400LIGHTING, SIGNS, AND TRAFFIC CONTROL

NE · 2017 Standard Specifications✓ Full text on BuildSpecBook pages 215–218 Save this section

Ask about Section 400

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

- 181 - DIVISION 400 -- LIGHTING, SIGNS, AND TRAFFIC CONTROL 401 -- LIGHTING, TRAFFIC SIGNAL AND INTELLIGENT TRANSPORTATION SYSTEM (ITS) DEVICE GENERAL REQUIREMENTS

- 184 -

- 185 - SECTION 401-- LIGHTING, TRAFFI C SIGNAL AND INTELLIGENT TRANSPORTATION SYSTEM (I TS) DEVICE GENERAL REQUIREMENTS

401.01Description

1.The requirements in thisSe ction apply when the Contractor

furnishes or installs all or part of the following systems:

a.Sign lighting system. b. Traffic signal system.
c.Permanent lighting system.
d.Temporary lighting system. e. ITS Devices. 2. When the pay item listed in the Basis of Payment Subsection of

each Section includes the word "Install" , then the Department will furnish the item and the Contractor shall install it. If the word "Install" is not in the pay item listed in the Basis of Payment Subsection of each Section, then the Contractor shall furnis h and install the item.

3.Specifications for State supplied items are available for viewing at

the Nebraska Department of Transportation Construction Office, Room 104, 1500 Nebraska Highway 2, Lincoln, Nebraska.

401.02Material Requirements

1.Prior to ordering any material, the Contractor shall submit to the

Engineer, for review, 8 copies of a list showing all roadway lighting system, sign lighting system, traffic signal system and ITS device items to be used on the project. This list of items shall be known as the "Materials List." A separate material list shall be submitted for each system involved. Material Lists combining items from different systems will be returned without review for resubmittal as separate Material Lists. No shop dr awings or certificates of compliance will be reviewed without first having received the correct Materials List.

2.All equipment and material must be reviewed before installation.

Once reviewed, there shall be no substitutions for any of the items on the "Materials List" without a prior written request for a substitution and written approval by the Engineer. The Department shall not be liable for any equipment or materials ordered or purchased by the Contractor before review.

3.The Contractor shall provide 8 se ts of submittals as required by

Table 401.01. These submittals will be reviewed for compliance with the contract. Materials to be incorporated into the project will be checked for compliance with the reviewed submittals.

4.The Contractor shall transfer all manufacturer's warranties and

guarantees to the Department. All manufacturers’ warranty and guarantee documentation and all operation and parts manuals shall also be given to the Department.

5.All items shown on the "Mater ials List" will be reviewed for

compliance with the contract. Two copies of the reviewed "List" will be returned to the Contractor. Review does not relieve the Contractor if submittals differ from the contract. If sufficient data is not available to

Get an email when 400 changes

Nebraska revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Nebraska Standard Specifications for Highway Construction, 2017 Edition. Pages 215–218 of 1,048. View official source ↗