow additional erosion, siltation, and pollution control measures
specified in the plans or Special Provisions. 215215215215215215215215215215
This work includes furnishing materials either from the roadway excavation or other sources and hauling and the
placing of rock embankment. Use materials that meet the requirements of Subsection 208.2.B, as shown on the
plans or directed by the Engineer.
avoid pockets.
finished grade of the embankment, or within 2 ft. (600 mm) of any structure.
adjoining earth embankment concurrently. Ensure that neither is larger than 4 ft. (1.2 m) higher than the other
at any time.
After constructing the entire embankment, shape the surface of the roadbed and the slopes to reasonably
true grade and cross-sections as shown on the plans or established by the Engineer.
Open ditches, channels, and drainage structures (both existing and those constructed or extended) to
effectively drain the roadway. Maintain the embankment areas until Final Acceptance of the project.
208.3.06 Quality Acceptance
General Provisions 101 through 150.
208.3.07 Contractor Warranty and Maintenance
General Provisions 101 through 150.
208.4Measurement
The following section details measurement for payment for the work described in this Section:
area method, or other acceptable methods, when embankment is in place and accepted.
The quantity will be calculated as the neat volume, above the original ground surface, between the template line
shown on the plans or authorized changes by the Engineer, and the original ground surface.
The original ground surface is determined by conventional field, photogrammetric, or other methods. The
Department will not deduct for the volume of culverts and manholes.
In-place embankment necessary for the construction of temporary detours will not be measured for payment and
is considered incidental to the completion of the work unless specifically stated otherwise on the plans.
Where work includes excavating of unstable materials below the ground line, the volume of embankment required
for backfill below the ground line is calculated based on the neat line measurement for the cross-section shown on
the plans or established by the Engineer by the average end area method or other acceptable methods.
Where permitted by the Engineer or required by the plans, material removed from the existing roadbed, special
ditches, berm ditches, or dry land borrow pits and used in making embankment will be paid for as in-place
embankment regardless of the method of excavation.
208.4.01 Limits
General Provisions 101 through 150. 216216216216216216216216216216
208.5Payment
Except as provided for herein, the Department will not make separate payment for placing embankments,
backfilling structures, and constructing earth berms, including surcharges.
Payment will be included at the Contract Unit Price for the items covered by Section 204, Section 205, and
Section 206. Prices are full compensation for the work covered by this Section.
The Unit Prices bid per cubic yard (meter) for in-place and rock embankments (when included as Contract bid
Items) are full compensation for furnishing suitable material, hauling, placing, compacting, finishing, and dressing
according to these Specifications or as directed by the Engineer.
Payment will be made under:
Item No. 208 In-place embankment Per cubic yard (meter)
Item No. 208 Rock embankment Per cubic yard (meter)
208.5.01 Adjustments
General Provisions 101 through 150.. 217 217 217 217 217 217 217 217 217 217