3-1 Division 3
PIPE CULVERTS
300-1 General
Excavate, undercut, provide material, condition foundation, lay pipe, joint and couple pipe sections and furnish and place all backfill material as necessary to install the various types of pipe culverts and fittings required to complete the project. Install pipe in accordance with the detail s in the plans. Do not waste excavation unless permitte d. Use suitable excavated material as backfill; or in the formation of embankments, subgrades and shoulders; or as otherwise directed by the Engineer . Furnish disposal areas for the unsuitable material. The Engineer will identify excavated materials that are unsuitable. Where traffic is to be maintained, install pipe in sections so half the roadway width is available to traffic.
300-2 Material S
Refer to Division 10. Item Section Flowable Fill, Excavatable 1000 -7 Grout, Type 2 1003 Geotextiles , Type 4 a 1056 Joint Materials 1032 -6(F) Select Materials 1016 Provide foundation conditioning material in accordance with Article 1016 -3 for Class V or VI select material as shown in the contract. Provide bedding material in accordance with Article 1016 -3 for Class II (Type 1 only) or Class III select material as shown in contract. Provide backfill material in accordance with Article 1016 -3 for Class II (Typ e 1 for flexible pipe) or Class III select material as shown in the contract. Provide filtr ation geotextile in accordance with Section 1056 for any type of geotextile . Provide foundation conditioning geotextile and geotextile to wrap pipe joints in accordance with Article 1056 for Type 4a geotextile . Do not use corrugated steel pipe in counties listed in Article 310 -2.
300-3 Unloading and Handling
Unload and handle pipe with reasonable care. Do not roll or drag metal pipe or plates over gravel or rock during handling. Take necessary precautions to ensure the method used in lifting or placing the pipe does not induce stress fatigue in the pipe. Use a lifting device that uniformly distributes the weight of the pipe along its axis or circumference. Repair minor damage to pipe when permitted. R emove pipe from the project that is severely damaged or is rejected as being unfit for use. Undamaged portions of a joint or section may be used where partial lengths are required.
3-2 300-4 Preparation of Pipe Foundation
Prepare the pipe foundation in accordance with the applicable method as shown in the contract, true to line and grade and uniformly firm. Where material is found to be of poor supporting value or of rock and when the Engineer cannot make adjustment in the location of the pipe, undercut existing foundation material within the limits established i n the plans. Backfill the undercut with foundation conditioning material . Encapsulate the foundation conditioning material with foundation conditioning geotextile before placing bedding material. Overlap all transverse and longitudinal joints in the geotextile at least 18 inches . Maintain the pipe f oundation in a dry condition.
300-5 Invert Elevations
The proposed pipe culvert invert elevations shown on the Drainage Summary Sheets are based upon information available when the plans were prepared. If proposed invert elevations are adjusted during construction based upon actual conditions encountered, no claim for an extension of time for any reason resulting from thi s information will be allowed. When a pipe culvert is to be installed in a trench and the average actual elevation of the pipe between drainage structures deviates from the average proposed elevation shown on the Drainage Summary Sheets by more than one foot , a pay adjus tment will be made as follows: Pay Adjustm ent (per linear foot) = ( )[ ]( ) CUP AAE APE × ± −15 . 0 Where: APE = Average Plan Elev. = ( )
300-6 Laying Pipe
The Department reserves the right to perform forensic testing on any installed pipe.
3-3 Repair lift holes in concrete pipe, if present. Thoroughly clean and soak the lift hole and
complete ly fill the void with grout. Submit alternate details for repairing lift holes to the Engineer for review and approval. For all pipes 42 inches in diameter and larger, wrap geotextile around all pipe joints. Extend geotextile at least 12 inches beyond ea ch side of the joint. Secure geotextile against the outside of the pipe by methods approved by the Engineer.
300-7 Backfilling
Loosely place bedding material, in a uniform layer, a depth equal to the inside diameter of the pipe divided by 6 or 6 inches , whichever is greater. Leave bedding material directly beneath the pipe uncompacted and allow pipe seating and backfill to accomplish compacti on. Excavate recesses to receive the bells where bells and spigot type pipe is used. Place fill around the pipe in accordance with the applicable method shown i n the plans in layers not to exceed 6 inches loose unless otherwise permitted by the Engineer . Compact to the density required by Subarticle 235 -3(C). Approval of the backfill material is required before its use. Use select material as shown in the contract. Take care during backfill and compaction operations to maintain alignment and prevent damage to the joints. Keep backfill free from stones, frozen lumps, chunks of highly plastic clay or other objectionable material. Grade and maintain all pipe backfill areas in such a condition that erosion or saturation will not damage the pipe foundation or backfill. Flowable fill may be used for backfill when approved by the Engineer. When using flowable fill, ensure that the pipe is not displaced and does not float during backfill. Submit methods for supporting the pipe and material placement to the Engineer for review and approval. Do not operate heavy equipment over any pipe until it has been properly backfilled with a t least 3 feet of cover. Place, maintain and finally remove the required cover that is above the
3-4 proposed finished grade . Remove and replace pipe that becomes misaligned, shows excessive
settlement or has been otherwise damaged by the Contractor's operations.
300-8 Inspection and Maintenance
Ensure proper jointing and that deformations do not exceed allowable limits as described in the Department’s Guidelines for Post Installation Evaluation and Repair of Newly -Installed Drainage Pipe . Maintain all pipe installations in a condition such that they wi ll function continuously from the time the pipe is installed until the project is accepted by the Engineer . The Engineer will randomly video, deflection test, and/or manually inspect installations of completed pipelines prior to final acceptance.
300-9 Measurement and Payment
No measurement will be made of any work covered by this section except as listed below. Removal and disposal of existing pavement and unsuitable material above the pipe invert are a part of the excavation for the new pipe culvert installation. Repair of the pavement will be made in accordance with Section 654. Placing, maintaining and removing the required cover is incidental to the work of this section. Removing and replacing pipe that becomes misaligned, shows excessive settlement or has been otherwise damaged by the Contractor's operations is incidental to the work of this section.
Article 225 — 7.
Local material used for conditioning the foundation will be measured and paid in accordance with Article 225-7 for Unclassified Excavation or in accordance with
Article 230 — 5 for Borrow Excavation depending on the source of the material.
Local material used to replace pipe undercut excavation will be measured and paid in accordance with Article 225-7 or Article 230-5.