15-5 1505 -5 Concrete Encasement of Utility Lines
Encase existing or proposed utility lines in concrete for protection in areas as shown on the utility plans or as directed by the Engineer . Place the concrete completely around the line with a minimum thickness of 6 inches . 1505 -6 MEASUREMENT AND PAYMENT Foundation Conditioning Material, Minor Structures and Foundation Conditioning Geotextiles will be measured and paid as provided in Article 300-9. Asphalt Plant Mix , Pavement Repair will be measured and paid as provided in Article 654-4. Class B Concrete for Encasing Utility Lines will be measured and paid in cub ic yards of concrete, measured in place. __" Concrete Sidewalk and __" Concrete Driveways will be measured and paid in accordance with Article 848 -4. Trenching, excavation, pipe laying, bedding, backfilling and disposal of unsuitable materials for utility construction are included in the contract price for the applicable utility item and no separate measurement or payment will be made. The following work and items are included in the contract price for the applicable utility item 16 and no separate measurement or payment will be made for items (A) through (F) below:
15-6 Use 2 inch plastic marking tape colored blue with “ Caution Water Line ” or similar wording,
permanently printed at 36 inch centers. Protec t steel rods and other metal clamps and lugs by galvanizing or painting with approved bituminous paint as found on the NCDOT APL . 1510 -3 CONSTRUCTION METHODS
WATER LINES in other states
Get an email when 1510 changes
North Carolina revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.