A minimum of 30 percent of the work, as represented by the original contract amount, must be performed by the Contractor’s organization. When calculating the percentage of the work to be performed by the Contractor, the Engineer will deduct from the original contract amount the contract price of contract items identified by the contract as specialty items. The Engineer will include the delivered cost of commercially produced materials and manufactured components purchased by the Contractor in the percentage of the work to be performed by the Contractor. Sublet, sell, transfer, assign, or dispose of any portion of the contract only with the Engineer’s prior written approval. To obtain approval, submit a Prime Contractor’s Request to Sublet (SFN 5682) for each proposed subcontractor with a copy of the subcontract and associated lower -tier subcontracts. For a partially subcontracted contract item, explain in detail and show the subcontract amount associated with the partially subcontracted contract item . If a proposed subcontractor is not currently prequalified, certified as a DBE, or registered as a subcontractor with the Department, submit a Subcontractor Registration Request (SFN 52243) with the Prime Contractor’s Request to Sublet. When the contract specifies a DBE Goal, execute a subcontract with all firms approved through the Department’s Good Faith Effort process. If the Department classifies the firm as an oil hauler, supplier, broker, vendor, regular dealer, or manufacturer, no subcontract is required, but the firm must be used to perform the work. Begin subcontracted work only after the Engineer approves the Prime Contractor’s Request to Sublet. A subcontract, transfer of all or a portion of the contract, the Engineer’s approval of the Prime Contractor’s Request to Sublet, or the Department’s prequalification, DBE certification, or registration of a subcontractor:
A.Preconstruction Conference. Before beginning the work, including pit operations specific to the project, and unless waived by the Engineer, coordinate and hold a preconstruction conference with the Engineer at a mutually agreed time and place. Notify subcontractors, utility companies, and other interested parties of the time and place of the preconstruction conference. Submit the following to the Engineer before or at the preconstruction conference:
1.A company safety plan and the name of the safety officer;
2.An EEO / affirmative action plan and the name of the EEO officer;
3.A list of key project personnel and their phone numbers;
4.The initial or baseline schedule in accordance with Section 108.03, "Progress Schedule";
5.A list of proposed subcontractors requested in accordance with “Subletting of Contract” ;
6.A list of material suppliers;
7.A list of pits to be used (owner and legal description);
8.All COAs in accordance with Section 107.05, “Material Source Approval” ;
9.The applicable storm water permits and the SWPPP in accordance with Section 107.02.C, “Storm Water Permits” ;
10.The names of Quality Control Personnel and a Quality Control Plan in accordance with Section 430.04 A, “Contractor Quality Control (QC).”
B.Weekly Planning and Reporting Meeting. The weekly planning and reporting meeting is only required when specified in the plans. Organize a weekly meeting to coordinate efforts between subcontractors, utilities, local authorities, and others. The Engineer will develop a list of parties to be invited to the meeting and will prov ide the list to the Contractor at the Preconstruction Meeting. The Engineer may provide an updated list with additional attendees at any time. Send a knowledgeable representative to conduct the meeting. Prepare minutes for each meeting and make the appropriate distribution of the minutes. Distribute the minutes within 48 hours of the meeting conclusion. Allow the Engineer to review and approve the minutes before distribution. Include in the meeting agenda a discussion of problems encountered since the las t meeting, and information of interest to those invited to the meeting. Provide a written schedule of the next week’s work and a tentative schedule for the following week. 77 108.03 PROGRESS SCHEDULE
A.General. Prepare and submit to the Engineer a schedule in accordance with Section 108.03 B, “Bar Chart Method,” unless the contract requires a Critical Path Method (CPM) schedule. If the contract requires a CPM schedule, prepare and submit to the Engineer a CPM schedule in accordance with Section 108.03 C, “Critical Path Method (CPM).” Prepare and submit progress schedules in accordance with the AGC’s Construction Planning & Scheduling Manual . In case of a conflict between the Construction Planning & Scheduling Manual and the scheduling requirements in the contract, the contract requirements will take precedence. Use the schedule to plan, coordinate, and manage the work, whether the Contractor’s personnel are performing the work or not. Share copies of the complete baseline schedule, update schedules, and revised schedules with all subcontractors, suppliers, and utility companies affected by the work. Float is a shared commodity and is not for th e exclusive use or benefit of any party. It is available to all parties as needed until it is consumed. The Engineer will accept or reject a schedule based on the schedule meeting the requirements of Section 108.03, “Progress Schedule,” and any other contract requirement. The Engineer’s acceptance of a schedule:
1.Does not modify the contract;
2.Does not constitute endorsement or validation by the Engineer of the Contractor’s activity logic, activity durations, or assumptions in creating the schedule;
3.Does not guarantee that the project can be performed or completed as depicted in the schedule; and
4.Does not relieve the Contractor of its obligation or responsibility to submit complete and accurate information. If the Contractor or Engineer discovers an error after the Engineer has accepted a schedule, the Contractor shall correct the error in the next schedule submission. If the Contractor fails to prepare and submit a progress schedule that is acceptable to the Engineer as required by the contract, the Engineer will withhold progressive estimates until the Contractor submits an acceptable schedule.
B.Bar Chart Method.
1.Submission Requirements. Provide the following items with the initial, baseline, update, and revised schedule submissions:
a.Narrative Reports. Narrative reports shall include:
1.An explanation of the overall plan to complete the project;
2.The number of crews and the following for each crew:
a.The number and types of workers;
b.The number and types of equipment;
c.The working days per week, the number of shifts per day, the number of hours per shift, and the holidays to be observed; and
d.The schedule activities being performed;
3.A desc ription of how the schedule accounts for adverse weather days;
4.The quantity of work and estimated production rates for each critical activity;
5.Activities requiring coordination with the Department, other parties, or both;
6.A description of the critical path;
7.A description of all changes in the schedule and narrative report that differ from the last accepted schedule submission; and
8.For a revised schedule, a description of and the reason for all revisions to the schedule.
b.Graphical Depiction of the Bar Chart Schedule. Submit schedules in color as a paper printout or a .pdf file, with minimum dimensions of 11 inches by 17 inches.
c.Transmittal Letter. Submit a transmittal letter to the Department that identifies the schedule being submitted for review and states that the schedule being submitted has been developed in accordance with the contract.
2.Initial Schedule. At least 5 business days before the preconstruction conference, submit an initial schedule. The Contractor may submit the baseline schedule, as specified in “Baseline Schedule,” as both the initial and baseline schedule. For projects with expected durations of less than 90 calendar days, submit the initial schedule as the baseline schedule. Define and sequence activities to accurately describe the project and to comply with all contract requirements, including those related to the scope of work, phasing or staging, sequencing, ac commodations for traffic, and milestones. The initial bar chart schedule is a schedule prepared for the first 90 calendar days of work and shall include the following minimum information: 79 a. The activities needed to perform and complete the work;
b.The planned start and completion dates for each activity, the duration of each activity (stated in working days, and with activities of more than 30 working days in duration broken into two or more activities distinguished by location or some other feature), and the sequencing of all activities;
c.Applicable project milestones, including notice to proceed, the start date of the work, and the completion date associated with the expiration of the contract time;
d.The location of the work;
e.Dates relate d to the procurement of significant materials, equipment, and articles of special manufacture;
f.Dates related to the submission of work drawings, plans, and other data specified for review by the Department;
g.Dates related to required inspections; and
h.Dates related to work by the Department and other parties. Submit a summary schedule for the balance of the project work after the first 90 calendar days; activity durations on the summary schedule may exceed 30 working days. Within 5 business days after the preconstruction conference, the Department will respond in writing accepting the initial schedule, rejecting the initial schedule and identifying the reasons for rejection, or requesting more information. Within 5 business days after the date of the Department’s written response, address the reasons for rejection and resubmit the initial schedule or provide the information requested.
3.Baseline Schedule. Within 30 calendar days after the preconstruction conference, prepare the baseline schedule and submit to the Department for review. For projects with expected duration of less than 90 calendar days, the Department will not require the Contractor to submit a baseline schedule. The baseline schedule shall include the requirements set forth by “Initial Schedule,” items “a” through “h”, but for the entire project and all work. Note any differences between the initial schedule and the baseline schedule in the narrative report submitted with the baseline schedule. Within 10 business days after receipt of the baseline schedule, the Department will respond in writing accepting the baseline schedule, rejecting the baseline schedule and identifying the reasons for rejection, or requesting more information. Within 5 business days after the date of the Department’s written response, address the reasons for rejection and resubmit the baseline schedule or provide the information requested. 80 4. Update Schedule. After the Department’s written acceptance of the baseline schedule, prepare and submit an update schedule every month with a data date of the first business day of the succeeding month. Report the progress of work performed up to, but not including, the data date. S ubmit the update schedule within 3 business days after the data date. Schedule and conduct weekly progress meetings with the Engineer to discuss schedule progress. Update the schedule to reflect this actual progress. For activities that have started or fi nished since the data date of the last accepted schedule, include the actual start or finish dates. For activities started and still ongoing, show the remaining durations and planned finish dates. Do not make changes between the last accepted schedule and the update schedule, such as adding or deleting activities, increasing or decreasing activity durations, changing the sequence of work, or renaming activities or changing activity descriptions. Within 5 business days after receipt of the update schedule, the Department will respond in writing by accepting the update schedule, by rejecting the update schedule and identifying the reason for rejection, or by requesting more information. Within 5 business days after the date of the Department’s written response, address the reasons for rejection and resubmit the update schedule or provide the information requested.
5.Revised Schedule. Prepare and submit a revised schedule if a revision to the schedule is necessary. The Department may request the submission of a revised schedule if any of the following circumstances occur:
a.There is a delay (actual or projected) to the scheduled milestone or project completion dates;
b.There is a difference between the actual sequence or durations of the work and the sequence or durations depicted in the last accepted schedule; or
c.The Department executes a contract revision that adds or deletes work, modifies the planned sequence of work, or modifies the means and methods of its performance. The requirement to prepare a revised schedule is not a directive by the Department to accelerate the work. Prepare and submit the revised sch edule as soon as the need for a revised schedule is necessary, but no more than 5 business days after the Department’s request. Within 5 business days of receipt of the revised schedule, the Department will respond in writing accepting the revised schedul e, rejecting the revised schedule and identifying the reasons for rejection, or requesting more information. Within 5 business days after the date of the Department’s written response, address the reasons for rejection and resubmit the revised schedule or provide the information requested. 81 C. Critical Path Method (CPM).
1.General. Use CPM scheduling software that is compatible with Microsoft Project.
2.Submission Requirements. Submit an electronic copy of the CPM schedule in its native format containing the entire schedule. Submit schedules in a format compatible with Microsoft Project. Calculate the CPM schedule using retained logic. Calculate total float based on finish dates. Calculate schedule durations as contiguous. Calculate start-to-st art lags from early dates. Provide the following items with the initial, baseline, update, and revised schedule submissions:
a.Narrative Report. Narrative reports shall include:
1.An explanation of the overall plan to complete the project;
2.The number of crews and the following for each crew:
a.The number and types of workers;
b.The number and types of equipment;
c.The working days per week, the number of shifts per day, the number of hours per shift, and the holidays to be observed; and
d.The schedule activities being performed;
3.A description of how the schedule accounts for adverse weather days;
4.The quantity and estimated production rates for each critical activity;
5.Activities requiring coordination with the Department, other parties, or both;
6.A description of the critical path;
7.A Claim Digger or equivalent report showing all changes in the schedule and a description of all changes in the narrative report that differ from the last accepted schedul e submission; and
8.For a revised schedule, a description of and the reason for all revisions to the schedule.
b.Logic Diagram. Logic diagrams shall be in color and on standard D size sheets (24 inches by 36 inches). 82 c. Tabular Sorts. Tables shall include sorts of activities listed by the following:
2.Predecessor and successor;
3.Phase or stage by early start;
5.Total float.
d.Graphical Depiction of CPM Schedule. The graphical depiction shall be a bar chart view of all activities grouped by phase and stage, and sorted by early start date.
e.Look-Ahead Schedule. The look -ahead schedule shall be a bar chart view of the 60-calendar -day period starting with the data date, and sorted by early start.
f.Transmittal Letter. Submit a transmittal letter to the Department that identifies the schedule being submitted for review and states that the schedule being submitted has been developed in accordance with the contract.
3.Initial Schedule. At least 5 business days before the preconstruction conference, submit an initial schedule as specified by Section 108.03 B.2, “Initial Schedule”, except that if submitting a baseline schedule as the initial schedule submit the baseline schedule as specified in Section