- 366 - SECTION 515 -- ARMOR COAT OR CHIP SEAL
515.01 Description
515.02 Material Requirements
515.03 Construction Methods
515.03 Armor Coat or Chip Seal
- 368 - f. Seamless transverse joints shall be obtained by placing 15 pound tar paper at the joint at the beginning and end of each shot. This should ensure that the correct rate of application is achieved for the full length of the shot and avoid double application of emulsified asphalt. The emulsified asphalt application shall commence with a running start on a strip of tar paper. The spray bar needs to be stopped on the tar paper at the end of each shot to ensure a straight tr ansverse construction joint. Transverse joints shall have no more than 0.25 inch (6.5 mm) difference in elevation across the joint as measured with a 6 foot (2m) straightedge. The Armor Coat or Chip Seal edge shall be neat and uniform along the roadway lane, shoulder and curb lines. The Armor Coat or Chip Seal edge shall have no more than 2 inches (50 mm) variance in any 100 fo ot (30m) section, along the roadway edge or shoulder.
515.04 Method of Measurement
515.05 Basis of Payment
515.05 Armor Coat or Chip Seal
- 370 - 2. Aggregate not meeting the gr adation requirements listed in Table 515.01, 515.02, or 515.03 will not be accepted for payment.
515.04 If the resultant Pay Factor for the material indicates rejection as an
option, the Engineer will determine if the non-compliant material will be removed. Table 515.04 Tolerances and Pay Factors Specified Property Tolerance Pay Facto r AASHTO T 59, Residue after Distillation ≥ 64.0% 1.00 63.0%-63.9% 0.75 < 63.0% 0.40 or Reject AASHTO T 301, Elastic Recovery, 77°F, CRS-2P ≥ 49.5% 1.00 44.0% - 49.4% 0.75 < 44.0% 0.40 or Reject Pay Factors for AASHTO Tests for ALL other Properties Specified* 1.00 for a deviation of ± less than or equal to 10% 0.75 for a deviation of ± greater than 10% to less than or equal to 25% 0.40 or Reject for deviation of ± greater than 25% * When the specification requiremen t is stated as a percentage, the test result deviation from the s pecification will be divided by the specification value. The resulting deviation percentage is then applied to the listed criteria. Note: When more than one specified property exceeds specification tolerances, the largest pay Factor Reduction will be applied.