General Provisions (00100-00999)

400LIGHTING, SIGNS, AND TRAFFIC CONTROL

NE · 2017 Standard SpecificationsBook pages 215218View official source ↗

- 181 - DIVISION 400 -- LIGHTING, SIGNS, AND TRAFFIC CONTROL 401 -- LIGHTING, TRAFFIC SIGNAL AND INTELLIGENT TRANSPORTATION SYSTEM (ITS) DEVICE GENERAL REQUIREMENTS .................................................................................................................. 185

401.01 Description ........................................................................... 185

401.02 Material Requirements ........................................................ 185

401.03 Tests of Lighting Systems .................................................... 187

401.04 Grounding ............................................................................. 188

401.05 General Construction Requirements ................................. 188

401.06 Secondary Electrical Connections .................................... 189

402 -- WIRE AND CABL E IN CONDUI T ................................................... 192

402.01 Description ........................................................................... 192

402.02 Material Requirements ........................................................ 192

402.03 Construction Methods ......................................................... 192

402.04 Method of Measurement ...................................................... 193

402.05 Basis of Payment .................................................................. 194

403 -- DIRECT BURIED WIRE AND CABLE ............................................ 195

403.01 Description ........................................................................... 195

403.02 Material Requirements ........................................................ 195

403.03 Construction Methods ......................................................... 195

403.04 Method of Measurement ...................................................... 196

403.05 Basis of Payment .................................................................. 196

404 -- AERIAL CABLE ............................................................................. 197

404.01 Description ........................................................................... 197

404.02 Material Requirements ........................................................ 197

404.03 Construction Methods ......................................................... 197

404.04 Method of Measurement ...................................................... 197

404.05 Basis of Payment .................................................................. 197

405 -- CONDUIT ........................................................................................ 198

405.01 Description ........................................................................... 198

405.02 Material Requirements ........................................................ 198

405.03 Construction Methods ......................................................... 198

405.04 Method of Measurement ...................................................... 199

405.05 Basis of Payment .................................................................. 202

406 -- PULL BO XES ................................................................................. 201

406.01 Description ........................................................................... 201

406.02 Material Requirements ........................................................ 201

406.03 Construction Methods ......................................................... 201

406.04 Method of Measurement ...................................................... 201

406.05 Basis of Payment .................................................................. 201

407 -- POLE AND TOWE R FOUNDATION S ............................................ 202

407.01 Description ........................................................................... 202

407.02 Material Requirements ........................................................ 202

407.03 Construction Methods ......................................................... 202

407.04 Method of Measurement ...................................................... 203

407.05 Basis of Payment .................................................................. 203

408 -- POLES AND TOWERS .................................................................. 204

408.01 Description ........................................................................... 204

408.02 Material Requirements ........................................................ 205

408.03 Construction Methods ......................................................... 205

408.04 Method of Measurement ...................................................... 206

- 182 - 409 -- SIGNAL HEADS ............................................................................. 208

409.01 Description ........................................................................... 208

409.02 Material Requirements ........................................................ 208

409.03 Construction Methods ......................................................... 208

409.04 Method of Measurement ...................................................... 208

409.05 Basis of Payment .................................................................. 208

410 -- DETECT ORS .................................................................................. 209

410.01 Description ........................................................................... 209

410.02 Material Requirements ........................................................ 209

410.03 Construction Methods ......................................................... 209

410.04 Method of Measurement ...................................................... 209

410.05 Basis of Payment .................................................................. 210

411 -- TRAFFIC SIGNAL CONTROLLE R ................................................ 211

411.01 Description ........................................................................... 211

411.02 Material Requirements ........................................................ 211

411.03 Construction Methods ......................................................... 211

411.04 Method of Measurement ...................................................... 211

411.05 Basis of Payment .................................................................. 211

412 -- LUMINA IRES .................................................................................. 212

412.01 Description ........................................................................... 212

412.02 Material Requirements ........................................................ 212

412.03 Construction Methods ......................................................... 212

412.04 Method of Measurement ...................................................... 213

412.05 Basis of Payment .................................................................. 213

413 -- LIGHTING CONT ROL CENTER S .................................................. 214

413.01 Description ........................................................................... 214

413.02 Material Requirements ........................................................ 214

413.03 Construction Methods ......................................................... 214

413.04 Method of Measurement ...................................................... 215

413.05 Basis of Payment .................................................................. 215

414 -- HIGH MAST LOWE RING SYSTEM S ............................................. 216

414.01 Description ........................................................................... 216

414.02 Material Requirements ........................................................ 216

414.03 Construction Methods ......................................................... 216

414.04 Method of Measurement ...................................................... 216

414.05 Basis of Payment .................................................................. 216

415 -- MAINTENANCE OF PROJEC T LIGHTING SYSTEM .................... 217

415.01 Description ........................................................................... 217

415.02 Material Requirements ........................................................ 217

415.03 Construction Methods ......................................................... 217

415.04 Method of Measurement ...................................................... 218

415.05 Basis of Payment .................................................................. 218

416 -- TEMPORARY LIGH TING SYSTEM S ............................................. 219

416.01 Description ........................................................................... 219

416.02 Material Requirements ........................................................ 219

416.03 Construction Methods ......................................................... 219

416.04 Method of Measurement ...................................................... 220

416.05 Basis of Payment .................................................................. 220

417 -- HIGHWAY SIGNS ........................................................................... 221

417.01 Description ........................................................................... 221

417.02 Material Requirements ........................................................ 221

417.03 Construction Methods ......................................................... 222

417.04 Method of Measurement ...................................................... 225

- 183 - 417.05 -- BASIS OF PAYMENT .................................................................. 226 418 -- OVERHEAD SIGN SUPPORTS ..................................................... 227

418.01 Description ........................................................................... 227

418.02 Material Requirements ........................................................ 228

418.03 Construction Methods ......................................................... 232

418.04 Method of Measurement ...................................................... 249

418.05 Basis of Payment .................................................................. 241

419 -- TRAFFIC CONTROL MANAGEMENT AND SURVEILLANCE ..... 242

419.01 Description ........................................................................... 242

419.02 Construction Methods ......................................................... 242

419.03 Method of Measurement ...................................................... 246

419.04 Basis of Payment .................................................................. 246

420 -- DELINEAT ORS .............................................................................. 247

420.01 Description ........................................................................... 247

420.02 Material Requirements ........................................................ 247

420.03 Construction Methods ......................................................... 248

420.04 Method of Measurement ...................................................... 248

420.05 Basis of Payment .................................................................. 248

421 -- REMOVING AND RESETTI NG DELINEAT ORS ............................ 249

421.01 Description ........................................................................... 249

421.02 Construction Methods ......................................................... 249

421.03 Method of Measurement ...................................................... 249

421.04 Basis of Payment .................................................................. 249

422 -- TEMPORARY TRAFFIC CONTROL SIGNS AND DEVICES ......... 250

422.01 Description ........................................................................... 250

422.02 Material Requirements ........................................................ 251

422.03 Construction Methods ......................................................... 253

422.04 Method of Measurement ...................................................... 263

422.05 Basis of Payment .................................................................. 265

423 -- PERMANENT PAVEM ENT MARKING .......................................... 268

423.01 Description ........................................................................... 268

423.02 Material Requirements ........................................................ 268

423.03 Construction Methods ......................................................... 281

423.04 Method of Measurement ...................................................... 287

423.05 Basis of Payment .................................................................. 288

424 -- TEMPORARY PAVEME NT MARKING .......................................... 289

424.01 Description ........................................................................... 289

424.02 Equipment .............................................................................. 290

424.03 Material Requirements ........................................................ 291

424.04 Construction Methods ......................................................... 291

424.05 Method of Measurement ...................................................... 295

424.06 Basis of Payment .................................................................. 296

- 184 - - 185 - SECTION 401-- LIGHTING, TRAFFI C SIGNAL AND INTELLIGENT TRANSPORTATION SYSTEM (I TS) DEVICE GENERAL REQUIREMENTS

401.01 Description

1.The requirements in this Se ction apply when the Contractor furnishes or installs all or part of the following systems:
a.Sign lighting system. b. Traffic signal system.
c.Permanent lighting system.
d.Temporary lighting system. e. ITS Devices. 2. When the pay item listed in the Basis of Payment Subsection of each Section includes the word "Install" , then the Department will furnish the item and the Contractor shall install it. If the word "Install" is not in the pay item listed in the Basis of Payment Subsection of each Section, then the Contractor shall furnis h and install the item.
3.Specifications for State suppli ed items are available for viewing at the Nebraska Department of Transportation Construction Office, Room 104, 1500 Nebraska Highway 2, Lincoln, Nebraska.

401.02 Material Requirements

1.Prior to ordering any material, the Contractor shall submit to the Engineer, for review, 8 copies of a list showing all roadway lighting system, sign lighting system, traffic signal system and ITS device items to be used on the project. This list of items shall be known as the "Materials List." A separate material list shall be submitted for each system involved. Material Lists combining items from different systems will be returned without review for resubmittal as separate Material Lists. No shop dr awings or certificates of compliance will be reviewed without first having received the correct Materials List.
2.All equipment and material must be reviewed before installation. Once reviewed, there shall be no substitutions for any of the items on the "Materials List" without a prior written request for a substitution and written approval by the Engineer. The Department shall not be liable for any equipment or materials ordered or purchased by the Contractor before review.
3.The Contractor shall provide 8 se ts of submittals as required by Table 401.01. These submittals will be reviewed for compliance with the contract. Materials to be incorporated into the project will be checked for compliance with the reviewed submittals.
4.The Contractor shall transfer all manufacturer's warranties and guarantees to the Department. All manufacturers’ warranty and guarantee documentation and all operation and parts manuals shall also be given to the Department.
5.All items shown on the "Mater ials List" will be reviewed for compliance with the contract. Two copies of the reviewed "List" will be returned to the Contractor. Review does not relieve the Contractor if submittals differ from the contract. If sufficient data is not available to
Source: Nebraska Standard Specifications for Highway Construction, 2017 Edition. Pages 215218 of 1,048.