General Provisions (00100-00999)

421REMOVING AND RESETTING DELINEATORS

NE · 2017 Standard SpecificationsBook pages 283283View official source ↗

- 249 - SECTION 421 -- REMOVING AND RESETTING DELINEATORS

421.01 Description

1.The Contractor shall remove and reset flexible post and standard delineators at the locations shown in the contract.

421.02 Construction Methods

1.The Contractor shall remove t he delineators, intact, and stockpile them at designated locati ons for future resetting.
2.Any material lost or damaged s hall be replaced by the Contractor at no additional cost to the Department.
3.The delineators shall be set plumb and anchored as described in the contract.

421.03 Method of Measurement

1.Removing and resetting delineators will be measured by the each.

421.04 Basis of Payment

1.Pay Item Pay Unit Remove & Reset Delineators Each (ea) Remove & Reset Flexible Post D e l i n e a t o r s E a c h ( e a )
2.Payment is full compensation for a ll work described in this Section. - 250 - SECTION 422 -- TEMPORARY TRAFFIC CONTROL SIGNS AND DEVICES

422.01 Description

1.The Contractor shall furnish, install, operate, and maintain temporary traffic control signs and devic es at the locations shown in the contract. When the work is complete, the Contractor shall remove the temporary traffic control signs and devices described in this Section.
2.Permanent Signs
a.Permanent Signs (Sign Day) are signs furnished by the Department and installed and maintain ed by the Contractor on posts and hardware supplied by the Contractor whic h are subsidiary to the “Sign Day” pay item.
3.Temporary Signs a. Temporary Signs (Temporary Sign Day) are signs furnished by the Contractor and mounted on temporar y sign supports supplied by the Contractor which are subsidiary to the “Temporary Sign Day” pay item.
b.Barricade Signs (Barricade Sign Day) are signs furnished by the Contractor that are mounted on barricades that are paid for separately by the Department.
4.General Requirements: a. All signs and devices shal l be constructed and erected in accordance with the contract and MUTCD.
b.Sign legends and symbols shall be of professional quality workmanship and in uniformity with the Standard Highway Signs and Markings Manual. All signs shall meet the requirements of the American Traffic Safety Services Association (ATSSA) "Quality Guidelines for Work Zone Traffic Control Devices”. Hand printing or poor workmanship shall not be allowed.
c.The initial placement, replacement, and removal of the traffic control signs and devices shall be done with extreme care and consideration for the traveling public.
d.Permanent and temporary signs and devices shall not be removed without the Engineer's approval.
e.The temporary traffic control signs and devices, except materials furnished by the Department, shall remain the property of the Contractor.
Source: Nebraska Standard Specifications for Highway Construction, 2017 Edition. Pages 283283 of 1,048.