8-10 Submit a revised or additional reclamation plan to the Engineer if the non -permitted waste
or disposal area is expanded by more than one acre or is significantly changed from the previously approved submittal.
802-3 Measurement and Payment
Seeding and mulching, fertilizer topdressing and establishing erosion control measures for waste or disposal areas will be measured and paid at the contract unit prices for the items established in the contract. When permitted to waste within the right of way and when the waste area requires additional covering material before seeding, provide covering material at no cost to the Department. When waste areas are located outside the right of way, no payment will be made for any borrow used to cover rock, broken pavement, masonry or other inert materials. Except as otherwise provided above, no direct payment will be made for the work covered by this section. Payment at the contract prices for the var ious items in the contract will be full compensation for all work covered by this section. RIGHT -OF-WAY AND CONTROL -OF-ACCESS MARKERS
806-1 Description
Furnish and install precast concrete or granite markers to mark the boundaries of the right of way or the control of access in accordance with the contract.
806-2 Materials
Refer to Division 10. Item Section Steel Bar Reinforcement 1070 -2 Precast Concrete Units 1077 The Contractor may, at his option, use either granite or concrete markers. Make granite markers from granite that is hard and durable, of a light color, free from seams which impair its structural integrity, and of a good, smooth splitting appearance.
806-3 Construction Methods
Precast the right -of-way and control -of-access marker s in watertight forms of a size and shape that will produce a completed marker of the dimensions shown in the Roadway Standard Drawings . Construct the forms so as to impres s the concrete with the lettering and markings shown in the contract . Cure the concrete in accordance with Article 420 -15. Give that portion of the marker that will be above the surface of the ground ordinary surface finish in accordance with Subarticle 420-17(B). If using granite markers, q uarry and finish the markers to the dimensions indicated i n the contract . Drill holes will be permitted in the sides and bottom. Install the markers vertically in the ground to the depth and locations specified in the contract. Thoroughly tamp backfill material.
806-4 Measurement and Payment
Right -of-Way Markers will be measured and paid in units of each for the actual number of right - of-way markers furnished, installed and accepted. Control -of-Access Markers will be measured and paid in units of each for the actual number of control -of-access markers furnished, installed and accepted.