298 SECTION 626
626.01 Description
This work consists of designing, constructing, dewatering, maintaining, removing, and backfilling cofferdams.
626.02 Equipment
Reserved.
626.03 Materials
Reserved.
626.04 Construction Requirements
626.05 Method of Measurement
The Engineer will measure as specified in Section 109.01, “Measurement of Quantities” and as follows: If multiple cofferdams are constructed to protect a single portion of the work, the Engineer will measure it as a single cofferdam. Excavation for cofferdam s will be measured as specified in Section 210.05, “Method of Measurement” . Excavation inside the cofferdam and outside the limits defined in the plans will not be measured. 299 626.06 BASIS OF PAYMENT Pay Item Pay Unit Cofferdam Each Pier Cofferdam Each The Department will pay 50 percent of the contract unit price when the cofferdam is installed. The Department will pay 50 percent of the contract unit price when the cofferdam is removed. Excavation for cofferdams will be paid for as specified in Section 210.06, “Basis of Payment” . Include excavation inside the cofferdam and outside the excavation limits defined in the plans in the contract unit price for cofferdam items. Such payment is full compensation for furnishing all materials, equipment, labor, and incidentals to complete the work as specified. Section 650 300 SECTION 650 OVERLAY OF CONCRETE BRIDGE DECKS
650.01 Description
This work consists of removing and replacing unsound concrete and/ or chloride contaminated concrete and resurfacing a bridge deck.